Public Utility Commission
Regular MeetingFarmington, NM · June 4, 2014
Minutes
BOARD OF PUBLIC UTILITY COMMISSIONERS
The special meeting of the CITY OF FARMINGTON BOARD OF PUBLIC UTILITY
COMMISSIONERS was held Wednesday, June 4, 2014 at 3:00 p.m., in the Executive Conference Room
at City Hall, 800 Municipal Dr., Farmington, New Mexico, in full conformity with the laws and
ordinances of the Municipality.
I. GENERAL
1. Commission members present: Amanda Weese
James Spence
Jeff Parkes
Tory Larsen
Carol Cloer
Marty Johnson
Chris Hunter
Commission members absent:
Keith Johns
Bill Standley
Vic Eicker
Bill Hall
City Council Liaison: Gayla McCulloch
City personnel present:
WaterlWastewater JeffSmaka
CH2MHill OMI Ron Rosen
PUC Secretary Amy McKinley
Utility Business Operations Susan Nipper
Electric Utility Director Michael Sims
Electric Transmission & Distribution Rodney Romero
Electric Generation Jim McNicol
Electric Engineering John Armenta
Administrative Services Andy Mason
Accounting Sheree Wilson
2. Chair Weese called the meeting to order at 3:00 PM with a quorum present to conduct
the business of the Commission.
3. Commissioner Cloer made a motion to approve the Minutes of the May 14, 2014
meeting. Commissioner Johnson seconded the motion and the motion passed
unanimously.
II. BUSINESS
1. NMMEAA Gas Prepay Agreement:
Mr. Sims stated the purpose for calling the special meeting of the PUC was to discuss
the proposed amendment to the New Mexico Municipal Energy Acquisition Authority
(NMMEAA) Gas Prepay Agreement. Mr. Sims stated this presentation was for
informational purposes only and that no recommendation from the Commission was
required.
Ms. Nipper reviewed a presentation detailing the current gas prepay agreement
between NMMEAA and the City of Farmington as well as the changes offered in the
proposed amendment. Discussion ensued regarding the proposed amended agreement.
Chair Weese asked how the situation changed so that action by the Commission was
no longer necessary.
- 1
Mr. Sims stated that in discussions he had with Mayor Roberts, Mayor Roberts had
some questions of his own regarding the proposed amendment and since the
documentation continued to be in a state of flux, Mr. Sims and Mayor Roberts both
agreed that it was unfair to ask the Commission to make a recommendation on such an
important issue without more information; information staff was not prepared to offer
at the time. Mr. Sims reported that Mayor Roberts stated if the Commission chose to
offer a recommendation, the Mayor would be amenable to it, but the Commission was
not obligated to offer a recommendation.
Chair Weese asked if the City Council would have information that was not available
to the Commission at this special meeting.
Mr. Sims stated he was not aware of any information regarding this matter that would
be presented to the City Council that had not· already been presented to the
Commission. Mr. Sims stated the information presented to the Commission was
information that was only recently made available.
While a recommendation from the Commission was not required, Commissioner
Hunter made a motion to recommend to the City Council the adoption of a resolution
to continue the finalization of the proposed NMMEAA gas prepay amendment for
signature by Mayor Roberts. Vice Chair Spence seconded the motion. The motion
passed unanimously.
2. Water/Wastewater Report:
Mr. Smaka presented the WaterlWastewater report for the month of May.
Mr. Smaka reported that NMED approved funding of the waste water treatment plant
Upgrade through the Clean Water State Revolving Loan Fund program. Mr. Smaka
stated the loan documents are in the hands of the NMED legal department.
Mr. Smaka stated Red Oak Consulting is working on the rate study. Mr. Smaka
anticipates receiving information regarding the rate study from Red Oak by the end of
June.
Mr. Smaka reported on the various water and wastewater projects throughout the city.
3. WaterlWastewater Operations Report:
Mr. Rosen reported on water/wastewater operations for the month of May.
Mr. Rosen stated the household hazardous waste drop-off day was held in May and
362 cars came to the drop-off location. Commissioner Larsen stated he managed the
Aztec household hazardous waste drop-off location and approximately 125 cars came
through the Aztec location.
Mr. Rosen stated the meter replacement project has begun and approximately 590
meters have been installed at the date of this meeting.
4. Electric Utility Report:
Ms. Nipper presented the May and year to date Electric Utility Report. The
Commission had no questions.
