Airport Commission
Regular MeetingFitchburg, MA · October 19, 2022
Minutes
Fitchburg Municipal Airport
Commission Meeting Minutes
October 19, 2022
LOCATION: City of Fitchburg Legislative Building
TIME: 6:02 PM
Attendees: Airport Commissioners: Chair Clayton Raymond, Richard Liberatore
Others in attendance: Airport Manager Peter Kettle, Gale Representative Jackie
Marks and Ibrahim Diarra, City Solicitor Pusateri, Director of City Economic
Development Mary Jo Bohart, and via zoom is Co-Chair Beth Walsh.
Meeting Protocol: Meeting called to order by Chair Raymond
C h a i r R a y m o n d i n t r o d u c e d t h e C o m m i s s i o n m e m b e r s a n d a l l o t h e r w h o were in
attendance at this meeting.
Previous Months minutes-including special meeting minutes:
Chair Raymond asked for a motion to accept the September Monthly Minutes.
Motion was made by Commissioner Walsh and 2nd by Chair Raymond to accept the
September Minutes. All in favor, 3-0. 22-10-01
Action Items for previous meeting:
Building 18-Ken MacLean: Mr. MacLean has started his HVAC project. The job
is not yet completed.
Action: Airport Manager Kettle
Valentine Eye Care: The new agreement has signed by all parties and the Airport
Manager Kettle did deliver the documents to Valentine.
Action: Airport Manger Kettle and City Solicitor Pusateri
Tie Downs (FPA-COOP): The City Solicitor will be drawing up an amendment to
the current Tie Down Lease advising rent payable on Sq. Ft. instead of Tie Down
rate.
Action: Airport Manager Kettle
RFP-7 and 9 Hangers: The joint efforts from Chair Raymond, Manager Kettle , Eric
Sheffels and his attorney at the City Solicitor's Office have put together a final draft
of the Lease Agreement proposal. There are just a few minor differences that need
attention and this should be a completed document very shortly.
Action: City Solicitor and Chair Raymond
Roofs for Hangers 2 and 3: It was discovered that the roofs had some minor leaks
in them and the contractor has come out to do the repair work to finish the roof
repairs.
Action: Airport Manager Kettle
Minimum Standards: This is still an ongoing document in progress.
Action: Airport Manager Kettle
Negal Agreement: The Airport has a signed and approved 20 year Lease
Agreement with Negal for Hanger 10. The Lease includes a 5 plus 5 option which
makes this a 30 year Lease. This agreement is completed.
GPU Unit: The Sale has completed for the GPU device and the Unit will eventually
be moved to the Administration Building once electrical installation is completed.
This may go out to bid.
Action: Airport Manager Kettle
Cullen Smith: Has shown interest in constructing a 40 to 45K sq. ft. Hanger. Mr.
Smith is waiting to see the results of the Airport Land Lease Agreement which is in
its final stage of completion.
Action: Airport Manager Kettle
Steven Dyke: The new Lineman at the Airport would like to receive benefits fron
the City but needs to work 20 plus hours to do so. Airport Manager Kettle needs to
set up a meeting with the Mayor to discuss the situation.
Action: Airport Manager Kettle
nce to the commission:
Just one from Direct Energy to the Chair. How the price of energy will be reduced in
the next 15 years.
Project Review-Gale: Monthly Project Update
Jackie Marks was accompanied by Mr. Ibrahim Diarra who is a Senior Staff
Engineer with Gale Associates.
Jackie Marks began her presentation by giving the Gale Monthly Updates on the
ongoing projects at the Airport.
Airport Master Plan and Airport Layout Plan update – AIP No. 3-250018-029-2021
The Airport Layout Plan has been signed by the Airport and MassDOT. FAA
confirmed that the ALP approval letter will be issued and the ALP will be signed
this coming week. Once the ALP has been signed, the project closeout report
and final reimbursement request can be submitted.
