Water & Wastewater Commission
Regular MeetingFitchburg, MA · December 12, 2018
Minutes
Water/Wastewater Commission
Meeting Minutes
December 12th, 2018
J.A. Provencial Building
1200 Rindge Rd, Fitchburg MA 01420
A meeting for the City of Fitchburg Water/Wastewater Commission was held on Wednesday December
12, 2018 at the J.A. Provencial Building, 1200 Rindge Rd, Fitchburg MA, 01420.
The meeting commenced at 5:06 pm
Members present: Lenny Laakso, Commissioner DPW
Rick Healey, Chairman
George Siener, Commission Member
Joshua Bedarian Commission Member
Mike Mclaughlin, Commission Member
Others present: John M. Deline., Deputy Commissioner of Water
Jeff Murawski., Deputy Commissioner of Wastewater
Jennifer Lambert Principal Clerk Water Office
Janet Morrison, Land Consultant
Members absent: Steven Bodurtha, Commission Member
Item #1
Approval of last meetings minutes: Motion to approve minutes from November 14, 2018 meeting was
granted by unanimous vote.
Item #2
Public Forum: None
Item #3
Water Division:
Jane Morrison started meeting off by updating the Commission on our latest land acquisition.
Said land is approx. 60 acres in Hubbardston MA near our watershed. This land is a donation
from the Dimmick Family Trust. Cost to the city would be minimal, as a title search will need to
be done, a baseline documentation report, closing costs, and attorney fees. Motion to approve
spending approx. $11,000 for the acquisition of said land was granted by unanimous vote.
John informed the Commission that at the end of November he sent over a revised schedule to
MA DEP on the remaining items to be fixed per our Consent Order. One major item is our Oak
Hill Tank, which either needs to be upgraded or replaced altogether. I have asked if this item can
wait until FY20 as we are in the process of upgrading our meter program and will not be able to
fit all projects in. We are waiting to hear back from MA DEP.
Operational issues continue to be a challenge here at the Falulah treatment plant. Our color
numbers are down from the mid-sixties to the thirties. Numbers are still high, but better than
they were. This plant runs between 1-2 mil gallons a day when it was designed to run approx. 6
mil gallons a day.
The Commission was updated on the quarterly results of disinfection byproducts. Organic
carbons that are already found in the water react with chlorine which then creates disinfection
byproducts. The limit for these byproducts are 80 parts per billion. All of our test sites were
below the limits with one at 74 parts per billion.
Regarding the Meter Upgrade Project, John informed the Commission that we are close to
awarding the bid. We are finalizing suppliers and numbers with the help from Purchasing.
Item #4
Wastewater Division:
Jeff informed the Commission of an audit that was conducted at the East Plant by MA DEP
December 4th through 6th. This audit was basically an overall view of how we’ve been
progressing with the USEPA’s Clean Water Act, Consent Decree and the NPDES Permit. At the
end of the three days, we had an exit interview which basically just recapped their observations,
and comments and recommendations.
Regarding City Code Chapter 147 & Rules and Regulations, Jeff informed us that the City
Solicitor has been briefed on the proposed ordinance change. Legal is reviewing it in more
depth, and will put a petition together and approach City Council on the proposed change.
Update was also given from Jeff on the CWMP. Tighe & Bond have already checked in with MA
DEP regarding the status of their review on the Phase 1 draft report. MA DEP reached out to
Tighe & Bond on Nov 27th and verbally communicated their comments on the Phase 1 draft
report. Tighe & Bond will incorporate those comments into a finalized Phase 1 Report by Dec
31st and also provide the city with a draft of the Phase 2 report. Regarding the WWMP, Weston
& Sampson began review of EPA agenda, including items related to the collection system and
preparing for the EPA meeting. They have also continued analyzing the City’s modeling files and
requested model output files.
Lastly Jeff gave quick updates on the Construction projects. The SSU project is 68% to substantial
completion, 64% to final completion and 81% of the contract price through the end of
November. For work completed over the last month or planned work for the month ahead, see
attachment. The next Combined Sewer Separation Project is under way. We continued
reviewing CCTV videos, conducted light cleaning and CCTV of sewers that are unable to be
televised by city forces. We have also conducted smoke testing, prepared the building
inspection kick-off packet for city review, requested gas improvement GIS layer from Unitil, and
began conducting dye testing/flooding on potential inflow sources identified during smoke
testing.
Item #5
Other Business:
The Water/Wastewater Commission will next meet at 5:00 pm. on Wednesday January 9, 2019
at the J.A. Provencial Building, 1200 Rindge Rd. Fitchburg MA, 01420.
Meeting adjourned at 6:03 P.M.
Agenda
Water/Wastewater Commission
Meeting AGENDA
Wednesday – December 12th, 2018
5:00 p.m.
J. A. Provencial Building
1200 Rindge Rd.
Fitchburg, MA 01420
1. Review minutes from November 14th, 2018 Commission Meeting
2. Public Forum: None
3. Water Division
Southern Watershed Area – Land Protection Projects
MA DEP – Consent Order (revised schedule)
Falulah Water Filtration Plant – Operational Issues
Disinfection byproducts – Quarterly Results
Meter Upgrade Project – Status update
4. Wastewater Division
USEPA’s Clean Water Act / Consent Decree / NPDES Permit Audit (Dec. 4th – 6th)
Status Update Items:
o City Code Chapter 147 & “Rules and Regulations” Presentation (by Kate Edwards, of
Arcadis). City Solicitor was briefed on the proposed Ordinance change, and counseled
on approach to City Council on the petition.
o CWMP (Tighe & Bond) Update:
The following work was completed in November:
Checked in w./MassDEP regarding the status of their review on the Phase 1
Report;
Comments on the Draft Phase 1 report were verbally communicated by
MassDEP to Tighe & Bond on Nov. 27, 2018. T&B anticipates incorporating
comments into a finalized Phase 1 report by Dec. 31st and providing the City
with a draft of the Phase 2 report by mid-Jan. 2019.
Continued drafting the Phase 2 Report, and the Massachusetts Environmental
Policy Act (MEPA) Environmental Notification Form (ENF).
The following work is expected to be completed in December:
Finalize Phase 1 report after incorporation of comments from MassDEP.
Continue drafting Phase 2 report and MEPA ENF.
o WWMP (Consent Decree)….(Weston & Sampson):
The following work was completed in November:
Began review of EPA Agenda including items related to the collection system
and preparing for the EPA meeting.
Continued analyzing the City’s modeling files and requested model output
files.
The following work is expected to be completed in December:
Continue preparing documents for the EPA Meeting.
Review model output files provided by the City.
Begin developing CSO Control Alternatives for the LTCP using T&T Cost
information and the hydraulic model.
Construction Projects (Updates):
o SSU Project
Completion: 68% to “Substantial Completion”, & 64% to “Final Completion”;
and Price: 81% of Contract Price (thru end of November 2018)
Work completed over last month included: (See Attachment).
Planned work over next month includes: (See Attachment).
Next Combined Sewer Separation Project (“CSO 039, 048 and Clarendon Street Project”):
Continued reviewing CCTV videos provided by the City.
Conducted smoke testing throughout the project area.
Prepared the building inspection kick-off packet for City review.
Requested gas improvement GIS layer from Unitil.
Began conducting dye testing/flooding on potential inflow sources identified during
smoke testing.
Began conducting light cleaning and CCTV of sewers in the project area unable to be
televised by City forces.
5. Other Business
The Water/Wastewater Commission will next meet at 5:00 pm on Wednesday
January 09, 2019 at the J.A. Provencial Building, 1200 Rindge Rd. Fitchburg, MA
01420.
Adjourn
Get email alerts for Fitchburg
A daily email when new agendas and minutes are posted.