Committee of the Whole
Regular MeetingGahanna, OH · July 25, 2022
Minutes
200 South Hamilton Road
City of Gahanna Gahanna, Ohio 43230
Meeting Minutes
Committee of the Whole
Merisa K. Bowers, Chair
Karen J. Angelou
Nancy R. McGregor
Kaylee Padova
Stephen A. Renner
Michael Schnetzer
Trenton I. Weaver
Jeremy VanMeter, Clerk of Council
Monday, July 25, 2022 7:00 PM City Hall, Council Chambers
A. CALL TO ORDER:
President of Council Stephen A. Renner, Acting Chair, called the meeting to
order at 7:02 p.m. Vice President Bowers and Councilmember Padova were
absent. All other members were present for the meeting. There were no
additions or corrections to the agenda.
B. DISCUSSIONS:
1. Economic Development Training Series #1
2022-0219 Economic Development - Basics Course Materials
Nate Strum, Director of Economic Development, introduced the presentation
agenda for “Back 2 Basics,” which included an overview of economic
development and tools in the toolbox, such as incentives, special entities, and
miscellaneous items. Economic development involves programs, financials,
and incentives to strengthen the City’s tax base and create opportunities for
residents to live, work, and invest in the community. By doing so, the
community will have better infrastructure and schools. There were a couple
economic development programs last year, specifically Mill Street and ADB
Safegate. Regarding tax abatements, Strum reviewed that there were two
types of tax abatement incentives: the Community Reinvestment Area (CRA)
and the Enterprise Zone (exclusive to county). Historically, Enterprise Zones
are in unincorporated areas. There are some in municipalities that have
Enterprise Zones but are the result of being formerly unincorporated areas
that were annexed into the municipality. The City of Gahanna only has CRAs.
There are five CRAs in the City. Strum pointed out that a key distinction
between the City’s CRAs is “Pre-1994” and Post-1994.” On July 1, 1994, the
state legislature changed the Ohio Revised Code (ORC) so that if an
incorporated CRA was made prior to July 1, 1994, the CRA would be
identified as “Pre-1994” and subject to prior laws of ORC, meaning fully
City of Gahanna Page 1
Committee of the Whole Meeting Minutes July 25, 2022
entitled to incentives, and no negotiations with councils or school districts but
rather a baseline entitlement. Everything after June 30, 1994, is a “Post-1994”
CRA. This means everything is on the table from a negotiation standpoint.
There have been some adjustments to Gahanna’s CRAs over the years. The
City, even in its Pre-94 CRA status, had the authority to adjust to meet the
needs of the community. Strum reviewed the Ohio Department of
Development (ODOD) table and noted in the Pre-94 CRA, it was all
determined by what an authorizing resolution did. For example, in Gahanna’s
CRA 5, which is Pre-94, it lists what can and cannot be utilized in the original
authorizing legislation, such as up to 10 years on residential remodels, up to
12 years on multi-unit, up to 15 years on residential new construction, up to
12 years on commercial/industrial remodels, and up to 15 on
commercial/industrial new construction. This means that as a Pre-94, you
can go up to those values, but those values were initially established by
Council. The state government allowed cities and villages to police their own
levels and choose what it wants to do in the Pre-94 status. In Post-94 status,
these are all negotiated. The Council and school districts, typically the two big
voting parties, oftentimes you will see whether there was a funding agreement
whenever there was a CR application coming into the City for Post-94 CRAs.
Members of Council and the schools would negotiate the agreement and
bring those applications back to the Council and then act on it independently,
hoping that both would coalesce some level of agreement through that
process. Strum added that because of the current agreement with the
schools, everything is approved pending [the Council’s] approval. The schools
waive their right to it, but then want fully compensated for it.
Strum reviewed CRA No. 1. This is a Post-94 CRA and dates to the early
80s. It has been amended multiple times. If public body amends or adjusts
values three times, the CRA reverts to Post-94 status. If you want to adjust
the values that are eligible within the CRA, you can do so but the minute you
do it a third time, it becomes a Post-94 CRA. The values drop considerably.
Also, in a Post-94 CRA, you start at 50 percent per Ohio Revised Code. The
baseline for this is a 10-year, 50 percent abatement on improved values
within the dwelling (two units), commercial/industrial remodel, and
commercial/industrial new construction. Everything above that is a negotiation
between schools, city, and developer/business owner. CRA No. 2 around the
Donatos property (the headquarters and manufacturing and R&D facilities) at
Taylor Station Road is Pre-94. This is only for industrial use. Although Council
originally formed this CRA, allowing for dwelling remodel and
commercial/industrial/housing remodels just like any other traditional CRA, in
reality all that is there is commercial and industrial uses. Therefore, this is a
15-year, 100 percent abatement on improved values tied to those
improvements near and around the corner of Taylor Station Road area. CRA
No. 3 is Post-94. This is Central Park and the former brownfield site where
there is a lot of industrial development. It has been reclaimed. It is now the
golf depot and out parcels on Tech Center Drive and Science Blvd.
Predominantly, the area is industrial/commercial, so there is more in the
15-year, 100 percent on improved values for new construction but some of
the commercial/industrial remodels of up to 12-years and 100 percent on
City of Gahanna Page 2
Committee of the Whole Meeting Minutes July 25, 2022
improved values. With this being a Post-94, when there are applications,
such as with Edison Brewing and The Peak at Edison that came in a few
years ago for their incentivization, there is a negotiation. They negotiated
those values to create jobs in that office building as well as the brewery next
door. CRA No. 4 is Pre-94 where the Crescent is (Officenter area, or lower
part of Central Park). This is where the AEP corporate office is and where the
Crescent project is on the western side of the CRA. Council can decide how
things are adjusted in Pre-94s. In this instance, the Council did two things.
