Planning Commission
Regular MeetingEugene, OR · April 9, 2007
Minutes
SUMMARY MINUTES
Regular Meeting
Eugene Planning Commission
Sloat Room—The Atrium—99 West 10th Avenue
April 9, 2007
11:30 a.m.
PRESENT: Rick Duncan, President; Randy Hledik, Vice President; Jon Belcher, Phillip
Carroll, Ann Kneeland, John Lawless, Anthony McCown, members; Alissa
Hansen, Steve Nystrom, Planning and Development Department; Chris Henry,
Gary McNeel, Public Works Department; Rick Satre, Rosie Pryor, Rob Dehnert,
Ann Simas, Tom Adams, Bill Goetz, Jim Spickerman, Deobrah Jeffries, Ashley
Garrett, Christo Brehm, guests.
ABSENT: Mike Sullivan, ex officio.
PUBLIC COMMENT ON NON-AGENDA ITEMS
I. STUDY SESSION: PLAN AMENDMENTS/ZONE CHANGE PROCESS AND
CRITERIA (MCKENZIE-WILLAMETTE MEDICAL CENTER)
Staff: Alissa Hansen, 682-5508
II. ITEMS FROM COMMISSION AND STAFF
A. Other Items from Staff
B. Other Items from Commission
MINUTES—Eugene Planning Commission April 9, 2007 Page 1
MINUTES
Regular Meeting
Eugene Planning Commission
Sloat Room—The Atrium—99 West 10th Avenue
April 9, 2007
11:30 a.m.
PRESENT: Rick Duncan, President; Randy Hledik, Vice President; Jon Belcher, Phillip
Carroll, Ann Kneeland, John Lawless, Anthony McCown, members; Alissa
Hansen, Steve Nystrom, Planning and Development Department; Chris Henry,
Gary McNeel, Public Works Department; Rick Satre, Rosie Pryor, Rob Dehnert,
Ann Simas, Tom Adams, Bill Goetz, Jim Spickerman, Debobrah Jeffries, Ashley
Garrett, Christo Brehm, guests.
ABSENT: Mike Sullivan, ex officio.
Mr. Duncan convened the Planning Commission meeting.
PUBLIC COMMENT ON NON-AGENDA ITEMS
There was no one wishing to offer public comment.
I. STUDY SESSION: PLAN AMENDMENTS/ZONE CHANGE PROCESS AND
CRITERIA (MCKENZIE-WILLAMETTE MEDICAL CENTER)
Ms. Hansen provided the staff report. She said the purpose of the study session was to provide an
opportunity for the Planning Commission to become familiar with the relevant approval criteria
and gain an understanding of the proposal in the context of Statewide Planning Goal 12
(Transportation) to enhance the commission’s efforts in the upcoming public hearing and
deliberation. She reviewed the schedule for Planning Commission review of the amendment and
zone change requests, noting that the staff report containing the staff recommendation would be
available on April 17, 2007. She distributed a binder containing the applicant’s materials. She
drew the attention of commissioners to a map posted on the wall entitled, Significantly Affected
Transportation Facilities and Proposed Mitigations. Copies of the map were also distributed to
commissioners.
Ms. Hansen stated the applicant had requested approval of the following:
• Metro Plan Amendment (City file MA 06-1) to amend the Metro Plan land use
diagram from designation of Parks and Open Space to a designation of Commercial
for the subject property.
• Refinement Plan Amendment (City file RA 06-1) to amend the Willakenzie Area
Plan land use diagram from a designation of Parks/Open Space to a designation of
Commercial for the subject property and amend the text by adding a policy to limit
the use of the subject property to hospital/medical.
• Zone Change (City file 06-8) to rezone the subject property from the existing zoning
of R-1 Low Density Residential with /SR Site Review overlay to C-2 Community
MINUTES—Eugene Planning Commission April 9, 2007 Page 1
Commercial with/SR Site Review overlay.
Ms. Hansen stated development of the site with a hospital required the approval of the three
applications as well as a conditional use permit and a site review, which would be later steps in
the process.
Ms. Hansen said the applicant was proposing construction of a 423,000 square foot hospital as
well as 100,000 square feet of medical office space. The applications were initiated by the
applicant and site specific to the property previously identified. While the City of Eugene had
sole jurisdiction over the decision, referrals of the application had been sent to Lane County and
the City of Springfield. Additionally, the City had coordinated with Lane County and the Oregon
Department of Transportation (ODOT) on transportation issues.
Ms. Hansen explained that the role of the Planning Commission was to provide a
recommendation to the City Council to approve, approve with modifications, or deny the three
applications.
Referring to the agenda item summary included in the agenda packet, Ms. Hansen reviewed the
three criteria, noting that the April 17, 2007 staff report would address each of the criteria in
detail:
• Eugene Code (EC) 9.7730(3) Criteria for Approval of Metro Plan Amendments.
