Economic and Community Development Committee
Regular MeetingGardner, MA · July 29, 2026
Agenda
Add to calendar
Agenda
City of Gardner
Economic and Community Development Committee - Meeting of April 29, 2026
I. Call to Order
Chair Elizabeth J. Kazinskas called the meeting to order at 8:30 a.m. on Wednesday, April 29,
2026, in the City Council Chamber. The Clerk called the roll, and a quorum was present. The
Chair announced the Open Meeting Law recording notice and noted that no members of the
public were recording the meeting.
II. Review and Approval of Meeting Minutes
No prior meeting minutes were presented for approval.
III. First Time on the Agenda
Measure No. 11821 – April 2026 Waterford Community Center Update
Mayor Michael Nicholson provided the Committee with an update on the Waterford Community
Center.
Senior Center transition
The Mayor reported that he, Council President George C. Tyros, Executive Aide Ryan Egan,
and Senior Center Director Michael Ellis had begun developing a 90-day transition plan for
moving the Senior Center into the Waterford Community Center. The plan would identify work
required before the move, establish 30-day implementation phases, and include a post-move
evaluation of room usage, furniture placement, and any additional work that may be needed.
The Mayor anticipated completing the draft by the end of May and providing it to the City
Council and the public.
The Committee discussed the importance of consistent communication with the Council on
Aging and Senior Center users. The Chair requested that the Mayor or a representative of his
office attend Council on Aging meetings when Waterford updates were provided so that the
Council, administration, and public received consistent information.
Accessibility ramps and exterior work
The Mayor reported that engineers were reviewing whether the proposed concrete ramp system
qualified as a 30-year capital improvement. The review required analysis of the proposed
concrete, reinforcing materials, warranties, and engineering plans. He anticipated receiving a
determination within approximately three weeks.
The proposed work would include concrete ramping around the building. A separate ramp near
the future Senior Center entrance had already been installed, with handrails to be added after
installation of the new entrance door. The Committee emphasized the need to establish firm
deadlines so the remaining work would not delay occupancy.
Page 1 of 5
City of Gardner
Economic and Community Development Committee - Meeting of April 29, 2026
Parking expansion and playground equipment
The Mayor reported that the Department of Public Works had removed the playground
equipment and rubber mulch from the two-story side of the building. Some equipment was
found to be damaged below ground and could not be reused. The Department was evaluating
which remaining pieces could be relocated to Bickford Playground.
The former playground area was expected to accommodate approximately nine additional
parking spaces. Approximately $90,000 had been set aside for paving the Waterford parking lot,
including that area. Final paving and parking configuration would follow completion of the ramp
work to avoid disturbing newly paved surfaces.
Disability Commission
The Mayor reported that he had toured the building with members of the Gardner Disability
Commission to explore space for a proposed disability awareness and resource center.
Potential locations had been identified, and the Mayor expressed support for including the
Commission as a tenant in the Community Center.
The Committee discussed accessibility improvements already completed, including wider
exterior doors and renovated bathroom partitions. The Architectural Access Board had reviewed
the site and found that the completed work met applicable requirements. The Mayor
nevertheless emphasized that technical compliance did not always ensure practical accessibility
and committed to continuing consultation with the Disability Commission.
Disability Commission representatives described their vision for an accessible community space
honoring longtime Commissioner Eric Knudsen. The center would help reduce isolation among
residents with disabilities, connect them with City and community services, and encourage
broader participation in community life.
Gardner Educational Television
The Mayor reported that Gardner Educational Television would relocate from Gardner High
School to the Waterford Community Center because rooms currently used as its studio were
needed to accommodate the consolidation of Gardner Academy into the high school.
Two rooms behind the gymnasium had been identified as a larger and more suitable studio
location. The Mayor and GETV Director Tim Josti were developing a transition plan, targeted for
completion by the end of May, so the move could occur before the beginning of the school year.
The plan would address equipment relocation, Comcast connections, electrical needs, access,
and other infrastructure.
The Mayor stated that the principal immediate cost would likely involve extending Comcast
wiring into the new studio. Funding was available through the cable department’s capital
Page 2 of 5
City of Gardner
Economic and Community Development Committee - Meeting of April 29, 2026
account, which is supported by Comcast franchise fees. The final transition plan and any
required appropriations would be submitted to the City Council.