First, Council created the CRA in the late 80s, was to amend it to expand to
include portions of where Buckles Court and Tech Center Drive is currently
located closer to the airport. Second, Council reduced the value. Originally,
this CRA was set up to be a 15-year, 100 percent abatement and Council
adjusted those values to what is currently the 10-year, 80 percent maximum
value on it. That counts as an adjustment or revision. If one more amendment
to the CRA occurs, it would become a Post-94 CRA. Strum said that in his
professional capacity, given the level of development that is happening here,
he would not recommend amending it. He said this could have a detrimental
effect long-term to what is happening in this portion of the city. CRA No. 5 is
Pre-94 and encompasses the west side of Gahanna - Library property going
west through Creekside and Olde Gahanna and West Johnstown
Road/Stygler Road/Agler Road areas. He referred to the values for dwelling
and remodels, commercial/industrial/housing remodels and new construction
activities. Ohio HD went through a Pre-94 application, which was approved
for a 12-year, 100 percent abatement on the improved values. They invested
over $1 Million into their facility to modernize their building during COVID-19.
They just applied it to the most recent round of property tax inclusions. This
did not require Council action as a Pre-94. The Post-94s are what come
before Council. Councilmember McGregor asked what building this was for
the business. Mayor Jadwin said it was the former Wonder Bread building.
Strum said this was a multi-tenant expansion and investment.
Director Strum reviewed the other principal program that the City has, Tax
Increment Financing (TIF). He walked through the chart on the slide with the
TIF Assessed Value (AV) Over Project Life. Anytime something goes through
TIF, the base value is set at year one. Those taxes attributed to that year one
value will be paid every year to those various taxing authorities for the next 30
years. Any improvement or incremental value change from that year one is
then captured and diverted into the TIF Fund. With Council, Strum said it had
been previously discussed what a “Non-School TIF” was. This sets the year
one value for everything but school value. So, the schools continue to get paid
as incremental value increases on property but the other non-school related
values, the city, county, and other levies that are not school, are diverted in
TIF Fund. This is captured and utilized to pay off eligible expenses related to
the TIF Ordinance. Council sets the TIF Ordinance. The Council has
exclusivity for what is and is not eligible for TIF inclusion. Gahanna’s TIFs are
predominantly infrastructure, but there are several TIFs that include language
around Public Service facilities and Public Safety facilities and articulate
intersection improvements. These can get very detailed or stay very broad,
but ultimately City Council sets the authorizations as to what is and is not
City of Gahanna Page 3
Committee of the Whole Meeting Minutes July 25, 2022
eligible. Values are redirected for 30 years. At the end of the 30-year period,
the TIF Fund for the project or property is dissolved and the new taxes on
year 31 are disbursed as if they would normally have been the entire time.
Strum said this was one of the most powerful tools the City had from a public
financing standpoint because TIF funds everything. Infrastructure
improvements, such as storm sewers, water lines, sanitary sewers, trails are
the most eligible things the City has under TIF. Strum stated it is important to
continue to evaluate where the City is growing and what the City’s needs are.
TIF is one of the best tools to not only plan but to implement current projects.
Authorizing ordinances will have listings of eligible expenses related to
facilities and TIF.
Strum stated that another tool available for economic development exclusively
through Gahanna to manage and operate was through the Office & Industrial
incentive (income tax). He noted there would be further discussion later, as
he had an Ordinance for the body to review that pertained to an incentive. The
City allows for some level of rebate for new business expansion. Under the
City’s guidelines, this program cannot be comingled with other incentive
programs. For example, a CRA could not be mixed with an O&I incentive.
Strum provided an example for someone who is going to give a $10 Million
anticipated payroll for 2.5% income tax. The City would give a 25 percent
rebate over a five-year term. The overall value would be about $1.25 Million.
The city would receive $937,500 and the company would receive $312,000.
Strum also provided Council with an overview of special units of government
that relate to economic development. First, Community Improvement
Corporations (CIC) help aid in economic development activity within the City
and defined by the authorizing legislation. For Gahanna, the City government
gives the CIC leeway for economic development assistance and land
disposal. Essentially, the CIC is serving as the City’s landbank. The City could
empower the CIC solely to take on economic development and dissolve the
City’s department. New Community Authority (NCA) is another special unit.
This came up with the Crescent project. An NCA has independent bonding
capacity that allows for NCA charges and community development charges.
The public body, such as City Council, establishes parameters around which
an NCA can be implemented. The NCA can implement various taxes, levies,
and liens within the property it governs to govern higher levels of parks and
infrastructure improvements. These would all be defined as part of the petition
to create the NCA. The most common one in the region right now is Bridge
Park. He referred to a slide showing a receipt with an NCA charge (0.50
percent charge) to pay for roads, garages, etc. defined in the parameters set.
Tanger Outlets in Delaware is an NCA. This pays for road improvements and
bridge improvements over interchanges. Councilmember Angelou asked if
this charge was always 0.50 percent. Strum responded, no, this would all be
defined in the petition creating the NCA and depends on what the level of
infrastructure invested is. The NCA does not go away. Once created, it is
there. Another example of an NCA is New Albany Beauty Park. For this, fees
are taken out of the project, even with the abatements that may be on
property, to fund infrastructure improvements and other activities. A Special
City of Gahanna Page 4
Committee of the Whole Meeting Minutes July 25, 2022
Improvement District (SID) is another special unit of government. This has an
expiration, as a SID cannot exceed ten years. However, it can be renewed. It
must include 60 percent of the frontage of all real estate upon a public
right-of-way within a defined area or 75 percent of all property located within
that District. This means that 60 percent of people who front roads or 75
percent of everyone must be involved in this once completed. They can
assume similar fees to an NCA. They can do taxing fees, charge fees to
customers on commercial real estate activities, and attach SID fees on the
conveyance of property. Over The Rhine in Cincinnati is a SID example for
charges that go to public parks, public art, and historic renovations in the
defined neighborhood. There is a board that is created and represented by
city officials and local neighborhood officials. The board governs and
administers the dollars for programs. Locally, the most common SID is
Nationwide Arena. The planters and special security details are paid for by the
SID. The Energy Special Improvement District (ESID) is a special designation
under Ohio Revised Code. Strum noted the City is already part of this.