Environmental and Wildlife Hazard Assessment – AIP No. 3-25-0018-XX-2022
FAA confirmed that the Airport's AIP application submitted in April of this year
can be applied to the BIL grant. The package is under review by FAA and they
will let the Airport and Gale know if any additional items need to be submitted in
order to approve the BIL grant.
NewEarth Ecological, our Environmental Consultant, has been updated about the
project funding delay and confirmed that they are ready to begin the Wildlife
Hazard Assessment work once the grant has been awarded.
Other Gale Items:
The Airport Captital Improvement Program meeting with MassDOT and The FAA
did take place on September 29th , 2022.
Fitchburg Pilots Association (FPA)
Airport Manager Kettle stated that there was nothing to report.
New Business:
Minimum Standards – Item 2.3
Item 2.3 of the MS involves aircraft storage hangers. These hangers are designated
for the sheltering of and aircraft only. Maintenance of any kind will be done by the
aircraft owner only in this space. All other aircraft maintenance needs to be in said
hanger that is equip for maintenance duties.
Mr. William Taylor, a pilot on the airport aired his concerns on the MS Item 2.3. Mr.
Taylor thought that the MS's were very vague and unfair to the tenants at the
airport. He wanted the pilots to have the opportunity to have some say to the
Standards as they are being redeveloped. Mr. Taylor also stated that most pilots
and tenants would want to see a larger variety and choice of services at the city
airport.
Mr. David Straight, a pilot at the airport with an 80 year old aircraft stated that he
has to hire an outside mechanic to service his older plain because it takes a
mechanic with special skills to service his aircraft.
Chair Raymond stated that the understood that aircraft mechanics are coming in
from the outside but rules are in place that they need to get written approval from
the Airport Commission to conduct business here at the City Airport.
Airport Manager Kettle added that the MS are a document that keeps the tenants
and the residence of the City safe. Certainly a safety issue where the pilot himself
are the only person who can perform maintenance in a hanger used for storage of
an aircraft. Insurance coverage is also a requirement that would properly cover
the cost of any damage or negligence that could occur during aircraft servicing.
Mark Estabrook, President of FACT would like his group of pilots to have the
opportunity to review the MS document Item 2.3 and to share in putting together a
document that is fair and efficient for both the Airport and the FACT group.
Presently the document is very vague and gray and in need of maintenance itself as
it is over 50 years old and does not reflect the current status.
Action: Airport Manager Kettle
Twin City Airmotive Agreement
The operators of Twin City Airmotive have been presented with a new Lease
Agreement with the Airport. They are suggesting a 5 plus 5 plus 5 Lease. This
agreement would not have to go before our City Council for approval.
Action: Airport Manager Kettle and City Solicitor Pusateri
Hanger 1 Agreement
The two tenants of this hanger are in default on there payment to the Airport. One
Hanger has a Lease and the other Hanger is a tenant at will. They owe the City
Airport $ 17K. Airport Manager Kettle has sent them a letter requesting payment
by the end of October. City Solicitor and the Commissioners are aware of the issue.
Action: Airport Manager Kettle
G.P.U. (Ground Power Unit)
Wiring installation at he Admin Building may have to go out to bid.
Action- Manager Kettle
Old Business:
Mass Development Site Readiness. Mary Jo Bohart, Director of City
Community Economic Development informed the Commission that the
Consulting Team has faithfully been meeting Bimonthly in order to get the ground
work moving forward and getting closer to presenting a layout plan for the
Airports non-aviation property. They are hoping for an informal presentation in
he the next month or two. They are excited to get constructive feedback from the
Commission.
Action- Mary Jo Bohart / Ed Starzec
Tie Down. (FPA-Coop). The Airport Manager Kettle is working with our
Assistant City Solicitor Attorney Pawlok on a new Tie Down Agreement. Manager
Kettle is waiting for the Assistant Solicitor to get back to him.