Growing Places and Gardner Community Action Committee
The Mayor reported that Growing Places was fully operating at Waterford and considering
additional storage needs as it consolidated operations from its Leominster location.
The Gardner Community Action Committee continued building a kitchen in the former principal’s
office, following the Council’s prior approval. Discussions with both organizations were ongoing
to evaluate their experiences in the building, identify remaining needs, and complete their
transitions. The Mayor hoped to complete these evaluations by the end of May.
Trades Week and building inspections
The Mayor reported that pressure testing of the mini-split heating and cooling units had been
completed and contractors were closing the associated wiring enclosures. Other Trades Week
work had been successfully completed, with the exception of replacing a brick removed to repair
a bathroom fixture.
Electrical work had been completed and inspected. Final plumbing and mini-split inspections
would occur after the remaining work was covered and the systems were tested. A
building-wide inspection would then establish the basis for temporary occupancy, followed by
the required review for a final certificate of occupancy.
The Committee emphasized the importance of deadlines, coordinated transition plans, and
continued efforts to identify additional tenants capable of contributing lease revenue while
complementing the Community Center’s public-service mission. The Chair stated that the
Council on Aging would be invited to future Waterford updates.
A motion was made and seconded to place Item 11821 on file.
Vote: Motion carried unanimously.
IV. In Subcommittee
Item 11454 – Report on the Investigation of the Maki Park Project
Director of Community Development and Planning Jason Stevens updated the Committee on
the Architectural Access Board’s notice of violations concerning Maki Park.
The City submitted its response on April 1, and the Architectural Access Board accepted it on
April 8, establishing an April 28 deadline for completion of the remaining work. The Board
identified concerns involving accessible seating, the accessible route through the park, and
surface conditions.
Page 3 of 5
City of Gardner
Economic and Community Development Committee - Meeting of April 29, 2026
Director Stevens reported that accessible seating had already been included in both the passive
recreation and game-table areas. The bicycle rack was removed because its location interfered
with the accessible route and an alternative location could create similar obstructions. The City
would consider a different rack design in the future.
The City also submitted specifications and compaction-testing information for the stone-dust
surface and confirmed that the Department of Public Works would perform annual maintenance
and recompaction. Director Stevens was awaiting confirmation as to whether the materials
submitted by email were sufficient or whether a formal response letter was required.
Director Stevens stated that all construction work and required corrective measures had been
completed. Confirmation from the Architectural Access Board was the final outstanding step
before the violation order and the Committee’s investigation could be closed.
The Committee discussed the Department’s collaboration with the Disability Commission and
emphasized the importance of involving the Commission early in future public projects. Director
Stevens expected a favorable response from the Architectural Access Board and anticipated
that the item could be removed from the agenda at the next meeting.
By unanimous consent, Measure No. 11454 remained in subcommittee pending formal closure
of the Architectural Access Board matter.
Item 11746 – Upcoming Community Development Projects
Rear Main Street project
Director Stevens reported that the anticipated completion date for the Rear Main Street project
had been extended from May 31 to July 31. The extension was necessary because of
complications involving relocation of electrical services and meters for Main Street businesses.
He commended the businesses, electrical crews, and contractors for coordinating the work and
minimizing disruptions.
The park and parking area were expected to be substantially completed around June 10.
Additional conduit work near 58 Main Street and Priscilla Candy Shop would require
approximately three additional weeks. Because the parking area would remain unpowered and
unlit during that period, the City was considering keeping it closed until lighting and electrical
work were complete.
Director Stevens described the completed project as including:
● Free, unmetered public parking;
● A central green space with pedestrian paths;
● A color-changing water feature;
Page 4 of 5
City of Gardner
Economic and Community Development Committee - Meeting of April 29, 2026
● A lighted shade structure;
● Tables and seating;
● Brick pavers through Sullivan’s Alley;
● A paved service road and concrete dumpster pads;
● Underground utility lines;
● Electric-vehicle charging stations; and
● Improved access to the lower levels of Main Street buildings.
The City Council would need to formally accept the parking area as a public lot before overnight
parking could be authorized. The Committee discussed coordinating the ordinance process with
the project schedule to avoid unnecessary delays in opening the lot.
Greenwood Pool pavilion
Director Stevens reported that fencing and seating repairs were underway at Greenwood
Memorial Outdoor Pool. The City expected to receive the 75-percent design documents for the
new pavilion within approximately one month, with bidding anticipated around June.