Property owners who wish to have energy efficient improvements done on
their property can petition to be added to the ESID. Gahanna did this in 2020
to be added to Franklin County Financing Authority ESID program. Strum is
the representative for the City on this ESID. This is a mechanism to support
Property Assessed Clean Energy (PACE). In short, PACE is a financing tool
that allows for entities to take advantage of energy efficient improvements on
their property at a low interest rate. Instead of having to pay back as a loan, it
is paid back on an assessment. In other words, it is added to the tax bill and
conveys with ownership. Strum said this is not widely used in Ohio. Churches
do a lot of ESID improvements with HVAC, windows, and roofs. Historic
structures also like to do this. Strum said in other states, this is more
commonly used around residential solar panels.
Councilmember Weaver thanked Strum for the presentation and pre-reading
materials. He asked whether Strum could talk about pilot payments and
how/when they are used and the advantage to the municipality. Strum said
this is a topic that would be discussed in Session 3 on residential
developments and how they have been used with school compensation.
These pilot payments are payments in lieu of taxes. The City’s process
involves a pre-negotiated structure with the Gahanna-Jefferson Public
Schools. Pilot payments are made annually. There is a determination on loss
of tax income would be to the schools based upon economic development
projects that have happened in the City for the past 12 months. Then, the City
makes pilot arrangements typically through some TIF monies. Strum said that
most TIFs are overperforming so they can be leveraged for these types of
programs. Strum reiterated that he would have an entire session on pilots,
how they work, and why it matters. Weaver asked in terms of CRAs and new
company coming to add jobs, are penalties automatic for failing to meet goals
or discretionary. Strum said these are discretionary. The Tax Incentive
Review Commission (TIRC) administered by the Franklin County Auditor’s
Office, with City appointees provides oversight. The program is administered
locally, and minutes are brought to Council. With the City’s TIRC, the
recommendation to the County Auditor was that everything complied per the
City of Gahanna Page 5
Committee of the Whole Meeting Minutes July 25, 2022
original agreements. Once the stenographer finalizes the minutes from the
County Auditor’s office, that same recommendation will be made to Council,
of which the body can accept, reject, or amend findings. The same level of
reports and conversations will be afforded to Council as afforded in the TIRC.
Strum noted that in his years of experience, he has had to revoke two.
Oftentimes, a lot of the agreements will say “good faith effort.” Strum said
what the City is seeing now is lesser job numbers but higher payroll numbers.
Based upon what their projections were five to seven years ago, they thought
they would need 30 jobs to get to the goal, but they needed 15. Strum’s
recommendation from a governance standpoint, is that we should not mind
the number of jobs being lower if they are meeting the estimations and goals
with payroll. This is what the City is really incentivizing through a CRA, but this
is also Council’s call. This is an annual meeting. Strum noted that on
Thursday at 4:30 p.m. the Community Reinvestment Area Housing Council
(CRAHC) board meeting would be held in-person at City Hall. This board will
meet for the same thing the TIRC does, but on the housing side.
President Renner thanked Strum for crafting this learning series. Strum said
he anticipated a representative from One Columbus coming for the next
session to talk about the JobsOhio network and the role of regionalism in
economic development and how Gahanna fits into this. The third session and
subsequent sessions will focus on pilot arrangements, relationship with the
schools, workforce development and housing. The last session will review
economic development and pulling everything together. Strum said the goal is
to provide Council with all this information and then show how a deal matters,
how a CRA tax abatement impacts rent rolls, small business creating jobs,
and how the whole cycle works.
C. ITEMS FROM THE DEPARTMENT OF ECONOMIC DEVELOPMENT:
ORD-0045-2022 AN ORDINANCE AUTHORIZING THE MAYOR TO ENTER INTO
CONTRACT WITH ODOT FOR PURSUIT OF STATE
INFRASTRUCTURE BANK (SIB) LOAN, WAIVING SECOND READING
AND DECLARING AN EMERGENCY - Tech Center Drive Extension
Director Strum reviewed various dollars having been pursued for ADB
Safegate through the Ohio Department of Development (ODOD) and Ohio
Department of Transportation (ODOT). He urged Council to go out to Science
Blvd to see the progress being made. He noted on his slide that the extension
highlighted in blue is the extension to Tech Center Drive to serve the property
and potentially what it could look like if extended to Taylor Station. When the
original bid for the project occurred in September 2021, the initial values
attributed to ODOD and ODOT were about $560,000 for the road extension.
The road extension has now gone up to $1.2 Million. A lot of this increase
could be attributed to public infrastructure improvements that were originally
captured under the ODOD and ODOT programming, specifically water and
sewer lines. With increased cost, the City needs to find another financing tool
to get the project moving on Tech Center Drive. This is where the State
Infrastructure Bank (SIB) administered through ODOT comes in. This is
City of Gahanna Page 6
Committee of the Whole Meeting Minutes July 25, 2022
about lowest rate loan out there. Strum said the Department is pursuing
authorization to get these funds. He said he would then come back to Council
with a reimbursement agreement that would partner with the developer. The
Council can then review. He said the City will support the program with
ODOT and ODOD grants, TIF funds previously appropriated under prior
legislation, as well as some water funds to support the increased cost of
water lines. The Department does not yet have the values of those costs yet.
They are working through the engineering process. The goal would be to get
the SIB loan underway because there is a little bit of lag time from submission
to authority to enter into agreement.
President Renner noted the request for waiver and emergency on the
legislation. Strum said this was required to be able to file the application as
soon as possible.
Recommendation: Introduction/First Reading/Waiver & Emergency Adoption on
Consent Agenda on 8/1/2022.
ORD-0046-2022 AN ORDINANCE TO AUTHORIZE THE MAYOR TO ENTER INTO AN
OFFICE & INDUSTRIAL INCENTIVE AGREEMENT WITH COLUMBUS
AESTHETIC & PLASTIC SURGERY FOR A PERIOD OF 10 YEARS
Director Strum noted the Columbus Aesthetics & Plastic Surgery (“CAPS”)
office is looking to expand into the east side marketplace. They reached out to
Strum on the former Penzone facility location on Cherry Way near Morse
Road in Gahanna. In reviewing the opportunity with CAPS, the City identified
that the Office & Industrial (O&I) incentive is really the only thing to support
this type of an opportunity from an incentivization standpoint. Strum said the
City is competing with multiple municipalities that are offering better
incentives. The intake form was also provided with the application. This
consists of 52 jobs at about $150,000 per year, high-end medical positions.
