October 16, 2024
LOCATION: City of Fitchburg Legislative Building
TIME: 6:02 PM
Attendees: Airport Commissioners: Commissioner Richard Liberatore, Commissioner Eric Tkal, and
Commissioner Paul Hathaway.
Others in attendance: Airport Manager Peter Kettle, and from Gale Associate is Jackie Marks.
Meeting Protocol: Meeting called to order by Commissioner Liberatore who is filling in for Chair
Raymond. Commissioner Liberatore introduced the Commission Members and all others who were in
attendance.
Previous Months Minutes-including special meeting minutes:
Commissioner Liberatore asked for a motion to accept the September Meeting Minutes. Motion was made
by Commissioner Hathaway and 2nd by Commissioner Tkal to accept the minutes as recorded.
All in favor, 3-0. 24-10-01
Action Items from Previous Meeting:
Action Items will be covered during the regular meetings agenda.
Correspondence to the Commission:
There were one correspondence sent to the Airport Commission this month and it will be discussed under
New Business in the agenda.
Project Review- Gale: Monthly Project Update
Gale Representatives Jackie Marks presented the Monthly project updated report.
Environmental Assessment and Wildlife Hazard Assessment: AIP 3-25-0018-034-2023
On September 25, 2024, the FAA and MassDot confirmed no additional changes to the Wildlife Hazard Site
Visit (WHSV) report were needed. New Earth could then begin developing the Wildlife Hazard
Management Plan (WHMP).
New Earth provided Gale with a pre-draft WHMP on October 11, 2024 for internal review. Gale reviewed
the document and provided comments on October 16, 2024. We anticipate a draft to the Airport for
review early next week. Once the WHMP is finalized, this project can be closed out.
There is no action required by the Airport.
Design and Permitting for Main Apron Reconstruction:
Gale Associates were pleased to announce that the preliminary design of the apron has begun.
No action required by the Airport at this time.
Groove, Seal and Remark Runway 14-32 (ASMP-2024-FIT-29 and ASMP-2024-FIT-30)
Gale Associates announced that the MassDot closeout report has been completed and sent to the Airport
Commission for review and signature.
No action required by the Airport.
Design and Install Wildlife Fencing (AIP 3-25-0018-0XX-2025-TBD)
A scoping meeting for this project was held on October 10, 2024.
A scope of work is being developed for this project, based on feedback received during the scoping
meeting. Once the scope of work is finalized, the Airport will need to solicit services for an independent
fee estimate.
Other Items: Medstar Legal- Gale assisted the Airport in preparing and submitting an FAA and
MassDot Grant Application to recover funds associated with the Medstar lawsuit. We are currently
preparing a request for reimbursement from the FAA and MassDot.
New Business:
VASI Lights:
Airport Mgr. Peter Kettle explained that the old (VASI), the Visual Approach Slope Indicator assembly that
our pilots use to make their approach into the Fitchburg Airport was replaced with an updated VASI
system and there was a person interested in purchasing our old assembly. Mgr. Kettle has been speaking
with Mr. Gerald Farwell, the owner of the Brookline N.H. Airport. Mr. Farwell knew that we had an old
VASI assembly and he was hoping to purchase our unused system for $100.00. Mgr. Kettle made note to
the Commission that we would never be able to use this old assembly and he was looking to the
Commission for their approval to sell off the assembly to Mr. Farwell.
Commissioner Hathaway made a motion to sell the old VASI assembly to the Brookline N.H. Airport for the
sum of $100.00. Commissioner Takl second the motion and the vote was carried. All in favor 3-0.
24-10-02
Action- Airport Manager Kettle
Terrain Tower Lights:
Airport Mgr. Peter Kettle explained to the Commission that there are 11 signal lights on poles that
encompass the valley that the Airport sits in. About 3 to 4 years ago the FAA was discussing whether or
not these pole lights had a purpose. Today's aircraft have built in systems that depict terrain, so the
question remains, are these pole lights really needed?
Airport Mgr. Kettle received a call from Mr. Robert Barry Leominster Ma. and he wanted to notify the
Airport that the Pole light at 191 Cross St. Lunenburg Ma. was not functional and has been out for over a
year. Mgr. Kettle investigated and found the burnt out light sitting on a 70 foot high pole. Mr. Barry was
hoping the pole could be removed if the light could not be repaired. Mgr. Kettle informed the FAA of the
situation and Mgr. Kettle had to file a form #7460 to the FAA. Mgr. Kettle added that whether or not we
remove or repair this pole light, there is going to be a significant cost involved. We are waiting for a
response from the FAA.
Action- Airport Manager Kettle
Old Business:
RFP for Non-Aviation Land Lease Update:
Airport Mgr. Kettle spoke in regards to the Non-Aviation Land Lease. Mgr. Kettle stated that the City Legal
Dept. has completed the Contract Agreement for the RFP and the document is presently in the hands of
our Chairman Clayton Raymond. This RFP is for the restaurant only.
