Committee of the Whole
Regular MeetingGahanna, OH · April 14, 2025
Minutes
200 South Hamilton Road
City of Gahanna Gahanna, Ohio 43230
Meeting Minutes
Committee of the Whole
Trenton I. Weaver, Chair
Merisa K. Bowers
Jamille Jones
Nancy R. McGregor
Kaylee Padova
Stephen A. Renner
Michael Schnetzer
Jeremy A. VanMeter, Clerk of Council
Monday, April 14, 2025 7:00 PM City Hall, Council Chambers
A. CALL TO ORDER:
Gahanna City Council met for Committee of the Whole on Monday, April 14,
2025, in Council Chambers. Vice President of Council Trenton I. Weaver,
Chair, called the meeting to order at 7:03 p.m. The agenda was published on
April 11, 2025. Councilmember Nancy McGregor was absent. All other
members were present for the meeting. There were no additions or
corrections to the agenda.
B. ITEMS FROM THE SENIOR DIRECTOR OF OPERATIONS:
1. Gahanna Civic Center - 825 Tech Center Drive Update
2025-0086 Gahanna Civic Center (825 Tech Center Drive) Construction Update
4.14.2025
Exterior, Interior, Upcoming Updates
Senior Director of Operations Kevin Schultz provided the monthly update on
the 825 Tech Center Drive renovation and expansion project. He was joined
by Police Chief Spence to highlight progress specific to the Police
Department’s facilities. Schultz noted that February had been relatively slow
for construction, largely due to winter weather. However, in March of 2025, the
pace picked up significantly, and progress resumed across multiple areas of
the site. He reported that all utility work on the site, including water, sanitary,
and storm systems, was complete and the team had begun site grading. All
main rooftop heating, ventilation, and air conditioning (HVAC) units were
installed during a Saturday lift, and the building was prepared for conditioning.
The HVAC system was scheduled to be operational by mid-to-late May of
2025, and the building was expected to be fully dried in by the end of April of
2025.
Interior progress included ongoing drywall finishing on the second and third
floors. Schultz noted that the north-south wing of the third floor was drywalled,
City of Gahanna Page 1
Committee of the Whole Meeting Minutes April 14, 2025
patched, and painted. Ceiling grid installation began in that wing, and the
contractor planned to continue working from that area into the Police
Department wing and down through the second and first floors. He provided
updates on key infrastructure elements, including the installation of electrical
switchgear, information technology (IT) cabinets, and shaft wall
reconstruction. The interior shaft wall was removed and rebuilt to meet
current code requirements, addressing a previous issue. Progress also
continued in the Police Department’s holding facility. Schultz shared that he,
Chief Spence, and several officers planned to conduct a walkthrough later in
the week to finalize design and layout details, such as wall heights and the
flow of space dedicated for mugshots and fingerprints. On the first floor,
mechanical and electrical rough-ins were ongoing. Schultz confirmed that
good progress continued and emphasized that the project remained on
schedule.
Senior Director Schultz stated that the furniture, fixtures, and equipment
(FF&E) procurement process was underway, with responses due to the
architect, MSA, by the end of the week. The Administration anticipated
presenting the results at the second committee meeting in May of 2025. The
City also issued a separate request for proposal (RFP) for moving and
logistics, with proposals received the previous Friday, April, 11, 2025. To date,
the project reached 61% completion and experienced 24 weather-related
delay days. Schultz shared recent photos showing various areas of the
building. These included the newly poured first-floor concrete in the future
Mayor’s Court and City Council Chambers, painted walls in third-floor study
rooms, rooftop HVAC units, an IT closet under construction, and newly
installed electrical switchgear in the main electrical room. He noted that while
some images might seem routine, they represented essential systems
necessary for the building’s long-term functionality.
March Financial Updates
Senior Director Schultz continued the 825 Tech Center Drive project update
with a review of the overall construction contract and financing structure. He
presented a summary table showing the Guaranteed Maximum Price (GMP)
components of the construction contract. The total project construction cost,
comprising GMP 1 and GMP 2, was $59,627,855. As of the February pay
application, 46% of the construction costs were invoiced, totaling
approximately $27.5 million. The March invoice was not approved yet.
Schultz reviewed the status of allowances and contingencies, reporting that
$867,000 spent to date, representing approximately 26% of the total $4.7
million allocated for those items. He then addressed a request from
Councilmember Schnetzer to revisit original project assumptions. Schultz
explained that the construction cost breakdown remained consistent with
previous reports. Each GMP contract included construction expenses and
costs related to allowances, contingencies, construction management fees,
insurance, bonding, and commercial activity taxes (CAT). These components
collectively comprised the $59.6 million total.
Schultz moved on to a full project summary, outlining all costs beyond
City of Gahanna Page 2
Committee of the Whole Meeting Minutes April 14, 2025
construction. The City purchased the 825 Tech Center Drive building for
$8.75 million, including a $250,000 down payment noted on a subsequent
slide. Design and pre-construction services were included, along with the
$59.6 million construction figure. The FF&E (Furniture, Fixtures, and
Equipment) budget stood at $1.6 million and was increased by $500,000
using funds from a health and wellness refund. The additional funds
supported staff wellness improvements such as height-adjustable desks
across the facility. Additional project-related costs included third-party
inspections (e.g., for steel and concrete), builder’s risk insurance, permitting
and inspections, an easement agreement with American Electric Power
(AEP), and the acquisition of two acres of land at the rear of the 825 property.
Schultz concluded with a review of project financing. He explained that $3.3
million in prior-year cash reserves, identified by the Finance Department in
2021-2022, funded early planning efforts, including consultant MCP’s budget
validation and the building’s down payment. Legal and consulting costs
related to the property acquisition were also covered from this amount. He
noted that the building purchase was ultimately rolled into the first bond
issuance of $18.2 million, which also incorporated a 2012 bond refund.
Although the refunded amount was not specified, Schultz clarified that the
reduced total was not an error but an intentional accounting measure to avoid
duplicating the building purchase in the financial summary. The second bond
issuance occurred in June and totaled $33.5 million, covering the remaining
project costs. The City also committed $10 million in cash to the project-$3
million from the Capital Fund and $7 million from the General Fund, to support
FF&E and contingency budgets. Schultz explained that any unused
contingency funds would return to the cash allocation rather than the bond
proceeds.