Action- Attorney Pawlak / Airport Manager Kettle
The Pete Store. Action is on hold as this item is directly related to the
Airport Master Plan and the Airport Layout Plan (ALP).
Action- Assistant Airport Manager Deb Silvar
Convergent Energy. Action on hold as this item is directly related to the
Master Plan and the Airport Layout Plan (ALP).
Action- Gale
Financial Review:
Approval of Commitments and Abatement's.
There are none
Executive Session:
There is no executive session.
Next Regular Meeting:
November 16th , 2022 @ 6pm
Regular Meeting Adjourned:
Chair Raymond made a motion to adjourn the meeting at 7:39pm
Recording Secretary, Richard Liberatore
Agenda
FITCHBURG CITY CLERK
CITY OF FITCHBURG
Oct 17 2022 4:19 pm
NOTICE OF PUBLIC MEETING
AIRPORT COMMISSION
MEETING
MEETING DATE: Wednesday,October 19th - 2022
MEETING TIME: 6:00 PM
MEETING PLACE: LEGISLATIVE BUILDING.
FATVSTUDIOS
GOVERNMENT LIVE STREAM
COMCAST CHANNEL 99
VERIZON CHANNEL 37
AGENDA ITEMS:*
The public is invited to participate in the
Zoom webinar of
October 19th – 2022 @ 6PM.
Topic: Fitchburg Municipal
Airport Commission
Register in advance for the Public
Comment/Hearing portion of the
Agenda by going to:
https://us02web.zoom.us/webinar/register/WN_ETrOH83xSL2vQ_PWg2N-_Q
After registering, you will receive a confirmation email containing information about logging in to view/join the
Commission meeting electronically.
SEE ATTACHED AGENDA:
Peter E. Kettle – Airport Manager.
Name and title of person submitting this notice
*Please note: Massachusetts Open Meeting Law requires that all topics that the Chair reasonably anticipates must be listed and
that the list of topics must be sufficiently specific to reasonably inform the public of the issues to be discussed at the meeting.
1
Fitchburg Municipal Airport
October 19th - 2022 Airport Commission Meeting 6:00 PM
The public is invited to participate in the Zoom webinar
on October 19th - 2022 @ 6 PM
Topic:- Fitchburg Municipal Airport Commission
Register in advance for the Public Comment/Hearing portion of the Agenda by
going to:-
https://us02web.zoom.us/webinar/register/WN_ETrOH83xSL2vQ_PWg2N-_Q
After registering, you will receive a confirmation email containing information
about logging in to join the webinar.
Previous Months minutes Approval -including special meeting minutes.
1. Action items - from previous minutes?
2. Correspondence to the Commission. Yes
3. Gale – Review of ongoing work:-
A. Airport Master Plan update, incl. Environmental Assessment.
B. Draft Airport Layout Plan.
C. Standby Generator
D. C.I.P. meeting – Permit & Design for Main Apron.
2
4. Fitchburg Pilots Association
A. Update.
5. New Business
1. Minimum Standards – Item 2.3.
2. Nagle Agreement for Hangar 10.
3. Valentine Agreement – Sign on Erdman Way.
4. Twin City Airmotive Agreement.
5. Hangar 1 Agreement.
6. G.P.U – Installation.
6. Old Business
a. Mass Development Site Readiness - Airport Land (Tom S/Mary Jo B.)
b. Tie Downs. (FPA-Coop).
c. RFP - 7 to 9 Hangars Agreement.
d. Roofs for Hangars 2 & 3.
e. The Pete Store.
f. Convergent Energy.
g. Steven Dyke.
F. Financial Review
a. Approval of Commitments and abatements – BJ’s..
G. Executive Session.
No.
H. Date and time of next regular meeting: November 16th - 2022 @ 6.00PM at
Legislative Building.
I. Regular Meeting adjourned at :
The Chairman or designee may take out of order any agenda
Item’s with the majority vote of the commission.