I. GENERAL
l
1. Commission members present: Amanda Weese
James Spence
Chris Hunter
Tory Larsen
Marty Johnson
Vic Eicker
Keith Johns
Bill Hall
Commission members absent: Jeff Parkes
Carol Cloer
Bill Standley
City Council Liaison: Gayla McCulloch
City personnel present:
Water/Wastewater JeffSmaka
CH2MHill OMI Ron Rosen
PUC Secretary Amy McKinley
Utility Business Operations Susan Nipper
Electric Utility Director Michael Sims
Electric Transmission & Distribution Rodney Romero
Electric Generation Jim McNicol
Electric Engineering John Armenta
Administrative Services Andy Mason
Guests:
Kris Cope, Electric Engineering
2. Chair Weese called the meeting to order at 3:00 PM with a quorum present to conduct
the business of the Commission.
3. The Minutes of the April 2, 2014 were approved as circulated.
4. The Minutes ofthe April 2, 2014 Budget meeting were approved as circulated.
II. BUSINESS
1. Write-offs of Aged Inactive Utility, Accounts:
Ms. Parks presented an action item request recommending the approval to write off
aged/inactive utility accounts from 2009. Ms. Parks stated the total amount being
requested for write-off is $175,942.32. Ms. Parks stated that $36,859.69 of these
monies is the result of bankruptcies.
Commissioner Hunter made a motion to recommend to City Council the approval of
the Resolution to write off aged/inactive utility accounts. Commissioner Johns
seconded the motion and the motion passed unanimously.
2. Quarterly Financial Report:
Mr. Mason presented the quarterly financial reports of the electric, water and
wastewater utilities.
- 1
Mr. Mason stated the Electric Utility's net income was lower by $1.8 million from last
year. Mr. Mason stated that operating revenues increased by $1.4 million and electric
sales were up $1.2 million. Mr. Mason reported that residential customer sales
increased $758 thousand, commercial customer sales increased $658 thousand and
other revenues were up $180 thousand. Mr. Mason stated that auction proceeds were
$112 thousand higher, fiber optic leasing was higher by $45 thousand and
miscellaneous revenue was up by $24 thousand. Mr. Mason reported that the operating
expenses increased $3.8 million, most of that is in the purchased power which was up
$5.1 million from the prior year. Mr. Mason stated that natural gas costs decreased
$2.4 million. Mr. Mason stated salary and benefits were up $953 thousand because in
FY2014 the Safety Department became part of the Electric Utility.
Mr. Mason reported that in non-operating revenues and expenses revenues were up
$191 thousand, mainly due to increases in construction contributions. Mr. Mason
stated expenses were down $340 thousand. Mr. Masons stated the revenue bonds were
paid off in FY2013.
Mr. Mason stated the net income for the Water Utility was down $638 thousand from
FY2013. Mr. Mason stated operating revenues decreased $220 thousand, the majority
of which is from water sales. Mr. Mason stated water sales were down $239 thousand,
residential customer sales decreased $302 thousand and contract user sales decreased
$88 thousand. Mr. Mason stated the general service customer sales increased $197
thousand. Mr. Mason stated operating expenses increased $419 thousand. Mr. Mason
stated depreciation increased by $371 thousand. Mr. Mason reported the OMI contract
has increased $171 thousand. Mr. Mason stated that every year there is a CIP increase
in the contract and that FY20 14 had more work that was outside the scope of the
contract. Mr. Mason stated other operating expenses decreased $131 thousand; the
majority of this decrease was due to lower engineering costs of about $109 thousand.
Mr. Mason stated the non-operating revenues decreased by $8 thousand. Mr. Mason
stated much of this decrease was due to one-time payments for bulk sales and raw
water in FY2013 that was not received in FY2014. Mr. Mason stated that expenses
decreased by almost $9 thousand. Mr. Mason stated interest and amortization costs
were lower because the revenue bonds were paid off last year and the PIL Twas
slightly lower by $11 thousand.
