Water & Wastewater Commission
Regular MeetingFitchburg, MA · January 17, 2024
Minutes
Water/Wastewater Commission
Meeting Minutes
January 17th, 2024
Legislative Building, City Hall Campus
700 Main St, Fitchburg MA 01420
______________________________________________________________________________
A meeting for the City of Fitchburg Water/Wastewater Commission was held on Wednesday January
17th, 2024 at the Legislative Building, City Hall Campus, 700 Main St. Fitchburg, MA 01420
The meeting commenced at 5:01 PM
Members present: Rick Healey, Chairman
Nicholas Erickson, Commissioner of Public Works
Michael McLaughlin, Commission Member
George Seiner, Commission Member
Colby O’Brien, Commission Member
Others present: Mark McNamara, Deputy Commissioner Wastewater Division
John M. Deline Jr, Deputy Commissioner Water Division
Absent: Stephen Bodurtha, Commission Member
Item #1
Approval of meeting minutes: Motion to approve minutes from September 20, 2023 along with the
minutes from October 18, 2023 meeting were granted by unanimous vote.
Item #2
Public Forum: None
Item #3
Water Division
SCADA Upgrade Project – We are at a standstill right now with some of our equipment having to
be returned for manufacturing glitches. We had ordered new processers, and cards for the panels
and some of the parts that were manufactured on certain dates had to be returned to the
manufacturer to be redone. We had noticed that things were not running correctly, and were
having issues. There was a total of 17 that had to be returned. This will delay the project once
again. The good thing is that we completed all of the pump stations and can be monitored
remotely by FWD personnel.
Regional Water Treatment Plant – NPDES Permit –Our Regional Treatment Plants discharge
goes into the environment from a stream down to Wyman’s pond. Unlike our Falulah Plant where
the discharge goes right to the wastewater plant. Because of this, we need to meet new guidelines
on our Aluminum discharge. We have two years to meet the new stricter guidelines. We are
looking to file an extension for approx. 6 months to a year. There will be a lot of work to meet
these guidelines. Now that we know the discharge limits, we may need to come with a whole new
design on how we get rid of our aluminum discharge.
Boulder Dr/Main St Water Main upgrade – Boulder Dr. Water Main project is all designed and is
out to bid. Pre-bid conference next week, and then two weeks later we have the bid opening. This
will be phase one of the project. Boulder Dr. will have a whole new water main, as well as the
side streets which will facilitate in doing the Main St. project. The Main St. side is being designed
now, and will be done separately. There would be too much disruption traffic wise.
Meetinghouse Gatehouse & Mare Meadow Pump Station rehabilitation project – 4.4 Million for
this project, Meetinghouse Gatehouse is the last reservoir before the Treatment Plant. This is also
one of the projects that is on our consent order from MA DEP. The gatehouse is approx... 130-
140 yrs. old. It still uses traveling screens, which have been replaced multiple times and just
cannot be replaced any longer. Everything at the bottom of the reservoir will have to be brought
up and redone. We have a lot of power outages, heat problems and many others. The new
gatehouse will have a portable generator to cover these issues. Project is set to go out to bid late
spring. In addition to this, we also have our Mare Meadow pump station. This is our largest
reservoir, and the facility is in dire need of repairs. It was originally constructed in the 1950’s. We
will be doing the entire pump station, with new pumps, proper insulation along with a new roof.
Motion raised to recommend to the City Council to approve borrowing 4.4MIL for the
Meetinghouse Gatehouse & Mare Meadow Pump Station Project. Motion was granted by
unanimous consent.
Item #4
Wastewater Division:
SSO event at Birch Brook – October 30th, a call came in from a resident at 148 Heywood St.
about an odor issue. The odor was determined to be coming from the brook in the back of the
house. We went upstream and found that a raised manhole with a hole in its chimney was the
cause. This caused approx... 1000 gallons a minute to seep onto the brook. MA DEP, EPA, along
with Fitchburg and Leominster’s BOH’s were notified. Blue Diamond was called to assist us in
trying to locate the blockage. National Water Main was called to help us locate and figure out
what caused this. A rock was found around 13ft down sticking out of the pipe. Repairs were
completed by November 7th. Total cost for this was around $240,000
NPDES Permit – Our NPDES permit came in. We have been operating on our 2010 permit which
is good for 5 years and expired in 2015. We had reapplied for this back in 2015 when it expired,
and we received our draft permit in December. We have until January 28th for public comment.
Changes we have noted is that Westminster has been added as a co-committee for wastewater
sewer system. Big item noted was the lowering of our phosphorous limits. We have a consent
decree limit of .5 milligrams per liter, and they want to lower that limit down to .16. This is a
major concern, which would require more construction at the plant. We will try to extend this at
least until all the sewer separation projects are through.
CSO 10 – Polito Construction has ceased work through the winter and will pick back up in the
spring as soon as the weather allows. Final completion of this project is December 2024.
X-Cel Education – Nine minute video on how one company is training future water/wastewater
operators. They are located in Boston and come out to our treatment plant and train and teach
potential candidates.
Staffing update- Two positions, GIS engineer, and Sr. Wastewater Treatment Operator we have
interviewed candidates for. Waiting on HR to do what they do, so we can fill theses open
positions.
Item #5
Other Business:
We currently have an open position on the Water/Wastewater Commission if anyone is
interested. Stephen Bodurtha has recently resigned.
The Water/Wastewater Commission will next meet at 5:00 pm on Wednesday February 21,
2024 at the Legislative Building, City Hall Campus 700 Main St. Fitchburg, MA.
Meeting adjourned at 6:00 pm
Agenda
FITCHBURG CITY CLERK
Jan 09 2024 11:20 am
Water/Wastewater Commission
Meeting AGENDA
Wednesday – January 17th, 2024
5:00 p.m.
Legislative Building, City Hall Campus
700 Main St.
Fitchburg, MA 01420
Please note that the Legislative Building will be open to the public for this meeting. The public is also invited to
participate in the Zoom webinar of January 17th, 2024 05:00 PM Eastern Time (US and Canada).
Topic: Water / Wastewater Commission Meeting
If you wish to speak during the Public Comment/Hearing portion of the meeting, please register in advance by
going to: https://us02web.zoom.us/webinar/register/WN_CgGgBB1lRj2L-E_TkTaBXQ
After registering, you will receive a confirmation email containing information about logging in to join the
webinar.
_________________________________________________________________________________________
1. Review minutes from the September 20th, 2023 and October 18th, 2023 Commission Meetings.
2. Public Forum:
3. Water Division
SCADA Upgrade Project - update
Regional Water Treatment Plant - NPDES Permit - update
Boulder Drive/Main Street - Water Main Upgrade/Replacement Projects
Meetinghouse Gatehouse & Mare Meadow Pump Station - rehabilitation project, request to borrow
up to $4.4 million for said project
4. Wastewater Division
SSO event at Birch Brook on October 30, 2023
NPDES Permit - update
CSO 10 - update
X-Cel Education - 3.0 Public - X-Cel — TURNAROUND FILMS (turnaround-films.com)
Staffing Update
5. Other Business
Stephen Bodurtha – Resignation from Water/Wastewater Commission (one vacancy on Commission)
The Water/Wastewater Commission will next meet at 5:00 pm on Wednesday February 21st, 2024
at the Legislative Building, City Hall Campus 700 Main St. Fitchburg, MA
Adjourn