Planning initiatives
Director Stevens announced that the public-comment period for the City’s master plan had been
extended. The plan and comment form were available through the Community Development
Department’s webpage.
An open house concerning the municipal surplus property plan was scheduled for May 6, 2026,
from 4:00 to 6:00 p.m. at the Levi Heywood Memorial Library. The master plan, municipal
surplus property plan, hazard mitigation plan, and housing production plan were all expected to
be completed by June 30.
By unanimous consent, Item 11746 remained in subcommittee as a recurring update item.
V. Adjournment
Councillor Karen G. Hardern moved to adjourn. The motion was seconded.
Vote: Motion carried unanimously.
There being no further business before the Committee, the meeting adjourned.
Page 5 of 5
City of Gardner
Economic and Community Development Committee - Meeting of May 13, 2026
I. Call to Order
Chair Elizabeth J. Kazinskas called the meeting to order at 8:30 a.m. on Wednesday, May 13,
2026, in the City Council Chamber. The Clerk called the roll, and a quorum was present. The
Chair announced the Open Meeting Law recording notice and noted that no members of the
public were recording the meeting.
II. Review and Approval of Meeting Minutes
No prior meeting minutes were presented for approval. The Chair anticipated that minutes
would be available at the Committee’s next meeting.
III. FY2027 Budget Review
Community Development and Planning Department
Director of Community Development and Planning Jason Stevens presented the Department’s
proposed FY2027 budget. He reported that most operating expense lines—including repairs
and maintenance, telecommunications, professional development, travel, professional services,
and office expenses—were level-funded from FY2026. The Department’s proposed budget
represented an overall decrease of approximately $7,600 while maintaining existing services.
The Committee discussed the Department’s supporting budget narrative and noted the
significance of submitting a reduced budget during a difficult municipal budget year. Members
credited the Department’s recent restructuring with improving efficiency and reducing costs.
Termination leave
The Committee reviewed a prior-year expenditure of approximately $46,973 for termination
leave. Mayor Michael Nicholson explained that termination leave represents payment of
accrued vacation, personal, and sick-incentive time owed to employees upon separation from
City service.
Rather than budgeting anticipated termination expenses within each department, the City
maintains a consolidated account in the Mayor’s unclassified budget. When an employee
leaves, the appropriate amount is calculated by Human Resources and the City Auditor and
transferred into the former employee’s departmental termination-leave account for tracking
purposes.
The Committee noted that the expenditure reflected four departures from the Department during
the applicable fiscal year and expressed hope that the line would remain at zero as the
restructured Department achieved greater staff stability.
Department restructuring
Page 1 of 5
City of Gardner
Economic and Community Development Committee - Meeting of May 13, 2026
Director Stevens explained that the Department’s budget reduction was largely attributable to
restructuring and creation of the Economic Development Finance Manager position. The revised
position allowed the City to charge a larger percentage of the employee’s work to federal
Community Development Block Grant administrative funds because the position directly
administered those programs.
The restructuring produced approximately $7,600 in direct budget savings and an estimated
additional $30,000 in benefit savings. Committee members praised the restructuring as an
effective and creative use of available resources.
Department accomplishments
Director Stevens reviewed several Department accomplishments from the prior year.
Maki Park: The Department completed the corrective accessibility work required by the
Massachusetts Architectural Access Board, including improvements to the ramp and accessible
route, removal of obstructing bicycle racks, installation of accessible tables, and proper
compaction of the stone-dust surface. During the meeting, the Department received notice that
the Architectural Access Board had formally closed the matter.
Rear Main Street: Director Stevens discussed progress on the Rear Main Street project,
including management of unexpected subsurface conditions, revisions among grant line items,
utility work, and coordination with Main Street businesses. Completion was anticipated around
July 10. The project would provide free public parking, green space, a water feature, improved
access to downtown businesses, and a paved service road for deliveries, waste collection, and
winter maintenance.
The Committee discussed the possibility of holding the July 12 Food Truck Festival and a
ribbon-cutting ceremony at the site if construction had progressed sufficiently. The Mayor
explained that the event remained scheduled for City Hall as a contingency and would only be
moved if the site was ready. Because approximately three additional weeks of electrical work
would remain after substantial completion, the Committee emphasized the importance of clearly
communicating that the site would close again following any one-day event.