Questions from Council
Councilmember Schnetzer asked for clarification regarding the two
bottom-line items on the financial summary slide, specifically, the $3 million
and $7 million cash-funded contributions. He requested an explanation of why
these amounts were funded with cash rather than through bonds. He noted
his understanding that FF&E was excluded from bond funding due to its
shorter life cycle, which did not align with the 28-year term of the bonds. He
also asked for further clarification on the $7 million portion.
Senior Director Schultz responded that, in consultation with Finance Director
Joann Bury, the Administration determined that bringing $10 million in cash to
the project was appropriate. Of that, $4.7 million was allocated for
contingencies, $1.6 million for FF&E, and the remainder was rounded to an
even $10 million to balance bond issuance and repayment considerations. He
explained that FF&E expenses could not be financed through bonds because
such items do not meet the minimum 28-year life span required for
bond-funded capital expenditures. As a result, FF&E had to be funded with
cash.
Councilmember Schnetzer noted that contingency funds might ultimately go
unspent. He emphasized that funding these amounts with cash instead of
City of Gahanna Page 3
Committee of the Whole Meeting Minutes April 14, 2025
bonds avoided the risk of borrowing money that may not be needed and then
paying interest on it for 28 years. Schultz confirmed that this was correct and
added that the same principle also applied to the allowance line.
Senior Center Covered Entryway
Senior Director Schultz provided an update regarding ongoing discussions
about the potential addition of a covered walkway at the entryway to the
Senior Center portion of the 825 Tech Center Drive facility. He referenced the
upper portion of a site drawing as the focal area for the discussion. Schultz
reviewed the parking layout, noting that the facility included approximately 350
to 360 total parking spaces. According to Americans with Disabilities Act
(ADA) requirements, a facility of that size must have at least eight
handicap-accessible spaces. The site currently includes 17 designated
handicap parking spaces distributed throughout the lot. In addition, the City
established a series of “limited mobility” parking spaces, shown in lighter blue
on the drawing. These spaces are not legally enforceable but are intended as
a courtesy to provide easier access for individuals with mobility limitations.
Schultz explained that these spaces offer priority proximity to the building,
although anyone may park there without penalty. A few of these limited
mobility spaces were relocated from the front to the rear of the building,
where access is actually closer. In total, 21 such spaces were provided, split
roughly evenly between the front and back of the building.
Schultz then focused on the proposed covered walkway at the Senior Center
entrance. Staff engaged with the architect and construction manager, Elford,
to obtain a rough order of magnitude (ROM) cost estimate. The estimated
cost to design and construct the 23-foot-long covered walkway was between
$300,000 and $350,000. Schultz illustrated the 23-foot distance by
referencing the approximate space from Vice President Weaver’s seat to the
front row of Council Chambers chairs. He explained that the team also
evaluated the usage of the existing portico at the current Senior Center. Staff
estimated that it was used for two to four drop-offs per week, though it often
functioned more as a parking space than a dedicated drop-off area. Schultz
stated that conversations with members of the Senior Center suggested that
while the issue was important to a few individuals, it was not a widely shared
concern among the membership as a whole.
Schultz provided comparisons to similar facilities. Recently completed or
soon-to-open senior centers in Westerville, Upper Arlington, and Hilliard do
not feature covered walkways or porticos. In Upper Arlington, members must
walk a considerable distance from a parking garage to the building. In
Westerville, the uncovered distance to the entrance is approximately 30 to 35
feet. He noted that cost, aesthetics, and functionality were key considerations
in the evaluation. The architect expressed concern that a covered walkway
added post-design could appear as an afterthought and detract from the
building’s overall design. As an alternative, staff began exploring the idea of
planting trees to form a natural canopy over the walkway rather than installing
a structural one. Schultz concluded his remarks by inviting Police Chief
Spence to speak on the public safety implications related to the proposed
covered walkway.
City of Gahanna Page 4
Committee of the Whole Meeting Minutes April 14, 2025
Police Chief Jeff Spence provided remarks regarding public safety concerns
related to the proposed covered walkway at the Senior Center entry of the 825
Tech Center Drive facility. He noted that although the building appeared large
from the street, it became more scaled and compressed in appearance upon
closer approach due to the curtain wall design and layout. He emphasized
that the structure was multi-story, requiring accommodation for larger fire
apparatus and emergency vehicles. Chief Spence explained that the curved
roadway in front of the main entrance, where the covered walkway was
proposed, was a very short and confined space. He expressed concern about
the ability of a 60-foot ladder truck to navigate the space, calling it difficult if
not impossible. He added that standing vehicles in that area would further
complicate access for fire and Emergency Medical Services (EMS) vehicles,
including squads, first responder engines, and others responding to detainee
or walk-in medical emergencies. He pointed out that a key fire hydrant with
direct connectivity to the building was located near the lower edge of the
proposed area, as shown in the site rendering. This further limited feasible
vehicle staging in front of the building.
Chief Spence contrasted the proposed layout with the current Senior Center,
where the existing overhang is located off the main travel way, allowing
drop-offs to occur without obstructing circulation. In contrast, the front area of
the new facility is part of a main travel way and serves as a primary
circulation route around the building. He concluded by noting that, under
existing conditions, the current Senior Center’s covered area was often used
for parking rather than drop-off. This pattern further highlighted concerns that
a new covered structure could become similarly misused and pose
challenges for emergency access.
Questions and Comments from Council
Vice President Weaver thanked Senior Director Schultz and Chief Spence for
their detailed follow-up on the proposed covered walkway at the Senior
Center. He noted that he and several colleagues had previously reached out
with questions and appreciated the consideration of potential alternatives to
find the best possible solution.
Councilmember Schnetzer raised concerns about the estimated cost of the
walkway, noting that the back-of-the-envelope math suggested approximately
$15,000 per linear foot. He asked what the primary cost drivers were. Schultz
responded that the primary factor was that the structure was not part of the
original construction plan. He explained that the cost of steel, which continued
to rise, significantly impacted the estimate. Additionally, the design would
require the installation of four footings, two bollards, and electric wiring in the
roof structure. Schultz emphasized that electrical components in particular
added substantial costs. He acknowledged his own surprise when the cost
estimate came back at $300,000 to $350,000.
Councilmember Padova sought clarification on the public safety concerns.
