Board of Zoning Appeals
Regular MeetingFalls Church, VA · August 13, 2020
Minutes
1
BOARD OF ZONING APPEALS MEETING AGENDA
2
VIRTUAL PUBLIC HEARING
3
Thursday, August 13, 2020
4
7:30 p.m.
5
6
1. CALL TO ORDER
7
MR. BOYLE: I believe the recording may not have been
8
working at the very beginning, so what I'd like to do is simply
9
restate that this is the Special Meeting for the Board of Zoning
10
Appeals for August 13, 2020.
11
12
2. ROLL CALL
13
MR. BOYLE: Members present are David Calabrese, Roy
14
Jones, Keith Bartlett, Peter Kien. Absent are Dale Eppler and
15
John Misleh. Zoning Administrator is present. Deputy Zoning
16
Administrator and BZA Secretary Akida Rouzi is absent. And I
17
think that catches us up.
18
And just for the recording secretary, when she hears
19
this, for the record, insert this at the beginning for your
20
notes.
21
22
3. PETITIONS
23
4. OLD BUSINESS
24
25
5. NEW BUSINESS
26
a. Variance application V1616-20 by Jeff and Katie
27
Skalka, applicant and owner, for a variance to Section 48-238,
28
to allow 27.4% lot coverage instead of 25% maximum permitted by
29
Code, and 37.2% impervious lot coverage instead of 35% maximum
30
permitted by Code, for the purpose of constructing a front porch
31
on premises known as 205 Patterson Street, RPC #52-113-008 of
32
the Falls Church Real Property Records, zoned R-1A, Low Density
33
Residential.
34
(Continuing)
35
MR. BOYLE: In their presentation you should have a
36
multi-page presentation from the applicants that shows a cover
37
letter detailing what they feel their hardship is and scrolling
38
through, several graphics showing the proposed footprint shot
39
from their grading plan, and a depiction of what they're hoping
40
to do.
41
This Board has heard applications for increases in lot
42
coverage before and typically that's when the lot is substandard
43
for area and a consideration is given to what would they have
44
been allowed had the lot been the required minimum of 11,250.
45
And they address that in their cover letter.
46
The Board should have three emails sent yesterday and
47
today from neighbors. One in opposition, I think a second one
48
that was concerned about mitigating, and a third in favor.
49
What I think what the Board should consider is the
50
concerns raised by the neighbors deal with water runoff. And
51
it's something I think we struggle with in Zoning and in the
52
functions of this Board is that the Board typically and Zoning
53
typically is not concerned with where the water goes but are the
54
percentages being met.
55
And there is precedent in other considerations such as
56
special use permits where if a problem is created by granting
57
the variance or a special use permit, if that problem can be
58
mitigated by the imposition of conditions, then it can be
59
approved contingent on those conditions being applied.
60
And if the Board so chose to approve this variance
61
tonight, this project, these building plans and the accompanying
62
grading plan, are headed to the engineers and building
63
inspection for an extensive review and a grading plan review.
64
At that point the Board could condition an approval if
65
it chose, on whatever those reviewers felt would mitigate the
66
concerns of the neighbors.
67
So I don't want the Board -- and the reason I say this
68
is I don't want the Board to feel that in your expertise you
69
should feel obligated to determine how to mitigate the water
70
runoff concerns of the neighbors. That is something that can be
71
dealt with by the engineers and it's part of their routine
72
reviews.
73
So personally in Zoning, we don't have an answer for
74
questions like that. So don't be surprised if you find yourself
75
in a similar situation: What do we do to address these
76
neighbors' concerns. That can be handled, if the Board chooses,
77
in the following reviews by the engineers and the building
78
inspectors. They do have ways to address these things.
79
And they don't have to approve it at their level of
80
review. The neighbors will be invited to that conversation as
81
well, particularly the grading plan. If they're not satisfied
82
with the mitigation, then that staff, that group of staff that
83
reviews, in their expertise can decide not to approve it.
84
So by all means don't feel that you need to be an
85
expert in how to mitigate water runoff this evening. The focus
86
87
is in, is it a reasonable hardship based on the application that
88
you have in front of you to increase the percentages for
89
building coverage and impervious coverage with whatever
90
conditions that you feel are appropriate.
91
So I did feel that a little bit of background
92
explanation was appropriate for where this process will lead to
93
assist the Board in their deliberation this evening.
94
So with that, I'll defer to the applicants for their
95
presentation.
96
MR. JONES: Thank you, Mr. Boyle.
97
MS. SKALKA: Thank you, John. That was very helpful.
98
It was a very arduous process already to get some of these plans
99
together so forgive me if I stumble and don't say numbers quite
100
the way that they're supposed to be. I'm an educator by trade
101
but there's so many numbers so thank you for your patience as we
102
have obviously never done this before.
103
So, it came to our attention that our lot was
104
undersized and that if our lot were the standard size of 11,250
105
square feet, we would be afforded about 254 square feet of
106
additional coverage and about 355 square feet of additional
107
impervious area.
108
So when we applied for this covered area, we made sure
109
to design it within that constraint so that our percentages
110
based on an 11,250 site would still be within the 25 percent and
111
the 35 percent.
112
So we're hoping that you take a look at the numbers
113
difference and realize that we are right up at that minimum or
114
that maximum rather but we aren't a minimum lot size. So we're
115
hoping that given that hardship you'll afford us this extra
116
space on our lot.
117
I could rattle off all the numbers. I think that
118
would just sound like numbers soup. We understand that this is
119
our preference to build this way and that's not your
120
consideration. We understand that there will be water runoff
121
and that we have already contracted engineers at LDC. They have
122
an extensive grading plan that's already put into review. I
123
think it's already paid for and being reviewed right now.
124
And it's an extensive water mitigation, just so you
125
know, not that you need to be experts as John said, but the goal
126
is to be equal to or less than our current. And right now the
127
plan that we have in place for review is equal to. So we're
128
looking to not increase hardships to our neighbors because I
129
know that is something that you would be concerned about.
130
I guess I'm mostly interested in hearing what your
131
questions are because I feel like, you know, it's a very basic
132
construction. It's not laying on the ground. We have the
133
ability to mitigate with conditions anything that you would
134
propose. It's a very standard back porch actually, I know that
135
was a typo. We're hoping you don't make us put it on the front
136
if you approve it tonight.
137
So, I think we're ready to field questions if that's
138
how we proceed.
139
MR. JONES: Thank you very much for your presentation.
140
With that, I think, if that sort of concludes your
141
presentation, we'll start with questions from the Board.
142
If my colleagues don't mind, I'd like to lead off with
143
a question about your description of the hardship that would
144
sort of ensue by being within the current parameters of the
145
Code.
