Water & Wastewater Commission
Regular MeetingFitchburg, MA · July 20, 2022
Minutes
Water/Wastewater Commission
Meeting Minutes
July 20th, 2022
Legislative Building, City Hall Campus
700 Main St, Fitchburg MA 01420
______________________________________________________________________________
A meeting for the City of Fitchburg Water/Wastewater Commission was held on Wednesday July 20th,
2022 at the Legislative Building, City Hall Campus, 700 Main St. Fitchburg, MA 01420
The meeting commenced at 5:15 PM
Members present: Nicholas Erickson, Commissioner of Public Works & City Engineer
George Seiner, Commission Member
Stephen Bodurtha, Commission Member
Colby O’Brien, Commission Member
Mark Piermarini, Commission Member
Rick Healey, Chairman
Others present: John Deline Jr, Deputy Commissioner Water Division
Mark McNamara, Interim Deputy Commissioner Wastewater Division
Jennifer Lambert, Head Clerk Water Division
Absent: Michael McLaughlin, Commission Member
Item #1
Approval of meeting minutes: Motion to approve minutes from June 15, 2022 meeting was granted by
unanimous vote.
Item #2
Public Forum: None
Item #3
Water Division
PFAS – New US EPA health advisories: Lots of talk about PFAS lately, being on the news and also
the issues in Westminster (which does not affect us). PFAS is described as a forever chemical,
meaning it doesn’t break down. EPA has issued some new health advisories regarding PFAS,
they have not set any regulations as of yet, those will probably come out in a year or so.
Fitchburg water supply is far below detection limits. Our detection limits right now are around
1.8 parts per trillion, EPA is talking about detection limits be at .004 parts per trillion which is
around 1000 times lower. These are just advisories of what they would like to see, whether it be
at or below. There are six compounds that MA DEP are concerned about and have stricter
standards. Those six compounds combined should be 20 parts per trillion, we are at 4.36 parts
per trillion which is well below the 20. We are in compliance which is a good thing.
Unfortunately, PFAS is everywhere in our environment.
Westminster PFAS issue – Area of contamination are isolated to wells and groundwater. There
are over 100 wells that have been contaminated in the area of Bean Porridge Hill Rd in
Westminster Ma. This does not affect our watershed nor is it in our watershed.
Current Drought Conditions – The State has currently listed Worcester County to be in a level 2
significant drought. This means that customers are advised to limit landscaping watering needs.
Limit watering to hand-held only or drip irrigation. Water after 5pm or before 9am to avoid
evaporative losses.
Material/Parts shortages & lead times – Shortages in parts and materials are impacting all. Our
Scada project delayed due to this issue. We’ve recently had some issues with a circuit breaker at
one of our pump stations, tried ordering a new one, and it six months out. We had to order a
refurbished one for the time being.
Item #4
Wastewater Division
5th Year Rain Barrel Program – July 19th rain barrels were distributed to those who had
purchased. We sold 81 barrels this year.
West Plant Refurbishing – We have since conducted an initial review of the proposal. We had a
clarification meeting yesterday July 19th, with the proposer Synagro. Biggest concern of course is
PFAS. Of course PFAS gets into the sludge being disposed.
Grief Paper/odors – We have received numerous residence complaints of strong odors in the
West Fitchburg area of the City near the West Plant. Recent meeting with Greif personnel, BOH
as well as us. Greif of course is blaming us or the dump. We are addressing this issue and are
trying to find the cause. One issue is that Greif waste does go over to the West Plant. Once
there, we pump it to the East Plant. Also its open air at the West Plant, so some of what people
are smelling could be because of this, but not to the extent that people are describing.
EPA/MA DEP site visit to East Plant – Site visit today 7/20 at the East Plant for inspection. Tour of
the plant and discussion on the consent decree along with recent upgrades to the plant.
Collection Systems Construction updates – South Street sewer drain repair should be completed
by the end of this month. We will then address the combined sewers in this area. This will begin
in August and will most like go through November. This is part of our consent decree.
Westminster IMA (inter-municipal agreement) – The Town of Westminster has since signed the
IMA. This item is now completed.
Item #5
Other Business:
The Water/Wastewater Commission will next meet at 5:00 pm on Wednesday October 19, 2022
at the Legislative Building, City Hall Campus 700 Main St. Fitchburg, MA.
Meeting adjourned at 5:39 pm
Agenda
FITCHBURG CITY CLERK
Jul 15 2022 12:57 pm
Water/Wastewater Commission
Meeting AGENDA
Wednesday – July 20th, 2022
5:00 p.m.
Legislative Building, City Hall Campus
700 Main St.
Fitchburg, MA 01420
Please note that the Legislative Building will be open to the public for this meeting. For any member
of the public that might not be ready to return to a public setting, they are invited to participate in the
meeting via the Zoom webinar of July 20, 2022 at 5 PM Eastern Time .
Topic: Water/Wastewater Commission Meeting
Register in advance for the Public Comment/Hearing portion of the Agenda by going to:
https://us02web.zoom.us/webinar/register/WN_16bTU_3ZRYiY1mFdhjCtnw
After registering, you will receive a confirmation email containing information about logging in to
join the webinar.
_____________________________________________________________________________________
1. Review minutes from June 15th, 2022 Commission Meeting.
2. Public Forum: None
3. Water Division
PFAS – New US EPA health advisories
PFAS – area of contaminated wells/groundwater in Westminster
Current drought conditions and reservoir levels
Materials and part shortages/lead times
4. Wastewater Division
Rain Barrel Program update – 81 Rain Barrels sold
West Plant Refurbishing update – Conducted an initial review of the proposal,
clarification meeting with Synagro on 7/19/22
Greif Paper odors – Numerous resident complaints from surrounding
neighborhoods, Meeting with City and Greif Paper
EPA/MADEP site visit to the East Plant – Scheduled for a site visit on 7/20/22
Collection Systems Construction updates
Westminster IMA (inter-municipal agreement)
5. Other Business
August recess – No meeting this month.
The Water/Wastewater Commission will next meet at 5:00 pm on Wednesday
September 21, 2022 at the Legislative Building, City Hall Campus 700 Main St.
Fitchburg Ma.
Adjourn