She asked whether the issue was the physical presence of the canopy
structure or the likelihood that cars would stop and block access. Chief
City of Gahanna Page 5
Committee of the Whole Meeting Minutes April 14, 2025
Spence responded that it was a combination of factors. He noted that the
drawing illustrated two parked vehicles measuring about 22 feet each. The
total distance between the southernmost car and the apex of the roadway
curve was less than 40 feet, making it extremely difficult-if not impossible-for
large emergency vehicles to navigate the area. He clarified that the structure
under consideration would not extend out far enough to function as a
traditional overhang or portico, as site constraints would prevent that. The
canopy would stop at the sidewalk, and the area would remain a main
circulation route around the building. Spence emphasized that any vehicle
stopping there, even briefly, would likely cause obstruction. Schultz added
that in practice, a second vehicle would not likely stop where one was shown
in the illustration. Instead, it would pull up behind the first car in the designated
drop-off lane, which was constructed specifically for that purpose. He
highlighted the curve of the roadway and the proximity to pedestrian areas as
key design factors that guided the layout.
Councilmember Padova asked about the nature and frequency of drop-offs at
the current Senior Center. She inquired whether the facility regularly received
vans or buses transporting groups of people, such as residents from assisted
living facilities. Schultz responded that the two to four weekly drop-offs
monitored by staff reflected individual drop-offs-not group trips. For larger trips
or excursions, staff coordinated passenger loading away from high-traffic
areas, though not necessarily under a covered structure. Padova clarified her
question, asking whether the new facility would receive group drop-offs from
assisted living communities, particularly those transporting individuals with
mobility devices. Director of Parks and Recreation Stephania Ferrell
confirmed that the city staff maintained partnerships with assisted living
providers. She explained that these partners sometimes sponsored events
and brought residents to attend. Ferrell stated that she did not view the lack of
a covered walkway as a barrier. She emphasized that appropriate access to
the facility was available, and that staff could provide accommodations during
inclement weather as needed.
Vice President Weaver referred to a prior walkthrough of the 825 Tech Center
Drive facility with Senior Director Schultz, during which they discussed the
feasibility of constructing a covered walkway at the rear of the building, near
the dedicated Senior Center entrance. He asked Schultz to summarize those
considerations on the record. Schultz explained that creating a similar
covered structure at the rear of the building would require approximately
double the distance compared to the proposed front walkway. He indicated on
the site plan the location of the rear Senior Center member entrance and
explained that the distance from the door to a potential drop-off point was
significantly greater than the 23 feet required at the front. He added that the
primary challenge with constructing a covered structure at the rear was
related to traffic flow. The area immediately outside the rear entrance was
part of a key north-south travel lane. Stopping or standing vehicles in that
location would block most or all of the travel lane, creating significant
disruptions to site circulation and posing safety concerns.
Councilmember Padova followed up by asking whether any form of shelter
would be provided at the rear entrance, especially since members would be
City of Gahanna Page 6
Committee of the Whole Meeting Minutes April 14, 2025
required to use a badge or fob to access the door. Schultz confirmed that a
small three- to four-foot overhang would be affixed to the building above the
entrance. This structure, supported by the building itself, would provide
minimal coverage for individuals as they accessed the entrance, protecting
them from the elements while using their access credentials.
Police Department
Senior Director Schultz introduced the next portion of the presentation,
focused on the Police Department’s training and operational facilities at the
new 825 Tech Center Drive building. He noted that the layout emphasized
efficiency, future expansion capacity, and the creation of a safe and secure
facility. Schultz emphasized the intentional design separating staff and public
spaces to enhance safety for employees, officers, and visitors alike. He then
turned the presentation over to Police Chief Jeff Spence.
Chief Spence began with an overview of the Police Department’s lower-level
training center, located on the west side of the building. He described the first
set of images, including an observation area with large windows looking into
the range, the range itself with its backstop, and a storage area for equipment
such as lane dividers. Adjacent to these areas were the simulator room and
armory, as well as restrooms and secured storage space. The training center
included multiple doors and features to maintain positive HVAC pressure,
essential for safe environmental conditions. He also noted that this lower
level, including its stair tower, served as the designated storm shelter for the
entire facility-an important feature not available in current city buildings.
Spence continued with the second section of the training center, highlighting
the multi-functional training room, which will also serve as the City’s
Emergency Operations Center (EOC) during major weather events or other
emergencies. Additional images showed the fitness center and defensive
tactics room. The defensive tactics room would allow for simulation-based
training under stress, including scenarios like applying a tourniquet, where
officers' fine motor skills may be tested. He noted that this type of high-stress,
realistic training could help identify and resolve equipment or procedural
issues in a controlled environment before they occur during actual calls for
service.
Spence then described the "monument stair," a central stairwell connecting
all three floors of the Police Department. This stairwell would serve as a
unifying space linking the field services and training areas on the lower and
first floors to investigative services and administrative offices on the second
and third floors. He noted that other police departments, such as those in
Westerville, Hilliard, and Dublin, have done an excellent job preserving agency
history, and the new monument stair would allow Gahanna to do the same.
The stairwell would feature plaques honoring retirees and officers who
served, including one who died in the line of duty and two who died while
serving the City of Gahanna.
To provide context for the improvements, Spence shared current images of
the existing police facility across the street, focusing on the female locker
City of Gahanna Page 7
Committee of the Whole Meeting Minutes April 14, 2025
room. The existing locker room included one stall, one shower, and one sink.
Lockers were so closely spaced that two people could not open adjacent
lockers at the same time. The lack of benches and storage space made the
area cramped and inefficient. The space also doubled as gear storage,
contributing to further congestion. In contrast, the new facility would separate
gear storage into its own dedicated space near deployment areas, improving
organization and operational efficiency. The locker rooms under construction
would feature dedicated restroom facilities and a new HVAC system that
circulated air not only into the room but directly into the lockers. This system
would help dry wet equipment more effectively, reducing mold and odors, an
important consideration given the challenging environmental conditions
officers often face. Spence emphasized that these improvements would
support both hygiene and overall staff well-being.
Questions & Comments from Council
Councilmember Schnetzer asked Chief Spence to comment on the
importance of the structural hardening of the new police facility at 825 Tech
Center Drive. He emphasized the need for the facility to remain operational in
the event of a disaster, such as a tornado, and requested a summary of
relevant design features for the public record.