146
The Code, one of the things we look for besides any
147
potential negative impact on your neighbors which I think we can
148
touch on a little bit later, is whether the strict application
149
of the Code creates an un -- I forget the term, I think it's
150
unreasonable restriction on the utilization of your property.
151
So, for me, I think my first question, if my
152
colleagues would indulge me, is if you could speak a little bit
153
about how the hardship, how staying within the current Code is
154
sort of unreasonably restricting on your ability to enjoy your
155
property.
156
MS. SKALKA: It's an excellent question actually. So
157
our house is actually designed with what I'm calling "door to
158
nowhere" right now. The home was always intended for and
159
initial grading plan indicates the presence of a deck that was
160
not previously built.
161
So right now we have an entire section of our property
162
that we can't access through the doors to our house because it
163
stands six feet above the sewer, above the ground.
164
So that's one. I think that's kind of glaring as
165
we're in our house. And the way that the lot is designed, is
166
there's a very obvious section that should have a deck, or
167
something built on to the house there.
168
The majority of the rest of our property is landscaped
169
that we've improved upon even since the last grading plan so
170
this would be kind of the only area where we could enjoy and
171
being outside.
172
MR. JONES: Two of your neighbors submitted letters I
173
believe with concern about the water runoff which is sort of a
174
separate issue that Mr. Boyle touched upon.
175
Did any of your other neighbors indicate any concerns
176
with the actual building of the structure itself; i.e., it would
177
encroach upon a view or anywhere else? Did your neighbors sort
178
of indicate any other concerns other than just the water runoff
179
issue?
180
MS. SKALKA: Not to our knowledge. The house is set
181
back from the property of the two people that did write letters.
182
And we have -- when we built the privacy fence when we first
183
bought the property, we consulted them and made sure that they
184
were cool with what we put up.
185
That was a very smooth process. Everyone was very
186
glad to see us tear down the chain link fence and put up some
187
nice landscaping and fence and actually improve upon some of the
188
drainage at that point, which the current drainage plan does not
189
-- or the grading plan does not indicate any improvements that
190
we've done since then.
191
No, not that I know of. The way that the house is
192
structured, we're actually, if you look at the plans, just kind
193
of filling in an "L" to make the house a true box. Like I said,
194
it was always designed to have a deck that was within kind of a
195
contiguous rectangle. So it's not going to the side or going
196
deep into the property at all.
197
MR. JONES: Did you try to talk to any of your
198
neighbors about your structure? I know there's a notice
199
requirement. But did you try to engage them and say, Hey,
200
here's what we're doing?
201
MS. SKALKA: Yeah. Jeff, you talked to Jason a couple
202
of times.
203
MR. SKALKA: Mentioned it to Jason, who's directly
204
behind us. And I think that the understandable concern is
205
exactly what those letters written upon which is the drainage.
206
And prior to even having conversation with neighbors
207
or even John Boyle and the engineering firm that we engaged, we
208
thought of the idea of how do we be certain to mitigate any
209
potential additional runoff which would be inevitable.
210
And through the conversation with the engineering
211
firm, was when we started discussing what that could look like
212
and certainly we're very much in favor of doing so, for not only
213
environmental reasons but, of course, also being certain to keep
214
the neighbors and the City happy.
215
MS. SKALKA: Yeah, so, in short, I think, no, it's not
216
a higher roof line, it's not an extended footprint. In any of
217
our conversations, it's almost always has come back to water.
218
MR. JONES: Thank you. And my last question, I don't
219
want to monopolize all the time, I'll turn it over to my
220
colleagues, could you speak a little bit more to these "doors to
221
nowhere", and how that sort of creates a hardship on your
222
current living situation. Is this a situation where you open
223
the back door and you've got a drop-down or if you could speak a
224
little bit more to the "doors to nowhere".
225
MS. SKALKA: Yeah, yeah, that's exactly right. So
226
there's double sliding glass doors that currently have
227
construction tape across them so that nobody could fall out of
228
the house. You would fall down about six feet.
229
MR. JONES: Okay. Thank you. I appreciate that very
230
much.
231
That answers my questions so with that, I will happily
232
turn it over to my colleagues.
233
MR. CALABRESE: If I could ask a question.
234
So, you mentioned that you would be able to do work to
235
address additional runoff. But it appears from your neighbors'
236
letter that there's a significant problem now with runoff. So
237
if you could answer or address what would appear to be a bad
238
situation that could be getting worse with this add-on. Could
239
you address that.
240
MS. SKALKA: Yeah. Thank you for mentioning that.
241
So in reviewing Scott -- let me just make sure I get
242
the names right, his letter did mention that in the process of
243
building the house, and you should know that we did not contract
244
this particular house. It was a set house that we bought I
245
think several months after it sat on the market in 2018. We
246
bought it the last work day of 2018 and moved in in January of
247
2019.
248
And if you look at a lot of Scott's pictures, much of
249
that damage happened prior to us moving in and during the
250
construction process. I don't know how much of that was, that
251
they cleared the lot and let it sit there, that they didn't take
252
proper mitigation protocols when they were building the house.
253
We had noticed that there could be potential -- when
254
we took up the fence, that there could be potential for us to
255
disturb what were some natural blockages and filters, just weeds
256
and brush and old chain link fence.
257
So when we put in the fence, and we had talked about
258
it with him then, we put in extra landscaping and moved some of
259
the drainage around.
260
So I'm not entirely sure that some of what he's citing
261
is very current. Even the picture of 2020, it's not clear that
262
that damage occurred in 2020.
263
So, I guess I certainly wouldn't want to increase his
264
hardship but I'm not convinced that that's something that we
265
should necessarily be responsible for at this time.
266
And if our engineers come back to us and say that we
267
are putting off too much water already, then as I said before,
268
our goal is to be at what we're at or less. And that written in
269
as a special condition would be acceptable to us for sure.
270
MR. CALABRESE: Well, I think he's saying that it's
271
now, that the problem is now. That's what I got from his letter
272
and the other neighbor also appears to have a similar concern.
273
So you mentioned that the hardship of not building the
274
deck or the outside porch. Now, typically when we hear these
275
hardship requests, they're when you're building, you redesign
276
the house, you're adding another room, you're adding another
277
level. We don't typically hear it in terms of a hardship that
278
you cannot build a screened porch.
279
The question I would have is, well, maybe there's this
280
door that's non-functional. What about another design that
281
would keep you within a smaller design, that would keep you
282
within the numbers.
283
MS. SKALKA: So, I think currently we do not have
284
enough square footage to do anything that would be considered an
285
acceptable design. It wouldn't be worth constructing anything,
286
you could only fit a chair, for instance.