When looking through the lens of what the City thought would be appropriate
from the Incentive Advisory Committee, Strum said it hoped to do a total
investment of 50 percent for 10 years. This gets to a value of just over one
half million dollars, but the City would get about $1.75 Million. Strum said this
garners a 233 percent return on investment (ROI). In sum, if the City
contributes one half million dollars of its tax base through reimbursable,
performance-based incentive, it will receive $1.75 Million and grows
exponentially thereafter when the incentive rolls off. As a performance-based
incentive, this means that if CAPS does not meet their job performance goals,
the value of the incentive is lesser. If they exceed their job performance goals,
that number grows. If they do exceed, this is a good thing, as the City would
realize more income tax. The key is to get to the valuation to be competitive
with neighboring communities offering similar incentives and opportunities
was to waive the five-year period. Under the City’s guidelines, the Council has
the ability to waive any and all those guidelines to meet in a competitive
opportunity. The guidelines suggest a five-year term maximum. Strum is
seeking a waiver of that five-years to grant a ten-year period. He said this
adds high-level value to the City long term. In year 2023, they will be
contributing $75,000 of net income to the City. During the Incentive Advisory
City of Gahanna Page 7
Committee of the Whole Meeting Minutes July 25, 2022
Committee meeting, he noted there was a question as to the Issue 12 dollars
about the one percent versus the non-Issue12 dollars. Through the program,
by year five, if CAPS reached over $100,000 of net income into the City, that
number continues to grow exponentially over the years. The City is only
incentivizing the non-Issue 12 related funds, so this is a 50 percent credit on
the 1.5 percent non-Issue 12 income tax. The entire 1 percent on the Issue 12
dollars is collected. Strum said this was a net income credit of 30 percent.
President Renner clarified the 52 jobs versus 65 jobs on the spreadsheet.
Councilmember Weaver said that looking at ROI document, it mentions 15
years. Strum said this is correct, as he wanted to show a calculation on 15
years just for illustration. The proposal is for 10 years.
Recommendation: Introduction/First Reading on Regular Agenda on 8/1/2022
and Second Reading/Adoption on Consent Agenda 8/15/2022.
D. ITEMS FROM THE CITY ATTORNEY'S OFFICE:
RES-0022-2022 A RESOLUTION APPROVING A MEMORANDUM OF AGREEMENT
WITH THE BOARD OF EDUCATION OF GAHANNA-JEFFERSON
PUBLIC SCHOOLS TEMPORARILY SUSPENDING CITY
ORDINANCES IN CHAPTERS 1108 AND 1197 REGARDING DUTIES
OF THE PLANNING COMMISSION FOR THE NEW HIGH SCHOOL
PROJECT
Attorney Mularski introduced Sean McCarter, the City’s outside counsel, who
would be speaking. Mularski reviewed how the City got here with the proposal
in front of Council. Two weeks ago, the Mayor contacted Mularski about a
major legal issue that had come up in a meeting with the schools. They
discussed the issue on a Monday. Mularski and McCarter met and reviewed
the issue with attorneys for the school on the Wednesday and worked all the
way through it. That Friday, the attorneys had a good idea of what to do to
present to its clients to resolve the problem. On Monday, just a week ago,
they ended up deciding that this is how it would be pursued. In this past week,
the school with its two attorneys, engineer, developer, and school officials
along with the City’s two attorneys, Mayor Jadwin, Interim Engineer Ridge,
Director Crawford, and Director Blackford there were 12 different views trying
to put into writing to get what everyone wanted and what everyone thought
would work. On Friday at about 4:00 p.m. all of this came together. This is
why it took so long [getting the agenda out]. Mularski proceeded to explain
what the legislation was about. The “whereas” clauses set forth reasons why
this needs to be done. Mularski read the “whereas” clauses in the preamble of
the Resolution. He noted that the goal of the Resolution is trying to help the
school save millions of dollars, so our residents save millions of dollars.
Mularski added the problem the City has is the school has an abbreviated
timeline for fulfilling the terms of their bonds. They must put shovel to dirt in
August. To do this, the parties had to find a way to accomplish that. The
reason why is due to the Brownfield Supreme Court decision. Mularski noted
the Clerk had sent an article to Council on the decision that explained what
City of Gahanna Page 8
Committee of the Whole Meeting Minutes July 25, 2022
the case is about. What it says is that [the City] is a political subdivision and
the school is a political subdivision. Each get funded by public funds. Neither
can tell the other what to do with their public money. However, there are times
where the two areas will collide, such as with building construction and
zoning. What the City needs the school to do might be different from what
they need to do. Brownfield says we must work it out. If we do not work this
out, this goes to court. If it goes to court, there is a weighing process, and the
court decides what is the greater good to the most people. The court then
decides who wins. Mularski stated that in every case he has read, from
Brownfield and its progenies, the court has said “work it out.” This is what the
parties are trying to do here. Mularski noted further that there are differences
between the Resolution and the Memorandum of Agreement (MOA). The
MOA is between the City and schools. The Resolution is what Council is
being asked to do to make this happen. Council has the power to suspend
ordinances. This is what is being sought temporarily. Council cannot suspend
the Charter. However, Brownfield would trump the Charter. Therefore, in the
Resolution there is language to put off some of the requirements under
Section 1108.06 to a later time to allow the school to start digging so that they
can fulfill the requirements of bonds and not lose millions of dollars. Mularski
said this Resolution can only apply for a school or another political
subdivision. This is not something a developer could use. It is only between
entities that have the eminent domain ability. This is why the item is coming
from the City Attorney’s office and not a developer. This big of a deal normally
would take eight to 18 months before shovel to dirt. A final development plan,
design review, and any variance application, erosion control, and engineering
approval before they can move dirt. The proposal is saying to the school that
they do not have to do all these. The City is saying the school will need to do
erosion control and the engineering approvals. The other things can be
worked on and need to get done but do not have to be done before starting to
move dirt. This allows the school to maintain their tax-exempt status for their
bonds. Due to the school’s condensed time frame, we had to find a
compromise that would allow the school to begin moving this and save
money they could be losing. The City is still requiring approvals of engineer
and for erosion control but allowing demolition and digging to proceed on
stadium. Mularski added that under Brownfield, there is only certain things the
City can do, for example, in the areas of health and safety. When it comes to
sewers, traffic impact studies, and building code, these are all things the City
would win under Brownfield because of safety measures. Other things, such
as design of the school, placement of the stadium, the height of the fence,
etc. are things typically handled by Planning Commission but are things we
would most likely not prevail in under Brownfield. Mularski noted paragraph “C”
dealing with site work is what we are saying they can do. This allows the
school to get started without having all the final plans and approvals, but with
the agreement that we will do all the final plans and approvals in the future.