Chief Spence affirmed that the building will be constructed as a fully hardened
public safety facility. He acknowledged that certain design improvements
were made to the existing structure during both design and construction
phases to enhance its durability and operational resilience. He confirmed that
the facility will include a storm shelter and other components necessary to
maintain functionality during emergencies. Spence recounted a prior incident
from 2006 when a derecho storm caused two main doorways in the current
police facility to blow out due to inadequate door strength. At the time, the
facility was equipped with basic storefront doors that were neither hardened
nor commercial grade, leaving the building unsecured. He further explained
that the current facility contains additional vulnerabilities, including hollow core
doors and unsecured window areas. In contrast, the new facility is being
constructed with safety and security as top priorities. Design elements
include standoff distance to control approach access, secure parking, and
reinforced materials throughout. Spence noted that the Police Department
would have two lobby areas: a hard lobby for initial public access and a soft
lobby for secondary purposes such as taking police reports or conducting
interviews. The new facility also includes a designated safe room for
individuals in crisis who require immediate separation and protection. This
room can be secured with minimal staff involvement and is designed to
ensure occupant safety. He concluded by stating that the hardened design
and emergency features would benefit the Police Department and other City
staff working in the building.
2. Capital Improvement Plan (CIP) Update
2025-0087 Capital Improvement Plan (CIP) Presentation and Update 4.14.2025
City of Gahanna Page 8
Committee of the Whole Meeting Minutes April 14, 2025
Senior Director of Operations Kevin Schultz provided an update on the
Capital Improvement Plan (CIP) for the Committee of the Whole. He noted
that the CIP Advisory Committee met in March of 2025, to begin reviewing the
timeline and framework for the 2026 CIP update. Schultz reviewed the
published CIP adoption timeline, noting that the draft CIP report would be
introduced to Council on August 11, 2025, with final adoption targeted for
September 2, 2025, following a second reading and public hearing. He
reiterated that adoption of the CIP was not a formal approval of the capital
budget itself. However, the 2026 CIP was expected to reflect approximately
85-90% of the actual capital budget, with changes later presented as
amendments during budget deliberations. In response to previous Council
feedback, the Administration aimed to shift most capital-related presentations
into August and September to reduce presentation time during October and
November budget discussions.
Schultz then discussed the continued evolution and maturation of the CIP
document. He explained that while the document's intent remained
consistent, the city administration updated project phases and terminology to
reflect clearer planning expectations and eliminate confusion. In the past,
project phases were labeled numerically by year groupings, Phase 1 (Years
1-5), Phase 2 (Years 6-10), and so forth; this often led to misunderstandings
about when projects were expected to begin. Instead, city administration
proposed new terminology for project phases, aimed at better reflecting a
project's status rather than a specific year:
1. Actionable - Projects currently in design and scheduled for
construction. These projects were financed and were progressing,
such as 825 Tech Center Drive.
2. Assessment - Projects undergoing feasibility analysis, including
evaluation of cost, design, and funding needs. An example was the
Clark State Road multi-use trail feasibility study with the Franklin
County Engineer’s Office.
3. Identified - Projects that were recognized but not yet evaluated for
feasibility. These remained on the long-range planning list and could
be promoted in the future.
4. Visionary - Long-term conceptual projects, such as a hypothetical
100-acre solar farm. These projects were aspirational and unlikely to
proceed in the near term.
Schultz emphasized that projects could move fluidly between categories as
more information became available or as resources were allocated. He
stressed that the key goal was not to tie project status to a rigid timeframe,
but to maintain a clear categorization system that reflected feasibility,
planning stage, and readiness for execution. He concluded by explaining that
while some wording in the published document might still reflect the older
“Phase 1-4” terminology, staff will update the language in consultation with the
Advisory Committee and Council. The core intent of the plan, to identify,
prioritize, and phase projects appropriately, would remain unchanged.
City of Gahanna Page 9
Committee of the Whole Meeting Minutes April 14, 2025
Questions & Comments from Council
Councilmember Jones asked whether the newly proposed terminology-such
as "Actionable," "Assessment," and "Identified", would replace the “Start Year”
currently shown in the Capital Improvement Plan (CIP) document. She asked
if city administration would no longer include specific start years for projects.
Senior Director Schultz confirmed that the shift in terminology would replace
the use of a literal start year for most projects. For actionable projects, a start
year such as 2025 would still be included, but for projects in the “Identified”
phase, the column would instead show the label “Identified.” Schultz added
that the heading for the “Start Year” column may also be updated to reflect
this change.
President Bowers followed up, asking whether allocating funding for feasibility
assessments would automatically move a project from the “Identified”
category into the “Actionable” category. Schultz clarified that it would not. He
gave the example of the Clark State Road multi-use trail, noting that even with
allocated funding for feasibility work, the project would only advance to the
actionable category if Council explicitly authorized it. He emphasized that
feasibility alone did not guarantee advancement to construction. President
Bowers noted that the CIP Advisory Committee discussed the topic of
feasibility extensively and found it to be a productive conversation. She
highlighted that feasibility assessments should examine more than just cost
and include considerations such as land availability and location constraints.
Schultz agreed, citing the City’s service complex as an example. While the
project remained a high priority, it remained in the assessment category due
to the ongoing challenge of locating 10 to 12 acres of available land for the
facility.
Overview of Projects
Senior Director Schultz continued the Committee of the Whole update by
reviewing the nine largest capital projects currently identified within the City of
Gahanna’s Capital Improvement Plan (CIP). He noted that while the following
slides used an older nomenclature, referring to “short,” “mid,” and “long-term”
project phases, he would update the terminology to reflect the revised
“Actionable,” “Assessment,” “Identified,” and “Visionary” phases prior to
distributing the final slide deck. Schultz explained that the nine projects
represented a collective investment range of approximately $85 million to
$105 million in today’s dollars. He clarified that while many of these projects
were well-defined in terms of scale and scope, their prioritization and
implementation varied. He also noted that some projects contained
subcomponents with differing priority levels. For example, the Creekside
Garage and Plaza project included a portion deemed imperative and
therefore classified as a Priority 1 project, while other components were lower
in priority. He further explained that the “ Westside Utility Improvements”
project, frequently referred to as the “Westside Sewer Project”, was renamed
to better reflect its inclusion of water and storm sewer improvements in
addition to sanitary sewer. The estimate of $12-16 million applied to Phase 1
only and did not account for future phases that would increase the total
City of Gahanna Page 10
Committee of the Whole Meeting Minutes April 14, 2025
investment further.