5. Director's Report:
Mr. Sims reported on activities of the Electric Utility. Mr. Sims stated that all of the
plants are up and running. The Navajo plant is on line but operating at minimum load.
Mr. Sims stated the Compliance division continues to work on the permit process for
the new outfall at the Bluffview Plant.
Mr. Sims reported on the many activities of the Engineering division and briefly
reviewed the status of the contract with Ward Electric to replace a large amount of
distribution poles, many transmission structures and also conductor. Mr. Sims stated
this contract was recently completed and engineering staff are presently performing an
audit on the activities of the contractor. Mr. Sims stated that electric utility crews are
also performing similar work in areas throughout the system.
- 2
III. ADJOURNMENT
There being no further business to come before the Commission, upon motion duly
made and seconded, the meeting was adjourned.
The meeting was adjourned at 4:46 p.m.
Approved this 9th day of July, 2014.
(~3C::::Y' . (/vl dMA
Amanda Weese, Chair ~
-3
Agenda
~
~Cit" 01 Fa,·,••i"Uto"
" Tllter/ 'V#.sl'e,v#.te,·
DA
.. , ... for the regular meeting of the Public Utility Commission of the City of Farmington, Wednesday. June
4.2014. at 3:00 PM at the Executive Conference Room at City Hall, 800 Municipal Dr., Farmington, New
Mexico.
I. GENERAL
A. Roll Call
B. Convening of Meeting by Amanda Weese, Chair
C. Minutes of May 14, 2014 regular meeting submitted for approval. ......................... 1
II. BUSINESS
A. NMMEAA Gas prepay agreement (action item) (45 min) ....................................... 2
B. Water/Wastewater Report - Jeff Smaka (5 min) .................................................... 3
C. WaterlWastewater Operations Report - Ron Rosen (5 min) .... ............................. 4
D. Electric Utility Report- Sue Nipper (1 a min)... ............ .. ..... ...................................... 5
E. Director's Report -:- Mike Sims (5 min) ... ...... .. .. ... ........ ... ... .. ... ........ .... .... ................. 6
III. ADJOURNMENT
The next regular meeting will be on July 9, 2014
The City of Farmington will make every effort to provide reasonable accommodations for people with disabilities who wish to attend a public meeting . If
you need to request that an accommodation be made, please notify the Electric Administration office (599-1160) at least 24 hours prior to the meeting.
BOARD OF PUBLIC UTILITY COMMISSIONERS
The regular meeting of the CITY OF FARMINGTON BOARD OF PUBLIC UTILITY
COMMISSIONERS was held Wednesday, May 14, 2014 at 3:00 p.m., in the Executive Conference
Room at City Hall, 800 Municipal Dr., Farmington, New Mexico, in full conformity with the laws and
ordinances of the Municipality.
1. GENERAL
1. Commission members present: Amanda Weese
James Spence
Chris Hunter
Tory Larsen
Marty Johnson
Vic Eicker
Keith Johns
Bill Hall
Commission members absent: Jeff Parkes
Carol Cloer
Bill Standley
City Council Liaison: Gayla McCulloch
City personnel present:
Water/Wastewater Jeff Smaka
CH2MHill OMI Ron Rosen
PUC Secretary Amy McKinley
Utility Business Operations Susan Nipper
Electric Utility Director Michael Sims
Electric Transmission & Distribution Rodney Romero
Electric Generation Jim McNicol
Electric Engineering John Armenta
Administrative Services Andy Mason
Guests:
Kris Cope, Electric Engineering
2. Chair Weese called the meeting to order at 3:00 PM with a quorum present to conduct
the business of the Commission.
3. The Minutes of the April 2, 2014 were approved as circulated.
4. The Minutes of the April 2, 2014 Budget meeting were approved as circulated.
II. BUSINESS
1. Write-offs of Aged Inactive Utility Accounts:
Ms. Parks presented an action item request recommending the approval to write off
aged/inactive utility accounts from 2009 . Ms. Parks stated the total amount being
requested for write-off is $175 ,942.32. Ms. Parks stated that $36,859.69 of these
monies is the result of bankruptcies.
Commissioner Hunter made a motion to recommend to City Council the approval of
the Resolution to write off aged/inactive utility accounts. Commissioner Johns
seconded the motion and the motion passed unanimously.
2. Quarterly Financial Report:
Mr. Mason presented the qualierly financial reports of the electric, water and
wastewater utilities.