287
We're suggesting 15 by 17 feet, which if we add it's
288
still within the percentage of the adjusted lot size. And
289
actually to fill that entire space would be -- I think it's only
290
just filling in this corner.
291
So,I don't know, do you want to add something to that?
292
So, I agree with you that it feels like a preference or an extra
293
and the house was designed to have something there. It just
294
was not previously built prior to our buying the house.
295
MR. SKALKA: I agree and I think that -- I don't want
296
to harp on this but the design that we would look to have
297
approved would certainly require an engineer and the City's
298
approval of a mitigation tool that would ensure that there is no
299
additional runoff.
300
MR. CALABRESE: Right. And I'll just finish up with
301
kind of repeating my first question. You mentioned again,
302
additional runoff. It sounds like there's some very serious
303
concerns from some neighbors who appear to be suffering from a
304
current runoff.
305
So when we look at a hardship and looking at the
306
equities here, unless there's more information, it appears that
307
we're talking about an existing problem that we're going to add
308
on to but then we're going to try to mitigate the added-on
309
problem.
310
I don't know how, if you already have a runoff
311
problem, it would seem to me that we should be mitigating that
312
first before we go to the next stage, building an additional
313
area that could exacerbate a situation.
314
So, I don't know if we have enough information but
315
these are very strong letters. Stronger than what we normally
316
receive from directly-affected neighbors.
317
So that's my only comment I think.
318
MS. SKALKA: I appreciate that.
319
I read Jason's letter definitely as a hasn't had any
320
problems recently. I definitely read Scott's feeling like he
321
has a current problem.
322
We have not heard any of that until just now.
323
MR. SKALKA: I talked with Jason and Jason's mentioned
324
it. And he also mentioned that after we planned it, the
325
multiple plans that seems to have -- I don't know if he would
326
say the word "resolve" but it would be close to that, if not
327
resolve.
328
MR. CALABRESE: Thank you.
329
MR. JONES: Thank you, Mr. Calabrese.
330
I'm not able to see any of my other colleagues, but,
331
Mr. Kien or Mr. Bartlett, do you have any questions for the
332
applicants?
333
MR. BARTLETT: Yes, I have a question related to your
334
reference to lot size and why that's relevant to your hardship.
335
You keep saying that if you had a lot that was 11,320
336
feet, then you'd be able to build this. But the Code requires,
337
based on my understanding, the Code requires whether or not
338
you're R-1A or R-1B to comply with the same building
339
restrictions as far as lot coverage and impervious surface, 25
340
or 35 as well. So whether or not you're R-1A or R-1B, you have
341
to comply with the same percentages.
342
I know you're listed as a R-1A and you bought it as a
343
R-1A. I'm trying to figure out why we should create this
344
345
precedent to allow people to exceed strict adherence to the Code
346
based on that.
347
MS. SKALKA: It's my understanding that it wouldn't be
348
creating a precedent, that this is a hardship that has been
349
mentioned before when people want to exceed their percentage
350
based on an undersized lot.
351
MR. BARTLETT: Are you claiming your lot's undersized?
352
MS. SKALKA: Yes. Yes. A minimum standard lot for
353
our zone is 11,250 square feet and our lot is 10,234 square
354
feet.
355
MR. BARTLETT: Just to make sure I'm understanding what
356
you're saying, because your lot is below 11,000, that equates to
357
a hardship?
358
MS. SKALKA: Yes. It does not meet the minimum
359
standard for the zone.
360
MR. SKALKA: I don't know if there is any information
361
that Mr. Boyle has that would confirm that we're not setting a
362
precedent or if that's not appropriate for this time, we'll skip
363
that.
364
MR. BOYLE: I think the Board has considered lack of
365
square footage based on what the Code requires in the past,
366
maybe not for impervious and pervious issues. Staff does
367
consider a lack of square footage as substandard and then
368
there's a number of things that cascade from that. It's
369
potential for the height of the building or setbacks to be
370
reduced.
371
So staff would consider this a substandard lot.
372
MR. BARTLETT: So Mr. Calabrese asked a question
373
earlier about design alternatives. Did you think of installing
374
a different structure if you want to use this area that might
375
not lead to this issue?
376
MS. SKALKA: This is definitely the design that we'd
377
like to consider at this time. If our variance is not granted,
378
I think we'll have to go back and look at what our options are.
379
At the beginning of this process we looked at various
380
restructures that would stay within the percentage. There's a
381
system called the Equinox that's a louvered roof that I think
382
some people have used in the past. We were unable to find a
383
contractor that was willing to install it in Falls Church City,
384
just couldn't find anybody that had the product and had the
385
license to work in the City.
386
That's when it kind of came to our attention that we
387
could apply for a variance based on the substandard lot.
388
So, yeah, we did look at many different designs for a
389
roof and were unable to find anything other than a traditional
390
design, so.
391
MR. JONES: Mr. Boyle, can I ask you a question.
392
If this was a standard size lot, 11,250 square feet,
393
and the applicant had this exact same application package, would
394
the design as presented be within Code if this was a standard
395
size lot, 11,250 square feet?
396
MR. BOYLE: Let me do some quick math here. 11,250
397
times 35 percent is 3937.
398
Applicants, do you have your numbers on what your --
399
MS. SKALKA: Yes. Yeah. Would you like us
400
to --
401
MR. BOYLE: Yes.
402
MS. SKALKA: It's in the cover letter. Somewhere
403
toward the bottom of the first paragraph I believe. I don't
404
have it in front of me.
405
It says if our project were on a lot of 11,250 square
406
feet, we would be within the coverage maximum of 25 percent at
407
24.9 percent with 2808 square feet and we would be below the 35
408
percent impervious surface coverage of 3809.
409
So, yes, is our answer anyway. And like I said, the
410
math was a little much. I didn't want to rattle off all those
411
numbers but, yes, it would be within a standard lot.
412
MR. BOYLE: Yes, I'd agree with that point. It
413
appears what they're proposing would be by right if they had the
414
square footage.
415
The lot is shy 5 feet in width. It's 70. This zone,
416
175. And I think to make the math work it would have to be 150
417
feet deep. So they're missing on depth and width and that's
418
where the shortfall is.
419
So I think what they're proposing would be by right if
420
they had the square footage.
421
MR. JONES: Thank you.
422
Mr. Bartlett, any questions?
423
(No response.)
424
MR. JONES: Mr. Kien?
425
MR. KIEN: None for me.
426
MR. CALABRESE: If I could go back, so back to the
427
question about alternative design.
428
When you were answering the previous question, you
429
mentioned, you focused on the roof. Is this about the roof or
430
is this about the size of the porch?
