Water & Wastewater Commission
Regular MeetingFitchburg, MA · July 17, 2024
Minutes
Water/Wastewater Commission
Meeting Minutes
July 17th, 2024
Legislative Building, City Hall Campus
700 Main St, Fitchburg MA 01420
______________________________________________________________________________
A meeting for the City of Fitchburg Water/Wastewater Commission was held on Wednesday July 17,
2024 at the Legislative Building, City Hall Campus, 700 Main St. Fitchburg, MA 01420
The meeting commenced at 5:03 PM
Members present: Rick Healey, Chairman
Nicholas Erickson, Commissioner of Public Works
George Seiner, Commission Member
Joseph D. Byrne, Commission Member
Others present: Mark McNamara, Deputy Commissioner Wastewater Division
John M. Deline Jr, Deputy Commissioner Water Division
Absent: Michael Mclaughlin, Commission Member
Colby O’Brien, Commission Member
Item #1
Approval of meeting minutes: Motion to approve minutes from June 20, 2024 meeting were granted
by unanimous vote.
Item #2
Public Forum: None
Item #3
Constituent Proposal:
Jacquelyn Wehtje Fitchburg resident brought forward to the Commission her proposal to create
a tiered water/sewer rate system for properties that are not required to pay real estate taxes, or
pay reduced real estate taxes through a PILOT (payment in lieu of taxes agreement). Motion was
made by Chairman Rick Healey and seconded by Joe Byrne to request feedback from our City
Solicitor and consultants. Motion was granted by unanimous vote.
Item #4
Water Division
Boulder Dr. Water Main Replacement Project – Project is moving along well, a little slow right
now because we are in a tighter area between Putnam St. & lower Boulder Dr. Contractor is
working on replacing two water mains. Main St. over to Boulder, some with fire protection. Lots
of electrical conduits, gas, sewer, drains etc. Realignment was done down beneath the Water St.
bridge, because what they found in the field was different from what was on the plans as well as
Mass DOT’s plans on the bridge above us. This will all be connected at Main St. to the end of
Boulder Dr. The Main St. Project will be going out to bid in the next couple of weeks.
PFAS – We did another round of sampling to test for PFAS. We received the results and we are
below the new proposed limits set by EPA. With all of the sampling we’ve done the past couple
years we have been below Mass DEP’s standards but also below the new stricter limits that
come into effect in the next 5 yrs. We also need to investigate a little bit further as to where the
samples are taken and how they are taken. PFAS is in just about everything, and we need to
make sure it’s not say a piece of Teflon tape (which has PFAS in it) near the tap where the
sample was taken. Lots of contributing factors when it comes to PFAS, its might not necessarily
be in our water supply. We will continue to sample quarterly.
Item #5
Wastewater Division:
CSO 010 & CSO 032 – Our current project on upper Main St. is the CSO 10. This project is 61%
completed as of July 1st. We are scheduled for completion by December of this year. We are
continuing with new sewer and drain installation on School, Arlington, Bond and Prince St’s.
Paving will be taking place in the next couple of months with Caldwell Pl., Park St, and Chestnut
St. from Main to Goddard St, lower Bond St. and all of Goddard St, on the scheduled. The
remaining roads will be tackled next spring. Bids for our CSO 032 project closed on July 11th.
GVC Construction came in as the low bidder at $22,759,000 MIL. This project is scheduled to
begin next spring. This will finish upper Main St, Mechanic St.
Staffing – We are fully staffed with Sr. Operators but two are out right now on FMLA. One is
scheduled to return to work the end of August and the other hopefully will be back in the next
couple of weeks. Superintendent position is still available. We hoping to fill this soon. August 1st
we have a kickoff meeting to look and see what it takes to automate the facility. Right now the
plant is staffed 24hrs a day 7 days a week
NPDES Permit – We have received our new NPDES Permit and it took effect on July 1, 2024. Not
many changes except for a huge increase in testing. PFAS testing especially. The increase in cost
is about $10,000 just for the testing. A lot of these tests are for the industrial users that we have
in the city. Looking into possibly charging the Industrial users the cost for these tests.
Other Business:
The Water/Wastewater Commission will next meet at 5:00 pm on Wednesday September 18,
2024 at the Legislative Building, City Hall Campus 700 Main St. Fitchburg, MA.
Meeting adjourned at 5:25 pm
Agenda
FITCHBURG CITY CLERK
Jul 12 2024 1:49 pm
Water/Wastewater Commission
Meeting AGENDA
Wednesday – July 17th, 2024
5:00 p.m.
Legislative Building, City Hall Campus
700 Main St.
Fitchburg, MA 01420
This meeting will be open to the public, including a virtual option. For any member of the public that
wish to participate remotely, they are invited to participate in the meeting via the Zoom webinar of
July 17, 2024 at 5:00 PM Eastern Time.
Register in advance for the Public Comment/Hearing portion of the Agenda by going to:
https://us02web.zoom.us/webinar/register/WN_Wx_FKZ1zSiWV4yfDCwbKaA
After registering, you will receive a confirmation email containing information about logging in to
join the webinar.
_____________________________________________________________________________________
OPPORTUNITIES FOR THE PUBLIC TO SPEAK DURING A WATER/WASTEWATER COMMISSION
MEETING:
1. Public Forum: The Chairman will ask if anyone in the audience wishes to speak on any matter
appearing on the Agenda. If you wish to address the Commission, you must stand and be
recognized and follow these rules before speaking.
State your name and the community you reside in.
Approach the center table and either sit or stand. This allows you to be seen and clearly heard
by everyone in attendance.
You may speak only on items appearing on the agenda for no more than (2) minutes.
2. Constituent Proposal – To create a tiered water/sewer rate system for properties that are not
required to pay real estate taxes, or pay reduced real estate taxes through a PILOT (payment in lieu
of taxes agreement.
3. Review minutes from June 20th, 2024 Commission Meeting
4. Water Division
• Boulder Dr. Water Main Replacement Project
• PFAS - update
5. Wastewater Division
• CSO’s Update – CSO 010 and CSO 032
• Staffing Update – Senior Operators, Superintendent, Future Plans/Automation Study
• NPDES Permit Update – New permit in effect as of July 1, 2024
6. Other Business
• The Water/Wastewater Commission will next meet at 5:00 pm on Wednesday September 18,
2024 at the Legislative Building, City Hall Campus 700 Main St. Fitchburg Ma.
• Adjourn