Business Improvement District
Regular MeetingGallup, NM · November 19, 2020
Minutes
Gallup Business Improvement District Meeting
November 19, 2020, 3 PM
Minutes
Call to order – 3:06 PM
Attendance – roll call: Present: A. Biava, A. Baca, J. Rich, L. Bonaguidi, M.
Ustick. Approved absence: S. Gurley. M. Menapace, JM DeYoung
Motion to Approve Agenda: J. Rich, 2nd: L. Bonaguidi. Roll Call: A. Biava-yes,
A. Baca-yes, J. Rich-yes, L. Bonaguidi-yes. Approved
Motion to Approve Minutes from October 15, 2020 meeting: L. Bonaguidi;
2nd: A. Baca. Roll Call: A. Biava-yes, A. Baca-yes, J. Rich-yes, L. Bonaguidi-
yes. Approved
Motion to Approve Monthly Financial Report: J. Rich; 2nd: L. Bonaguidi Roll
call: A. Biava-yes, A. Baca-yes, J. Rich-yes, L. Bonaguidi-yes. Approved.
Note: James Rich asked that a motion be placed on the agenda for the
December regular Board meeting. The motion will ask City Council to
approve a 50% reduction in the amount that the City of Gallup charges
Gallup BID for managing the accounts receivable for the special property
owners district assessment fees.
Discussion:
Alley Improvement project update – Maryann Ustick:
Phase one - Alley between 1st & 2nd; Phase two – the alley between 2nd & 3rd.
Phase one: Running the electric lines underground between 1st & 2nd is
now underway. When that work is completed, City will go out for bids
for the surface work including the pavers, drainage, in-ground trash
receptacles (“herbie” replacements)
Phase two: the alley between 2nd & 3rd. City has the funds to do the
work from 2nd Street to the walkway. The electrical work being
performed for the Coal Avenue Commons Project is tied into the
walkway. This portion of the alley must be kept open and passable
because Coal Avenue between 2nd & 3rd is under reconstruction (torn –
up). Hence the water and sewer pipe work in the alley is on hold until
after the reopening of Coal Avenue. City will go out for bids for the
water and sewer work in early 2021. After the water and sewer work is
complete, City will go out for bids for the final phase of the work in this
alley. At this time, The City has not yet secured funding for this
portion of the work, which includes the in-grounding of the trash
“herbies”, drainage, pavers and placing the electrical lines
underground. City will seek funds for this work from NM Legislature
during the coming session. A complication: there is a large drainage
structure at the alley and 3rd, in addition to water and sewer lines, that
the electrical line must go under. This particular electric phase of the
project may cost as much as $1 million.
Coal Avenue construction update: Maryann Ustick – work is proceeding on
schedule. Note: included in the current phase one part of the Coal Avenue
project are the walkway and the full intersection of Coal & 2nd Street. It was
necessary to obtain a permit NM DOT to perform the work on 2nd Street,
which is a state road. Hence, it will not be necessary to ask City Council for a
change order to address the work in those areas (walkway and 2nd St.
intersection)
Discussion of the rationale for establishing the regional alliance, including the
Agreement between the NWNM regional economic development partners:
Gallup BID, GGEDC, NWNM COG, Cibola Communities Economic
Development, City of Farmington Economic Development and 4 Corners
Economic Development to work together; and the Agreement between the
local partners and National Development Council.
The partners agreed that Gallup BID should be the main coordinator and the
fiscal agent for the MOU and the NDC Agreement. This process is very similar
to process BID followed when it set up the Gallup Main Street organization.
There will be a separate bank account for our local ED alliance.
James Rich expressed reservations about Gallup BID being the fiscal agent
(on the hook financially) of the alliance for the payment of the monthly fee to
NDC. The portion of the MOU that obligates the members of the alliance to
pay their share of the NDC to the BID on a monthly basis was discussed.
There was a discussion of the services, including funding opportunities that
each alliance partner will receive under the NDC agreement, including:
advanced training, the potential to participate in NDC’s “Grow America Fund”
in which NDC will provide $3 for every $1 invested by the local alliance,
potential to participate with NDC’s low to middle income Housing
Development unit and the NDC Tax credit syndication department. The goal
is to become more professional, more efficient and more successful in our
(BID) efforts to rehab buildings to get them back into active use, to attract
new businesses to downtown Gallup and to help existing businesses expand.
The NDC approach to working with the local alliance partners is referred to as
“lean by doing”. They will train us in advanced methods and also work with
us on our individual efforts…to coach us. In that way we will learn to perform
the work at the highest level of accomplishment. Each member of the local
alliance will have equal attention from NDC. Each of the local partner ED
officers will have direct contact with NDC trainer/consultant/loan officer. BID
will not manage any part of the work being done by the local alliance
partners. The member EDOs of the alliance will have a virtual zoom meeting
once a month.
Increasing commerce, consumer spending, tax revenue, etc. is crucial at this
time as our regional economy is suffering from closure of coal mines, coal
fired power plants, marathon refinery. Improving the regional and local
community economies is an imperative. It will increase consumer spending in
the downtown BID District.
BID ED F Bee will resend NDC literature to the Board.