The school has agreed they will be liable for any overruns that this costs. The
reason why the City has all the final planning done first before anyone can
move dirt is for them to not have to go back and change things later. If they do
have to go back and change things, it will be on them. Mularski said McCarter
had put this together and could answer questions. Mularski concluded by
City of Gahanna Page 9
Committee of the Whole Meeting Minutes July 25, 2022
asking what happens if we do not do this. The school would be put in a
position to file suit and a temporary restraining order, everyone then spend
tens of thousands of dollars in attorney fees, and the court will likely say,
“work it out.” They would then present this agreement, which Mularski
believes to be reasonable, and the judge would likely say this was reasonable
and what should be done. To compromise and work out and save the school
and the City residents millions of dollars, his office is proposing this
Resolution to accept the MOA.
Mr. McCarter said that he, along with attorneys for the schools, Attorney
Mularski, and engineering officials were on a conference call a week ago from
Friday. The schools were stressing to have this be brought forward and that
this was in a follow-up to a request that they had sent an MOA that does not
look anything like this one. It was much more of a blank check. During the
conversation, one of the things the City said was the school does not get to
connect to sewers and overwhelm them. They agreed with that. Their
response was they are already connecting and using from the site, so they
ought to be able to use that. McCarter said ok, but the school might only be
limited to that until the sewer problem is ultimately fixed. The City knows the
school wants more capacity than the site currently has but until capacity is
established, they would not get that. The school can live with this, and their
occupancy limited to what they have now. This is one of the
acknowledgements. The sewer problem is going to take some time to work
out. They do not have time to resolve this to move dirt. This was a big issue.
The traffic issue is another one. The school needs to do the studies.
McCarter said the MOA provides this must be approved by the City in
accordance with controlling law. One of the big issues was a timing
standpoint for the onsite work. The Planning Commission was set up as a
gatekeeper for many things to make sure that before a project gets the “OK”
that everything is in place. The school’s position was they will deal with these
things as they go but at this time but right now, they need the “OK” to move
dirt. On the conference call, the City’s team landed on getting 95 percent of
way there by requiring the compliance with permits and engineering approvals
etc. What is not there is “good idea, bad idea” use of this site feedback by
Planning Commission. This is the political subdivision distinction [from
Brownfield]. They are charged with providing schools and how they develop
their site. They get to make the decision. McCarter said that a later case
involving the City of Mentor stressed meeting the “work out” provision. If this
provision is not met, there is the balancing test by the court. One thing the
court noted in this case was “in light of the applicability of Brownfield to further
conclusions inexorably follow. First, we hold that the proceeding before the
Mentor Planning and Zoning Commission was superfluous. Because the
determination whether Laketran is immune from the Mentor zoning resolution
will be dispositive of whether it can build the proposed park-and-ride facility,
the commission's denial of the request for a conditional use permit is
meaningless. Simply stated, the hearings before the commission should have
never been held.” McCarter said the point was you either work it out or go to
court. Courts have held they are not required to follow permitting, zoning,
variance, etc. types of processes and that this is part of the “work out.” Trying
City of Gahanna Page 10
Committee of the Whole Meeting Minutes July 25, 2022
to take the position of working it out and deal with the timing issues and
developing a process that kept all health and safety approval processes in
place, this is what they came up with. In seeking a role for Planning
Commission, to make sure everything is in place, but not say “good idea/bad
idea” and continue to serve as a gatekeeper, [this is what the parties had
come up with in the MOA].
Councilmember Angelou said she wanted to be responsive to what is going
on. She asked how this got to this point and not done many months ago, as
obviously this was known. If it was not known, why was it not known because
right now the school would be getting the shovels out? Angelou said the
school is part of our community, the City wants this to be great. She again
asked why this has happened. McCarter responded, only in part, as the City
is not the developing entity. We did not control the timing and process or
starting the bonding process and setting a payout schedule, and all those
types of things creating some of the issues here. McCarter said it is his
understanding that early warnings were given. The offsites were always at
issue, two huge hurdles that were presented as impediments to having the
ability to tee this up to go to Planning Commission. They were not going to
have their offsites done in time in any kind of timeline that would make this
workable. This was a significant issue presented to the City. Second,
McCarter said splitting the dirt moving versus the other activities, he did not
think the City is doing anything differently than anyone else. As school got into
process, this is where they have found themselves. McCarter said he did not
think the City dragged its feet. He said maybe there was an “Aha” moment.
Several issues had been on the table for the while. Mayor Jadwin was at the
meeting. McCarter said it seemed the school was hitting the crisis button and
asking for help. Mayor Jadwin said this had evolved within the last two to three
weeks. She said it is important to take notice that the City and schools are
separate, distinct legal entities. People think the City and the schools are all
part of one entity. The City is funded and managed differently from how the
school is funded and managed. Jadwin added the school has had their
timeline for this project. She said it had been announced back in January and
had a timeline they were working under. The City also has parameters. The
City first met as a team February 28 and walked through potentially what a
calendar could look like, understanding a project of this magnitude would take
eight to 18 months to go through all the planning process, review between the
development of the Final Development Plan, Design Review, and Variance
applications, stormwater and erosion control, and EPA requirements that
must be followed. This is a situation where the City is trying to balance the
processes and parameters and code provisions in place with the leniency
school districts have with the Brownfield case as established by the Ohio
Supreme Court. Jadwin said we want to try to reach a compromise of that but
also make sure the City is protected and there is some mechanism for overall
interests of the community and greater good. She said the City recognizes
this is a substantial project for the community and for the schools. It is sitting
on the busiest intersection through the mid-Ohio region. The impact to the
community is significant. Jadwin stressed finding a way to help the schools
move forward within confines of the Brownfield case and understanding what
City of Gahanna Page 11
Committee of the Whole Meeting Minutes July 25, 2022
the City needs to have. The timeline is not ideal. She added she was sure if
everyone could do over again, the school would get an earlier start, and
everyone would be better off for that. Jadwin said that at the end of day, we
are where we are, and the school needs to get shovels in the ground. The
City needs to help make that happen or else it is the taxpayers that are going
to pay for it. It is the City and school in this together. Jadwin said she thought
the City needed to do what it needed to do to help make this move forward.