Schultz then introduced the individual project slides, each of which included a
project description, CIP phase (to be updated), priority level, detailed cost
estimates for design, pre-construction, and construction, and potential
funding sources. He informed the Council that the slide deck would be
available for review and encouraged members to interrupt with questions as
needed. The first detailed project discussed was the Big Walnut Trail, a
multi-phase, long-term initiative more than ten years in the making. Schultz
noted ongoing work to traverse I-270 via an Ohio Department of
Transportation (ODOT) bridge project and stated that the City of Gahanna
applied for LinkUS funding to help close the gap in the $4.35-$5.9 million
project cost range. Estimated costs were broken out by easement
acquisition, design and pre-construction, and construction phases.
The next project highlighted was the Link to Literacy Trail. This trail would
connect Hamilton Road to Creekside by way of Shull Park. Schultz explained
that this project was currently classified as “Actionable” and “Essential,” due
in part to the City’s leveraging of NatureWorks grant funding. He presented
the full cost estimate of $2.1-$2.65 million, with breakdowns for land
acquisition, design, and construction.
President Bowers inquired about the grant funding associated with the Link to
Literacy Trail project. Director Ferrell confirmed the City of Gahanna secured
$500,000 in Clean Ohio Trail funding for the project. When asked whether the
funding carried a timeline for use, Ferrell explained that while the funding was
secured, the agreement was not initiated yet. Once a signed agreement was
in place, the project timeline for construction would be determined.
Senior Director Schultz then transitioned to an overview of the Creekside
Garage and Plaza project. He noted that although the project was currently
categorized under “Facilities,” it could also be considered a Parks project.
Federal Emergency Management Agency (FEMA) mandated that the City of
Gahanna mitigate flooding at the Creekside Garage; the City was working with
Fishbeck to develop mitigation strategies. Schultz emphasized that FEMA’s
requirement pertained only to flood mitigation, not to water seepage or
waterproofing of the plaza itself, though those enhancements were also
explored as a potential opportunity. The project was classified as “Actionable”
due to its current status in the design phase and carried a Priority Level 1
designation because of the FEMA flood mitigation requirement. Schultz noted,
however, that only a portion of the project was truly imperative, while other
components, such as plaza enhancements, could be considered
discretionary. The scope of the project included garage and trail
improvements, plaza reconstruction, streetscape enhancements, and ADA
accessibility upgrades. The portion referred to as “garage and trail
improvements” (shown in gray on the visual provided) would address
FEMA-required mitigation and include ADA switchback ramps and stair
access from the lower trail to the upper plaza. Schultz emphasized that this
portion alone was estimated at $6.25-6.8 million.
Senior Director Schultz further explained that the red and green portions on
City of Gahanna Page 11
Committee of the Whole Meeting Minutes April 14, 2025
the slide represented the lower and upper plaza reconstructions, respectively.
Councilmember Padova asked for clarification on what the green portion
included. Schultz stated that it encompassed complete reconstruction of the
plaza area, replacing street furniture, lighting, pavers, and railings, and
installing new design elements such as decorative coverings and a fireplace
feature. The upper plaza enhancements would also waterproof the garage
ceiling beneath it. Padova confirmed with Schultz that the full $18.9-$22.3
million project estimate reflected a complete reconstruction of the Creekside
Plaza, not general maintenance, and matched the concept renderings that
were shared with the public at the Mill Street Market. She requested that those
renderings be shared with the Council again for reference, noting that some
members may not have seen them.
Senior Director Schultz also discussed anticipated funding sources, which
included capital funds, TIF funds, and private investment. He explained that
private investment was being sought in part to support utility relocation for the
adjacent commercial buildings. In addition, the City recently applied for federal
earmark funding to support the FEMA-required flood mitigation component.
Mayor Jadwin added that this was the first year Ohio’s U.S. senators opened
the opportunity for federal appropriations requests. The City of Gahanna
submitted one application the previous Friday, April 11, 2025, and planned to
submit two more in the upcoming week, including one through
Congresswoman Beatty’s office.
President Bowers asked whether the earmarked federal funds would apply to
the FEMA-required mitigation. Schultz confirmed that they would and that the
$6.25-6.8 million estimate for the garage and trail improvements was the
portion for which earmark funding was requested. In response to a final
question from Bowers, Schultz noted that there was no specific maximum
award cap for this type of member-directed spending.
West Johnstown Road Transportation Improvements
Schultz presented the planned improvements for West Johnstown Road,
including the segment from James Road to Goshen Lane. Although the map
used during the presentation erroneously extended toward the interchange,
the actual project limits ended at Goshen. The project, developed by Director
Komlanc, included land acquisition, design and pre-construction, and
construction phases. Schultz noted that this project would be coordinated
with both the Westside Utility Improvements project and a Columbia Gas
project scheduled for 2026 in the same corridor.
Westside Utility Improvements
Schultz outlined the scope and funding of the Westside Utility Improvements,
emphasizing that the project addressed sanitary, stormwater, and water
infrastructure simultaneously. The slide provided a detailed breakdown of
funding allocations for each utility. Schultz noted that, since this work involved
utility infrastructure, the project would be eligible for funding from specialized
sewer, water, and stormwater capital funds, in addition to Tax Increment
Financing (TIF) dollars. He added that completing all three utilities
City of Gahanna Page 12
Committee of the Whole Meeting Minutes April 14, 2025
concurrently would provide long-term service improvements and avoid
repetitive construction disruption.
Service and Parks Garage Relocation
Schultz discussed the proposed relocation of the service and parks garage.
The current facility, situated on approximately 10 acres just north of
Friendship Park, was inadequate. The City determined that relocating the
facility would require 10 to 12 acres, but identifying suitable land within
Gahanna remained a challenge. For this reason, the project remained in the
“assessment” phase. Schultz explained that land acquisition costs in Central
Ohio were driven up due to regional development pressures, including the
regional Intel project, and estimated the cost of the acquisition at $1.5 to $2.5
million for the needed acreage. Construction and pre-construction estimates
were drawn from a past facility study by Pizzuti and updated using recent
cost data from Elford, the City's partner on the 825 Tech Center Drive project.
