Water & Wastewater Commission
Regular MeetingFitchburg, MA · April 13, 2016
Minutes
FITCHBURG WATER & WASTEWATER
COMMISSION MINUTES
April 13, 2016
A meeting for the City of Fitchburg Water/Wastewater Commission was held on April 13, 2016
at the J.A. Provencial Water Treatment Facility Building 1200 Rindge Rd, Fitchburg MA, 01420.
The meeting commenced at 4:58 PM
Members present: Lenny Laakso, Commissioner DPW
Rick Healey
Ron Lubianez
George Siener
Others present: John Deline Jr., Deputy Commissioner of Water
Jeff Murawski, Deputy Commissioner of Wastewater
Janet Morrison, Member of North County Land Trust
Nina Nazarian
Members absent: Michael Mclaughlin
Item #1
Approval of last meetings minutes: Motion to approve minutes from March 9, 2016 meeting
was granted by unanimous vote.
Item #2
Public Forum: No public forum comments were received.
Item #3
Water Division:
Janet Morris of the North County Land Trust discussed the proposed FY17 Water Supply
Grant Application. The application is for conservation of 3 tracts of land in Ashby. She
asked that the commission recommend to the City Council approval of the grant
application for the Northern Watershed so it can be sent to the state. Council does not
need to vote on the expenditure of funds at this time. If and when the state approves
the grant we will come back to ask the city to vote to expend funds. Motion to approve
said grant application and send to city council was granted.
Motion was raised to recommend acceptance of the conservation restrictions acquired with
Forest Legacy funds for 3 tracts of land in the Southern Watershed. Motion to approve was
granted.
Janet also asked commission to authorize the reimbursement of $1500 of the $4500 appraisal
fee that land owner(Chernoch) will have to pay upon acceptance or conveyance of the
conservation restriction in Westminster. Motion to approve was granted.
Mr. Deline discussed with the commission the Lacava Pump Station which supplies water to the
Great Wolf Lodge. The pump station is approximately 25 yrs. old and is need of repair. Upgrades
to the pumps and the controls would greatly improve efficiency.
Mr. Deline also spoke about the River Street MassWorks Project Grant. He will be speaking to
Larry Cassasa and Dick Sarasin about borrowing money for water main infrastructure
improvement on River Street. Upgrades to the pipes are greatly needed for fire protection
safety, and also to eliminate deadlines that are going nowhere.
FY17 water budget was talked about briefly by Mr. Deline. He stated that it does not differ much
from FY16 water budget. He pointed out that David Berger is retiring in February so he
increased the Distribution Systems Manager salary about $14,000 to hire and train someone
before David leaves. Made some adjustments in expenses by moving a few things around like
the distribution repairs. We are also looking to save money by outsourcing the monthly bills.
Item #4
Wastewater Division:
Mr. Murawski started by informing the commission about the ongoing projects that are in the
works with Procurement, like the SSU(Secondary Systems Upgrade) Engineering for bid of
construction & post construction, the Beech/Hazel project and the CMHs Separation project. He
also let the commission know about the Wastewater On-call Services contract that will expire in
May of 2017 and the On-call Engineering contract for the DPW, Water/Wastewater divisions
that will expire in October of 2016. These items will also land with Procurement in the near
future. There are no active construction projects as of now, but we are coming into the phase
being it springtime.
Mr. Murawski also discussed with the commission the city’s Consent Decree, and what the SSES
(sewer system evaluation survey) is and what its purpose is. The system as of now has too much
infiltration/inflow from defective sewer pipe joints, breaks, manhole defects, rainfall, sump
pumps etc. that is flowing into the system which reduces the capacity and capability of the
system. He gave the commission several informational packets regarding the city’s code for
sewers, guidelines for performing and upcoming changes to Infiltration/Inflow Analyses and
SSES, he also gave the commission a copy of the Consent Decree.
Brief discussion about the FY17 Wastewater draft budget was held also. Mr. Murawski pointed
out a couple of changes in the line items but informed the commission that there wasn’t much
change from the FY16 budget for wastewater.
Item #5
Other Business: None
The next meeting is scheduled for May 11th, 2016 at 5:00 P.M. at the J.A. Provencial Building, 1200
Rindge Rd., Fitchburg, MA.
Meeting adjourned at 6:54 P.M.
Agenda
Water/Wastewater Commission
Meeting AGENDA
Wednesday – April 13th 2016
5:00 p.m.
J.A. Provencial Building
1200 Rindge Rd.
Fitchburg, MA 01420
1. Review minutes from March 9th, 2016 Commission Meeting
2. Public Forum
3. Water Division
Land Conservation Projects
- Northern Watershed:
A. Proposed FY-17 Water Supply Grant Application for conservation of 3 tracts in
Ashby
- Southern Watershed:
A. Votes to accept Conservation Restrictions acquired with Forest Legacy funds
B. Votes regarding the donation of a Conservation Restriction in Westminster
Lacava Pump Station
River Street MassWorks Project
FY-17 Water Budget
4. Wastewater Division
Procurement in-the-works:
a. SSU OPM. ….. SSU Engineering for bid, construction & post construction? ….
Bidding?
b. Beech/Hazel Project & CMHs Separation Project.
c. Wastewater On-Call Services Contract? (not in the works…..expires May 2017)
d. On-Call Engineering? (not in the works……expires October 2016)
Consent Decree 101:
a. What is “SSES”?
b. What is its purpose?
c. What will be the likely outcome/result of SSES?
d. Water ave. daily output: 3.7 MGD …. vs. …. Wastewater ave. daily flow to
headworks: 7.7 MGD
e. I/I ?!? … What is it? ….. What do you mean “the Code” prohibits it?
“FOG” ….and “NICE” Subcommittee efforts.
Wastewater FY-17 Budget.
5. Other Business
Set next meeting date and location
Adjourn