Councilmember Angelou said if you knew this was happening, was there
something where you could not come to where we should be. She said she
had attended the school’s workshop with Planning Commission. She said
she was surprised then that the questions all came from the Planning
Commission. Angelou wanted to understand how this could happen. She said
it has been a long time since the City has had a lot of building and it would be
wonderful to have a new high school. She said she thought it was right to do
things to help the students, teachers, and administrators. She still wanted to
understand why it has come to this. Angelou said it is not the City’s fault.
McCarter said that is why he said the school district was working through a
process here and maybe had different expectations. Coming into the meeting
two weeks ago, McCarter said it was expressed there was a severe problem
here. On the Monday conference call with building and engineering people
and the parties started to work through the problem and get around what the
issues were. McCarter said the “whys” have more to do with the school than
the City.
Councilmember Schnetzer said Mularski provided a succinct way of boiling
down a complex legal issue. Schnetzer said it sounds like certain steps along
the way and the approval process are not necessarily being ignored, but the
order is changing. Mularski said he thought that was a very good way to put it.
Schnetzer added that those items pertaining to health, safety and welfare are
not being changed. Mularski said this was correct. Schnetzer added that he
was not trying to place blame on anybody. We have one political entity which
is the school board, the decision-making entity for the school district. The
Council is the decision-making entity for the City. One political entity is asking
another, “due to extenuating circumstances, here is what we need to move
this forward for the benefit of the residents.” Based on what he is seeing,
Schnetzer said it seems like a relatively reasonable request and given that
nothing is being ignored but rather the order is changing, this was not too
heavy of a lift for him and should move forward.
Councilmember Weaver thanked McCarter for the additional commentary. He
said the Mayor had said it well with a project this size, as the body looks to
have discussion about its own projects, there are time constraints, and the
City will be feeling pressures as well. Weaver said Councilmember
Schnetzer had made a good point the oversight is still there and just the order
of things being adjusted slightly. Weaver added the Brownfield decision
makes it clear. If you read the Brownfield decision, the decision does not
provide immunity for health and safety requirement as noted. He thought this
is a reasonable request. With the health and safety measures being
addressed and still being there, this comes down to protecting the taxpayers.
City of Gahanna Page 12
Committee of the Whole Meeting Minutes July 25, 2022
Weaver said this would be the fiscally prudent decision.
Mayor Jadwin noted that Attorney Mularski worked on this project last week,
along with Mr. McCarter, and Director Blackford, Ken Fultz, and Ms. Ridge.
She appreciated everybody’s tireless hours for getting this together. Angelou
thanked the administration for doing this. She hoped that when something like
this might happen to the City, the schools might help the City.
Councilmember McGregor said this is difficult for her because when planning,
the school came back in February to the meeting. That was five months ago.
She asked why we were waiting two weeks before and suddenly it is an
emergency. She said she felt like the Council was being dragged into a pool
inhabited by sharks because the planning of the school board was not done.
This is not the school’s first project. They just did Lincoln Elementary. The
school knows what timelines are and knows how to draw funds for a bond.
McGregor said the felt like Council is having to make up for the problem that
was someone’s fault from the school or their attorneys. She said it seems like
we are having to make it work because of the poor planning that has gone on.
McGregor said she was not saying the Council should not do this and that
maybe it should. She would have to think about it. In thinking about
suspending codes, McGregor said she thought Councilmember Schnetzer’s
point was right that if health and safety is still going to be done, but if
something goes wrong because the City reverses the order, McGregor said
[the school] is going to drag the City in because it waived the codes and the
order. She said she sees potential for [the City] being blamed when it was not
something that is the City’s fault. McGregor asked McCarter if the City does
nothing, can the school still go ahead. Does the Council have to waive the
codes for them to start? McCarter said if the Council does nothing, it would
not be accommodating the request to work it out. They will, in his opinion,
have satisfied the requirement to have sought to work it out, which gives them
the right to go to court. McCarter’s expectation is that given the amount of
money, they would go to court and would get a temporary restraining order
and say to the judge, “the process they are putting us through, we (the school
district) are not required to follow and file the permitting, and Planning and
Zoning does not have the right to tell us good idea/bad idea. We got to go. We
are going to lose a bunch of money.” He thought that given his experience in
temporary restraining order hearings, the judge will tell the Council to work it
out and not to come back and say it cannot be worked out. McCarter said if it
does not get worked out, it will go to an immediate consolidated hearing on
preliminary and final injunction, a trial on merits, and it will happen fast due to
the school’s assertions of extreme financial. There will be a court decision.
He thinks the school will have cleared a hurdle for trying to work it out at this
point. The first reaction of the court would be telling the parties to work out.
Mularski added that when push comes to shove, you should always blame
the attorneys.
President Renner said publicly we heard a narrative from Attorney Mularski
and by Council a little bit that there has been ongoing dialogue and meeting
and talking about these things. Renner said he really quivers and takes point
City of Gahanna Page 13
Committee of the Whole Meeting Minutes July 25, 2022
with the use of the word fault and sharks. That kind of stuff is erroneous. He
added to not forget, the State of Ohio in 1980 with Brownfield had already
established a path. With this in the backdrop of what the schools and the City
have been talking about, Council needs to temporarily turn off the final
development plan and design review part while the schools are doing stuff.
Renner said in his experience of managing multiple development projects,
timelines and project management 101 can be nightmare. He said he
applauded the City, the Mayor and her staff for taking interest. Renner said he
understands the schools are under the gun. They have very complicated
funding mechanisms to do the high school and complicated structure they
are trying to develop. So, Council is being asked to do this temporary thing.
