Committee of the Whole
Regular MeetingGahanna, OH · January 9, 2023
Minutes
200 South Hamilton Road
City of Gahanna Gahanna, Ohio 43230
Meeting Minutes
Committee of the Whole
Trenton I. Weaver, Chair
Karen J. Angelou
Merisa K. Bowers
Nancy R. McGregor
Kaylee Padova
Stephen A. Renner
Michael Schnetzer
Jeremy A. VanMeter, Clerk of Council
Monday, January 9, 2023 7:00 PM City Hall, Council Chambers
A. CALL TO ORDER:
Vice President of Council Trenton I. Weaver, Chair, called the meeting to
order at 7:00 p.m. The agenda for the meeting was published on January 6,
2023. All members were present for the meeting. There were no additions or
corrections to the agenda.
B. DISCUSSIONS:
2023-0006 Council Resolutions Calendar for 2023 (Anticipated)
Vice President Weaver asked Clerk VanMeter to print out the prior year’s
calendar of resolutions that had been circulated towards the end of the year.
Weaver said he wanted to get a sense from Council if there were any
additions, corrections, modifications, or subtractions from the list.
Councilmember Bowers noted she had an additional resolution she plans to
work on with community members to recognize Urban Beekeeping
Awareness Month. She is targeting July as the month for adoption.
Mayor Jadwin asked for the list of the resolutions so that she can compare
with her proclamations for the year. Jadwin said she does not like to duplicate
efforts but would also like to see if there is a possibility of joining in on one.
Clerk VanMeter confirmed that he would send the list to Mayor Jadwin.
Councilmember Bowers asked whether the intention was to proceed with the
same list or mostly replicate what was done in 2022. Weaver responded that
he thinks that is the intention, unless there is a reason not to replicate. For
example, he said there are a couple of different arts-related resolutions that
he might prefer swapping out.
Councilmember Angelou suggested adding a resolution commemorating the
library’s grand opening coming up in March. Bowers thought that was a good
City of Gahanna Page 1
Committee of the Whole Meeting Minutes January 9, 2023
idea. Bowers added that she appreciated everyone's participation in these
resolutions. Sometimes it might feel performative, but Bowers thinks that it
means something to the people who are receiving them. It draws people into
Council Chambers, and that helps encourage breaking down those barriers
between people participating in their local government. She sees value to this.
C. ITEMS FROM COUNCIL OFFICE:
RES-0001-2023 A RESOLUTION RECOGNIZING MARTIN LUTHER KING, JR. DAY AND
NATIONAL DAY OF SERVICE, JANUARY 16, 2023
Recommendation: Introduction/Adoption on Consent Agenda on 1/17/2023.
RES-0002-2023 A RESOLUTION RECOGNIZING JANUARY AS NATIONAL BLOOD
DONOR MONTH
Vice President Weaver noted that he had put this one together. January is
National Blood Donor Month. He encourages folks who are able and eligible to
give blood. Weaver noted he had seen a lot of about the shortage in supply.
He asked if anyone had any feedback. President Renner thanked Weaver for
the reminder on blood donation.
Recommendation: Introduction/Adoption on Consent Agenda on 1/17/2023.
D. ITEMS FROM THE DEPARTMENT OF ENGINEERING:
ORD-0001-2023 AN ORDINANCE ACCEPTING A DEED OF EASEMENT FOR
PARCEL NO. 025-01376700 FROM CP CRESCENT, LLC,
ASSOCIATED WITH THE PIZZURRO PARK WATERLINE
IMPROVEMENTS, WAIVING SECOND READING, AND DECLARING
AN EMERGENCY
Tom Komlanc, Director of Engineering, said that the first item is requesting
acceptance of waterline easement in the Pizzurro Park and Buckles Tract
area. This easement inadvertently was not recorded. The waterline
improvements are in the ground and currently servicing the area. As the City
was working through with the potential development along the Buckles Tract,
it was uncovered that this had not been recorded. The Department is
requesting the emergency and waiver so that the City can get this to the
county to be recorded.
Recommendation: Introduction/First Reading/Adoption with Waiver and
Emergency on Consent Agenda on 1/17/2023.
MT-0001-2023 A MOTION AUTHORIZING THE DIRECTOR OF ENGINEERING TO BID
CONTRACT FOR THE 2023 STREET PROGRAM (ST-1101)
Director Komlanc said he is requesting permission to bid the 2023 Street
Maintenance Program. There is a visual map of the streets that the City is
proposing for rebuild our asphalt and overlay and seal for preventative
maintenance. The Department is also going to be assisting the Parks &
Recreation Department with some parking lot work at Woodside Green.
