Recreation & Parks Advisory Board
Regular MeetingFalls Church, VA · September 5, 2012
Minutes
Regular Meeting of the Advisory Board of Recreation and Parks
Held at the Falls Church Community Center
223 Little Falls Street, Falls Church, Virginia 22046
Minutes
September 5, 2012
1. Call to Order
Mr. O’Hara called the meeting to order at 7:06 p.m.
Members present were Charley O’Hara, Kathy Chandler, Greg Rasnake, Ruth Rodgers, Leslie
Rye, Steve Selby, and Dave Tarter. Staff members present were Danny Schlitt, Director of
Recreation & Parks, and Krissy Loerch, Senior Administrative Assistant.
2. Receipt of Public Petitions and Board Member Petitions
Mr. O’Hara asked if there were any petitions from the public or board members. There were
none.
3. Minutes
Mr. Selby moved to approve the minutes from the June 6th meeting. Ms. Chandler seconded the
motion. Ms. Rye abstained from the vote. Upon voice vote, the motion passed.
4. Recreation Director’s Report
• The Tinner Hill Blues Festival was more organized than in previous years. This year the
festival made a profit as reported by Tinner Hill.
• The Fourth of July event was a success this year. The fireworks were shot 10 minutes
earlier than planned due to the approaching storm. The department collected $1,091.00 in
donations from the public at the event. This amount was $500 less than the previous year.
Mr. Schlitt thanked Mr. O’Hara and his family for helping staff the donation boxes.
• The summer camp programs ran effectively this year under the supervision of Ms.
Maltese. The total receipts from the summer camp programs this year are approximately
$700,000 and the registrations totaled 5,200. Mr. Schlitt stated that the Summer Fun
program was exceptional this year with the direction of incredibly creative and
enthusiastic staff.
• Over the summer the field at Madison Park was replaced with bermuda grass. The field
opened in time for the fall youth soccer season and looks extraordinarily healthy. Mr.
Schlitt will move forward with plans to replace the field at Thomas Jefferson Elementary
School next year.
• The schools are planning to fix the tennis courts at George Mason High School and have
the funds to do so immediately. The plan is to improve the drainage in and around the
courts while resurfacing them. This project will cost approximately $100,000 and the
schools have asked the Recreation & Parks Department to contribute funds that we deem
appropriate.
• A scout project took place at West End Park to preserve eroding timbers.
• The Community Center was closed for activities from August 27-September 3 for annual
cleaning and maintenance. The gym floor was sanded, painted and recoated. The dance
studio was also sanded and recoated. All of the drywall and trim in the center was
repainted but not the cinderblock areas.
• The Farmers Market received recognition in three magazines this year to include The
Washingtonian, Northern VA, and Virginia Living. Voting for the Farmers Market
through the American Farmland Trust took place again this year. We anticipate finishing
in the top 3 in Virginia for medium markets.
• The department purchased a new 15 passenger van this summer and utilized it for camp
programs in the remaining weeks. Mr. Schlitt thanked the board for its continual support
of Recreation & Parks needs.
• Fall class registration began on August 20 for City residents and August 27 for non-City
residents. The overall trend in the numbers suggests that registrations are up from last
year.
• Registration for fall youth soccer and flag football is concluded. The total number of
soccer participants has increased with seven new teams. Flag football is completely filled
with 36 teams and approximately 360 participants. Flag football is broken down into
teams of 2nd -3rd, 4th -5th, and 6th -7th graders.
• Mr. Schlitt became aware of a situation involving a permanent sign on the bike trail
advertising a local bike shop. The bike shop received approval from the Northern
Virginia Regional Park Authority (NVRPA) and paid a $75 fee to have it installed by the
NVRPA. The City is forming a committee to meet with the NVRPA regarding the future
of signage on the bike trails located in the City. The City pays a yearly fee to the NVRPA
for membership.
• The summer Concerts in the Park series on Thursdays from June 21 to August 2 was a
success again this year. The Sunset Cinema series on Fridays on August 24 & 31 and
September 7 attracted a larger than usual crowd this year.
• The Fall Festival and Taste of Falls Church is on Saturday, September 15 from 10 a.m. to
4 p.m. The entertainment stage will be located by the tennis courts this year in an attempt
to have the music closer to the festival. There will be tables set up in front of the stage to
serve as an eating area. Thirteen restaurants are participating in the Taste of Falls
Church. This year the event had one sponsor and thirteen supporters that overall
contributed $13,650 to the event. At last year’s event we had ten sponsors contributing a
total of $8,600.
• The Frady Park gazebo that was destroyed in the storm will be replaced this fall. A tree
fell onto the gazebo but the concrete structure remained intact. An exact replica of the
gazebo will be installed.
5. New Business
a. Lincoln Park
• Part of the playground structure at Lincoln Park was hit by a car. The damaged
equipment needs to be replaced and is approximately ten years old. Mr. Schlitt is
exploring the possibility of replacing the damaged portion with a new and creative
structure. During this process the park will be brought up to ADA compliance.
The funds necessary to complete this project will come from the insurance
collected and the remainder from the CIP. Mr. Schlitt estimates the total cost of
this project between $180,000 to $200,000.