North Central Pathway: Director Stevens reported that the initial pathway phase and paving
along Crystal Lake Drive had been completed and that the 25-percent design for the remaining
pathway was substantially finished. National Grid was responsible for replacing and stabilizing a
culvert near Pearly Brook and was also performing clearing and access improvements
associated with its utility right-of-way. Director Stevens confirmed that the culvert replacement
would not be a City expense.
Greenwood Memorial Pool: Demolition of the former pool and bathhouse was substantially
complete, with final grading underway. The City avoided certain landscaping expenses because
construction of the new pavilion would follow. The work would not delay the regular opening of
Page 2 of 5
City of Gardner
Economic and Community Development Committee - Meeting of May 13, 2026
the outdoor pool, and the temporary construction fence would be replaced with permanent
fencing before the season.
Community Development Block Grant social-service programs
Director Stevens reported that three of four FY2024 CDBG social-service projects had been
completed and that the remaining recipient was submitting its final invoice.
The funded programs resulted in:
● Athletic fee scholarships for 121 low- and moderate-income middle and high school
students;
● Food, heating, or emergency assistance for 1,131 Gardner residents;
● Short-term rental assistance for 24 individuals experiencing or at risk of homelessness;
and
● Domestic-violence prevention, training, or survivor assistance benefiting 55 individuals.
The Committee praised the impact of the programs and the Department’s work to standardize
applications, invoicing, eligibility documentation, and reporting requirements for social-service
providers.
Boards, commissions, and permitting
Director Stevens briefly reviewed activity by the Conservation Commission and Planning Board,
including orders of conditions, determinations of applicability, emergency certifications involving
beaver dams, certificates of compliance, and site-plan reviews. He noted that the Planning
Board had recently approved the Walmart fueling facility.
Grant funding
Director Stevens reviewed major grant awards obtained or administered during the year:
● $850,000 FY2025 CDBG Mini-Entitlement Grant for Phase V downtown improvements,
Waterford Community Center electrical and fire-protection improvements, and local
social-service organizations;
● $32,000 Land Use Planning Grant to expand the master-plan process and prepare a
housing production plan;
● $1.48 million MassWorks Grant for utility, roadway, pedestrian, accessibility, and
streetscape improvements along East Broadway in South Gardner;
● $50,000 Real Estate Technical Assistance Grant to inventory and develop a strategy
for vacant or underused municipal property; and
● $50,000 Vacant Storefront Grant to provide tax credits supporting local storefront
revitalization.
Page 3 of 5
City of Gardner
Economic and Community Development Committee - Meeting of May 13, 2026
The municipal-property inventory identified seven parcels for further consideration and potential
public bidding. Director Stevens reported interest from developers who attended a recent open
house. Committee members noted that returning appropriate City-owned parcels to productive
use could expand the tax base and generate long-term economic benefits.
Director Stevens reported that the Department, Mayor’s Office, and Keller Partners worked
jointly on grant applications. The grants discussed totaled approximately $2.4 million—more
than ten times the Department’s annual municipal budget.
A motion was made and seconded to recommend approval of the Community Development and
Planning Department’s FY2027 budget to the full City Council without amendment.
Vote: Motion carried unanimously.
IV. In Subcommittee
Item No. 11454 – Report on the Investigation of the Maki Park Project
During the meeting, the City received formal notice from the Massachusetts Architectural
Access Board that the complaint involving Maki Park had been resolved.
The Board determined that materials submitted by the City provided sufficient evidence that:
● The accessible route maintained a minimum clear width of 36 inches following removal
of the bicycle racks;
● Accessible tables had been provided; and
● The stone-dust surface had been compacted according to applicable specifications.
The Board concluded that the cited conditions had been brought into compliance with 521 CMR.
Director Stevens confirmed that the project was complete and the accessibility matter formally
closed.
The Committee agreed that the Board’s resolution and the complete project record should be
placed before the full City Council to provide a final public accounting of the matter.
A motion was made and seconded to forward the completed Maki Park report and Architectural
Access Board resolution to the full City Council.
Vote: Motion carried unanimously.
Item No. 11746 – Upcoming Community Development Projects
RAISE Grant
Page 4 of 5
City of Gardner
Economic and Community Development Committee - Meeting of May 13, 2026
Director Stevens reported that the Federal Highway Administration had determined that the
City’s existing on-call engineering contracts did not satisfy the federal procurement requirements
applicable to the RAISE Grant.