City of Gahanna Page 2
Committee of the Whole Meeting Minutes January 9, 2023
Councilmember McGregor referred to a lot where the old FOP was. A church
owns it, but a lot of people that use the lot for Park parking. Has the City
looked at sharing a cost to have that lot repaved? She said it is in pretty bad
condition. Is this something the City could do? Mayor Jadwin responded that
the City attempted several times to have conversations with Stonybrook.
When the City had reached out about that the church was just transitioning
pastors. The church asked if the City could wait until the new pastor came.
When the City reached out to the new pastor, the pastor was still getting
settled. Jadwin said the City will pick up that conversation again with the
church. Jadwin thought there is some concern around their future use and
how that would prevent them for future use of the lot. That dialogue will
continue. Jadwin knows that people think that the City owns that property
because it is at a trailhead. If there is a way that the parties can work
something out for use of that lot, Jadwin indicated this would be beneficial.
Vice President Weaver asked if this Program was on the same scale or
scope as recent years. Komlanc responded this was around $4 million in
overall effort but depended on the bid environment. Mayor Jadwin said, yes, it
is the same scope as the previous two years.
Recommendation: Adoption on Consent Agenda on 1/17/2023.
MT-0002-2023 A MOTION AUTHORIZING THE DIRECTOR OF ENGINEERING TO BID
CONTRACT FOR THE HAVENS CORNERS ROAD WATERLINE
IMPROVEMENT PROJECT (ST-1072)
Director Komlanc noted this item is for Havens Corners waterline
replacement. This project was anticipated to be a 2022 project. However,
given staffing and adjustments, the Department is now in a position to bring
this project forward. There have been several waterline breaks on this line.
The City is now wanting to replace it.
Councilmember Padova asked what the typical lifespan was of these water
lines. Is 60 years about average? Komlanc said it depended on the material
type. Waterlines that have been installed in the 60s have typically a
60-to-65-year lifespan when you have old cast iron pipe. The newer ductile
iron pipe and some of the PVC pipe is extending well past 100 years of useful
life. The Department is looking to go with a more modern material, such as
ductile iron pipe, depending on material availability, or PVC pipe depending on
availability of the waterline. He said all piping would be meeting American
Water Works Association (AWWA) standards.
Councilmember McGregor asked what kind of material would be used. Was it
the ductile iron? Komlanc responded the City will have it within its standards.
The ductile iron pipe is one of the waterline materials and PVC is another
alternative material that is used within the community. There will be a tracer
wire added with those so that the City knows where they are for future
locating. McGregor said if the county ever gets around to widening the road,
would this be ok where the line is? Komlanc said, yes, it will.
City of Gahanna Page 3
Committee of the Whole Meeting Minutes January 9, 2023
Recommendation: Adoption on Consent Agenda on 1/17/2023.
ORD-0002-2023 AN ORDINANCE AUTHORIZING THE MAYOR TO AWARD AND
ENTER INTO CONTRACT WITH NEWCOMER CONCRETE
SERVICES, INC FOR CONSTRUCTION WORK FOR THE 2021
SIDEWALK MAINTENANCE PROGRAM
Director Komlanc said the cost came in 9.7 percent over the engineer’s
estimate for the 2021 Sidewalk Maintenance Program. He said that in
researching what was notified to the residents, the Department saw cost
increase of a little over 13 percent to the residents. Given the timing of when
that estimate was prepared (early spring of last year) and just getting the bid
in December with construction activity slated to occur in in 2023, Komlanc
said while it is about a 13 to 13.5 percent increase, not every parcel would
necessarily see this. It is not an equal weighted distribution to each individual
parcel. He explained that when the bids came in, the joint repair was nearly
double the unit cost of what was originally anticipated. Some parcels had the
joint repair. Others did not. Therefore, some parcels could see a significant
increase within this. Given the time and delay (over a year now), Komlanc
wanted to open conversation with Council on whether or not there would be
an appetite for the City picking up the cost differential. The City has been
working toward this project for a while. It is the first phase, which has been on
the learning curve associated with establishing the Sidewalk Maintenance
Program. Mayor Jadwin added that part of this is as Director Komlanc
mentioned. There has been a delay from the time the City initially received the
first estimates to when it went to bid. She reminded Council that the
Engineering Department went through a tumultuous year last year. They City
went from five engineers down to one. Finding engineers in Franklin County
these days are like finding a needle in a haystack. Part of that delay was due