• EC 9.8424 Refinement Plan Amendment Approval Criteria.
• EC 9.8865 Zone Change Approval Criteria.
Ms. Hansen stated that criteria EC 9.8865(4) and EC9.8865 (5) were not applicable to this
process.
Goal 12 Transportation: Ms. Hansen offered an orientation of Goal 12 transportation issues.
She drew the attention of commissioners to the map. She added detailed information on
transportation issues would be included in the April 17, 2007 staff report. She said Goal 12 was
implemented through the Transportation Planning Rule (TPR) as defined in the Oregon
Administrative Rules (OAR) 660-012-0060, a copy of which had been provided in the agenda
packet. She reviewed the TPR.
Ms. Hansen responded to questions from commissioners.
Question: What was the planning period?
Answer: The planning period used in the Transportation Impact Analysis (TIA) submitted by the
applicant was 2025.
Q: What was the maximum volume to capacity ratio?
A: On Beltline, a state facility, volume to capacity ratio was the standard of measurement used,
with the current maximum being .80.
Q: Did the City of Eugene agree with the nine facilities identified as Significantly Affected
Facilities?
A: Yes.
MINUTES—Eugene Planning Commission April 9, 2007 Page 2
Q: Were the Delta Highway/Goodpasture Road, and Beltline Road/Coburg Road interchanges
evaluated?
A: The scoping of the TIA did not look at the Goodpasture interchange. Lane County had not
felt it needed to be evaluated because it had auxiliary lanes between Beltline Road and
Goodpasture that assisted with weaving maneuvers. The county did include the interchange at
Valley River Drive, which was included in the TIA. There were no performance mobility issues
on Beltline Road east of Delta Highway, thus it not evaluated. Additionally, Crescent and Gilham
Road, as well as Gilham Road and Ayres Road were evaluated by the City of Eugene. The
Beltline Road and Coburg Road intersection was not evaluated. The City of Eugene, Lane County
and ODOT worked together on scoping the TIA. While the map illustrated the significant
intersections areas that were studied, the scope of the TIA was broader.
Q: What plans were used as resources in developing the TPR?
A: In addition to the ODOT Oregon Highway Plan and City of Eugene TransPlan, the Regional
Transportation (TRP), although not in a way that would make it a Transportation System Plan
(TSP) for purposes of this plan, was referenced in the TPR.
Q: Various planning documents from different agencies and jurisdictions contained different
planning periods. How was the 2025 date selected?
A: Because different planning documents and planning periods impacted the project, it was felt
best to select and apply one for consistency across the project.
Q: Did the Metro Plan contain performance standards for transportation facilities?
A: The Metro Plan adopted TransPlan performance standards for transportation facilities.
Q: How valid was the TransPlan work since the West Eugene Parkway (WEP) project had been
dropped. Was additional capacity for Beltline Road considered for the applicant’s project in light
of the WEP change?
A: The applicant did have to address the WEP because it was in the existing plan. The regional
transportation model completed for TransPlan included scenarios with and without the WEP, and
it did show that the volumes on Beltline Road would be higher without the WEP. The
transportation planning study for the proposed project used the model with the WEP. In the
applicant’s analysis, they needed to assume everything that was planned in TransPlan, including
the WEP, would be in place, thus producing somewhat of a disconnect.
Q: What was TSP?
A: Every community was required by the state to have a Transportation System Plan. Eugene’s
TSP was TransPlan.
Q: As the OAR that implemented Goal 12, was the TPR the only thing that implemented Goal
12, or was there other text in the goal that may be pertinent to the application?
A: Although the TPR was a large document, staff had identified the elements of the TPR that
were pertinent for the application and the commission’s consideration.
MINUTES—Eugene Planning Commission April 9, 2007 Page 3
Q: In terms of Goal 12 how did the TPR relate to existing policies such as the Metro Plan,
Willakenzie Refinement Plan pertaining to streets and traffic?
A: TPR required local jurisdictions and the state to adopt their transportation system plans, and
established the metropolitan planning organization. TransPlan was developed to be consistent
with the TPR.
Q: The Willakenzie planning team had not anticipated a TPR when policies for the Willakenzie
Area Plan were developed. If there were policies in the Willakenzie Area Plan that addressed
traffic, how did they apply against the TPR?
A: The Plan policies applied more to TransPlan rather than TPR directly. The refinement plans
were required to be consistent with TransPlan. Although TPRs and TransPlan changed over time,
the connections were more likely to tie to TransPlan.
Mitigation of Impacts: Ms. Hansen stated the applicant had identified significant impacts, they
would need to show how they would mitigate those impacts. Referring to the TPR OAR text in
the staff note, section (3)(a) through (3)(e), Ms. Hansen said it was important to note they were
only applicable for facilities currently performing above the acceptable volume to capacity
performance standard, i.e., above .80. The only facilities that had been identified as currently
performing worse than .80 were along Beltline Road. This would require the applicant to show
that they met the (3)(a)-(e) criteria. Ms. Hansen reviewed the applicable mitigations illustrated on
the map as well as information provided in the binder.