- 1
Mr. Mason stated the Electric Utility's net income was lower by $1.8 million from last
year. Mr. Mason stated that operating revenues increased by $1.4 million and electric
sales were up $1.2 million . Mr. Mason reported that residential customer sales
increased $758 thousand, commercial customer sales increased $658 thousand and
other revenues were up $180 thousand. Mr. Mason stated that auction proceeds were
$112 thousand higher, fiber optic leasing was higher by $45 thousand and
miscellaneous revenue was up by $24 thousand. Mr. Mason reported that the operating
expenses increased $3.8 million, most of that is in the purchased power which was up
$5 .1 million from the prior year. Mr. Mason stated that natural gas costs decreased
$2.4 million. Mr. Mason stated salary and benefits were up $953 thousand because in
FY20 14 the Safety Department became part of the Electric Util ity.
Mr. Mason reported that in non-operating revenues and expenses revenues were up
$191 thousand, mainly due to increases in construction contributions. Mr. Mason
stated expenses were down $340 thousand. Mr. Masons stated the revenue bonds were
paid off in FY2013.
Mr. Mason stated the net income for the Water Utility was down $638 thousand from
FY2013. Mr. Mason stated operating revenues decreased $220 thousand, the majority
of which is from water sales. Mr. Mason stated water sales were down $239 thousand,
residential customer sales decreased $302 thousand and contract user sales decreased
$88 thousand . Mr. Mason stated the general service customer sales increased $197
thousand. Mr. Mason stated operating expenses increased $419 thousand . Mr. Mason
stated depreciation increased by $371 thousand. Mr. Mason reported the OMI contract
has increased $171 thousand. Mr. Mason stated that every year there is a CIP increase
in the contract and that FY2014 had more work that was outside the scope of the
contract. Mr. Mason stated other operating expenses decreased $131 thousand ; the
majority of this decrease was due to lower engineering costs of about $109 thousand .
Mr. Mason stated the non-operating revenues decreased by $8 thousand. Mr. Mason
stated much of this decrease was due to one-time payments for bulk sales and raw
water in FY2013 that was not received in FY2014. Mr. Mason stated that expenses
decreased by almost $9 thousand. Mr. Mason stated interest and amortization costs
were lower because the revenue bonds were paid off last year and the PILTwas
slightly lower by $11 thousand.
Mr. Mason reported that the Wastewater Utility's net income had a slight increase of
$42 thousand over last year. Mr. Mason stated operating revenues were higher by
$164 thousand. Mr. Mason reported that wastewater sales increased $149 thousand ;
commercial customer sales were $172 thousand higher and residential customer sales
were up $3 thousand. Mr. Mason stated that other fees (mainline extension, tap &
septic tank) were down $30 thousand. Mr. Mason rep0l1ed that operating expenses
were $224 thousand higher. Mr. Mason stated the OMI contract was up $104
thousand and there is a CIP increase every year in the contract. Mr. Mason stated that
in FY20 14 there was more work done that was outside the scope of the contract. Mr.
Mason stated that other operating expenses increased $86 thousand due to an increase
in cost for engineering and laboratory/testing fees. Mr. Mason reported that non
operating revenues increased $95 thousand . Mr. Mason stated there was a contribution
of $88 thousand by San Juan County which donated a lift station to the City. Mr.
Mason stated expenses decreased $6 thousand . Mr. Mason stated interest and
amortization costs were lower because the revenue bonds were paid off last year and
the PILT was slightly higher by $8 thousand .
3. Water/Wastewater Report :
Mr. Smaka presented the Water/Wastewater report for the month of April. Mr.
Smaka repo11ed that Red Oak Consulting is working on the rate study which it is
anticipated will be presented to the Commission later this year. Mr. Smaka reported
that OMI has begun work on the meter replacement project. Mr. Smaka stated the Lift
Station 5 improvements are nearing completion; all the electrical systems are in and
crews are waiting for the pumps to be delivered and this project should be completed
by June. Mr. Smaka reported that the replacement of existing 12" clay pipe sewer line
in the area of the Bisti Highway and Murray Drive is 90% complete.
-2
4. Water/Wastewater Operations Report:
Mr. Rosen offered a PowerPoint presentation which discussed the issue ofTDS (Total
Dissolved Solids) and the EPA's requirements for reducing TDS levels. Mr. Rosen
stated this is a presentation he gives at various local club meetings.