Aquatics Master Plan Implementation
Schultz provided an overview of the Aquatics Master Plan, referencing a
conceptual rendering of a potential new aquatic facility at Gahanna Swimming
Pool (GSP). He clarified that the total project cost estimate of $21 to $26
million only applied to reconstruction at GSP and did not include upgrades to
the Hunter’s Ridge pool. Features in the conceptual design reflected
community priorities, such as a relocated competition pool, zero-depth entry,
slides, and a lazy river. The project remained in the "identified" or "midterm"
phase of the Capital Improvement Plan. Schultz stated that the next step
would be conducting a feasibility assessment to determine the viability of
constructing the proposed facility.
Councilmember Jones asked for clarification regarding the categorization of
the Aquatics Master Plan project. She inquired whether, under the newly
introduced CIP terminology, the project should be considered “visionary.”
Senior Director Schultz responded that the project currently resided in the
“identified” category, which is the third level of project readiness in the new
framework.
Stygler, Agler, US 62
Senior Director Schultz then presented the final capital improvement project,
the Stygler Road, Agler Road, and U.S. 62 intersection improvements. He
acknowledged that while the community previously engaged in various
planning efforts for the area, there remained no clear consensus or finalized
direction. Schultz summarized that although several designs were presented
in the past, the project ultimately lacked momentum and needed
reinvigoration. He noted that Burgess & Niple were contracted through the
City’s Comprehensive Transportation and Mobility Plan and were evaluating
options for the intersection as part of their broader analysis. However, Schultz
emphasized that the project lacked a defined scope or strategy at present
and therefore remained in the “identified” category.
City of Gahanna Page 13
Committee of the Whole Meeting Minutes April 14, 2025
Concluding Remarks
Senior Director Schultz concluded by explaining the next steps for the
administration. The City of Gahanna’s leadership team, including the Mayor,
Director of Finance Joann Bury, and department directors, would begin
internal discussions regarding potential funding strategies for the nine major
projects. These discussions would precede and inform future meetings with
the CIP Advisory Committee. Schultz suggested one possible strategy:
implementing a multi-year capital budget approach. This approach would
involve projecting and allocating revenue beyond a single fiscal year, enabling
the City of Gahanna to begin financing longer-term projects by anticipating
revenues from subsequent years. He clarified that this was only one example
and that no decisions were made. He noted that these strategic
conversations would continue during the June 2025 CIP Advisory Committee
meeting, with the intent of advancing practical funding pathways for the larger
capital priorities. He closed by noting that, while not one of the nine core
projects discussed in detail, Academy Park was another large capital initiative
and was already fully funded for 2025.
Councilmember Padova thanked staff for the comprehensive information and
noted that while some projects were familiar to her due to her participation on
the Aquatics Steering Committee and her previous viewing of the Creekside
concept at Mill Street Market, others might not be as familiar to her colleagues
or members of the public. She asked whether the Council would receive
additional presentations or updates on these projects prior to July of 2025.
Senior Director Schultz responded that July would likely be the next
opportunity to revisit these items unless a project needed advanced more
quickly. He explained that, because the highlighted projects are large and will
require long-term funding strategies, additional time is needed for planning.
He also noted that while renderings can be helpful, they can also lead to
confusion about the phase or status of a project. For that reason, staff have
been careful to label renderings as “conceptual” and to refrain from showing
them publicly until the appropriate stage of planning and funding.
Councilmember Schnetzer thanked Senior Director Schultz for the overview
and suggested the administration consider treating the Westside Utility
Improvements project differently from a funding perspective. He noted that
water and sewer-related infrastructure can legally be funded through
revenue-backed bonds, which are secured by water and sewer charges and
may allow for an alternative financing path if cash funding is not feasible.
Councilmember Jones thanked staff for the presentation and asked for
clarification on how the city administration will transition from the nine
highlighted projects to the next set of projects, especially as the new CIP
format moves away from assigning specific “start years.” She asked how
projects like the community center would now be tracked. Schultz explained
that each of the nine current projects addresses a specific and often urgent
need, such as aging infrastructure, FEMA-mandated improvements, or
long-term gaps in park facilities. He noted that the community center project
is a good example of a long-range initiative that remains important but
currently falls into the “visionary” category due to the cost, complexity, and
City of Gahanna Page 14
Committee of the Whole Meeting Minutes April 14, 2025
land requirements involved. He added that being categorized as “visionary”
does not preclude a project from moving forward as funding strategies or
community priorities evolve. Councilmember Jones followed up, confirming
that the community center project, while previously listed with a dollar
amount, was not currently categorized under the new framework. Schultz
confirmed that it will be placed in the “visionary” category in the updated plan.
C. ITEMS FROM THE DEPARTMENT OF ENGINEERING:
Returning for further discussion (Wynne Ridge Bridge):
RES-0015-2025 A RESOLUTION DECLARING THE CITY OF GAHANNA'S INTENT TO
PARTICIPATE FINANCIALLY IN THE WYNNE RIDGE COURT BRIDGE
REPLACEMENT PROJECT (ODOT PROJECT NO. 116417) AND
AUTHORIZING THE MAYOR TO ENTER INTO A PARTICIPATORY
AGREEMENT WITH THE OHIO DEPARTMENT OF TRANSPORTATION
City Attorney Tamilarasan provided an update regarding the Wynne Ridge
Bridge project, which is being completed in conjunction with the Ohio
Department of Transportation (ODOT). She explained that ODOT originally
submitted a sample resolution for the City's consideration, which appeared on
the original agenda for first reading. However, Attorney Tamilarasan
requested that the item return to Committee due to procedural concerns
regarding the form of the legislation and potential conflicts with an ordinance
previously passed in October of 2025. Attorney Tamilarasan noted that the
resolution format was inconsistent with the type of authority being granted and
that additional clarity was needed regarding what the City was authorizing
ODOT to proceed with. She shared that she met earlier that day with
ODOT’s Assistant Chief Counsel to clarify the required documentation. As a
result of that meeting, a revised ordinance was created and uploaded that
afternoon. The new ordinance replaces the resolution and amends the prior
ordinance to reflect updated project estimates and contractual requirements.
Two distinct documents were attached to the ordinance: a new Local Public
Agency (LPA) contract and an amendment to the original LPA agreement.