Renner (acknowledging the three Planning Commission members in
attendance) said in his understanding of the process in talking with Attorney
Mularski that Planning Commission understands what is going to change and
what their mechanisms are. Mularski said he met with members prior to this
meeting and went through this whole thing and hopes they understand. If not,
he said he is happy to meet with them again. Renner said this is unique and
odd for Council, as it had not come up before during his time on Council.
Councilmember Angelou asked whether there would be a timeframe given to
the Planning Commission so that this does not go on for a long time and so
that things that need to be going through them are not forgotten. Renner said
it sounded like Planning Commission is involved. Angelou asked if there
would be a timeframe from the schools or whether they would be getting
together. Mr. McCarter said [the schools] get to in some part control their
destiny. They have told us that their immediate need is the site work. The
school can only work to extent they have permits, which is clearly in [the
MOA]. To the extent they can get their permits, they can work. The two
offsites are not going to necessarily preclude them from going forward on
their onsite work but they face the need to resolve the traffic and sewer before
the City approves occupancy and with knowing the potential limitations
coming out of that. McCarter said this was designed to give them more
control of their destiny to get their stuff done but cut [the City’s] system to be
done piecemeal instead of whole. Mayor Jadwin added the entire construction
team (for the high school project and the City’s internal team) have been
having biweekly meetings regularly since the end of February when the first
meeting occurred. Between these two weeks of meetings, there are multiple
conversations between our engineers and their engineers. These meetings
have been scheduled into the future on an ongoing basis. Jadwin reiterated
she thought it was to everyone’s best interest to ensure the outstanding
issues get resolved as quickly as possible. This is a three-year phase project.
As costs continue to escalate, it makes sense that everybody gets locked in
as soon as they can. As those meetings continue to happen and timeframes
become more identifiable and narrower, Planning Commission will be kept in
loop. Director Blackford, as part of his updates during Planning Commission,
will keep them in the loop throughout the process.
Recommendation: Introduction/First Reading/Adoption on Regular Agenda on
8/1/2022.
E. ITEMS FROM THE DEPARTMENT OF PARKS & RECREATION:
City of Gahanna Page 14
Committee of the Whole Meeting Minutes July 25, 2022
RES-0024-2022 A RESOLUTION ADOPTING THE DEPARTMENT OF PARKS &
RECREATION 2022 PRICING POLICY AS RECOMMENDED BY THE
PARKS AND RECREATION BOARD
Stephania Ferrell, Director of Parks & Recreation, noted that the Resolution is
to adopt the Pricing Policy as recommended by the Parks & Recreation
Board. The policy is reviewed annually. It sets the charges and fees for any
type of membership and programs for the Department. Changes made were
to better define the operation. Ferrell noted that none of the policy was
ultimately changed.
Recommendation: Introduction/First Reading/Adoption on Consent Agenda on
8/1/2022.
F. ITEMS FROM THE DEPARTMENT OF FINANCE:
ORD-0041-2022 AN ORDINANCE AUTHORIZING THE CREATION OF THE ONEOHIO
FUND NO. 2440
Joann Bury, Director of Finance, requested the establishment of a fund for the
OneOhio opioid settlement which the City is participating in. Over an 18-year
period, the City will receive an annual distribution from the settlement, which
is broken into two parts. Bury reviewed breakdowns based on state and local
government distribution percentages as noted in her report. The first
settlement was received July 18 as an EFT. This is to establish the fund to
place the settlement funds in as they are received.
Councilmember Weaver confirmed there were restrictions on what the funds
can be used for. Bury said this was correct and all defined in the settlement.
As the City identifies what those purposes are, it will determine an appropriate
program or way to use the funds. No appropriations are being sought at this
time.
Recommendation: Introduction/First Reading on Regular Agenda on 8/1/2022
and Second Reading/Adoption on Consent Agenda 8/15/2022.
G. ITEMS FROM THE DEPARTMENT OF PUBLIC SERVICE & ENGINEERING:
MT-0017-2022 A MOTION AUTHORIZING THE DIRECTOR OF PUBLIC SERVICE &
ENGINEERING TO ENTER INTO CONTRACT AND WAIVE
COMPETITIVE BIDDING PURSUANT TO CODE SECTION 135.05(e)(3)
FOR EMERGENCY REPLACEMENT OF TRAFFIC SIGNAL CABINET
AT US-62 AND OLDE RIDENOUR ROAD
Grant Crawford, Director of Public Service & Engineering, stated a traffic
signal cabinet was recently hit by a vehicle just this morning. It had been
struck previously in late May during a vehicle accident that knocked it off a few
feet away from its foundation. This has now happened twice. Crawford said it
has temporarily been reconnected again. It is currently operational, but some
of the equipment, such as vehicle detection cameras, has been destroyed
City of Gahanna Page 15
Committee of the Whole Meeting Minutes July 25, 2022
and is not able to be repaired in-kind. The City had obtained a copy of the
police report from when it was first hit. The first driver had insurance. As with
all damage to City property, we will be pursuing reimbursement from the
driver and insurance company. Code allows for exemption from formal
bidding for emergency purchase. This will allow immediate action by hiring a
contractor to replace the cabinet components, fiber lateral, and will preserve
the community’s health, safety, and welfare. The first action had occurred two
months ago, and it has taken this long to receive at least one quote back due
to supply chain issues and material shortages. Crawford said the City needs
to move on this as expeditiously as possible.
Councilmember Angelou and whether there was a reason to move it since it
has now been hit twice in two months. Crawford said this is the first he is
aware of it being hit. The first hit was due to a driver trying to gain a yellow
light and hit another car turning. He was not sure of today’s circumstances.
He did not have reason to believe it is in an inopportune location subject to
damage.
Councilmember Schnetzer said an important factor is that monies are likely
to be reimbursed by insurance. The City would pay the money up front for the
repair and recoup the cost. He said he thinks the request was reasonable.
Councilmember McGregor asked whether a stolen car had been involved.
Director Crawford stated he did not know. McGregor said this repair had to be
made.
Recommendation: Adoption on Consent Agenda on 8/1/2022.