to the transition in staff from losing Mr. Moorehead and Ms. Ridge and then
hiring Director Komlanc and him being able to get his arms around the
Department. She said that situation is not something likely to repeat itself
going forward, but they did have the conversation internally on the City picking
up the cost differential. What was the will of Council with regard to absorbing
the approximate $46,000 differential as the City works through this very first
year of the Program given the staffing and implementation? Komlanc added
that at the time the Department provided notice to Council in regard to the
anticipated cost of construction for the City’s portion, there were some
omissions from that notice. For example, maintenance of traffic (MOT) was
not included within that. There was roughly $19,000 of expenditures
associated with MOT, which is predominantly at the ADA wheelchair ramps at
each intersection as well as the tree removals that will require some MOT to
get vehicular traffic around while trees are being removed in in the area. That
is all a City expense, as well as curb and gutter work adjacent to those ADA
ramps. There were costs that were not recognized at the time it was brought
forward in May. He referred to the screen showing the costs from the notice
versus the bid for City costs at $40,000 difference. Jadwin asked Komlanc to
speak to the budgeted amount. Komlanc stated the engineer’s estimate for
the project was around $503,000. The City has enough to cover the overall
City of Gahanna Page 4
Committee of the Whole Meeting Minutes January 9, 2023
project. When the City adds the traditional 10 percent contingency to the
project, the City is going to need slightly more, between $30,000 to $35,000
worth of addition to bring appropriations up to cover the 10 percent
contingency. Hopefully, the City will not need the contingency. Mayor Jadwin
said the original amount covers all of this, but the $30,000 supplemental
would just be needed for the contingency. Komlanc said that is correct.
Councilmember Bowers confirmed that this is still year one of the Program
that Council is discussing. She recalled that last year, Council received a list
of every resident and each estimate that had been projected for each of the
parcels at that time. She remembered this gave her a little bit of a “sticker
shock” because it was higher than she thought the City was anticipating in
terms of impact to residents. With the additional $46,500, is that above that
spreadsheet that Council previously saw with each identified parcel?
Komlanc said that is correct. He reiterated that this additional cost is not an
even distribution. Again, the joint repair was nearly double the cost that was
originally anticipated. If a parcel had significant joint repairs, they could see
$1,000 to $1,200 of additional cost from what the city originally was projecting.
Bowers asked if this had gone on forward on the initial timeline that the City
had hoped to be able to provide, would the residents not have seen that
$46,000 cost? Komlanc said the residents likely would have seen some of it.
He thought that just with the material and labor escalations in the market now,
the City could have seen a reduced cost. He cannot say what that exactly
would have been, but the delay is part of it. Bowers asked that in going
forward, would Council see quite as wide a discrepancy between those
estimates and then the actual costs? Are residents going to maybe be able to
have better confidence that those estimates are going to be close to those
actual construction costs? Komlanc responded that now that the City had
hard bids, the Department can utilize that information to help inform the 2022
Program, which will also be constructed within a calendar year 2023. These
bids, as well as unit prices obtained from the Street Maintenance Program,
will go to providing those cost estimates. Bowers said that given all of that
information and that particularly residents had maybe already budgeted for
certain costs, and that there is some responsibility on the City’s part, she
thinks the cost differential should be covered. She appreciated the
administration bringing this forward to Council and requesting this. This is an
important aspect that Council can provide some support to residents. Bowers
would be fully supportive of supplementing the additional cost.
Councilmember McGregor said she agreed. Considering that everything has
gone up in price everywhere, was there a way the City could do a two or three
percent increase? She added that even if the City did not have this long of a
delay, it might have been different estimates or it might have been the same,
a little lower, or a little higher. Would that be prohibitive to do a two or three
percent increase and then the City just take responsibility for the rest? She
said she is not proposing half and half, but just a little bit more of an increase
than before. Komlanc responded that they would need to look into the data.