The Department prepared new requests for qualifications to conduct a separate competitive
engineering procurement process. The revised documents had been submitted to the Federal
Highway Administration and the Massachusetts Department of Transportation for compliance
review before public advertisement.
The Committee thanked Director Stevens for responding promptly and beginning the revised
procurement process. Item No. 11746 remained in subcommittee as a continuing update item.
V. Committee Comments
Committee members commended Director Stevens and Department staff for their
responsiveness, grant work, management of difficult projects, and ability to reduce the municipal
budget while maintaining services.
Members emphasized that successful economic development required both encouraging
appropriate investment and ensuring that proposed projects were consistent with the City’s
planning goals and community needs. The Committee encouraged the Department to continue
addressing problems promptly, maintaining relationships with stakeholders, and leveraging
outside funding to advance City projects.
VI. Adjournment
A motion was made and seconded to adjourn.
Vote: Motion carried unanimously.
There being no further business before the Committee, the meeting adjourned.
Page 5 of 5
City of Gardner
Economic and Community Development Committee - Meeting of May 27, 2026
I. Call to Order
Chair Elizabeth J. Kazinskas called the meeting to order at 8:30 a.m. on Wednesday, May 27,
2026, in the City Council Chamber. The Clerk called the roll, and a quorum was present. The
Chair announced the Open Meeting Law recording notice and noted that no members of the
public were recording the meeting.
II. Review and Approval of Meeting Minutes
The Committee considered the minutes of the March 25, 2026 meeting.
Councillor Heath moved to waive the reading of the minutes and approve them as presented.
The motion was seconded.
Vote: Motion carried unanimously.
III. Monthly Waterford Community Center Update
Mayor Michael Nicholson presented the monthly update on activities and ongoing work at the
Waterford Community Center.
Roof Replacement and Solar Project
The Mayor reported that temporary repairs had addressed existing roof leaks while plans moved
forward for a complete roof replacement in conjunction with installation of a behind-the-meter
solar energy system. Through an agreement with the solar developer, the City would receive a
new roof in lieu of a portion of lease payments while also significantly reducing future electricity
costs for the facility. The project was awaiting final National Grid approvals, with construction
anticipated to begin within approximately twelve months. Committee members discussed the
long-term savings associated with the project and expressed support for the investment in
renewable energy.
Bathroom Renovations and HVAC Improvements
The Mayor reported that installation of ADA-compliant restroom partitions had been completed.
HVAC installation was substantially complete, although one unit required a minor repair to
address a fluid leak. Final plumbing, electrical, building, and health inspections remained
pending before the project could be formally closed. The Committee requested that this update
remain a recurring agenda item until all inspections had been completed.
Page 1 of 4
City of Gardner
Economic and Community Development Committee - Meeting of May 27, 2026
Gardner Farmers Market
The Mayor reported that the Gardner Farmers Market had returned to the front lawn of the
Community Center and was being held on the third Saturday of each month. This year's market
featured monthly themes intended to encourage broader vendor participation beyond traditional
produce sales. Committee members discussed the growth of the market, available vendor
space, and coordination with Growing Places to provide temporary storage for market signage
within the building. The Mayor noted that, to his knowledge, the Thursday farmers market
previously held at Park Street Park would not return this year.
Senior Center 90-Day Transition Plan
The Mayor reported that the draft 90-day transition plan for relocating the Senior Center
continued to be refined to provide a clearer implementation schedule. Once finalized, the plan
would be distributed to the City Council and Council on Aging. The Mayor and Council President
had also requested an opportunity to present the plan directly to the Council on Aging.
The Committee emphasized the importance of maintaining a single, consistent source of
information regarding the project and encouraged Council on Aging members to attend future
monthly updates. Discussion also addressed communication surrounding a recently announced
$50,000 state budget earmark for senior center capital improvements. The Mayor stated that
neither he nor his office had requested the earmark and indicated that he intended to meet with
the Senior Center Director to determine its origin and intended purpose before providing
additional information to the City Council. The Committee requested that future information
concerning the earmark be shared with the Council President and Council as it became
available.
Concrete Accessibility Ramps
The Mayor reported that design work and bid preparation were underway for construction of
new concrete ramps and accessible walkways serving the Community Center. The project
would reconstruct the primary entrance walkways, provide accessible connections to the
single-story wing, and improve accessibility at multiple entrances. Because the estimated cost
exceeded $50,000, the project would be publicly bid.