ORD-0042-2022 AN ORDINANCE AUTHORIZING SUPPLEMENTAL APPROPRIATIONS
AND WAIVER OF SECOND READING - Traffic Signal Cabinet at US-62
and Olde Ridenour Road
Director Crawford noted that the City do not typically budget this much for
repair. Smaller amounts for maintenance and repair are budgeted. This is
sought due to moving forward with the repair items. As Councilmember
Schnetzer mentioned, the City will seek recoupment of costs through the
driver and insurance company.
Recommendation: Introduction/First Reading/Waiver & Adoption on Consent
Agenda 8/1/2022.
ORD-0043-2022 AN ORDINANCE AUTHORIZING SUPPLEMENTAL APPROPRIATIONS
- Damage to City Property
Crawford said this and ORD-0044-2022 are the standard quarterly
supplementals. He is requesting supplemental appropriations to move funds
that were used to make repairs back to expense accounts. Likewise, he is
requesting a supplemental for water meter fees from water meter purchases
for developers. The request is to move funds back to their expense accounts.
Recommendation: Introduction/First Reading on Regular Agenda on 8/1/2022
and Second Reading/Adoption on Consent Agenda 8/15/2022.
City of Gahanna Page 16
Committee of the Whole Meeting Minutes July 25, 2022
ORD-0044-2022 AN ORDINANCE AUTHORIZING SUPPLEMENTAL APPROPRIATIONS
- Water Meter Fees
Recommendation: Introduction/First Reading on Regular Agenda on 8/1/2022
and Second Reading/Adoption on Consent Agenda 8/15/2022.
H. ITEMS FROM THE COUNCIL OFFICE:
RES-0023-2022 A RESOLUTION DESIGNATING AUGUST 2022 AS SAFE DRIVING
AND SHARE THE ROAD AWARENESS MONTH IN THE CITY OF
GAHANNA
Recommendation: Introduction/First Reading/Adoption on Consent Agenda
8/1/2022.
I. ADJOURNMENT:
With no further business before the Committee of the Whole, the Chair
adjourned the meeting at 8:38 p.m.
Jeremy A. VanMeter
Clerk of Council
APPROVED by the Committee of the Whole, this
day of 2022.
Stephen A. Renner
City of Gahanna Page 17
Agenda
200 South Hamilton Road
City of Gahanna Gahanna, Ohio 43230
Meeting Agenda
Committee of the Whole
Merisa K. Bowers, Chair
Karen J. Angelou
Nancy R. McGregor
Kaylee Padova
Stephen A. Renner
Michael Schnetzer
Trenton I. Weaver
Jeremy VanMeter, Clerk of Council
Monday, July 25, 2022 7:00 PM City Hall, Council Chambers
A. CALL TO ORDER:
B. DISCUSSIONS:
1. Economic Development Training Series #1
2022-0219 Economic Development - Basics Course Materials
C. ITEMS FROM THE DEPARTMENT OF ECONOMIC DEVELOPMENT:
ORD-0045-2022 AN ORDINANCE AUTHORIZING THE MAYOR TO ENTER INTO
CONTRACT WITH ODOT FOR PURSUIT OF STATE INFRASTRUCTURE
BANK (SIB) LOAN, WAIVING SECOND READING AND DECLARING AN
EMERGENCY - Tech Center Drive Extension
ORD-0046-2022 AN ORDINANCE TO AUTHORIZE THE MAYOR TO ENTER INTO AN
OFFICE & INDUSTRIAL INCENTIVE AGREEMENT WITH COLUMBUS
AESTHETIC & PLASTIC SURGERY FOR A PERIOD OF 10 YEARS
D. ITEMS FROM THE CITY ATTORNEY'S OFFICE:
RES-0022-2022 A RESOLUTION APPROVING A MEMORANDUM OF AGREEMENT
WITH THE BOARD OF EDUCATION OF GAHANNA-JEFFERSON
PUBLIC SCHOOLS TEMPORARILY SUSPENDING CITY ORDINANCES
IN CHAPTERS 1108 AND 1197 REGARDING DUTIES OF THE
PLANNING COMMISSION FOR THE NEW HIGH SCHOOL PROJECT
E. ITEMS FROM THE DEPARTMENT OF PARKS & RECREATION:
RES-0024-2022 A RESOLUTION ADOPTING THE DEPARTMENT OF PARKS &
City of Gahanna Page 1 Printed on 7/22/2022
Committee of the Whole Meeting Agenda July 25, 2022
RECREATION 2022 PRICING POLICY AS RECOMMENDED BY THE
PARKS AND RECREATION BOARD
F. ITEMS FROM THE DEPARTMENT OF FINANCE:
ORD-0041-2022 AN ORDINANCE AUTHORIZING THE CREATION OF THE ONEOHIO
FUND NO. 2440
G. ITEMS FROM THE DEPARTMENT OF PUBLIC SERVICE & ENGINEERING:
MT-0017-2022 A MOTION AUTHORIZING THE DIRECTOR OF PUBLIC SERVICE &
ENGINEERING TO ENTER INTO CONTRACT AND WAIVE
COMPETITIVE BIDDING PURSUANT TO CODE SECTION 135.05(e)(3)
FOR EMERGENCY REPLACEMENT OF TRAFFIC SIGNAL CABINET AT
US-62 AND OLDE RIDENOUR ROAD
ORD-0042-2022 AN ORDINANCE AUTHORIZING SUPPLEMENTAL APPROPRIATIONS
AND WAIVER OF SECOND READING - Traffic Signal Cabinet at US-62
and Olde Ridenour Road
ORD-0043-2022 AN ORDINANCE AUTHORIZING SUPPLEMENTAL APPROPRIATIONS -
Damage to City Property
ORD-0044-2022 AN ORDINANCE AUTHORIZING SUPPLEMENTAL APPROPRIATIONS -
Water Meter Fees
H. ITEMS FROM THE COUNCIL OFFICE:
RES-0023-2022 A RESOLUTION DESIGNATING AUGUST 2022 AS SAFE DRIVING AND
SHARE THE ROAD AWARENESS MONTH IN THE CITY OF GAHANNA
I. ADJOURNMENT:
City of Gahanna Page 2 Printed on 7/22/2022
Get email alerts for Gahanna
A daily email when new agendas and minutes are posted.