Airport Commission
Regular MeetingFitchburg, MA · November 29, 2017
Minutes
Fitchburg Municipal Airport Commission
Meeting Minutes
November 29, 2017
PLACE: Terminal Building
METTING TIME: 6:00PM
ATTENDEES:
Airport Manager Scott Ellis, Mayor DiNatale, Assistant Solicitor Christine Tree
Airport Commissioners: Chairman Naylor, Comm. Clayton Raymond, Comm. John Early, Comm. Richard
Liberatore Commissioner Kushmerek,
Note: Comm. Peter Kettle absent at this month’s meeting
1. Meeting Protocol Motion to suspend the reading of the protocol Motioned 2nd
Vote 4-0 (17-11-01)
Chair Naylor introduced the commission members in attendance.
Chair Naylor motioned request to record audio (granted) and approved
Commissioner Raymond and Airport Manager Scott Ellis request to record
audio.
2. Previous Month’s Minutes
Motion to accept October, 2017 airport minutes motion proposed by Comm.
Early accept minute’s seconded Comm. Liberatore Vote 4-0 (17-11-
02)
3. Correspondence to the Commission
1. Scott Ellis received a letter regarding an incident at the air port. A pilot
stated he was landing on the grass area adjacent to the runway and
struck a stick. Scott noted that this runway was not an official landing
area and was not published as an approved runway. This area is used at
the pilot discretion, land at your own risk. The city is not liable for the
minor damage it caused to the pilots aircraft. Scott spoke to the pilot’s
insurance company and they agree the Airport is not responsible.
4. Project Review-Gale
2. Runway Construction Armand Dufresne Senior Airport Planner of Gale
Associates Inc began the conversation with a brief history of the runway
project in order to update the Mayor and the current Commissioners on
the runway extension project.
3. Armand Dufresne of gale Associates submitted a copy of a memorandum
dated February 6 2012 provided by GZA Geo Enviromental, Inc. Subject:
Summary of test pit exploration and observations
4. Armand stated Airport commissioners as far back as far back as the year
2002 have requested to extend the runway to 5000 feet. During this
timeframe the city experienced a few different airport Managers resulting
in poor continuity on the subject. In 2012 the decision was made to move
the runway to 14 32 rotating the runway as far from the capped landfill as
possible. The environmental impact report was completed and published
by Gale and distributed. Since then no issues were raised by any of the
agencies involved to include DEP, FAA, DOT, etc. at that time. Armand
Dusfresne stated that the commission was asked to provide funding in
2013 & 2014 for further investigation to determine the extent of the land
fill boundary and depth.
5. Comm. Kushmerek Motion to delay last month’s decision to delay
nd
acquiring an opinion of a environmental company on how to proceed 2
Chair Naylor Vote 4-0 17-11-03
6. Motion to request Gale to invite Weston and Sampson to discuss with the
commission possible remedies for the solid waste solutions to
accommodate the proposed extended runway (Vote 4-0 17-11-04)
There are four (4) projects that Gale Associates, Inc. (Gale) is
administering on behalf of the Fitchburg Airport Commission. They are:
1. Phase III Avigation Easement Acquisitions and Permitting (AIP No. 3-
25-0018-24-2015)
Project Description: This project is a Phase III avigation easement
acquisition project to acquire avigation easements over approximately
22 parcels in the Runway 32 approach
surface, adjacent to the Airport. Additionally, this project includes
permitting efforts necessary to remove obstructions from the Runway
14-32 approach surfaces.
Project Cost: FAA Share: $ 2,183,850.00 (90.0%)
State Share: $ 121,325.00 ( 5.0%)
Local Share: $ 121,325.00 ( 5.0%)
Total Cost: $ 2,426,500.00 (100%)
Project Status:
• The property owner has received all required documents, and they
are circulating for signature.
• Execute the Certificate of Vote on Land and Easement Acquisitions.
This will get filed with a copy of the recorded easement for the
Airport’s records.
Actions Required by the Airport this month:
• Execute the Certificate of Vote on Land and Easement Acquisitions.
This will get filed with a copy of the recorded easement for the
Airport’s records.
Actions Required by the Airport this month:
Execute the Certificate of Vote.
Motion to execute to vote 4-0
2. Runway 14 End Obstruction Removal and Aeronautical Survey (Off
Airport Property)
AIP No. 3-25-0018-25-2015
Project Description: This project is an obstruction removal project to
clear obstructions
identified on nine (9) off-airport properties in the Runway 14 approach
surface, and to
complete an Aeronautical Survey.
Project Cost: FAA Share: $ 675,000.00 (90.0%)
State Share: $ 37,500.00 ( 5.0%)
Local Share: $ 37,500.00 ( 5.0%)
Total Cost: $ 750,000.00 (100%)
Project Status:
• Pending final acceptance by the Airport, all tree removal work has
been completed.