431
MS. SKALKA: I think it's mostly about the roof,
432
increasing our coverage.
433
MR. CALABRESE: But the roof design you said was the
434
problem.
435
MS. SKALKA: Well, yes, it would be a standard roof so
436
it would be considered coverage on the lot versus something that
437
might be a pergola or a louvered system.
438
MR. BOYLE: I might be able to assist with that, Mr.
439
Chair.
440
Our Code defines a building as a roof supported by
441
columns or walls. So even something that is built as a deck
442
with planks that in and of itself were pervious, if a roof goes
443
over it, then the Code defines it as a building. Then it's
444
capped for both the building coverage of 25 and the impervious
445
coverage of 35. So that's where the roof plays a role in this
446
conversation.
447
MR. CALABRESE: Right. But I guess the question I had
448
was when we were asking the question about alternative designs,
449
now there was a comment made that you could go back and look at
450
alternative designs. But I thought what you were saying though
451
is that the problem isn't the size, it's the type of roof that
452
is the problem, finding the right type of contractor to build
453
that type of roof, was not available or --
454
MR. BOYLE: I might be able to speak to that as well.
455
There is a type of roof where the surface rotates 90
456
degrees. Instead of being a flat surface roof it rotates and
457
becomes a pergola. And currently in our Code, the Code doesn't
458
anticipate that type of design. So I like to phrase it as the
459
"pergola police" will not go out and check and see if your roof
460
is flat or are the slats vertical.
461
So that type of design is not defined as a roof, so
462
it's not then defined as a building.
463
And what the applicant was referring to, is there is a
464
design out there that rotates its panels. So at one moment it's
465
maybe flat, the next moment it's rotated to let sun and water
466
come through.
467
We do not define that as a roof or coverage at this
468
time. Code change in the future might change that and I think
469
her point was that they couldn't find a contractor of that type
470
of product that would come in and do the work here.
471
MR. CALABRESE: Okay. My question was more on the
472
hardship side. Are we talking about a hardship because of the
473
design, a preferred design that's not available, or just
474
difficult design, or are we talking about something that's
475
essential, that has to be this type of roof?
476
MR. BARTLETT: Or that it has to have a roof at all.
477
MR. CALABRESE: Right, right.
478
MR. BARTLETT: Because if this was a deck, we wouldn't
479
be having this conversation.
480
MR. CALABRESE: Right.
481
MR. BARTLETT: And I feel for the applicant because
482
the builder maxed out impervious and covered surface based on
483
percentages and then they left it vacant space here for the
484
potential owners to resolve.
485
I do empathize.
486
MR. CALABRESE: Yeah, I agree.
487
MS. SKALKA: The thing that we're willing to -- yes,
488
thank you. The builder was not as considerate as he could have
489
been.
490
And at the same time, the focus that we want to stick
491
with during this application process is the Code itself and what
492
conditions we need to meet to achieve a variance and the
493
hardship of an undersized lot being something that people cite
494
in other cases and that the design that we're asking for still
495
puts us under the maximum if we consider the difference between
496
our substandard lot and a standard lot.
497
MR. CALABRESE: Yes. I would be interested in hearing
498
more about the precedential value of undersize lots being the
499
source of a hardship. I mean, people buy the lots knowing that.
500
And excuse me for saying this, but you bought it
501
knowing it was a substandard or undersize lot.
502
MR. BARTLETT: One of my initial reactions to the
503
question is, then we wouldn't have percentages. We would just
504
have a fixed number of buildable area that if your lot was
505
10,000, then you could build 3500 square feet, and 2500 square
506
feet, instead of a percentage which is for all residential
507
zoning structures because of the variability of these lots.
508
MR. CALABRESE: Right.
509
MS. SKALKA: My understanding that the percentages are
510
specifically though to mitigate potential environmental hazard.
511
And our desire is not to increase any environmental hardships to
512
ourselves or our neighbors and our ultimate design would be
513
taking those things into consideration.
514
So we're hoping that you'll hear our one neighbor that
515
says that we do care very deeply about the City and we do want
516
everyone to feel as included in the process as possible and to
517
ultimately be much better off. I mean, this project could very
518
well solve a lot of problems that this neighbor Scott is having.
519
It's interesting to me, you know, I understand and I
520
agree that his design to be a percentage and we're hoping that
521
you'll grant the variance based on the difference.
522
MR. JONES: Okay. If there's no more questions for
523
the applicants, we will close the presentation.
524
Thank you very much for the amount of work you've put
525
into this. And we will sort of confer -- I'm sorry, are you
526
all done with your presentation?
527
MR. SKALKA: I believe so.
528
MS. SKALKA: Unless there are more questions, yes.
529
MR. BOYLE: Mr. Chair, a point if I could.
530
MR. JONES: Absolutely.
531
MR. BOYLE: I think with four or five members, I
532
neglected to point out that we should give them that option of
533
continuing for a full Board. We appreciate the Board making
534
time in August for a special meeting.
535
Secondly I see, on my screen anyway, that we have two
536
or more guests that are observing.
537
MR. JONES: Okay.
538
MR. BOYLE: Perhaps we should give them an opportunity
539
to speak. I did not notice that during the public conversation.
540
MR. JONES: Okay.
541
MR. BOYLE: Number of Board plus the public who would
542
like to speak, if possible.
543
MR. JONES: Great. Thank you for pointing that out.
544
I guess on my screen, I wasn't able to see that we had
545
any members of the public, so I apologize.
546
If you would like to speak about this variance
547
application, if you could please state your name clearly for the
548
record and then once you've stated your name, we will swear you
549
in.
550
MS. SAVITZ: Hi, can you hear me?
551
MR. JONES: Yes.
552
MS. SAVITZ: This is Natalya and Scott Savitz. We
553
live at 212 South West Street. We own that property and we're
554
the neighbors of the 205 Patterson Street, like we're
555
kitty-corner to that property.
556
MR. JONES: Okay. Thank you.
557
Is there any other members of the public who are going
558
to speak on this application?
559
(No response.)
560
MR. JONES: Not hearing or seeing anyone else, Mr.
561
Boyle, if you see any other members of the public, please let me
562
know. I'm unable to see them from my screen.
563
Ma'am, would you and your husband raise your right
564
hand and swear to tell the whole truth.
565
MS. SAVITZ: Yes, we do.
566
MR. SAVITZ: Yes.
567
MR. JONES: Thank you.
568
So we understand that you wrote a letter to this
569
Board about this application and if you have anything that you
570
would like to say, I think we would appreciate hearing it.
571
MS. SAVITZ: Yes. We bought our house in 2012. At
572
that time the 205 Patterson Street had a relatively small house
573
with a small shed. We didn't have any problems at that time.