Both documents serve separate functions in enabling the City of Gahanna to
move forward with the project. Because the ordinance authorizes a
construction project, it would take effect upon signature. However, Attorney
Tamilarasan advised that a waiver of second reading would be necessary in
order to meet ODOT’s April 25, 2025 deadline.
President Bowers thanked the City Attorney for her additional review and
efforts.
Vice President Weaver confirmed that both the resolution and ordinance
would appear on the agenda for the upcoming meeting. Attorney Tamilarasan
clarified that her recommendation was for the resolution to be tabled
indefinitely, followed by a vote on the ordinance waiver, and then a vote on the
ordinance itself. Vice President Weaver confirmed the process with Clerk
VanMeter and thanked both Senior Director Schultz and Attorney Tamilarasan
for their work on the matter.
City of Gahanna Page 15
Committee of the Whole Meeting Minutes April 14, 2025
Recommendation: Postpone Indefinitely on Regular Agenda on 4/21/2025.
ORD-0017-2025 AN ORDINANCE TO AMEND ORDINANCE 0058-2024 AND TO
AUTHORIZE THE MAYOR TO PROVIDE CONSENT AND ENTER
PARTICIPATORY AGREEMENTS AND ANY NECESSARY
AMENDMENTS WITH THE OHIO DEPARTMENT OF
TRANSPORTATION FOR BRIDGE REPLACEMENT ON WYNNE
RIDGE COURT; AND WAIVING SECOND READING
Recommendation: Introduction/First Reading on Regular Agenda with Waiver
and Adoption on 4/21/2025.
Request for Council Action (Fishbeck Engineering Services Proposal):
ORD-0018-2025 AN ORDINANCE AUTHORIZING THE MAYOR TO ENTER INTO AN
AGREEMENT WITH FISHBECK FOR UTILITY ENGINEERING
SERVICES; AND DECLARING AN EMERGENCY
Senior Director of Operations Kevin Schultz reported that on February 26,
2024, the city issued a Request for Qualifications (RFQ) for engineering
services. He explained that the RFQ served as a general solicitation covering
various disciplines within the Engineering Department. Schultz stated that the
city entered into a staff-type contract with Fishbeck for utility engineering
services in 2024. This contract remains in effect until May 2, 2025. The
purpose of the contract was to provide services previously handled by the
city’s former Senior Utility Engineer. He noted that the position remained
vacant since the departure of the previous engineer, despite continuous job
postings and active efforts to recruit a replacement. He emphasized the
critical importance of utility engineering to city operations. Schultz
recommended entering into a new agreement with Fishbeck to continue
providing utility engineering services. He clarified that the RFQ process from
2024 remained valid and competitive, covering a two- to three-year period and
still serving as a basis for contractor selection. He requested an ordinance
authorizing the Mayor to enter into the agreement with Fishbeck. Given the
upcoming expiration of the existing contract, Schultz also requested that the
Council pass the legislation as an emergency measure.
President Bowers asked for clarification on whether the Fishbeck utility
engineering contract was related to the water engineering position the City
previously experienced difficulty filling. Senior Director Schultz explained that
the former Water Resources Engineer position was reclassified as the Senior
Utility Engineer position several years ago, and confirmed it was the same
role. He stated the position was vacant since approximately May of 2024, the
previous year. The previous employee served as a project manager, but
transferred to the Parks and Recreation Department in a lateral move during
that time. President Bowers inquired whether a staffing realignment might
help address the vacancy. Senior Director Schultz stated that hiring
engineers was currently very difficult, and that hiring a utility engineer was
even more challenging. Mayor Jadwin added that it was akin to "a needle in a
haystack." Senior Director Schultz noted the city posted for multiple positions,
City of Gahanna Page 16
Committee of the Whole Meeting Minutes April 14, 2025
including Senior Utility Engineer, Utility Engineer, and Utility Project
Administrator, but applicants were scarce.
President Bowers asked whether any of the responsibilities being proposed
for Fishbeck could be handled internally by a different position. Senior Director
Schultz explained that the tasks involved were highly specialized and required
true utility engineering services, which no current staff member was qualified
to perform. Bowers asked if other communities were experiencing similar
challenges. Schultz confirmed that the position was posted in several
neighboring municipalities, all facing similar difficulties. President Bowers
acknowledged the challenge and expressed concern about the cost of the
Fishbeck contract, noting that it appeared to be significantly more than the
salary of a staff engineer. Schultz agreed, stating the position required a
professional engineer (PE) credential. Bowers asked whether the position
was in the correct classification and pay grade. Schultz responded that the
position was upgraded to Senior Utility Engineer to ensure appropriate
classification, though the current pay may not be competitive enough to
attract qualified applicants. Mayor Jadwin added that paying more for the role
than for the current City Engineer or Senior Transportation and Mobility
Engineer would have broader compensation implications, and that the current
contract approach was an effective way to meet the city's needs in the
interim. Bowers asked whether the contract with Fishbeck could be canceled
if the city hired someone for the position. Schultz confirmed that upon hiring,
the Fishbeck contract would be phased out responsibly, and there was no
commitment to the full expenditure.
Vice President Weaver noted the contract was structured as “not to exceed”
and that billing would occur only for actual work performed. Schultz confirmed
that Fishbeck provided on-site services several days per week, and that the
city received monthly invoices. Vice President Weaver emphasized the
importance of ensuring the city had the staff it needed and welcomed a
broader conversation about remaining competitive with other communities in
order to attract and retain engineering talent.
Councilmember Renner urged further research into the overall shortage of
engineers, calling it a significant problem. Vice President Weaver
acknowledged the challenge and agreed that all municipalities were
competing for the same limited pool of qualified candidates.
Recommendation: Introduction/First Reading on Regular Agenda on 4/21/2025;
Second Reading/Adoption with Emergency on Consent Agenda on 5/5/2025.
D. ITEMS FROM COUNCILMEMBERS:
Councilmember Padova:
1. Joint Resolution for Herb Week
RES-0018-2025 A JOINT PROCLAMATION AND RESOLUTION RECOGNIZING MAY
3-10, 2025 AS HERB WEEK IN THE CITY OF GAHANNA
City of Gahanna Page 17
Committee of the Whole Meeting Minutes April 14, 2025
Councilmember Padova introduced a joint proclamation and resolution
created in collaboration with Mayor Jadwin to recognize Herb Week. She
noted that the Council received the document earlier that day. The
proclamation honored the city’s historical designation as the Herb Capital and
recognized Jane “Bunnie” Geroux’s contributions in achieving that distinction.