Action- Airport Mgr. Kettle / Chair Raymond / Mary Delaney / Attn. Lisa Mead
Minimum Standards – Item 2.3
Commissioner Liberatore Tabled the discussion of the MS until Chair Raymond's return.
Action – Chair Raymond / Commission
Crawford Street Safety Update- Nick Erickson:
Airport Mgr. Kettle did speak with our DPW Commissioner Nick Erickson and the Chapter 90 State Grant
Funding has been approved. The Airport now has the money necessary for doing the guardrail work
closest to the Airport. Mgr. Kettle is hoping that the guardrail systems will be installed before the winter
months.
Action- Commissioner Erickson / Mgr. Kettle
Rocking Horse Enterprises:
Airport Manager Kettle stated that he has been in contact with the FAA regarding the construction idea's
for 30 new hangar's that we wish to pursue. Mgr. Kettle explained how we need the cooperation from the
FAA and the FAA permission to follow through on our idea's of how these new hangar's will sit on the
designated site.
The design for these hangars is for the hangar to catch as much sunlight as possible. This becomes more
crucial in the winter months where the sunlight will help keep the hangar doors from freezing up. Airport
Mgr. Kettle has submitted available dates to the FAA for a meeting with them so we can sit down and
explain our idea's and design's with them. This will then allow us to have a true site plan drawn up by the
engineering company. The most important thing at the moment is to get approval from the FAA so we can
continue to move forward in this planning stage.
Action-Airport Mgr. Kettle
After Hours Bathroom Facility:
The Commission will table this item until Chair Raymond returns.
Action- Airport Mgr. Kettle / Commission
Financial Review: Approval of Commitments and Abatement's:
Nothing at this time.
Next Regular Meeting: November 20, 2024 at 6pm.
Regular Meeting Adjourned:
Commissioner Liberatore made a motioned to adjourn the meeting at 6:41 pm. All were in favor.
Respectfully Submitted,
Richard Liberatore
Recording Secretary
Agenda
CITY OF FITCHBURG
NOTICE OF PUBLIC MEETING
AIRPORT COMMISSION
MEETING
FITCHBURG CITY CLERK
MEETING DATE: Wednesday 16th October - 2024 Oct 11 2024 8:32 am
MEETING TIME: 6:00 PM
MEETING PLACE: LEGISLATIVE BUILDING – 700 Main Street.
View the meeting live on:-
COMCAST CHANNEL 9
VERIZON CHANNEL 36
fatv.org/gov and or fatv.org/government
AGENDA ITEMS:*
The public is invited to participate in the
meeting – October 16th – 2024 @
6.00PM.
Topic: Fitchburg Municipal
Airport Commission
Register in advance for the Public
comment/Hearing portion of the
Agenda by going to:
https://us02web.zoom.us/webinar/register/WN_6lyM07A0SuK_L1rl3tec-Q
After registering, you will receive a confirmation email containing information about logging in to view/join
the Commission meeting electronically.
Meeting can be viewed live:- fatv.org/government - fatv.org.gov - Comcast Channel 9 or
Verizon channel 36.
SEE ATTACHED AGENDA:
Peter E. Kettle – Airport Manager.
Name and title of person submitting this notice
*Please note: Massachusetts Open Meeting Law requires that all topics that the Chair reasonably anticipates must be listed and
that the list of topics must be sufficiently specific to reasonably inform the public of the issues to be discussed at the meeting.
1
Fitchburg Municipal Airport
October 16th - 2024 Airport Commission Meeting 6:00 PM
The public is invited to participate in the Zoom webinar
on Wednesday – October 16th - 2024 @ 6.00 PM
Topic:- Fitchburg Municipal Airport Commission
Register in advance for the Public Comment/Hearing portion of the Agenda by
going to:-
https://us02web.zoom.us/webinar/register/WN_6lyM07A0SuK_L1rl3tec-Q
VOTE - - Previous Months minutes Approval - including special meeting
minutes.
Action items - from previous minutes.
1. Correspondence to Commission. Yes – see 4a.
3. Gale – Review of ongoing work:-
A. Apron Design & Permit - Runway 32/14 Grooving – Fencing - Wild
Life Hazard Assessment.
4. New Business
a. VASI – Lights.
2
b. Terrain Tower Lights.
5. Old Business
a. RFP for Non-Aviation Land Lease.
b. Minimum Standards.
c. Crawford Street Safety Update.
d. Rocking Horse Enterprises.
e. After Hours Bathroom facility.
F. Financial Review
a. Approval of Commitments and abatements .
G. Executive Session.
H. Date and time of next regular meeting: Nov 20th – 2024.
I. Regular Meeting adjourned at :
The Chairman or designee may take out of order any agenda
Item’s with the majority vote of the commission.
3
Get email alerts for Fitchburg
A daily email when new agendas and minutes are posted.