574
We didn't have any flooding on our lot.
575
After their house was gutted and the new structures
576
were built, we started getting periodic flooding on our property
577
which resulted in pretty much standing water in the back and the
578
side of our property and also damage to our finished basement.
579
So we're very concerned about the proposal to increase
580
the variance, even the proposals for them to just build the deck
581
because that means that they are increasing impermeable surface.
582
There will be no planting under that deck to absorb the water so
583
the water will be running downhill right to our property and
584
creating more damage.
585
I feel for the Skulkas. I understand they would like
586
to have a deck but in this case it's creating damage to the
587
surrounding properties which is not fair and is not desirable
588
for anyone.
589
Would you like to add anything?
590
MR. JONES: When you say that it's creating damage --
591
MS. SAVITZ: Our letter to show the damage, both the
592
outside damage, how the water was standing there, as well as the
593
inside damage that we've incurred.
594
We've already spent thousands of dollars trying to
595
mitigate that and we still are looking at 20,000 or more to fix
596
what was already broken because of this new structure.
597
MR. JONES: And when you say the damage to your
598
property, this is a recent phenomena, it started I guess in
599
20 --
600
MS. SAVITZ: The end of 2018, yes.
601
MR. JONES: And it still continues currently.
602
MS. SAVITZ: Yes.
603
MR. JONES: Thank you.
604
Any questions from the Board for the presenter?
605
MR. KIEN: I have one.
606
So your property, the northeast corner of your
607
property abuts the southwest corner of the Skulkas' property, is
608
that accurate?
609
MS. SAVITZ: Yes.
610
MR. KIEN: And the water flow from what I can tell
611
from the topographical maps basically flows kind of due south,
612
from corner to corner on your lot; would that be accurate to
613
say, that it flows from the northeast corner to the southwest
614
corner?
615
MS. SAVITZ: Yes. Because we have a retaining wall so
616
that kind of moves the water down to the south side of our
617
property, yes.
618
MR. KIEN: Between your property and where your
619
property joins the Skulka property, can you describe what that
620
looks like. Is it green open space or is it other space? I'm
621
trying to get a sense of where the water was standing in the
622
pictures that you were sending because I can't see them in
623
regards to the wall.
624
MS. SAVITZ: Right. So the back of our property is a
625
garden. There are a lot of trees and vegetation there. Where
626
627
the water was standing is on the south side of our property, so
628
that's on the side of the building, not in the back of the
629
building for the most part. And that's grass and there's some
630
vegetation there as well.
631
MR. KIEN: Okay. Thank you.
632
MR. CALABRESE: You say you had some professional
633
remediation. Have those individuals posited any opinion on
634
where the water is coming from?
635
MS. SAVITZ: Basically they said it's coming from the
636
neighbors. It's running downhill and then accumulating on our
637
property.
638
MR. CALABRESE: Neighbors referring to?
639
MS. SAVITZ: The Skulkas.
640
MR. CALABRESE: Okay.
641
MR. JONES: Okay. Any additional comments?
642
MR. CALABRESE: Do we have a letter from the Becks,
643
David and Jennifer Beck? There was no letter from them, was
644
there?
645
MR. BOYLE: No, sir.
646
MR. JONES: I don't believe so.
647
Mr. Boyle, there are no more members of the public
648
that want to opine or express an opinion on this application, is
649
that correct?
650
MR. BOYLE: I think that's correct. They show up as
651
guests, so all we can do is poll them and see if they're willing
652
to speak. I think you've done that.
653
MR. JONES: I appreciate that. I don't know if my
654
technical limitations but I can't see anybody, so that's
655
helpful. Thank you very much.
656
Now that we've heard from the members of the public
657
and the applicants, we'll close the presentation and the
658
comments and now we'll open it up to the Board to discuss among
659
themselves any thoughts or comments or opinions.
660
MR. CALABRESE: I guess I'm concerned that it sounds
661
like we do have an existing problem unfortunately. And the
662
Savitz, it sounds like they are experiencing some pretty severe,
663
moderately severe water problems. And I think, well those,
664
that's up to the neighbors how they wish to address that.
665
But to me, that has to be resolved before you would
666
add on, you would go grant any exceptions to allow an expansion
667
of the impervious area which may be the problem now, the
668
expanded building.
669
So I'm just very concerned about again, as I
670
mentioned, making a bad situation worse.
671
MR. KIEN: So, John, I emailed you during this. Can
672
you pull that up and show the two pictures that I sent to you.
673
MR. BOYLE: Let's see. Who's speaking? I'm sorry.
674
MR. KIEN: I'm sorry, John. This is Peter.
675
MR. CALABRESE: And, John, my screen is frozen. Maybe
676
it's just me but I'm frozen here. If others can see, then maybe
677
it's okay.
678
MR. KIEN: So, David and other Board members, I shared
679
the same concern regards when I saw those pictures. So I
680
personally went to the property today and walked both streets to
681
try to see what we were dealing with here.
682
And much of this is topography-driven in that the
683
water naturally wants to flow from Patterson Street to the
684
southwest street due to elevation change. And it looks as
685
though the water wants to flow basically perfectly south which
686
would sheet across the applicant's yard towards the Savitz'
687
yard.
688
Where I'm struggling, I certainly understand the
689
mitigation factor for what the new build was. I'm struggling
690
somewhat with holding the Skalkas responsible for 100 percent
691
where their builder or their property 100 percent for the water
692
issues on the adjacent property based on the composition of that
693
property and what has been built there, which is from the
694
existing structure to the Skalkas' property is almost all
695
impervious area on the Savitz home and they're very much reliant
696
on the Skalkas' green space for their yard to keep water off
697
their property, which I don't know if that's a fair
698
responsibility to place on your neighbor. And I say that, just
699
saying I don't know if that's fair or not.
700
But it looks as though there's nothing to stop the
701
water to enter their property until it almost gets to the back
702
of their home due to the driveway and detached garage that is in
703
that northeast corner of their lot.
704
So I think there are contributing factors on both
705
properties and it would be hard to determine which one was
706
ultimately responsible.
707
MR. JONES: Okay.
708
MS. SAVITZ: Can I respond to that please?
709
So, our driveway and garage are on a different side of
710
the building than the one that's getting flooded. Getting
711
flooded is entirely where we have green area and the water is
712
going through our garden as well. So we're not expecting
713
Skulkas to take care of, absorb all of that water. We're
714
absorbing a lot of their water.
715
The driveway actually functions perfectly because it
716
just lets the water flow right on to South West Street. It's
717
the other side, the green side of our house that's actually a
718
problem.
719
MR. KIEN: So that's the lowest point on the property
720
there that's collecting the water at these times and that's
721
where the entry point is.
