November 10th, 2021
Legislative Building, City Hall Campus
700 Main St, Fitchburg MA 01420
______________________________________________________________________________
A meeting for the City of Fitchburg Water/Wastewater Commission was held on Wednesday November
10th, 2021 at the Legislative Building, City Hall Campus, 700 Main St. Fitchburg, MA 01420
The meeting commenced at 5:03 PM
Members present: Nicholas Erickson, Interim Commissioner of Public Works & City Engineer
George Seiner, Commission Member
Michael Mclaughlin, Commission Member
Mark Piermarini, Commission Member
Stephen Bodurtha, Commission Member
Others present: John Deline., Deputy Commissioner of Water
Jennifer Lambert, Head Clerk Water Division
Nathan Glenny, FATV
Anthony Maressa, Sewer Collection Manager
Kasia Allen, Constituent – 68 Bilotta Way
Absent: Rick Healey, Chairman Water/Wastewater Commission
Item #1
Approval of meeting minutes: Motion to approve minutes from October 13, 2021 meeting was granted
by unanimous vote.
Item #2
Public Forum:
Motion was made by Mark Piermarini to reopen the case regarding 68 Bilotta Way, Fitchburg
Ma. George Seiner seconded the motion. Motion carries unanimously. Mrs. Kasia Allen spoke
again about not agreeing with the Commissions twice denial of this sewer abatement request.
No new information given by Mrs. Allen. Commission again discussed that abatements are not
given for irrigation purposes. No clear evidence that there was anything wrong with irrigation
system by Mrs. Allen, nor by Greg’s Irrigation Company. Many hours spent comparing water
consumption from years past and nothing out of the ordinary was found to support such
abatement. Motion to vote made by Mark Piermarini, seconded by Mike Mclaughlin. Motion
carries unanimously. Motion made by Mark Piermarini and seconded by Mike Mclaughlin to
uphold the Commission’s decision of denial of sewer abatement for 68 Bilotta Way that was
made on October 13, 2021. Motion carries unanimously.
Item #3
Water Division:
Falulah Transmission Main Project and SCADA Project – We experiencing some supply chain
issues regarding the replacement of the Falulah Transmission Main. Project was supposed to
start about a month. Contractors have been having trouble getting the 24 in pipe. We will have
to come up with a new schedule and are working on that. SCADA project is more or less the
same issue. Chip shortages are impacting this project.
Water Meter upgrade Project – The project is 96% complete. We have 10,864 out of 11,357
meters. We have been sending out shut off notices to our non-compliant customers, which has
worked out well. They are quick to call and make appointment. We also came across a few
vacant properties by doing this and water has been shut and wouldn’t be a problem this winter.
We have 493 meters left to change with approx... 184 meters with bad service lines. We are
going to put in for some of the ARPA funding to help some of these eligible (income wise)
customers with replacement of their service lines.
Oak Hill Storage Tank Replacement – Engineering should be done on this project by the end of
December and hopefully will go out to bid sometime near the end of January early February
2022.
Item #4
Wastewater Division
Combined Sewer Projects – Sewer replacement on Clarendon St. and Nashua St. contractors will
be working until the end of the year. CSO Water St. at Mid-town Beef and Market Basket will
start in two weeks.
Downtown Combined Sewer Project –Project on going. Borings are being set. Design and
Investigation work completed along with the smoke testing has been completed.
West Plant Anaerobic Digestion – RFP (request for proposal) due date had to be extended to
March 31, 2022. Needed more questions answered and this will give bidders a little more time
to put together there package.
East Plant Gravity Thickeners- We have received a draft OPM/RFP from our Purchasing Division
due to the cost of the project and Chapter 149. We hope to have this out within the next couple
of weeks.
Westminster IMA – Worked with Josh Hall DPW Director for the town of Westminster and
agreed to do a two year temporary agreement. This will give us tome to look into Westminster
having more flow. Flow meters to be installed near Monty Tech to monitor.
Lunenburg Sewer Ordinance update – We have not heard from the town of Lunenburg as of yet.
We will be reaching out to them within the next couple weeks.
Item #5
Other Business:
Interim DPW Director Nicholas Erickson spoke to the Commission on the recommendation of
appointment of Sewer Collection Manager Anthony Maressa to fill the vacant position of Deputy
Commission of Wastewater Division. Letter drafted on November 5th, 2021 and sent to
Commission. Motion made by Mark Piermarini of a favorable recommendation to the Mayor for
the appointment of Anthony Maressa to Deputy Commissioner of Wastewater. Mike Mclaughlin
seconded the motion. All were in favor. Motion carries.
The Water/Wastewater Commission will next meet at 5:00 pm. on December 8, 2021 at the
Legislative Building, City Hall Campus 700 Main St. Fitchburg MA, 01420.
Meeting adjourned at 6:07 pm
Agenda
FITCHBURG CITY CLERK
Nov 05 2021 3:02 pm
Water/Wastewater Commission
Meeting AGENDA
Wednesday – November 10th, 2021
5:00 p.m.
Legislative Building, City Hall Campus
700 Main St.
Fitchburg, MA 01420
Please note that the Legislative Building will be open to the public for this meeting. For any member
of the public that might not be ready to return to a public setting, they are invited to participate in the
meeting via the Zoom webinar of November 10, 2021 at 5 PM Eastern Time .
Topic: Water/Wastewater Commission Meeting
Register in advance for the Public Comment/Hearing portion of the Agenda by going to:
https://us02web.zoom.us/webinar/register/WN_9sEJUCAJQzWfxYNAQQgrgw
After registering, you will receive a confirmation email containing information about logging in to
join the webinar.
_____________________________________________________________________________________
1. Review minutes from October 13th, 2021 Commission Meeting.
2. Public Forum:
CONTINUED: 68 Bilotta Way - Hearing Appeal for denial of ‘Sewer Billing
Abatement Request’, Regarding Private Irrigation System Water Usage. Former
Deputy Commissioner of Wastewater Jeff Murawski along with the Water/Wastewater
Commission have both previously denied this appeal.
3. Water Division
Supply chain issues causing project delays (e.g., Falulah transmission main,
SCADA)
Water Meter upgrade project – update
Oak Hill Storage Tank Replacement - update
4. Wastewater Division
Combined Sewer Projects – Clarendon & Nashua St. until the end of year long with
CSO Closure – Water St. at Mid-Town Beef in 3 weeks
“Downtown” Combined Sewer Project – Smoke testing complete & survey started
West Plant Anaerobic Digestion – RFP due date to be extended to March 31st 2022
East Plant Gravity Thickeners – OPM will be placed out to RFP in mid-November
Westminster IMA
Lunenburg’s Sewer Ordinance update
5. Other Business
Deputy Commissioner of Wastewater Recommendation for Appointment
The Water/Wastewater Commission will next meet at 5:00 pm on Wednesday
December 8, 2021 at the Legislative Building, City Hall Campus 700 Main St.
Fitchburg Ma.