2
6. Old Business
a. Rain Garden
• Mr. Widstrom updated the board members on the status of the rain garden
projects at Crossman, Lincoln, and Berman Parks. The projects suffered various
set backs including heavy rain causing flooding at Berman and incorrect soil
installed at one of the sites. This is the second rain garden project that the City has
undertaken.
• At Crossman Park the seeding and irrigation projects need to be completed. The
irrigation project was not in the initial part of the grant. This is because the City
anticipated cost savings by having the Urban Forestry crew complete the
installation. However, due to the set back in the timeline to complete the project,
the irrigation will be completed by a contractor. The seed is ordered and delivery
is expected next week. However, planting the seeds will not occur until the
irrigation is complete. Mr. Widstrom was advised not to plant the seed before
September 15th. Mr. O’Hara requested that Mr. Widstrom follow up with the
contractor to remove concrete that is currently in the park and address the opening
in the curb where there are sandbags.
• At Lincoln Park they are over seeding in the grassy areas that did not initially
take. Every two weeks the area is weeded and landscaped by the City contractor.
The irrigation at this park is completed and is on an automatic timer. The rain
garden will be watered heavily for the first two years. After two years the plants
will be fully grown in and accustom to the changing weather conditions. Mr.
Widstrom is working with Public Utilities to drop the valve for water service into
a meter box.
• Ongoing observation is taking place at Lincoln Park to determine the
effectiveness of the under drain system. Initial testing indicated that the soil did
not perk which required installation of under drains from the rain gardens to the
storm drain. The under drain system was completed except for one connection to
the system that required disturbance around a pin oak tree. Recent observations
after rain events show that the soil is indeed perking and that the unfinished
connection is not necessary at this time.
• At Berman Park the heavy rains impeded progress as the initial hole excavated for
the rain gardens needed to dry out before proceeding. The sides of the hole
collapsed which led to an increase in the size of the rain garden. The north garden
is completed and on a weeding schedule. Grading and plantings around the north
garden are planned. The upper bank of the south garden was planted, and work
remains on the lower area by the boardwalk. Burms were installed as well as
erosion stone at the boardwalk edge to help alleviate the demand on the rain
garden during a large storm. Once the grading is completed, seeding for turf grass
will take place followed by irrigation. After irrigation they will install the
remaining plants currently at the Property Yard followed by composting the area.
• The consistent watering of the Berman Park rain gardens has been challenging
since they are deeper into the park. Urban Forestry is working with the contractor
to bring in irrigation. The quotes for this irrigation will be sought with the quote
for the Crossman Park irrigation.
• The raised boardwalk structure at Berman Park is nearly complete. Mr. Widstrom
reported that they will attempt to decrease drop off by building up the ground with
3
4 inches of compost and plantings that will grow taller than the boardwalk. The
board expressed concerns about the height of the drop and that camouflaging the
drop off will only increase the hazard. Numerous additional safety concerns were
expressed by the board to include: the curve to the right heading towards Kent St.
is more drastic than anticipated; the bike ability of the boardwalk; the rocks
underneath and around the boardwalk; and the storm sewer and storm drain.
• Several potential solutions were discussed and the board concluded that proactive
measures should be taken now to correct the potential hazard. Mr. Widstrom
suggested constructing a separate asphalt bike path to the side of the boardwalk.
Another option is to install railings around the curve and near the drains. Mr.
Widstrom suggested that we could add more compost to bring up the height of the
garden closer to the board walk. Ms.Chandler suggested building an additional
boardwalk around the curve. Mr. Widstrom advised that this option would be very
costly because of the curvature of the specialty recycled boards.
b. Lynn Place Property
• The owner is willing to speak with the City about entertaining the first right of
refusal on the property. Mr. Schlitt is in the process of scheduling a meeting with
the property owner and City Manager.
c. Bike/Ped Plan Update
• The Council instructed the committee to review the plan and to not reduce on
street parking. There are three public hearings scheduled in September for citizens
to express their opinions. The committee will meet with Council after these
hearings.
7. Other Business
• Mr. O’Hara suggested that the board review the West End Project site plans at the
next meeting.
8. Adjournment
Mr. Selby moved to adjourn the meeting; Ms. Chandler seconded the motion. Following a
unanimous voice vote, Mr. O’Hara adjourned the meeting at 8:55 p.m.
The City of Falls Church is committed to the letter and spirit of the Americans with Disabilities
Act. This document will be made available in alternate format upon request. Call 703-248-5027
(TTY 711).
4
Agenda
AGENDA
REGULAR MEETING OF THE ADVISORY BOARD OF RECREATION AND PARKS TO
BE HELD AT THE FALLS CHURCH COMMUNITY CENTER, 223 LITTLE FALLS STREET,
FALLS CHURCH, VIRGINIA 22046
September 5, 2012
7:00 P.M.
1. Call To Order
2. Receipt of Public Petitions and Board Member Petitions
3. Minutes for Approval: June 6, 2012
4. Recreation Director’s Report
5. New Business
a) Lincoln Park
6. Old Business
a) Rain Garden Update (Jason Widstrom, Public Works)
b) Lynn Place property
c) Bike/Ped Plan update?
7. Other Business
8. Adjournment
“The City of Falls Church is committed to the letter and spirit of the Americans with
Disabilities Act. To request a reasonable accommodation for any type of disability call
(703)248-5077.