722
MS. SAVITZ: Yes. And furthermore, the damage is also
723
because the grading on the Skalkas' property changed when the
724
new house was built. The grading became much steeper. The
725
trees that were there were removed, so Skulkas' property was not
726
absorbing the water that they're generating, in addition to a
727
much bigger house.
728
So this all started, we owned our house for six years
729
with no problems. Then that building went up and we started
730
having problems. That's pretty much 100 percent their -- like
731
the builders.
732
MR. JONES: Okay. Mr. Kien, any other comments?
733
(No response.)
734
MR. JONES: And, Mr. Boyle, procedurally I think when
735
we close, I appreciate the public's input but I think my concern
736
is once we close it, are we still able to engage in additional
737
conversations with either the applicants or members of the
738
public?
739
MR. BOYLE: Mr. Chair, I did receive an email from a
740
neighbor that's trying to communicate and is not being heard.
741
I've suggested they try the instant message option on the lower
742
left.
743
But I think they must be the guest here. It looks
744
like their microphone is off. I'm seeing a guest, Mr. Bartlett,
745
a council member, and that's everyone accounted for.
746
So I'm not sure how to make contact. If that party
747
can send me an email, I could read their concerns.
748
I'll show you the email I received from Jason Hobbie,
749
variance application.
750
"We're watching the public hearing. We tried to
751
speak, we not able to. No one heard us."
752
So, they may be the guest shown on the screen. For
753
whatever reason, they're -- if they can hear us, you need to
754
turn your microphone on there or try the Instant Messenger
755
option over on the bottom left of the screen.
756
I'm troubled that they're not able to communicate.
757
Everyone else is accounted for.
758
MR. JONES: Okay. I want to make sure that members of
759
the public have the ability to either voice their concerns or
760
their support of the applicant. I'm a little concerned that a
761
member of the public is not able to do that.
762
MS. SKALKA: I see them typing right now.
763
MR. BOYLE: Yes. Can you see that?
764
Boy, in the future will we have stories to tell of
765
what we went through to have a public discourse. We had it
766
tough.
767
MR. CALABRESE: I can't -- maybe if you can read. For
768
some reason my screen is just frozen. I'm having some problem.
769
MR. BOYLE: Mr. Jason Hobbie is typing a message.
770
"Just clarifying that we are the owners of the Beck's
771
property shown on the plat. The current owners."
772
So on the -- looks like -- immediately behind.
773
So on the survey shown on the screen, the Hobbies are
774
the owners of the property indicated as Beck, directly behind.
775
MR. CALABRESE: So we have a letter from Mr. Hobbie,
776
right?
777
MR. BOYLE: Yes. Can everyone see what they're typing
778
or shall I read it?
779
MR. CALABRESE: I can't see it.
780
MR. BOYLE: They're the current owners directly
781
behind. "I am not sure what the current drainage discharge
782
point is currently on the Skalkas' property."
783
"Before they purchased the property I noticed that the
784
builder had routed everything to a point near the corner of
785
their lot with ours and the Savitzes. Routed all the drainage.
786
There was a corrugated black pipe discharging there. That
787
probably is contributing to the amount of water the Savitzes are
788
experiencing. If it is still there."
789
MR. JONES: Thank you, Mr. Hobbie.
790
Do you have any other comments or concern that you'd
791
like to type?
792
MR. BOYLE: He's typing.
793
He says he just wanted to provide clarification and
794
because a BZA member had asked about ownership.
795
So again, he's the owner of the property to the rear
796
on the document shown on the screen.
797
As staff, is anyone who could hear me satisfied that
798
they -- is anyone who could hear me not satisfied that they have
799
been able to make their positions known?
800
While we did have a glitch in the advertisement, the
801
public notice that went out, this particular item did have the
802
benefit of being advertised in the paper for two months plus two
803
neighbor notices, so staff is confident that everyone with an
804
interest in this case was notified that it was going to be heard
805
by a special meeting tonight.
806
For whatever reason, the electronics are a bit of a
807
challenge tonight. But I want to make sure from Zoning
808
Administrator's point of view, that everyone who has something
809
to say feels they've been adequately heard.
810
And as I speak, Mr. Hobbie says, "Because a BZA member
811
had asked about ownership. And how the water was draining."
812
And he says, Thank you.
813
So not to interrupt the Chair's duties, but if there's
814
anyone monitoring tonight that feels that they have not been
815
given an opportunity to speak, please do so using your
816
microphone or using the messaging tool, the little cloud on the
817
bottom left, and we'll receive your comments.
818
I think everyone is accounted for.
819
Mr. Chair.
820
MR. JONES: Thank you very much, Mr. Boyle.
821
So I just, in my mind there's two issues and the
822
public concerns that I have just for consideration on the Board.
823
One is the obvious concern with the runoff situation
824
as far as negatively impacting the neighbors is a concern for
825
me. And the second concern I have is the percentages and how
826
that relates to the hardship as presented by the applicants in
827
this case, especially any precedential value that this could
828
have.
829
Those are my concerns. I'm struggling with this one,
830
sort of what in my mind is something that is in favor of
831
approving the application, in my mind is that it's a substandard
832
lot. If this was a standard lot, 11,250 feet, the structure as
833
built would be within Code. So that weighs in favor for me.
834
Also, the way that the house is constructed, having
835
the doors, you know, so to speak, that aren't functional that
836
are leading essentially to nowhere in my mind is a favorable --
837
in favor of approving the application.
838
But my main concern is how this is going to impact the
839
neighbors.
840
Mr. Boyle, I don't know if we can present -- I know we
841
able to attach conditions to any variance approval but I think
842
for me, Mr. Calabrese hit it sort of right on the head, is that
843
the negative impact on the neighbor's property weighs very
844
heavily and if the grading plan or the engineering can be
845
created such that the neighbors could have enjoyment of their
846
property without this runoff sort of mitigates some of my
847
concerns.
848
I think Peter also in my mind hit it right on the head
849
that there are some topographical concerns with the runoff. I
850
don't think it's completely the Skalkas' fault that the water is
851
running off in the direction that it is.
852
So those are my concerns and those are sort of the
853
things that are weighing in favor of approving the application
854
for me. Those are my thoughts. I'm very interested to hear any
855
other thoughts or comments from my colleagues on the Board.
856
MR. CALABRESE: Yeah, I think you, John, have
857
identified the issues correctly.
858
In my weighing of it, I guess I'm probably in a little
859
bit of a different direction. I'm weighing the hardship
860
presented to the petitioner that they cannot build the type of
861
deck that they would prefer with the roof design they prefer.