5. Major Status RepOit Engineering:
Mr. Armenta reviewed and discussed the many engineering projects and the
completion status of various projects.
Mr. Armenta discussed the GPS Point Inventory project presently underway which
will locate, photograph, catalog and store every piece of distribution equipment from
the substation to the meter in the FEUS GIS data base. Mr. Armenta stated this project
will offer many benefits including the basis of an outage management system.
Mr. Armenta introduced the project manager for this project, Ms. Kris Cope, FEUS
GIS Technician . Ms. Cope reviewed a map of the FEUS service area where the
contractor, Chappel Mapping is presently gathering this GPS inventory data .
6. Electric Utility Report:
Ms. Nipper presented the April and year to date Electric Utility Report.
General discussion took place regarding the information presented by Ms . N ipper.
7. Director's RepOlt:
Mr. Sims reported that the Navajo plant is not running at this time due to low river
flows. Mr. Sims stated the Bureau of Reclamation is not going to have a spring release
in the interests of recovering the reservoir levels. Mr. Sims stated San Juan Units 3 and
4 are on line, but are at reduced load due to issues with the use of low quality coal. Mr.
Sims stated an outage occurred at the Bluffview plant due to the detection of metal in
the lube oil. Mr. Sims stated this was determined to be a minor issue and was
corrected and the unit is back on line.
Mr. Sims stated that Business Operations/Customer Service has been dealing with
issues with the IVR phone system; staff has been working with the vendor to resolve
these issues.
Mr. Sims stated there are on-going effOits in progress for an NPDES outfall
construction contract and outside engineering services contract in support of NPDES
outfall construction at the Bluffview plant.
Mr. Sims reported that a new map board has been installed in the Control Center at the
Municipal Operations Center.
IIl. ADJOURNMENT
There being no further business to come before the Commission, upon motion duly
made and seconded, the meeting was adjourned .
The meeting was adjourned at 4:45 p.m.
Approved this 11th day of June, 2014.
Amanda Weese, Chair
-3
CITY OFFARMINC;TON- PUBLIC WORKS DEPARTMENT (PW) ,
Division: Water·Wastewater I Program: Water & Wastewater
Report Prepared by: Jeff Smaka I Title: Waterl Wastewater Administrator
Reporting Period: May 1,2014 through May 31,2014 I PUC Meeting Date: 4 June 14
,
,-,' .ACCOMPLISHMENTS
"
• Waste Water Treatment Plant. Phase III Design - HDR Engineering has submitted the design
drawings for the plant upgrades. Staff is reviewing the layout and design flow capacity of the
proposed improvements. Construction of Medium Rate Activated Sludge (MRAS) basin in 2015
budget to provide redundancy at the WWTP and maintain compliance with EPA permit. NMED
approved funding the waste water treatment plant upgrade through the Clean Water State
Revolving Loan Fund (CWSRF) program. Estimated project cost $14,000,000.
• 0& M Contract. The current 8 year Operation and Maintenance Contract with CH2MHILL OMI
nd
expires on Dec 31, 2015. City Council approved the contract 2 amendment for the installation of
the water meters by CH2MHILL.
• Utility Rates. Red Oak Consulting working on the rate study.
• Engineering Design Contract.
o 2P Waterline Project - HDR has submitted 90% design drawings. City Council included
this project in the City's Infrastructure Capital Improvement Plan submitted to the state
estimated cost six million dollars.
o LaPlata Highway - Project redesign for water line replacement to be completed by City
staff. Will be submitting revised highway construction permit to NMDOT for approval.
• Capital Project Review.
o Capital Improvement Project
• Meter Replacement - NMED: Drinking Water State Revolving Loan Fund
Program. Loan amount $5,959,000. Water meter installation will be done by
CH2MHILL OMI. Meter installation began on May 22,2014.
o Renewal and Replacement
• Wildflower Parkway - 4P Pump Station - Cheney-Walters-Echols (CWE) is
designing pump station along with survey for acquiring property for pump station.
Budgeting for the construction of new pump station FY14.
• Blake St - Main to Apache - Replace existing 6" CI waterline with an 8"PVC
waterline - completed.
th
• 20 St - Municipal to Sunset - Replace existing 24" and 16" steel waterline Street
with a 24" PVC and 16" PVC waterline. - Construction 30% complete.