Mr. Mason reported that the Wastewater Utility's net income had a slight increase of
$42 thousand over last year. Mr. Mason stated operating revenues were higher by
$164 thousand. Mr. Mason reported that wastewater sales increased $149 thousand;
commercial customer sales were $172 thousand higher and residential customer sales
were up $3 thousand. Mr. Mason stated that other fees (mainline extension, tap &
septic tank) were down $30 thousand. Mr. Mason reported that operating expenses
were $224 thousand higher. Mr. Mason stated the OMI contract was up $104
thousand and there is a CIP increase every year in the contract. Mr. Mason stated that
in FY20 14 there was more work done that was outside the scope of the contract. Mr.
Mason stated that other operating expenses increased $86 thousand due to an increase
in cost for engineering and laboratory/testing fees. Mr. Mason reported that non
operating revenues increased $95 thousand. Mr. Mason stated there was a contribution
of $88 thousand by San Juan County which donated a lift station to the City. Mr.
Mason stated expenses decreased $6 thousand. Mr. Mason stated interest and
amortization costs were lower because the revenue bonds were paid off last year and
the PIL T was slightly higher by $8 thousand.
3. Water/Wastewater Report:
Mr. Smaka presented the Water/Wastewater report for the month of April. Mr.
Smaka reported that Red Oak Consulting is working on the rate study which it is
anticipated will be presented to the Commission later this year. Mr. Smaka reported
that OMI has begun work on the meter replacement project. Mr. Smaka stated the Lift
Station 5 improvements are nearing completion; all the electrical systems are in and
crews are waiting for the pumps to be delivered and this project should be completed
by June. Mr. Smaka reported that the replacement of existing 12" clay pipe sewer line
in the area of the Bisti Highway and Murray Drive is 90% complete.
-2
4. Water/Wastewater Operations Report:
Mr. Rosen offered a PowerPoint presentation which discussed the issue ofTDS (Total
Dissolved Solids) and the EPA's requirements for reducing TDS levels. Mr. Rosen
stated this is a presentation'he gives at various local club meetings.
5. Major Status Report Engineering:
Mr. Armenta reviewed and discussed the many engineering projects and the
completion status of various projects.
Mr. Armenta discussed the GPS Point Inventory project presently underway which
will locate, photograph, catalog and store every piece of distribution equipment from
the substation to the meter in the FEUS GIS data base. Mr. Armenta stated this project
will offer many benefits including the basis of an outage management system.
Mr. Armenta introduced the project manager for this project, Ms. Kris Cope, FEUS
GIS Technician. Ms. Cope reviewed a map of the FEUS service area where the
contractor, Chappel Mapping is presently gathering this GPS inventory data.
6. Electric Utility Report:
Ms. Nipper presented the April and year to date Electric Utility Report.
General discussion took place regarding the information presented by Ms. Nipper.
7. Director's Report:
Mr. Sims reported that the Navajo plant is not running at this time due to low river
flows. Mr. Sims stated the Bureau of Reclamation is not going to have a spring release
in the interests of recovering the reservoir levels. Mr. Sims stated San Juan Units 3 and
4 are on line, but are at reduced load due to issues with the use of low quality coal. Mr.
Sims stated an outage occurred at the Bluffview plant due to the detection of metal in
the lube oil. Mr. Sims stated this was determined to be a minor issue and was
corrected and the unit is back on line.
Mr. Sims stated that Business Operations/Customer Service has been dealing with
issues with the IVR phone system; staffhas been working with the vendor to resolve
these issues.
Mr. Sims stated there are on-going efforts in progress for an NPDES outfall
construction contract and outside engineering services contract in support ofNPDES
outfall construction at the Bluffview plant.
Mr. Sims reported that a new map board has been installed in the Control Center at the
Municipal Operations Center.
III. ADJOURNMENT
There being no further business to come before the Commission, upon motion duly
made and seconded, the meeting was adjourned.
The meeting was adjourned at 4:45 p.m.