This will be a voting item on the December 17, 2020 BID Board meeting
agenda
Committee to create actionable programs for improving downtown safety and
security. Gallup BID is a member of this committee. Mayor Bonaguidi
described concepts under discussion, including having more Community
Service officers on patrols. James Rich and Anna Biava asked that more
police attention be paid to the problem of prostitution in Gallup.
Other discussion
Reports
Oct 21 – Telephone discussion with Evan Williams, Executive Director
NWNMCOG, to discuss participation levels of entities involved in the NW NM
Regional Economic Development effort.
Oct 23 – Monthly GEDA meeting – presentation by M> Ustick about City of
Gallup initiatives.
Oct 27 – Virtual meeting for progress update and clarification of elements of
the Coal Avenue construction project and review of construction plans by
George Radnovitch (Partner- architect at Sites Southwest), Murphy Builders,
Wilson Engineering, Mayor, City Electric Department, City Planning Director,
City Manager, Asst. City Manager, and Gallup Main Street ED for progress
update and clarification of elements of the project.
Oct 29 – Conference call meeting to discuss proposed improvement project
at 223 West Coal Avenue. Participants: owners Dolph Barnhouse & Damon
Maddox, CB Strain, M. Ustick, K. Smith, R. Bennett (architect)
Oct 29 – Telephone meeting with Sheldon Bartel, NDC, to discuss NWNM
COG CEDS document and its importance in our NWNM effort to work
together as a regional economic development team.
Oct 30 – Telephone meeting with GLD Partners consultant about the Gallup
Mobility project
Nov 6 – Meeting with Mayor Bonaguidi to review NDC consultant’s
recommendations to improve NWNMCOG CEDS document. The CEDS is
required by US EDA and is used by them when making decisions on grant
applications.
Nov 11 – Telephone meeting with Sherman McCorkle about the NM Mobility
initiative
Nov 11 – Meeting at Mayor’s office with Dolph Barnhouse and Damon
Maddox of Barnhouse Holdings, to discuss the proposed renovation at 223
West Coal and the needed infrastructure improvements in the alley behind
that building
Nov 12 – Meeting of City of Gallup Safety & Security initiative committee at
City Hall.
Nov 12 - Telephone meeting with attorneys David Buchholtz and Peter Kelton
at Rodey Law to discuss revisions to the MOU between the Northwest New
Mexico Regional Economic Development partners.
Date of next BID meeting – December 17, 2020, 3PM
Motion to Adjourn: L. Bonaguidi; 2nd: J. Rich. Roll call: A. Biava-yes, A. Baca-
yes, J. Rich-yes, L. Bonaguidi-yes. Approved
Agenda
Gallup BID Board meeting, November 19, 2020, 3 PM
Zoom access –
https://us02web.zoom.us/j/81208915978?pwd=TENpcUQ5dlNJSlRaVzlaMkFJdTM1Zz09
Meeting ID: 812 0891 5978
Passcode: 676961
Agenda
Gallup Business Improvement District Meeting
November 19, 2020, 3 PM
Call to order
Attendance – roll call
Motion to Approve Agenda
Motion to Approve Minutes from October 15, 2020 meeting
Motion to Approve Monthly Financial Report
Discussion:
Alley Improvement project update
Coal Avenue construction update
NDC – NWNM agreement for Economic Development – process and MOU.
This will be a voting item on the December 17, 2020 BID Board meeting
agenda
Committee to create actionable programs for improving downtown safety and
security. Gallup BID is a member of this committee.
Other discussion
Reports
Oct 21 – Telephone discussion with Evan Williams, Executive Director
NWNMCOG, to discuss participation levels of entities involved in the NW NM
Regional Economic Development effort.
Oct 23 – Monthly GEDA meeting
Oct 27 – Virtual meeting for progress update and clarification of elements of
the Coal Avenue construction project and review of construction plans by
George Radnovitch (Partner- architect at Sites Southwest), Murphy Builders,
Wilson Engineering, Mayor, City Electric Department, City Planning Director,
City Manager, Asst. City Manager, MainStreet ED for progress update and
clarification of elements of the project.
Oct 29 – Conference call meeting to discuss proposed improvement project
at 223 West Coal Avenue. Participants: owners Dolph Barnhouse and Damon
Maddox, CB Strain, M. Ustick, K. Smith, R. Bennett (architect)
Oct 29 – Telephone meeting with Sheldon Bartel, NDC, to discuss NWNM
COG CEDS document and its importance in our NWNM effort to work
together as a regional economic development team.
Oct 30 – Telephone meeting with GLD Partners consultant about the Gallup
Mobility project
Nov 6 – Meeting with Mayor Bonaguidi to review NDC consultant’s
recommendations to improve NWNMCOG CEDS document. The CEDS is
required by US EDA and is used by them when making decisions on grant
applications.
Nov 11 – Telephone meeting with Sherman McCorkle about the NM Mobility
initiative
Nov 11 – Meeting at Mayor’s office with Dolph Barnhouse and Damon
Maddox of Barnhouse Holdings, to discuss the proposed renovation at 223
West Coal and the needed infrastructure improvements in the alley behind
that building
Nov 12 – Meeting of City of Gallup safety & security initiative committee at
City Hall.
Nov 12 - Telephone meeting with attorneys David Buchholtz and Peter Kelton
at Rodey Law to discuss revisions to the MOU between the Northwest New
Mexico Regional Economic Development partners.
Date of next BID meeting
Motion to Adjourn