• Foothills Dr. - Main to Hill N Dale - Replace Existing 16" steel waterline - design
in process
rd th
• Santiago Av - 23 St to 25 St - Replace existing 6" CI waterline with a 8" PVC
waterline - Summer 2014
o Pressure Reducing Valve (PRV)
• PRV installation at Main Street and Gila Street - Construction completed.
• PRV installation at Main Street and Red Lobster - Construction 95%complete
o Sewer Main Extension
• Lift Station 5 Improvements - RMCI of Albuquerque - Rehab of the existing lift
station which includes the mechanical, pumping equipment and electrical systems
of lift station 5. Notice to Proceed for July 22 - Phase 1 of the project is the
reconstruction of the wet well, replacement of the piping and mechanical system.
Phase 1 is 98% complete, Lift Station is back in operation : Phase 2 - Electrical
submittals are being reviewed by HDR Engineering Inc. - Notice to Proceed
issued - electrical equipment on-site. Estimated completion June 30, 2014 .
• Lift Station 3 Improvements - HDR Engineering is designing the rehab of the
existing lift station which includes the mechanical, pumping equipment and
electrical systems. Design to be completed June 2014 . Construction summer
2014.
• Lift Station 2 Improvements - HDR Engineering is designing the rehab of the
existing lift station which includes the mechanical, pumping equipment and
electrical systems . Design to be completed July 2014. Construction fall 2014.
-3
• Bisti Hwy & Murray Drive - Replacement of existing 12" Vitrified Clay Pipe sewer
line an increased capacity with a 18" PVC sewer line. - Construction is 98%
complete
• Operational Review.
• Human Resource Issues. Job evaluations.
• Positions none
• Budget. - FY15 - budget presented to PUC on April 2, 2014.
• COF Department Support. Survey support to acquire manhole data for future sewer collection
system model continues
• Annual Utility Contract. - Annual utilities contract awarded to TRC Construction.
• Federal Funding
o Water Projects - Meter Replacement Project
• City Council to approved final loan application to New Mexico Finance Authority
(NMFA) - loan documents completed in January 2013.
o Wastewater Projects - submitting for funding in 2014
• WWTP - MRAS Basin, Final Clarifier, Solids Handling Facility & UV Disinfection
NMED funding source is the Clean Water State Revolving Loan Fund (CWSRF)
Program - Project approved by NMED, on Nov 5 City Council approved
permission to draft ordinance as required by NMED for loan. Michael Groshek
with Sherman and Howard submitted preliminary draft ordinance to [\IMED for
their approval.
• PRO"IECTS I INITIATIVES REQUIRING INTER-DIVISIONAL COORDINATION
• Farmington Reach - Navajo Municipal Pipeline.
o Working with Bureau of Reclamation and Navajo Tribe for agreements to transfer title to
the City for the tank and pipeline project along with an Operation, Maintenance and
Replacement (OM&R) agreement as required by Federal law - March 2009.
• WWTP NPDES PERMIT - EPA. City has received the EPA final permit. New permit went into
effect on November 1, 2010, permit expires October 31, 2015. - City staff and OMI are reviewing
the permit regarding Total Dissolved Solids (TDS) limits 400mg/1 requirement. On July 19,2013
the City received an Administrative Order (AO) from EPA Region 6 which specifies the activities
the City is to accomplish along with due dates for each activity, these tasks and due dates
correspond to those proposed in the City's letter to EPA. All tasks as outlined in the AO have been
completed the report has been submitted to EPA Region 6.
• Snowpack - Water Year 2013 - BOR reporting site: off line until fall 2014
• Animas River Basin - %
• San River basin - %
o
ATT ACHMENTS
WATER USAGE - COMMERCIAL CUSTOMERS
WATER FUND (602) - RENEWAL & REPLACEMENT
WASTEWATER FUND (603) - RENEWAL & REPLACEMENT
GRAPH WATER REVENUE FY 10 - FY14
-3.1
Commercial Classification
Usage - Gallons
300.000.000
V 250,000.000
0
200,000,000
150,000,000 - 2013
U . SYRAVG
100.000.000
m
50,000,000
e
Month - Fiscal Year
Commercial Classification
Usage - Gallons
300,000,000
250,000,000
V 200,000.000
0
150,000,000
U
- 2013
_ SYRAVG
m
100,000,000
e
.