The Committee discussed the importance of coordinating the work with planned parking lot
improvements to avoid unnecessary excavation after paving and confirmed that the Disability
Commission had reviewed the proposed plans.
Parking Lot Expansion
The Mayor reported that removal of the former playground equipment and rubber mulch had
been completed in preparation for expanding the parking lot. During demolition it was
determined that the playground equipment was no longer structurally suitable for relocation to
Page 2 of 4
City of Gardner
Economic and Community Development Committee - Meeting of May 27, 2026
Bickford Playground because of deterioration below grade. Salvageable components would be
reused where practical, while the remainder would be declared surplus and disposed of.
The Committee discussed the anticipated parking lot design, available funding, and whether the
final number of new parking spaces might require Planning Board review.
Disability Commission
The Mayor reported that discussions continued regarding providing permanent space for the
Gardner Disability Commission within the Community Center. No significant changes had
occurred since the previous monthly update, but conversations with the Commission remained
ongoing.
Gardner Educational Television
The Mayor reported that planning continued for Gardner Educational Television's relocation from
Gardner High School to the Community Center. Work was underway to prepare studio and
office space, coordinate Comcast infrastructure, and complete the move before July 1 to
accommodate classroom renovations at the high school. The Committee discussed building
access, public entry, and operational impacts during the transition. The Mayor anticipated only a
brief interruption to live programming while equipment was relocated.
Growing Places and Gardner Community Action Committee
The Mayor reported that discussions continued with Growing Places and the Gardner
Community Action Committee regarding their leased space within the building. Growing Places
continued evaluating its space needs following consolidation of operations from Leominster. The
Gardner Community Action Committee was awaiting completion of its kitchen construction
before fully occupying its space. Any future lease amendments resulting from those discussions
would be submitted to the City Council.
Historical Commission
The Mayor reported that roof leak repairs affecting space occupied by the Historical
Commission would be addressed through the roof repair project. A representative of the
Historical Commission thanked the Mayor and City Council for their continued responsiveness
to maintenance concerns.
Wilder Field Programming
The Mayor announced that a local Pentecostal church planned to begin a youth soccer league
at Wilder Field after requesting assistance from the City in identifying an appropriate location.
The organization completed the Department of Public Works field reservation process and
would begin using the field on scheduled dates. Committee members noted the value of
Page 3 of 4
City of Gardner
Economic and Community Development Committee - Meeting of May 27, 2026
encouraging additional public use of City recreational facilities and reviewed the process for
reserving municipal parks and fields.
IV. In Subcommittee
Item 11746 – Upcoming Community Development Projects
In the absence of Director of Community Development and Planning Jason Stevens, Mayor
Nicholson provided a brief update on several ongoing projects.
The Mayor reported that the Community Development Department continued work on multiple
grant applications and anticipated announcements regarding several economic development
grants in the near future. Preparatory work continued on the Rear Main Street project and the
South Gardner Infrastructure Improvement Project. Utility relocation work by Unitil had been
completed, allowing preliminary site work on the South Gardner project to proceed. The
Committee commended the Department for its continued progress on grant-funded projects and
infrastructure improvements.
The Committee agreed to retain Item 11746 in subcommittee for future updates.
V. Adjournment
A motion was made and seconded to adjourn.
Vote: Motion carried unanimously.
There being no further business before the Committee, the meeting adjourned.
Page 4 of 4
City of Gardner
Economic and Community Development Committee - Meeting of June 24, 2026
I. Call to Order
Chair Elizabeth J. Kazinskas called the meeting to order at 8:30 a.m. on Wednesday, June 24,
2026, in the City Council Chamber. A quorum was present. The Chair announced the Open
Meeting Law recording notice and noted that no members of the public were recording the
meeting. The Committee further announced that agenda items would be taken out of order,
beginning with the ongoing Community Development projects update.
II. Review and Approval of Meeting Minutes
The Chair reported that no meeting minutes were available for approval and stated they would
be presented at a future meeting.
III. In Subcommittee
Item 11746 – Upcoming Community Development Projects
Director of Community Development and Planning Jason Stevens provided an update on active
Community Development projects.
Director Stevens reported that surveying for the South Gardner Village Center Utility
Improvements had been completed and transmitted to National Grid for review of the proposed
underground utility relocation. He stated that the City and its engineering consultant were
working closely with National Grid to expedite the review process in order to maintain the project
schedule.