Q: Do improvements need to be in place before a major development could occur?
A: Prior litigation resulted in clarification that mitigation needed to be completed prior to
development.
Q: Was ODOT scheduled to conduct a corridor study of Beltline Road from Coburg Road to
West 11th Avenue? Would fixes be proposed and how would they impact the current mitigation
efforts.
A: A study identified in TransPlan was scheduled for 2009. The City of Eugene, Lane County
and ODOT had collaborated to minimize “throw away” improvements, with the intent that
interim fixes would not preclude larger projects.
Project Overview: Ms. Hansen said the property extended outside of the UGB. Only the
portion inside of the UGB was subject to the plan amendment.
Q: Although the site was privately owned, how was it designated parks and open space?
A: There were other private facilities designated parks and open space throughout the City.
Historically the designation had been placed on the subject property in recognition of the golf
course.
Q: Did we have current land use code regarding hospital citing?
A: No. When the City of Eugene adopted changes to the code several years ago, those changes
were appealed to the Land Use Board of Appeals (LUBA). LUBA remanded the issue to the
City, and the City had not yet responded. Thus, the prior code was the existing code. Within the
MINUTES—Eugene Planning Commission April 9, 2007 Page 4
C-2, community commercial zone, a hospital would be allowed with a conditional use permit
(CUP).
Planning Commission Review Schedule: Staff and commissioners reviewed the public hearing
and deliberation logistics and schedule for the application. It was agreed that the public hearing
would be continued on May 1, 2007 if it was not possible to hear all of the testimony on April 24.
Decisions regarding establishment of a comment period and keeping the record open would be
determined at the public hearing.
II. ITEMS FROM COMMISSION AND STAFF
A. Other Items from Staff
Mr. Nystrom said information regarding the minor code amendment process was forthcoming.
Staff was working with the consultant to develop a project timeline and citizen involvement
process.
Mr. Nystrom reviewed the commission’s April schedule, noting April 26, 2007 was being held
for a possible appeal hearing.
B. Other Items from Commission
Mr. Carroll reported he attended the River Road forum on April 3, 2007. Staff was working on
the next steps and there was community interest in moving forward. Ms. Gardner reported
planning staff had met with staff from the TGM grant office and negotiated an agreement to keep
the grant funding available after the original June 30, 2007 deadline.
Mr. Carroll reported the final meeting of the advisory committee to City Council on the Ballot
Measure 37 givings tax was held on April 6, 2007. The final report would be released in the near
future.
Mr. Duncan adjourned the Planning Commission meeting at 1:25 p.m.
(Recorded by Linda Henry)
m:\2007\planning and development department\planning division\planning commission\pc70409.doc
MINUTES—Eugene Planning Commission April 9, 2007 Page 5
Agenda
AGENDA
EUGENE PLANNING COMMISSION
Atrium Building, Sloat Room, 99 West 10th Avenue, Eugene, OR 97401
Phone: (541) 682-5481 Web site: www.eugene-or.gov
The Eugene Planning Commission welcomes your interest in these agenda items. Feel free to come and go
as you please at any of the meetings. This meeting location is wheelchair-accessible. For the hearing
impaired, FM assistive-listening devices are available or an interpreter can be provided with 48 hours notice
prior to the meeting. Spanish-language interpretation will also be provided with 48 hours notice. To
arrange for these services, contact the receptionist at 682-5481. Telecommunications devices for deaf
assistance are available at 682-5119.
MONDAY, APRIL 9, 2007 – REGULAR MEETING
(11:30 a.m.)
11:30 a.m. PUBLIC COMMENT
The Planning Commission reserves 10 minutes at the beginning of this meeting for
public comment. The public may comment on any matter, except for items
scheduled for public hearing or public hearing items for which the record has
already closed. Generally, the time limit for public comment is three minutes;
however, the Planning Commission reserves the option to reduce the time allowed
each speaker based on the number of people requesting to speak.
11:40 a.m. I. STUDY SESSION: PLAN AMENDMENTS/ZONE CHANGE PROCESS
AND CRITERIA (MCKENZIE-WILLAMETTE)
Staff: Alissa Hansen, 682-5508
1:15 p.m. II. ITEMS FROM COMMISSION AND STAFF
A. Other Items from Staff
B. Other Items from Commission
Commissioners: Jon Belcher, Phillip Carroll, Rick Duncan, President, Randy Hledik, Vice
President, Ann Kneeland, John Lawless, Anthony McCown
Ex officio member: Mike Sullivan, Division Manager, Community Development
Get email alerts for Eugene
A daily email when new agendas and minutes are posted.