50,000,000
o
~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~
Months - FIscal Year
-3.2
WATER
Renewal & Replacement
Water Fund - 602
FY10 FY11 FY12 FY13 FY14 FY14
REVENUES Actual Actual Actual Actual Y-T-D Budget
I I Renewal/Replacement Fee $1,733,666 $1,943,342 $2,018,436 $2,037,806 $1,707,104 $2,082,909
I I ------ --------- ------ ----- ------- -------
STATE GRANT - $825,000
REVENUE TODATE • $11,525,254
PROJECTED REVENUE FY07 - FY14 $13,608,163
FY10 FY11 FY12 FY13 FY14 FY14
Actual Actual Actual Actual Y-T-D Budget
EXPENDITURES
1602-5543 RENEWAL/REPLACEMENT
1651.70-60 Construction $1,375,293 $1,518,581 $1,706,469 $2,278,859 $1,585,129 $2,750,000
1 ---- ---- ---------- ----- ---------- -----
$9,770,965
Largo & Main PRV estimated $150,000
20th St - Red Lobster PRV estimated $150,000
Knollcrest Dr - Windsor to Klngsway actual $174,946
Holiday Dr - Windsor to Klngsway actual $100,368
Troy King - Piedras south to US 64 estimated $600,000
20th St - Municipal to Sunset estimated $995,000
Behrend - Apache to Commanche actual $73,904
Coyote Drive - LaPlata Hwy to end actual $65,870
Blake St - Main to Apache estimated $75,000
Foothills Dr - Hill & Dale to Main St estimated $700,000
N Court Av - Apache to S·hlprock actual $237,076
N Court Av - Shiprock to Main estimated $70,000
Schwartz - Broadway to Animas actual $62,175
E Main St - Plaza - Big Fat Greek estimated $100,000
Polyline Service Replacement estimated $100,000
Fire Hydrant 1950 Replacement estimated $100,000
$3,754,339
PROJECTED EXPENDITURES FY07 - FY14 $13,525,304
WATER RENEWAL & REPLACEMENT
$2,500,000
$2,000,000
r.n $1,500,000
~
..J
.Revenue
..J ClExpenditures
0 $1,000,000
c
$500,000
$0
Actual Actual Actual Actual Y-T-D
FY10 FY11 FY12 FY13 FY14
FISCAL YEAR
-3.3
WASTEWATER
Renewal & Replacement
Wastewater Fund - 603
FY10 FY11 FY12 FY13 FY14 FY14
REVENUES Actual Actual Actual Actual Y-T-D Budget
Charges for Utility Sef'Aces
I I Renewal/Replacement Fee $1,229,258
R ________
$1,385,827 $1,436,494 $1,441,591 $1,212,640 $1,494,391
I I ------ -------- --------- -------- -------
REVENUE TODATE $7,476,563
PROJECTED REVENUE FY07 - FY14 $8,970,954
FY10 FY11 FY12 FY13 FY14 FY14
Actual Actual Actual Actual Y-T-D Budget
EXPENDITURES
603-5543 RENEWAL/REPLACEMENT
751.70-60 Construction $592,933 $1,152,988 $501,814 $685,848 $943,053 $1,257,531
-------- ------- ----- ------ ---------- --------
Subtotal Capital $592,933 $1,152,988 $501,814 $685,848 $943,053 $1,257,531
Projects FY07- FY13 $4,364,995
Lift Station #5 Rehab $915,000
MRAS Basin $1,000,000
Lift Station # 3 Rehab $800,000
Murray Drive Sewer Rehab $250,000
Sewer Rehab $500,000
Scrubber Rehab $250,000
Manhole Rehab $150,000
Mainline Rehab $300,000
PROJECTED EXPENDITURES FY07 - FY14 $8,811,624
-3.4
OFY10
FY11 Total Water Revenue Per Month
FY12 FY10-FY14
. FY 13
. FY 14
2,000,000
1,800,000
1,600,000
1,400,000
1,200,000
1,000,000
800,000
600,000
400,000
200,000
JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN
BUDGET TO ACTUAL COMPARISON PER MONTH
FY 2010" FY 2011 .. FY 2012 •• FY 2013 ** FY 2014 **
Budget Actual Budget Actual Budget Actual Budget Actual Budget Actual
JUL 1,067,568 1,322,552 1,107,254 1,485,229 1,176,228 1,630,402 1,165,141 1,696,293 1,196,227 1,657,429
AUG 1,067,568 1,420,178 1,107,254 1,303,558 1,176,228 1,588,665 1,165,141 1,725,060 1,196,227 1,495,029