• The aeronautical study is underway. After some glitches with the
FAA’s Airport GIS system, we have gained access and the project has
been set up.
• Gale’s subconsultant (Col-East) has uploaded the statement of work
and technical plan, for review and approval by FAA and National
Geodetic Survey. We are currently awaiting their response.
• Compost log has been removed. Cook Forest Products has met all of
its obligations and Gale has prepared paperwork for Cook’s final
payment.
• The Aeronautical Study is ongoing. The final design of Runway 14-32
needs to be uploaded to the AGIS system as the next step. This step is
currently awaiting completion of final Runway design.
• Additional obstructions within the 15-degree offset approach are
eligible for removal under this project. Gale has reached out to Mike
O’Hara at the Conservation Commission to discuss the additional work
and the steps necessary to complete it. Gale will push for inclusion of
this work under the existing Order of Conditions.
• Addition of this work will require a Change Order for Cook and a
Supplemental Agreement for Gale.
Actions Required by the Airport this Month:
• None this month.
3. Runway 32 End Obstruction Removal (Off Airport Property) AIP No.
3-25-0018-26-2017
Project Description: This project is an obstruction removal project to
clear obstructions identified on up to twenty-seven (27) off-airport
properties in the Runway 32 approach surface in the City of
Leominster. One (1) property is partially in the City of Fitchburg.
Estimated Project Cost: FAA Share: $ 1,156,500.00 (90.0%)
State Share: $ 64,250.00 ( 5.0%)
Local Share: $ 64,250.00 ( 5.0%)
Total Cost: $ 1,285,000.00 (100%)
Project Status:
• FAA has made their grant offer, and City Council is expected to accept
the grant at their September 5, 2017 meeting.
• Gale has prepared the Contracts between Northern Tree Service, Inc.
and the City.These contracts have been fully executed by all parties, and
the bonds and insurance are in place.
• Gale has also prepared notification letters to the property owners.
These letters include an invitation to meet with Gale to gain a better
understanding of the project and what they can expect. A contact list
will be given to each land owner so they know who to call if they have
questions.
• Tree work began on September 11, 2017. The work is on-schedule as
of today.
• Contracts for the building modifications at 180 Crawford Street have
been fully
executed. Due to impending weather, this work will be completed in the
Spring.
• Contracts for the obstruction lighting have been fully executed. This
portion of the
project must wait until after the building modifications are complete.
Actions Required by the Airport this Month:
• None.
4. Shift, Rotate, Reconstruct, Mark, Light, and Sign Runway 14-32 and
Parallel Taxiway ‘D’; Construct Stub Taxiways ‘E’ and ‘F’; Install REILs
and PAPIs on Runways 14 and 32; and Install New Airfield Electrical
Vault AIP No. 3-25-0018-27-2018 (Pending)
Project Description: This project is to reconstruct Runway 14-32 with a
1.55-degree clockwise rotation, reconstruct parallel Taxiway ‘D’,
construct two (2) new stub taxiways,install Precision Approach Path
Indicators (PAPIs) and Runway End Identifier Lights (REILs)
on Runway 14 and Runway 32, install new airfield lighting and signage,
and install a new electrical vault. Runway 2-20 will be decommissioned
as part of this project.
Estimated Project Cost: FAA Share: $10,800,000.00 (90.0%)
State Share: $ 600,000.00 (5.0%)
Local Share: $ 600,000.00 (5.0%)
Total Cost: $12,000,000.00 (100%)
Project Status:
• A scoping meeting was conducted on April 10, 2017 at the Airport.
Peter Kettle, Rich Liberatore, and Richard Raymond were in attendance
on behalf of the Airport Commission. Scott Ellis and Debbie Silvar also
attended.
• Data collection (survey and soil exploration) began on August 24,
2017. The soil exploration work is complete, and we are awaiting the
design recommendations from the geotechnical engineer. Based on
material excavated during test pits at the Runway 14 end, there exists a
solid waste issue that needs to be addressed. Gale will be reaching out
to the Airport next week to schedule a meeting to discuss this.
• The survey work is ongoing; all data within the proposed Runway
environment has been collected, and once processed, Gale will be able
to develop the proposed Runway 14-32 profile. This will allow the
Aeronautical Study (part of AIP-25) to proceed.
• Taxiway ‘D’ will be renamed ‘A’ as part of the project, following
discussions with FAA and Scott Ellis.
• Preliminary geometry and lighting layout has been completed. The
preliminary drawing set was sent out for review on November 10,
2017.
• Buried solid waste at the Runway 14 end is complicating efforts to
finalize the runway and taxiway geometry. The current ground
conditions prohibit the construction of the Runway 14 end pavement in
traditional fashion. Metal, plastic,rubber, glass, ash, etc. were all
observed in most of the recent test pits. There are
options to remove or cap this material in place, but development of a
plan to construct pavement in this area needs to be established before
Runway design work can proceed.