Padova announced that the proclamation would be presented to Director
Kappes during the Herb Day celebration on May 3, 2025, at Creekside. The
presentation was scheduled to take place on the backstage area just before
the start of the celebration at 10:00 a.m., and she encouraged
Councilmembers to arrive by 9:30 a.m. to participate. Mayor Jadwin asked if
the version circulated to the Council was the same one she sent to
Councilmember Padova earlier that day. Padova confirmed that it was.
Recommendation: Introduction/Adoption on Consent Agenda on 4/21/2025.
2. Joint Certificates of Recognition: GLHS Paperclip Project and GRIN
Councilmember Padova informed the Council about the Paperclip Project
currently taking place at Gahanna Lincoln High School. She noted that many
Councilmembers had likely heard about the project or received emails from
participating students. The project began in 2014 with the goal of collecting six
million paperclips to create a monument honoring the victims of the
Holocaust. Padova announced that students involved in the project would
attend the next Council meeting. Students would speak about their work.
Padova acknowledged scheduling was still being finalized due to end-of-year
activities, including athletics. She shared that the Council Office prepared a
certificate of recognition to present to the students in honor of their efforts.
Vice President Weaver thanked Padova for the update and confirmed that no
legislative action was required.
Councilmember Padova continued by announcing that Gahanna Residents in
Need (GRIN) would hold a ribbon-cutting ceremony for its new food lockers
on Monday, April 21, 2025, at 5:30 p.m. She noted that the lockers were made
possible in part by the City of Gahanna’s Community Grant funding. The
Council Office would also prepare a certificate of recognition for GRIN, and
she invited any Councilmembers who planned to attend the event to notify
Clerk VanMeter or herself so their signatures could be included. For those
unable to attend the event but who still wished to sign the certificate, Padova
encouraged them to stop by Council Office prior to the event.
E. ITEMS FROM COUNCIL OFFICE:
2025-0085 Ohio Division of Liquor Control Notice to Legislative Authority Permit
TRFO 4233752 FROM JAMES SNYDER DBA ANTOLINOS PIZZA TO
JAMES SNYDER RESTAURANT GROUP LLC DBA ANTOLINOS
PIZZA 1050 BEECHER CROSSING N STE G, GAHANNA, OH
Clerk VanMeter informed the Council that the item under consideration was a
transfer of ownership for Antolino’s Pizza. He reported that he contacted the
Division of Police, which had no objections to the transfer. He stated that,
unless the Council had any objections, he would proceed with notifying the
City of Gahanna Page 18
Committee of the Whole Meeting Minutes April 14, 2025
state that a hearing was not requested. Vice President Weaver asked if there
were any questions or comments from Council. Hearing none, he directed the
Clerk to proceed accordingly.
Note: Clerk returned notice to Division of Liquor Control indicating no hearing
was requested.
F. ADJOURNMENT:
With no further business before the Committee of the Whole, the Chair
adjourned the meeting at 8:57 p.m.
Jeremy A. VanMeter
Clerk of Council
APPROVED by the Committee of the Whole, this
day of 2025.
Trenton I. Weaver
City of Gahanna Page 19
Agenda
200 South Hamilton Road
City of Gahanna Gahanna, Ohio 43230
Meeting Agenda
Committee of the Whole
Trenton I. Weaver, Chair
Merisa K. Bowers
Jamille Jones
Nancy R. McGregor
Kaylee Padova
Stephen A. Renner
Michael Schnetzer
Jeremy A. VanMeter, Clerk of Council
Monday, April 14, 2025 7:00 PM City Hall, Council Chambers
A. CALL TO ORDER:
B. ITEMS FROM THE SENIOR DIRECTOR OF OPERATIONS:
1. Gahanna Civic Center - 825 Tech Center Drive Update
2. Capital Improvement Plan (CIP) Update
C. ITEMS FROM THE DEPARTMENT OF ENGINEERING:
Returning for further discussion (Wynne Ridge Bridge):
RES-0015-2025 A RESOLUTION DECLARING THE CITY OF GAHANNA'S INTENT TO
PARTICIPATE FINANCIALLY IN THE WYNNE RIDGE COURT BRIDGE
REPLACEMENT PROJECT (ODOT PROJECT NO. 116417) AND
AUTHORIZING THE MAYOR TO ENTER INTO A PARTICIPATORY
AGREEMENT WITH THE OHIO DEPARTMENT OF TRANSPORTATION
ORD-0017-2025 AN ORDINANCE TO AMEND ORDINANCE 0058-2024 AND TO
AUTHORIZE THE MAYOR TO PROVIDE CONSENT AND ENTER
PARTICIPATORY AGREEMENTS AND ANY NECESSARY
AMENDMENTS WITH THE OHIO DEPARTMENT OF
TRANSPORTATION FOR BRIDGE REPLACEMENT ON WYNNE RIDGE
COURT; AND WAIVING SECOND READING
Request for Council Action (Fishbeck Engineering Services Proposal):
ORD-0018-2025 AN ORDINANCE AUTHORIZING THE MAYOR TO ENTER INTO AN
AGREEMENT WITH FISHBECK FOR UTILITY ENGINEERING
SERVICES; AND DECLARING AN EMERGENCY
City of Gahanna Page 1 Printed on 4/11/2025
Committee of the Whole Meeting Agenda April 14, 2025
D. ITEMS FROM COUNCILMEMBERS:
Councilmember Padova:
1. Joint Resolution for Herb Week
2. Joint Certificate of Recognition for GLHS Paperclip Project
E. ITEMS FROM COUNCIL OFFICE:
2025-0085 Ohio Division of Liquor Control Notice to Legislative Authority Permit
TRFO 4233752 FROM JAMES SNYDER DBA ANTOLINOS PIZZA TO
JAMES SNYDER RESTAURANT GROUP LLC DBA ANTOLINOS PIZZA
1050 BEECHER CROSSING N STE G, GAHANNA, OH
F. ADJOURNMENT:
City of Gahanna Page 2 Printed on 4/11/2025
Get email alerts for Gahanna
A daily email when new agendas and minutes are posted.