SEP 1,067,568 1,290,632 1,107,254 1,330,247 1,176,228 1,410,448 1,165,141 1,362,607 1,196,22 7 1,349,906
OCT 1,067,568 1,010,908 1,107,254 1,1 10,501 1,176,228 1,184,374 1,165,141 1,338,557 1,196,227 (123,250
NOV 1,067,568 735,252 1,107,254 886,031 1,176,228 887 ,002 1,165,141 936,091 1,196,227 805,566
DEC 1,067,568 791,478 1,107,254 810,541 1,176,228 832,980 1,165,141 839,767 1,196,227 813,492
JAN 1,067,568 760,713 1,107,254 835,520 1,176,228 851 ,299 1,165,141 851,542 1,196,227 838,647
FEB 1,067,568 740,561 1,107,254 838,187 1,176,228 813,970 1,165,141 401,518 1,196,227 818,588
MAR 1,067,568 727,418 1,107,254 824,263 1,176,228 823,706 1,165,14 1 788,759 1,196,227 812,113
APR 1,067,568 889,702 1,107,254 951,749 1,176,228 1,028.028 1,165,141 958,767 1,196,227 989,646
-
,
MAY 1,067,568 ' 1,099,110 1,107,254 1', 116,639 1,176,228 1,317,793 1,165,141 1,194,193 1,196,227
JUN 1,067,568 1,521,671 1.107,254 1,425,556 1,176,228 1,570,209 1,165,141 1,520,186 1,196,227 -
TOTAL: I 12,310, 175 12,918,021 1 13,938,876 1 13,613,340 I 10,703,666
REVENUE PER CLASS/CUSTOMERS
FY 2010 FY 2011 FY 2012 FY 2013 FY 2014
Budget Actual Budget Actual Budget Actual Budget Actual Budget Actual
R 5,901,722 5,742,019 6,338,837 5,962,727 6,275,000 6,509,749 6,481.728 6,464,202 6,676,180 4,842,638
GS 3,400,119 2,923,899 3,294,004 3,081,024 3,458,704 3,441,527 3,447,238 3,107,129 3,550,655 2,631,149
CU 1,247,750 994,443 1,062,666 1,118,738 1,117,925 1,096,582 1,129,104 1,123,093 1,151,686 863,588
REC 212,000 205 ,146 227,751 217,349 210,000 264,281 225,000 264,196 250,000 172,192
FH 92,225 80,933 96,793 89,526 125,000 112,642 118,750 76,419 118,750 81,070
R&R 1,419,550 1,733,666 1,744,954 1,943,342 1,910,000 2,018,437 2,055,322 2,037,805 2,082,909 1,707,104
GRANTS 10,82 1,688 5,814,967 3,226,226 1,292,048 500,000 284,788 2,510
OTHER 537,453 630,069 1,740,218 1,720,237 1,018,114 747,207 524 ,552 2,595,398 524,552 405,925
TOTAL: 23,632,507 18,125,142 ' 17,731 ,449 15,424,991 14,614,743 14,475,213 13,981,694 15,670,752 14,354,732110,703,666
SCHEDULE OF CUSTOMERS
R Residential
GS General Service,
Single (commerical
CU Contract Users (bulk water users)
REC Recreational/Raw
WaterWater Users
(city facilities and
FH Fire Hydrants
R&R Renewal & Replacement
OTHER Miscellaneous
-3 ,5
CH2MHILL
~.... OMI
Monthly Activity Report
May 2014
Prepared for
City of Farmington, Public Utility Commission
-4
ADMINSTRATION OPERATIONS
Safety Training and Incidences as of 5-27-14
TAILGATE TOPICS MAY 2014 YTD
Total Safety Training Hours 135 899.5
Incidences/accidents 0 3
Motor Vehicle Incidences/accidents 0 0
DELIVERABLES FOR DISTRIBUTION & COLLECTION SYSTEM
Deliverables as of 5-27-14
TASK TARGET YTD % COMPLETED
Pressure Regulator Inspection 59 6 10%
Valve Exercise 4624 337 7%
Storm Drain Cleaning 821 57 7%
Dead End Main Flushing 492 246 50%
Sewer Main Cleaning 6" - 24" 307560 134050 44%
Sewer Main Cleaning 24" - UP 9800 2300 23%
Sewer Main Video Inspection 184800 69786 38%
Fire Hydrant Inspection 2600 429 17%
Air Relief Valve Inspection 149 148 99%
Water breaks as of 5-27-14
MAY 2014 YEAR-TO-DATE
Main line breaks 3 Main line breaks 23
Service line breaks 6 Service line breaks 48
Estimated water loss for May => 29,300 (gallons)
New Meters and Sewer Taps as of 5-27-14.