862
You know, when we hear concerns from neighbors, they
863
usually are revolving around sight lines and proximity to their
864
property and trees. Here we're talking about what appears to be
865
from the one guest here, actual monetary damages they're
866
suffering.
867
And I guess, I must say if I were to balance the
868
hardship of not being able to build this compared to what is
869
already happening and could I think reasonably assume would
870
continue or if not, be exacerbated, I would lean towards not
871
granting it.
872
So, that's I think where I am.
873
MR. JONES: Thank you, Mr. Calabrese.
874
Mr. Bartlett, Mr. Kien, do you have any thoughts?
875
MR. BARTLETT: I do. I thank you both for your
876
discussion, Mr. Jones and Mr. Calabrese, and I also thank
877
everyone for participating today.
878
I am uncomfortable with the outcome of approving a
879
variance on the neighbors and that's one of the elements that we
880
have to consider, is the granting of the variance will not be a
881
substantial detriment to adjacent property, nearby property.
882
But I'm also very concerned about the precedential
883
nature of basically changing the Code. As a substandard lot, if
884
885
we're going to say a substandard lot is a hardship, then
886
regardless of the size of the lot, then they get to build up to
887
35 percent of 11,250 feet, or 25 percent of that same standard
888
minimum lot coverage, then any lot that's R-1A or R-1B is going
889
to say, I want to build up to the percentage of the minimum lot
890
size instead of the percentage of your lot as it is and as it's
891
outlined in our Zoning.
892
To me, that's more of a concern. No, we're not water
893
experts. And we discussed a lot of water issues, about where it
894
comes from and where it goes. We're not engineers and I don't
895
know that's our role. It would be a potential detriment to
896
neighbors but I believe the biggest issue is, as I said, about
897
changing Code practice. People would use this going over the
898
issue, the variance for lot coverage grievances because it's
899
deemed a substandard lot.
900
MR. KIEN: So, and I appreciate the comments of all
901
the other Board members tonight and change the comments that I
902
would have made had I spoken first.
903
Certainly I do understand, Keith, you're coming from
904
that kind of slippery slope type of situation that you do set
905
there but I also believe that the purpose of this Board is to
906
weigh individual circumstance and then apply reasonable to that.
907
The substandard lot size and, John, please correct me
908
if I'm wrong, the substandard lot size is something that the
909
City weighs in on in allowing build to occur in the first place
910
when they don't meet the minimum.
911
And I do feel that it can weigh in in affecting the
912
homeowner's ability to reasonably improve the lot.
913
I agree that none of us are engineers and I almost
914
prefer (inaudible) those who are more qualified to figure out a
915
way to mitigate that.
916
I do know that a grading plan and storm water drainage
917
plan was submitted to the City and approved in order to build
918
that house. The homeowner to be held accountable for the
919
detriment of that plan, it's hard for me to put that
920
responsibility when that process pre-dated them. They did not
921
participate in that process.
922
I do feel that preference to design like David said
923
versus truly a hardship, I think you said it earlier, I think
924
they can build a deck on this house and this is not an issue and
925
the doors that are now not operable doors, while I think it's
926
not the preferred design, I think it's the least intrusive based
927
on the set of facts and circumstances.
928
MR. JONES: If I can just pin you back on that, I
929
think I agree with Peter's sort of assessment. In my mind I
930
think if this was a single story home that had a door that had
931
two steps and goes down to the ground, that would weigh sort of
932
against the design of it. But here we have, the hardship in my
933
mind is we have a house that was constructed pre-current owners
934
and now you have these doors that essentially go nowhere.
935
They're not useable for the current house. They're not useable
936
for the current structure. And the addition, if I can call it
937
that, to the house would just make use of those doors.
938
So in my mind I am concerned with the precedential
939
value. I do know that we sort of evaluate each case that comes
940
before this Board on a very fact- specific case by case basis.
941
So I tend to agree with what Peter is saying. In my
942
mind I think the substandard lot with the current structure of
943
the house, those doors that essentially are non-operable, they
944
don't lead to anything, that adding this structure would make
945
use of those doors, allow the applicants to have full use of
946
their property, in my mind weighs in favor of approving the
947
application.
948
I think any, certainly in my mind if this Board were
949
to approve the application, we would have to certainly weigh
950
951
very heavily the impact on the neighbors. They very rightly
952
voiced their concerns and with the water and the damage that
953
they're experiencing is certainly a factor that weighs very,
954
very heavily with me as far as everybody having the right to
955
reasonably enjoy the use of their property.
956
So I think in my mind if we were going to approve this
957
variance, the condition would be the engineers or the planning
958
or the grading would certainly have to mitigate or reduce the
959
amount of water such that it could on the neighbors' properties,
960
I think we sort of highlighted the fact that we're not water
961
experts, but I do think that mitigating any damage to the
962
neighboring properties to reduce that water that they're
963
experiencing, it weighs very, very heavily with me.
964
And I think the applicants in their presentation did
965
not object to taking measures that would mitigate any sort of
966
runoff to their neighbors, so all these factors sort of weigh
967
very, very heavily with me but I think I would be in favor of
968
approving the application subject to the engineering firms, the
969
grading plan mitigating the water damage that is experienced by
970
the neighbors.
971
MR. CALABRESE: I'll add one more thing.
972
I think after hearing Mr. Bartlett, I want to amend my
973
comments that I'm also very concerned about the precedential
974
value of this.
975
And the only other comment I would make, is in terms
976
of their enjoyment, petitioner's enjoyment of the property,
977
again I go back to a comment I made, when they bought the house,
978
the house was substandard at that time, it had the door to
979
nowhere, and as most things happen in this market, everything is
980
priced accordingly.
981
So I understand the concerns about there could be a
982
detriment but it was purchased with this information known. So
983
I think it's perfectly reasonable that someone would want to
984
build this type of structure. I would too. But again, we have
985
some other considerations and it was purchased knowing these
986
facts.
987
I'll leave it at that.
988
MR. JONES: Okay. Thank you for that.
989
Mr. Boyle, I just want to make sure that we're very
990
clear with the applicants that before any motion is called, they
991
do have the option to continue this to our next meeting when we
992
do have a full Board, is that correct?
993
MR. BOYLE: That's correct because we're shy one
994
member.
995
MR. JONES: Okay.
996
MS. SKALKA: Thank you again. I think that we would,
997
if it's okay with the Board members, we would like to continue.
998
We would like a continuance this evening.
999
MR. JONES: Okay. Mr. Boyle, is there any official
1000
action that we need to take with the applicants' request for a
1001
continuance?