Regarding the Rear Main South project, Director Stevens reported that discussions continued
with the property owner of the remaining parcel necessary to begin construction. The City was
evaluating several acquisition options, including a lease-to-purchase agreement and acquisition
through the Gardner Redevelopment Authority.
Director Stevens reported that engineering design continued for Downtown Phase V, including
coordination among Police, Fire, DPW, and engineering staff regarding crosswalks, curb
improvements, and related infrastructure. Bid documents were being prepared for construction.
Director Stevens announced that Assistant Director Amy Yuhasz would be leaving the
Department to accept a position with another municipality. He thanked Ms. Wheeler for her
leadership administering the Community Development Block Grant (CDBG) program, including
oversight of social-service grants and financial administration. During the transition, Director
Stevens would assume responsibility for CDBG administration until a replacement was hired.
Committee members expressed their appreciation for Ms. Yuhasz's service and wished her
success in her new position.
Page 1 of 6
City of Gardner
Economic and Community Development Committee - Meeting of June 24, 2026
Director Stevens reported that the proposed Waterford Community Center fire protection
upgrade, originally planned as a CDBG-funded project, required additional review by the
Executive Office of Housing and Livable Communities to determine whether the building met the
federal low- and moderate-income benefit requirements. The Department was evaluating
alternative CDBG projects while completing the required analysis and indicated the fire system
project could be reconsidered under a future funding cycle if eligibility requirements were
satisfied.
Director Stevens reported that the contract for the Greenwood Memorial Pool Pavilion had
been awarded and construction would begin shortly with anticipated completion in the fall. He
confirmed that the work would not delay the opening of the pool for the summer season.
Committee members commended the Department for maintaining the construction schedule
while preserving the historic character of the pool complex. The Mayor added that demolition
work was substantially complete and remaining repairs to fencing, drainage infrastructure, and
site improvements were nearing completion.
Director Stevens provided updates on several additional projects, including:
● Rear Main North construction remained on schedule, with the primary public
improvements expected to be substantially complete by mid-to-late July and the overall
project concluding by the end of August.
● The City's Master Plan and Housing Production Plan had both been completed and
adopted.
● The Hazard Mitigation Plan remained under state and federal review, with an extension
granted through October 1, 2026.
● Procurement for the Downtown Mobility Plan funded through the federal RAISE Grant
was proceeding under revised federal procurement requirements.
● The Municipal Surplus Property Plan had been completed and adopted.
● The City had been awarded grants for North Central Pathway Phase II and the Keys
of Culvert Replacement Project, allowing both projects to move into design and
bidding.
Director Stevens also announced that Planner Justin Enright would be leaving the Department
to pursue graduate studies. He credited Mr. Enright with leading preparation of several
successful grant applications, particularly the fully funded culvert replacement project.
Committee members thanked Mr. Enright for his service to the City and wished him continued
success in his academic and professional endeavors.
The Committee agreed to retain Item 11746 in subcommittee as an ongoing update item for
future meetings.
Page 2 of 6
City of Gardner
Economic and Community Development Committee - Meeting of June 24, 2026
IV. Monthly Waterford Community Center Update
Mayor Michael Nicholson presented the monthly update on activities and ongoing improvements
at the Waterford Community Center.
Roof Replacement and Solar Project
The Mayor reported that engineering review of the proposed roof replacement and solar
installation remained underway. Updated financial projections were being prepared to evaluate
long-term energy savings, pilot payments, lease revenue, and overall project economics before
the proposal is presented to the City Council.
Gardner Farmers Market
The Mayor reported that the Gardner Farmers Market had successfully held its June event at
the Community Center and would continue operating on the third Saturday of each month
through October, with the November market returning to City Hall. Committee members praised
the continued success of the market, noting strong attendance, community pride, and the
suitability of the Community Center grounds as its permanent location.
Senior Center Transition
The Mayor reported that, following a recommendation from the Committee, he had attended the
most recent Council on Aging meeting to provide a direct update regarding the future relocation
of the Senior Center. He advised that he intended to attend future Council on Aging meetings
personally in order to provide consistent updates and eliminate the possibility of conflicting or
secondhand information. The Committee expressed appreciation for the improved
communication and noted that the Council President would also participate in future updates as
appropriate.