MAY 2014 YEAR-TO-DATE
NEW METERS 13 52
SEWER TAPS o 41
-4.1
WATER TREATMENT OPERATIONS
Farmington Lake Elevations - Monthly Average Comparison for May 2013 and 2014
563700
...... •••••••••• • ••••••••• •••••••••• • •••• )
5636.00
,.,..
5635.00
.,;'
" ..., ~
E
5634.00
I ............. ./'
e
v
5633.00
a
5632.00
t
i
5631.00
0
n
5630.00
Jan Feb Mar Apr May
-2013 5634.68 5633 .63 5634.58 5634.77 5635.02
2014 5633.02 5633.37 5634.75 5635.93 5636.13
Max Lake Capacity 5636.41 5636.41 5636.41 5636.41 5636.41
Water Treatment Plants - Total Effluent to System Comparison for May 2013 and 2014
500
450
400 ~
~
~
350
.
,....
./'
--- -
300
v;
c:
.2 250
-' ';;'' ~
.~ ~
-2c: 200
VI
.2
-ro 150
~
100
50
0
January February March April May
-2013 257.025 218.347 258.694 329.580 414.543
1'---;2014 243.941 227.214 272.812 338.938 286.926
-4.2
WASTEWATER TREATMENT OPERATIONS
FLOW
6.00
5.50
5.00
~
4.50 ~
~ ~ ~ ~
~ ~ ~ ~
~ ~
~ ~
4.00
~ ~ ~
~ ~ ~
~
3.50
~ ~ ~
~ ~ ~
~
3.00
~ ~ ~
~ ~
~
2.50
~ ~ ~
2.00
~ ~ ~ ~
~ ~ ~ ~
1.50
~ ~ ~ ~
~ ~ ~ ~
~
1.00
~ ~ ~
0.50
~ ~ ~ ~
~ ~ ~~ ~
~
0.00
Jan Fe~ Mar Apr May Jun Jul Aug Sep Oct Nov Dec
_INF 5.20 5.08 5.12 5.24 5.20
~EFF 4.71 4.62 4.66 4.83 4.71
-LIMIT 6.67 6.67 6.67 6.67 6.67 6.67 6.67 6.67 6.67 6.67 6.67 6.67
Final Effluent Total Flow [MG] 145.94
Final Effluent Average Flow [MG) 4.71
Total Number Septic Trucks 335
Total Gallons Septic Trucks 392,988
-4.3
OMR res NET INCREASE
.,.
~oo
.;oo-l-_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ __ --'..
"" "
·""If
:..:;
'~:::!If_
c!
'e"
'''''
200
100
III
Dole ( 11112014 10 l u.J112014 I
, OIolR TOS tf.:H IC~
PRETREATMENT ACTIVITES
• Collected samples for the WWTP monthly Technically Based Local Limits. Composed samples and
sent them to HALL Environmental for analysis.
• Held the household hazardous waste collection day. It was a success with 362 cars.
-4.4
Acronyms and Abbreviations
CM Corrective Maintenance
CMMS Computerized Maintenance Management System
gpd Gallons per day
gpm Gallons per minute
hp Horsepower
mg millions of gallons
mg/L Milligrams per liter
mgd Million gallons per day
NMED New Mexico Environment Department
NPDES National Pollutant Discharge Elimination System
O&M Operation and Maintenance
OMI Operations Management International
OOS Out of Service
PdM Predictive Maintenance
PM Preventive Maintenance
ppm Parts per Million
PRV Pressure Reducing Valves
PRVs Pressure Reduced Valves
QA/QC Quality Assurance/Quality Control
SCADA Supervisory Control and Data Acquisition
SMP Standard Maintenance Plan
SOP Standard Operating Procedure
TIHMs Trihalomethanes
-4 .5
USEPA U.S. Environmental Protection Agency
WEP Work Execution Plan
WWTP Wastewater Treatment Plant
-4.6
Get email alerts for Farmington
A daily email when new agendas and minutes are posted.