1002
MR. BOYLE: The Rules of Procedure says the Board
1003
shall grant one motion to continue, so perhaps there's a need to
1004
take a vote, but the "shall" is -- let's go ahead and take a
1005
vote. There's no harm in staff carrying this over anyway but
1006
the Board should probably speak on that continuation.
1007
So we need a motion and a vote.
1008
MR. JONES: Okay. So to be clear, we would need a
1009
motion to approve the request for a continuance and a "yes" vote
1010
would be in favor of the continuance and a "no" vote would not,
1011
is that correct?
1012
MR. BOYLE: Yes.
1013
MR. JONES: Okay. Do I have a motion on the
1014
applicant's request for a continuance?
1015
MR. KIEN: I make a motion to approve the continuance
1016
request.
1017
MR. JONES: Is there a second?
1018
MR. BARTLETT: I'll second that motion.
1019
MR. JONES: Roll call vote please, Mr. Boyle.
1020
MR. BOYLE: Mr. Calabrese.
1021
MR. CALABRESE: Yes.
1022
MR. BOYLE: Mr. Jones.
1023
MR. JONES: Yes.
1024
MR. BOYLE: Mr. Misleh.
1025
(No response.)
1026
MR. BOYLE: Mr. Bartlett.
1027
MR. BARTLETT: Yes.
1028
MR. BOYLE: Mr. Kien.
1029
MR. KIEN: Yes.
1030
MR. BOYLE: Okay. Four in favor.
1031
MR. JONES: Thank you.
1032
Mr. and Mrs. Skalka, I can't see you but I think we'll
1033
I guess see you at the next meeting. Thank you for your time.
1034
MR. BARTLETT: Mr. Jones, can we clarify what the
1035
requirements are for continuing and if they're continuing this
1036
with the intent that they will be providing new information at
1037
the next meeting.
1038
MR. BOYLE: If I could, Mr. Chair, I'll clarify what
1039
the Code provides. I don't think there's a hurdle they need to
1040
clear. There is in the event of a refusal, there is a statement
1041
in the Code about presenting new information. I don't think
1042
there is one for a simple continuance.
1043
The catch is that or the limitation is that there's
1044
only one continuance allowed by the request of the applicant.
1045
I'll check the Code to see if they need to come back
1046
with additional information. Because we've had this in the past
1047
and then if we do have a new member present, they haven't heard
1048
this case. So, how do we proceed? Do we rehear everything?
1049
So my sense is that there has to be something new for
1050
the Board to consider but I'll double check that and present it
1051
to everyone, including the applicants and the public.
1052
MR. BARTLETT: Thank you, John.
1053
MR. JONES: Thank you, Mr. Boyle.
1054
Thank you, Mr. and Mrs. Skalka.
1055
1056
6. APPROVAL OF MINUTES
1057
7. OTHER BUSINESS
1058
MR. JONES: Mr. Boyle, I don't believe you said we
1059
have any Approval of Minutes or any Other Business, is that
1060
correct?
1061
MR. BOYLE: That's correct.
1062
And that I think completes our business.
1063
1064
8. ADJOURNMENT
1065
MR. JONES: Very good. Thank you.
1066
Do I have a motion to adjourn?
1067
MR. BARTLETT: So moved.
1068
MR. JONES: Roll call please, Mr. Boyle.
1069
MR. BOYLE: Mr. Calabrese.
1070
MR. CALABRESE: Yes.
1071
MR. BOYLE: Mr. Jones.
1072
MR. JONES: Yes.
1073
MR. BOYLE: Mr. Bartlett.
1074
MR. BARTLETT: Yes.
1075
MR. BOYLE: Mr. Kien.
1076
MR. KIEN: Yes.
1077
MR. BOYLE: Four in favor of adjournment.
1078
MR. JONES: Thank you, everyone. That concludes the
1079
Thursday, August 13, 2020, meeting of the Board of Zoning
1080
Appeals. Thanks, everyone.
1081
MR. BOYLE: See you in September.
1082
1083
Agenda
BOARD OF ZONING APPEALS MEETING AGENDA
Virtual Public Hearing: https://meet.lync.com/fallschurch-fallschurchva/arouzi/68C78B7J
Thursday, August 13, 2020
7:30 p.m.
NOTICE: The meeting for which this agenda has been posted will be held pursuant to and in compliance with
the Virginia Freedom of Information Act, Section 2.2-3708.2 and state and local legislation adopted to allow for
continued government operation during the COVID-19 declared emergency.
All participating members of Board of Zoning Appeals will be present at this meeting through electronic means.
All members of the public may view the meeting virtually via this Skype link:
https://meet.lync.com/fallschurch-fallschurchva/arouzi/68C78B7J. Public comment and questions may be
submitted to zoning@fallschurchva.gov until 7:00 pm on August 13, 2020.
PLEASE NOTE: This meeting will be conducted via Skype. If you do not already use Skype, you will be
prompted to install it when clicking the meeting link, so please take some time ahead of the meeting to do so. If
needed, there are short instructions to install the application following the meeting agenda. Please email
cmester@fallschurchva.gov if you need assistance with installation. During the meeting, staff will likely not be
available to assist with installation.
1. Call to Order
2. Roll Call
3. Petitions
4. Old Business
5. New Business
a. Variance application V1616-20 by Jeff and Katie Skalka, applicant and owner, for a variance to
Section 48-238, to allow 27.4% lot coverage instead of 25% maximum permitted by code, and
37.2% impervious lot coverage instead of 35% maximum permitted by code, for the purpose of
constructing a front porch on premises known as 205 Patterson Street, RPC #52-113-008 of the Falls
Church Real Property Records, zoned R-1A, Low Density Residential.
6. Approval of Minutes
7. Other Business
8. Adjournment
The City of Falls Church is committed to the letter and spirit of the Americans with Disabilities Act. To request
a reasonable accommodation for any type of disability, call 703-248-5015, TTY711.
Accessing Skype – New Users
Smartphone: If you plan to view the meeting on a smartphone, access your preferred app store to download the
“Skype” app. You will have to allow Skype access to some features on your phone and accept their terms and
conditions.
PC/Windows: If you plan to view the meeting on a personal computer, visit www.skype.com to download and
install the program. You will have to allow Skype access to some features on your computer and accept their
terms and conditions.
After downloading Skype:
Click the advertised meeting link to join the Skype meeting.
When the app opens, click ‘Join as Guest’ and enter your name. Click the blue arrow to continue.
The meeting will start with your microphone and video features turned off. As an observer, you can
view or listen to the meeting without these features. If you are a meeting participant, you should
enable at least the microphone feature. Video is not required but may be useful. Depending on your
role in the meeting, there may be restrictions on whether you can speak during the meeting.
Get email alerts for Falls Church
A daily email when new agendas and minutes are posted.