As he mentioned before, there are some parcels that may have seen a
decrease in their overall cost. However, there were a significant number of
City of Gahanna Page 5
Committee of the Whole Meeting Minutes January 9, 2023
parcels that had this joint repair where the cost doubled. He did not have the
information right in front of him but said he could prepare this for Council. The
cost associated with the six-inch thick concrete walk at the driveway
approaches was slightly higher than the original engineer’s estimate, as well
as the four-inch walk. The biggest cost difference was associated with joint
repair. Those that had joint repair on their parcel would see a significant
increase. Therefore, giving them one, two, or three percent increase would be
really small comparatively. Komlanc said he looked at one of the parcels, and
it had $1,200 to $1,500 above what they otherwise would have had. This
increase was based off of the joint repair that they had on their parcel. He
thought this might have been a property on Daventry. McGregor stated that if
it happens again and prices keep going up, she hates to give estimates and
then every time Council is expected to pay the difference because the
estimate is not quite as accurate as it should be. She said people say, “Well,
you did it last year. Why aren't you doing it this year?” Mayor Jadwin
responded that they had that discussion internally when they were discussing
how to or whether to present this to Council. Jadwin thinks the differentiating
factor with this year is it is the very first year of the Program. The City was
going into it trying to sort through when the original estimate numbers came
in. She recalled then Assistant City Engineer Caitlyn Ridge going back
through the numbers and trying to totally understand them. Then,
compounding that with the delay the City had with the staff transitioning, that
is not likely to continue in future years. Jadwin shared that she had the same
concern, too, on whether the City was setting a precedent but concluded this
is a very unique circumstance given the fact that this is the first year of the
program and the City has had these multiple challenges around this first year.
With the new timeline that Director Komlanc has set out for future sidewalk
programs, beginning with the 2022 program, Jadwin thinks the timeline will be
much tighter.
Councilmember Padova referred to the unrecognized costs that Komlanc
was talking about. Were those part of this 13 percent increase or outside of
the increase? Director Komlanc said that the 13.4 percent increase is taking
the original $346,493 up to the $392,962.75. That is a 13.4 percent increase
above what they originally saw back in May. Padova asked if the $46,000
number includes the nearly $20,000? Komlanc said, no, the items down
below on the sheet are all unrecognized costs that otherwise would have
been attributable to the City. Padova indicated she understood. She
confirmed with Komlanc that Council covering those unrecognized costs did
not change anything for the residents. Komlanc added that the City’s cost
went up as a result of the bid, plus the costs that were not recognized in May
of last year.
Councilmember Schnetzer said he agreed with the moral justification behind
the Director’s suggestion, but he is curious about some input from the City
Attorney's Office on whether or not this is legally sets some precedent that
might cascade or domino in the future years as the City looks at decades’
worth of Sidewalk Maintenance Program years. Does Assistant City Attorney
Roth have anything that contemporaneously that he can speak to regarding
City of Gahanna Page 6
Committee of the Whole Meeting Minutes January 9, 2023
this? Mr. Roth stated he has not looked into any of this specifically. Based on
his prior experience, Roth noted there are always going to be claims that
there is a precedent. Whenever you do something extraordinary in one part of
town, another part of town is going to want that. However, Roth thinks there is
justification here. The City is doing the 2021 Sidewalk Program in 2023. The
City is not going to be doing that on each of the successive phases, hopefully.
He concluded he did not think there was anything legally binding on the City to
do this for anyone in the future but said there will be claims that the City
should. He is sure of that. Komlanc said while the City needs to get the 2021
Program moving forward, it is his goal to bring forward to City Council in
February the 2022 Program. On the heels of that Program, over the summer
the City will be evaluating the 2024 Program and be in a position in late
summer to provide notice to the residents that they are in the Program Area.
This will then give residents the opportunity during the fall, up to around
Thanksgiving, to perform that work on their own should they choose to do so.
At this point in time next year, he outlined that 2024 would go out for bidding.
Councilmember Angelou asked if Komlanc had found that people who are
doing it on their own are paying less than those in the Program. Komlanc said
he does not have costs associated with private work.
Councilmember Padova asked how many people decided to do sidewalk
maintenance on their own versus how many opted into this. Komlanc said he
can get that number. It has been kind of a moving target. Folks have opted
out, and then the City went to do inspections and they had not performed the
repairs. So, those are now back in the Program. Komlanc will have that
number available for next week. Padova asked if Komlanc thought with people
opting out, that this made numbers go up or was it simply the cost of
materials? Komlanc said he understands that there are some areas where a
group of residents got together and hired a contractor to perform work in a
given area to get economies of scale, but as a part of the permit process, the
City did not capture the associated cost with that private work. He believed
there were 219 parcels within the 2021 Program and would, again, provide to
Council the number of those opting out.
