Water & Wastewater Commission
Regular MeetingFitchburg, MA · March 11, 2020
Minutes
Water/Wastewater Commission
Meeting Minutes
March 11th, 2020
J.A. Provencial Building
1200 Rindge Rd, Fitchburg MA 01420
A meeting for the City of Fitchburg Water/Wastewater Commission was held on Wednesday March 11th,
2020 at the J.A. Provencial Building, 1200 Rindge Rd, Fitchburg MA, 01420.
The meeting commenced at 4:55 pm
Members present: Rick Healey, Chairman
Nicolas Bosonetto, Commissioner of Public Works
Steven Bodurtha, Commission Member
George Seiner, Commission Member
Joshua Bedarian, Commission Member
Others present: John M. Deline., Deputy Commissioner of Water
Jeff Murawski., Deputy Commissioner of Wastewater
Jennifer Lambert, Head Clerk Water Division
Absentees: Michael McLaughlin, Commission Member
Item #1
Approval of meeting minutes: Motion to approve minutes from February 12th, 2020 meeting was
granted by unanimous vote.
Item #2
Public Forum: None
Item #3
Water Division:
FY2021 Water Division Budget- Small discussion was had about minor changes within the
budget. Motion to recommend approval of Water Division’s FY21 Budget to City Council was
granted unanimously.
5-Year Capital Plan – John spoke to the Commission about the Water Divisions Capital Plan. This
plan prioritized infrastructure upgrades along with vehicles and equipment that might be
needed through the next five years. We will continue installing new water meters along with
electronic registers on all service lines and also install meter reading equipment through FY21.
We will also need to replace the roofs at six pump/PRV stations, install the inline turbine and
rehabilitate Narrows Rd. PRV station. Our Regional Plant will need a new roof, we will also be
upgrading our SCADA/Computer/Control systems at both the Regional and Falulah Water
Treatment Facilities. Other work that needs to be done will be to demolish and reconstruct the
Oak Hill water storage tank, replacement of the transmission main between Falulah plant and
Falulah storage tanks and water main replacement between the two water street bridges per
MA DOT.
Continuity of Service, Planning – The Commission was updated on the plans we at the Water
Division are taking to guard against the COVID-19 Coronavirus. We will continue to provide safe
drinking water as we always do. We have locked our gates and prohibited anyone that does not
work for the water dept. no access. We currently have one of our primary treatment operators
out on workman’s comp, and cannot afford for any of our treatment operators getting
quarantined or sick. They hold treatment licenses and are very essential to water treatment
operations. Fortunately, Steve Neal our Distribution Manager and I do have treatment licenses,
but are not familiar with the everyday practices and duties of our treatment operators. This
goes the same for our Distribution crew.
Item #4
Wastewater Division:
Fitchburg/Westminster Wastewater Intermunicipal Agreement – 2 year extension was granted
unanimously by City Council.
FY2021 Wastewater Division Budget- Small discussion was had about minor changes within the
budget. Motion to recommend approval of Wastewater Division’s FY21 Budget to City Council
was granted unanimously.
Construction Project Updates – SSU project 100% to Substantial completion, 88% to Final
completion due to the fact that the contractor will need to come back and fix some minor
system failures regarding clarifiers. 100% of Contract price through the end of February 2020.
Next Combined Sewer Separation Project – This project has been funded with a loan
authorization and we are very close to having the design bid documentation. Consulting
Engineer Weston and Sampson will be submitting contract documents to us for review and we
will return them with our comments for them to finalize and have ready to provide to the
procurement office.
SSES, Phase 4 Interceptor Sewer Evaluation – We are still moving forward with this. This is
where we are looking for excessive sources of infiltration & inflow. Engineers submitted draft
report to the city for review.
Combination Manhole Separation Project – Engineers are continuing to finalize the design plans.
We should be getting the bidding document pretty soon.
Siphon Cleaning Design & Bid, and Inspection Services Project – Engineers Weston & Sampson
finalized the contract documents based on City purchasing documents used with bid
advertisement. Documents have been provided to purchasing and we are anticipating receipt of
bids on March 19th.
Miscellaneous updates – We (wastewater division) will be participating in the FPS “STEM Gala”
event. We will debuting our new “Virtual Tour” of the Easterly Wastewater Treatment Facility.
Our 2020 Rain Barrels Program will be press released, and promotion will commence this
month. We also are preparing a Request for Expressions of Interest for a repurposing of the
Westerly Wastewater Treatment Facility. This will be a step 1 of a 2 step procurement process
that will be followed with a request for proposals.
Item #5
Other Business:
The Water/Wastewater Commission will next meet at 5:00 pm. on April 8, 2020 at the J.A.
Provencial Building, 1200 Rindge Rd. Fitchburg MA, 01420.
Meeting adjourned at 5:38 pm
Agenda
Water/Wastewater Commission
Meeting AGENDA
Wednesday – March 11th, 2020
5:00 p.m.
J. A. Provencial Building
1200 Rindge Rd.
Fitchburg, MA 01420
1. Review minutes from February 12th, 2020 Commission Meeting.
2. Public Forum: None
3. Water Division
FY2021 Budget
5-Year Capital Plan
Continuity of Service - Planning
4. Wastewater Division
Fitchburg/Westminster Wastewater Intermunicipal Agreement:
City Council update.
Wastewater FY-21 Annual Budget, Highlights Presentation.
Construction Projects (Updates):
o SSU Project
Completion: 100% to “Substantial Completion”, & 88% to “Final
Completion”; and Price: 100% of Contract Price (thru end of February
2020).
Work completed & planned work.
Next Combined Sewer Separation Project (“CSO 039, 048 and Clarendon Street
Project”) (Weston & Sampson): Update.
SSES, Phase 4 – Interceptor Sewer Evaluation (Weston & Sampson): Update.
Combination Manhole Separation Project (Weston & Sampson): Update.
Siphon Cleaning Design & Bid, and Inspection Services Project (Weston &
Sampson): Update.
Miscellaneous Updates:
Participating in Fitchburg Public School’s “STEM Gala” event at Fitchburg State
University’s Hammond Hall (Thurs. – Mar. 12th), where we will be debuting our
new “Virtual Tour” of the Easterly Wastewater Treatment Facility.
“2020 Rain Barrels Program” will be press released, and promotion will
commence this month (March).
Preparing to issue out a “Request for Expressions of Interest” (“RFEI”) for a
repurposing of the Westerly Wastewater Treatment Facility. This week, we
will/have received the drafting of the RFEI, from West Group Law, for City
review and comment. This RFEI will be a “Step 1” of a 2-step procurement
process, that will be followed with a “Request for Proposals”, which West Group
will also be assisting the City in preparing (which will partly be shaped by the
responses on the RFEI).
5. Other Business
The Water/Wastewater Commission will next meet at 5:00 pm on Wednesday April
8, 2020 at the J.A. Provencial Building, 1200 Rindge Rd. Fitchburg, MA 01420.
Adjourn
Get email alerts for Fitchburg