• Gale spoke with Weston & Sampson, Inc., who are expert in solid
waste issues.W&S advised that the existing landfill cap adjacent to the
Airport may be able to be extended, which would eliminate the need to
remove the solid waste material. Structural piles (e.g. timber piles)
would need to be installed in order to build atop
the material in place.
Actions Required by the Airport this Month:
• Discuss the solid waste issue that exists at the Runway 14 end.
• Advise on the level of involvement expected from Gale on this issue.
5. Other Items:
• Runway 14 Approach Procedure for Future RWY 14: Need to request
removal of “noise abatement” note from procedure design notes, and
ask that new approach be designed to align with RWY 14 centerline.
Motion to instruct Scott Ellis to request in writing the noise abatement
removal to the FAA Motion Comm. Early 2nd Comm Liberatore Vote 4-
0 17-11-05
5. New Business
A. Proposed Airport events regulations Chair Naylor is creating
new regulations and has included the input of a couple of
neighbors and the Mayor of Leominster. Chair Naylor expects
to be completed by next’s months meeting.
Scott Ellis: informed the committee that some events may
require a 7460-1 to be submitted to the FAA 45 days in
advance.
B. Hanger Space: Scott Ellis Stated some space is available for
aircraft storage
C. Airport lighting (Unitil) Scott Ellis SRE light is going to be
replacing a light and pole over the gate.
D. FPA Christmas event Richard Girsch representing Fitchburg
pilots association is requesting a event on Saturday
December, 9 2017for a Christmas Party and December 10
Santa landing Motion Comm. Raymond 2nd and voted to
approve Vote 4-0 17-11-06
6. Old Business
A. Hanger 7 repair status Scott Ellis will hand deliver the request of
occupancy to the city hall. Previous attempts from the contractor have
gone unanswered. Action Scott to deliver request for occupancy to the
city hall.
B. FCA Lease status The abatement meeting was cancelled and subject will
be discussed next month.
C. Bullock Lease Mr. Bullock has received his notice from the Airport to
increase his rent and he intends to continue the lease. Note the Lear jet
currently in the hanger will be leaving permanently
D. Emergency and Security plan update Not completed at this time
7. Financial Review No action taken
8. Subcommittee Reports
Fact Lease Attorney tree has been in contact with Attorney May and expects
some action from FACT soon. Manager operation report
9. Manager report
The airport will receive a rental fuel truck while the other truck is repaired
Motion to adjourn Comm. Naylor seconded Comm. Raymond vote 4-0
(17-10-09)
Executive session Not required NONE
Conclusion 7:29pm
Next Airport Regular meeting will be Wednesday December
27, 2017 6 pm Recording Secretary Commissioner Clayton
Raymond
Agenda
Fitchburg Municipal Airport
November 29th, 2017-Airport Commission Meeting 18:00 Hours
Airport Terminal, 567 Crawford Street, Fitchburg, Ma. 01420
Please notify the commission chair to record the proceedings (Audio, video)
1. Meeting Protocol
Meeting called to order and recognize commissioners in attendance
Monthly approvals are year-month-sequence
Opportunities for the public to speak during a Commission Meeting
The public forum occurs immediately after the meeting is called to order
and the roll is called. The Chairman or designee will ask if anyone in the
Audience wishes to speak on any matter appearing on the agenda. If you
do wish to address the commission, please stand and be recognized and
follow these rules before speaking:
*Please stand, so you can be clearly seen by others in attendance.
*State your name and address.
*You may speak only on the items on the agenda for a period of time
In which the chair feels that you have explained your purpose.
If you are in attendance for a specific item on the agenda,
You may speak at that time only to the purpose of the agenda item.
2. Previous Months minutes-including special meeting minutes.
3. Correspondence to the commission
4. Project Review-Gale
A. Phase III Easements
B. Phase I,II Obstruction removal
C. Runway reconstruction
5. New Business
A. Proposed Airport events regulations.
B. Hangar space
C. Airport lighting (Unitil)
D. FPA Christmas event.
6. Old Business
A. Hangar 7 repair status.
B. FCA lease status
C. Bullock Lease
D. Emergency and Security plan update.
7. Financial Review-
8. Sub Committee Reports
a. FACT lease- subcommittee
9. Managers Operation Report
10. Date and time of next regular meeting:
11. Executive Session (If required) by Roll Call
a. FCA lease negotiation status.
It should be noted that after the regular meeting, the commission will go
into Executive Session (If required) and will not come back into open
session.
12.Regular Meeting adjourned at :
13. Executive Session began at; and adjourned at:
The Chairman or designee may take out of order any agenda
items with the majority vote of the commission.
Get email alerts for Fitchburg
A daily email when new agendas and minutes are posted.