Councilmember Bowers said what has been discussed is why it will be
critical to have good estimates that are put out to residents for future Program
years. Bowers said she is wondering if Komlanc had seen any kind of
contracting with the City’s contractor that would restrict or get them to agree
to limit their cost, their final project cost, to encourage accurate bidding and
accurate estimates. Komlanc said the City has unit prices associated with
the scope and breadth of work. There will be construction administration
taking the quantities of actual field measurements that will go against the
actual installed work in the field. That is the quality assurance and quality
control during the course of construction. Bowers asked, would there be any
potential that a contractor would agree to limit their final cost to that 10
percent contingency? Komlanc said he is hoping that the City can keep it at
cost. The contingency is there for unforeseen site conditions. He hoped the
City does not encounter that.
City of Gahanna Page 7
Committee of the Whole Meeting Minutes January 9, 2023
Vice President Weaver said he believed the appropriate thing would be to
cover the cost here, given the length of the delay. He hoped that as the City
learns from the first year's Program, it will not have that significant delay in
future years and have more accurate bids as Director Komlanc was saying.
Weaver said he feels this is probably the appropriate path forward for the
2021 Program.
Recommendation: Introduction/First Reading on Regular Agenda on 1/17/2023;
Second Reading on Consent Agenda on 2/6/2023.
ORD-0003-2023 AN ORDINANCE AUTH O R I Z I N G A SUPPLEMENTAL
APPROPRIATION - 2021 Sidewalk Maintenance Program
Recommendation: Introduction/First Reading on Regular Agenda on 1/17/2023;
Second Reading on Consent Agenda on 2/6/2023.
E. ADJOURNMENT:
With no further business before the Committee of the Whole, the Chair
adjourned the meeting at 7:28 p.m.
Jeremy A. VanMeter
Clerk of Council
APPROVED by the Committee of the Whole, this
day of 2023.
Trenton I. Weaver
Chair
City of Gahanna Page 8
Agenda
200 South Hamilton Road
City of Gahanna Gahanna, Ohio 43230
Meeting Agenda
Committee of the Whole
Trenton I. Weaver, Chair
Karen J. Angelou
Merisa K. Bowers
Nancy R. McGregor
Kaylee Padova
Stephen A. Renner
Michael Schnetzer
Jeremy A. VanMeter, Clerk of Council
Monday, January 9, 2023 7:00 PM City Hall, Council Chambers
A. CALL TO ORDER:
B. DISCUSSIONS:
1. Resolutions Calendar for 2023
C. ITEMS FROM COUNCIL OFFICE:
RES-0001-2023 A RESOLUTION RECOGNIZING MARTIN LUTHER KING, JR. DAY AND
NATIONAL DAY OF SERVICE, JANUARY 16, 2023
RES-0002-2023 A RESOLUTION RECOGNIZING JANUARY AS NATIONAL BLOOD
DONOR MONTH
D. ITEMS FROM THE DEPARTMENT OF ENGINEERING:
ORD-0001-2023 AN ORDINANCE ACCEPTING A DEED OF EASEMENT FOR PARCEL
NO. 025-01376700 FROM CP CRESCENT, LLC, ASSOCIATED WITH
THE PIZZURRO PARK WATERLINE IMPROVEMENTS, WAIVING
SECOND READING, AND DECLARING AN EMERGENCY
MT-0001-2023 A MOTION AUTHORIZING THE DIRECTOR OF ENGINEERING TO BID
CONTRACT FOR THE 2023 STREET PROGRAM (ST-1101)
MT-0002-2023 A MOTION AUTHORIZING THE DIRECTOR OF ENGINEERING TO BID
CONTRACT FOR THE HAVENS CORNERS ROAD WATERLINE
IMPROVEMENT PROJECT (ST-1072)
ORD-0002-2023 AN ORDINANCE AUTHORIZING THE MAYOR TO AWARD AND ENTER
INTO CONTRACT WITH NEWCOMER CONCRETE SERVICES, INC
FOR CONSTRUCTION WORK FOR THE 2021 SIDEWALK
MAINTENANCE PROGRAM
City of Gahanna Page 1 Printed on 1/6/2023
Committee of the Whole Meeting Agenda January 9, 2023
ORD-0003-2023 AN ORDINANCE AUTHORIZING A SUPPLEMENTAL APPROPRIATION -
2021 Sidewalk Maintenance Program
E. ADJOURNMENT: