Water & Wastewater Commission
Regular MeetingFitchburg, MA · February 14, 2018
Minutes
Water/Wastewater Commission
Meeting Minutes
February 14th, 2018
J.A. Provencial Building
1200 Rindge Rd. Fitchburg, MA 01420
A meeting for the City of Fitchburg Water/Wastewater Commission was held on Wednesday February
14, 2018 at the J.A. Provencial Water Treatment Facility Building 1200 Rindge Rd, Fitchburg MA, 01420.
The meeting commenced at 4:34 pm
Members present: Lenny Laakso, Commissioner DPW
Rick Healey
Mike Mclaughlin
George Siener
Others present: John M. Deline., Deputy Commissioner of Water
Jeff Murawski., Deputy Commissioner of Wastewater
Mayor Stephen DiNatale
A.J. Tourigny, Chief of Staff to Mayor DiNatale
Carl Luck, Vice Chairman Lunenburg Sewer Commission
Mike Schrader, Engineer Tighe & Bond
Samantha Squailia., Councilor at Large
Janet Morrison., Land Conservation Consultant
William Shoemaker, Constituent
Jennifer Lambert Principal Clerk Water Office
Members absent: None
Item #1
Approval of last meetings minutes: Motion to approve minutes from January 10, 2018 meeting was
granted by unanimous vote.
Item #2
Public Forum: None
Item #3
Water Division:
Janet Morrison, land conservation consultant gave the Commission updates on the projects
currently in our Northern/Southern watersheds. Motion was also made to approve conservation
of the following properties: Wright property, 13.3 acres in Westminster with a probable fee sale,
the Nakrosis property, 56 acres in Westminster to be a conservation restriction, the Bomba
property, 40 acres in Princeton to be a conservation restriction. Motion to approve conservation
restrictions were granted by unanimous vote.
Regarding our MA DEP ACO, the state had given us a list of tasks to be completed by certain
deadlines. All deadlines have been met so far, with additional deadlines the end of this July and
also a few deadlines next year that have to do with our cross-connection, backflow program.
John next gave an update on the Oak Hill Storage Tank. We had a leak in that, and have had all
the cracks repaired that we could see, pressure washed everything, filled it back up a few weeks
ago and found that it is still leaking. The leak when first started was losing 8 gal a minute, and
the last week or two it’s been leaking approx. 3-4 gal a minute. The problem is the tank itself, it
is old and outdated and will need to be replaced at some point. We do need to do some work at
the top of the tank and replace the vent because it does not meet current standards. DEP’s main
concern is not that we are losing water. Their main concern is bacterial contamination have
other leaks in the system that we are not aware of, their main concern is bacterial
contamination if something were to get back in the system.
Our facility here on Rindge Rd, and also our treatment facility in Westminster have recently
undergone new lighting and energy efficient improvements. All lighting has been replaced with
LED lighting including our outdoor lights. They are also motion sensitive.
I have contacted MA DEP about the Gap Funding Grant and am waiting to hear back from them
regarding the in-line turbine up on narrows rd. at our pressure reducing station. I have heard
that we were probably going to get it and that the clean energy center said ok to all of their
parts. This will be a huge plus to get this grant, not only will the turbine generate electricity, but
this grant would basically pay for all of it.
Item #4
Wastewater Division:
Jeff started off by updating the Commission on the SSU project. The project is moving along and
is approximately 43% completed. Completion of the project in full will be sometime in October
of 2019.
City Code Chapter 147 & “Rules and Regulations” is still ongoing. Arcadis the city’s on-call
Engineering Services is helping with this task.
The Commission was also updated on a new “Past-Due” sewer service billing. Notification
correspondence was sent to the homeowner of New West Townsend Road. It seems the address
of 5 New West Townsend Rd, which is located in Lunenburg, has been tied into our sewer
service since the property was built, and we were not aware of this nor was the customer being
billed for service. The correspondence was sent using the updated City Solicitor Legal Review &
Interpretation dated March 22, 2017.
Wastewater Management Plan is also still ongoing. This is a remedial measure having 3 phases
with the first being submission, followed by two subsequent updates with a deliverable date of
July 1, 2018.
The Mass Dept. of Labor Standards completed a safety audit last August at the East plant. We
have completed all of the items on the list that was given to us for correction except for one. We
are working with Weston and Sampson to fix the final lock out tag out program. This is a very
involved process, so we have requested and received a time extension to complete this work.
Mike Schrader, Project manager from Tighe & Bond gave another more detailed presentation on
the City of Fitchburg’s Wastewater Rate Evaluation. The presentation provided a basic overview
of rate study basics, analysis, recommendations and the financial capabilities analysis. Motion
was raised for the commission to approve to adjust sewer billing rates as presented, and
indicate their preferred rate change alternative. Motion to approve rate change as a managed
monthly increase (alternative A) was granted by unanimous vote.
Item #5
Other Business:
The Water/Wastewater Commission will next meet at 4:30 pm on March 14, 2018 at the J.A.
Provencial Building 1200 Rindge Rd. Fitchburg, MA 01420.
Meeting adjourned at 6:36 P.M.
Agenda
Water/Wastewater Commission
Meeting AGENDA
Wednesday – February 14th, 2018
4:30 p.m.
J.A. Provencial Building
1200 Rindge Rd.
Fitchburg, MA 01420
1. Review minutes from January 10th, 2017 Commission Meeting
2. Public Forum: None
3. Water Division
Janet Morrison – Watershed land conservation
Project Updates
1. Northern Watershed
2. Southern Watershed
Vote to approve conservation of the following properties, in the Q2W Forest Legacy
Project:
1. Wright – 13.3 acres in Westminster, probable fee sale
2. Nakrosis – 56 acres in Westminster, conservation restriction
3. Bomba – 40 acres in Princeton, conservation restriction
MA DEP ACO - update
Oak Hill Storage Tank – update
Lighting/energy efficiency improvements at treatment plants
MA DEP Gap Funding Grant – update
Purchase of new utility service truck (heavy duty, enclosed)
4. Wastewater Division
Construction Projects (Updates):
o SSU Project
Status Update Items:
o City Code Chapter 147 & “Rules and Regulations”
o “Past-Due” sewer service billing notification correspondence (New West
Townsend Road); using the updated City Solicitor Legal Review & Interpretation
correspondence (dated: March 22nd, 2017).
o Consent Decree’s Wastewater Management Plan (WWMP)
o Massachusetts Department of Labor Standards – Safety Audit of the East Plant
Tighe & Bond presentation of …. “Sewer Rate Study”:
o Sewer Rate Model Study Update Presentation (by Mike Schrader, from Tighe &
Bond), and findings, including recommended rate scenarios.
o Jeff Murawski will request Commission vote to approve motion to adjust sewer
billing rates, as presented. It is also requested that the Commission indicate their
preferred rates change alternative.
5. Other Business
The Water/Wastewater Commission will next meet at 4:30 pm on March 14, 2018 at
the J.A. Provencial Building 1200 Rindge Rd. Fitchburg, MA 01420
Adjourn