Concrete Accessibility Ramp Project
The Mayor reported that the engineering scope for construction of new ADA-accessible ramps
had been received from the City's engineering consultant. With engineering services now
authorized, the project could proceed toward bidding and construction. The estimated
engineering oversight cost was approximately $35,000.
Disability Commission
The Mayor reported that discussions continued regarding establishment of a Disability Resource
Center within one of the classrooms in the Community Center's single-story wing. Committee
members noted positive feedback from members of the Disability Commission regarding the
opportunity to utilize the facility and encouraged continued collaboration.
Gardner Educational Television (GETV)
Page 3 of 6
City of Gardner
Economic and Community Development Committee - Meeting of June 24, 2026
The Mayor reported that Gardner Educational Television had begun relocating its equipment
into the Community Center. Most equipment had already been moved, with the remaining
transmission equipment scheduled to remain at Gardner High School until the final stages of the
transition. Comcast continued coordinating installation of the new broadcast connection.
The Mayor explained that live meetings, YouTube streaming, and Video-on-Demand services
would continue uninterrupted during the transition. Only traditional cable broadcasts on Channel
8 could experience a temporary delay until Comcast completed the final connection. The
Committee requested that the public be notified once a final transition schedule had been
established.
Growing Places and Gardner Community Action Committee
The Mayor reported that lease modifications for Growing Places had been submitted to the City
Council for approval. Proposed improvements included installation of a backup generator to
protect refrigerated food storage and placement of rooftop condensers supporting refrigeration
equipment. The Gardner Community Action Committee continued construction of its commercial
kitchen, while Growing Places remained fully operational within the facility.
Building Renovations, Accessibility Improvements, and HVAC Work
The Mayor reported that the Massachusetts Architectural Access Board had reviewed a
complaint alleging that the Community Center did not comply with state accessibility
requirements. Following an inspection, the Board concluded that the City should complete a
comprehensive self-evaluation documenting improvements already completed and identifying
any remaining accessibility work. The Mayor noted that many of the improvements requested by
the Board—including accessible restrooms, wider entrances, and planned accessibility
ramps—had already been completed or were underway.
The Mayor further reported that, during installation of new HVAC equipment, a contractor
inadvertently drilled through older asbestos-containing floor tiles concealed beneath newer
flooring in a limited portion of the building. The issue was identified during a routine inspection,
after which the City immediately contacted the Department of Environmental Protection to
conduct a comprehensive inspection.
The Department determined that the issue was confined to a small portion of the building's
two-story wing. The City was preparing a DEP-approved remediation plan and evaluating
long-term asbestos management options. The Mayor emphasized that asbestos was already
known to exist within portions of the former school building because of its age and that
encapsulated asbestos had been previously documented through required school inspections.
Committee members requested regular progress reports and emphasized the importance of
maintaining public confidence by clearly communicating that the affected area remained isolated
and did not impact occupied portions of the building.
Page 4 of 6
City of Gardner
Economic and Community Development Committee - Meeting of June 24, 2026
The Mayor estimated that remediation activities would largely be completed by the end of the
summer, subject to DEP approval of the required work plan. He further advised that the draft
90-day Senior Center transition plan was nearing completion but would not be finalized until
asbestos remediation within the future Senior Center space had been completed.
V. First Time on the Agenda
Item 11868 – Housing Production Plan Information and Discussion
Director Stevens presented the recently adopted Housing Production Plan for informational
purposes, noting that both the Planning Board and City Council had already approved the
document. He explained that the presentation was intended to familiarize Committee members
with the plan's goals, implementation strategies, and relationship to other planning initiatives
undertaken by the City.
The Director summarized the Housing Needs Assessment, noting that Gardner has a relatively
large renter population, an aging housing stock, lower median household income than
Worcester County as a whole, and a significant percentage of households considered housing
cost-burdened. Although Gardner currently exceeds the Chapter 40B affordability threshold, the
City must continue planning for future affordable housing as existing affordability restrictions
expire over time.
Director Stevens reviewed the plan's implementation strategies, explaining that many
recommendations were already being advanced through recently adopted zoning reforms and
other municipal planning initiatives. He highlighted efforts to encourage a wider variety of
housing types, promote redevelopment of existing properties, expand rehabilitation of existing
housing through Community Development Block Grant funding, and strengthen partnerships
with organizations such as Habitat for Humanity of North Central Massachusetts to expand
affordable homeownership opportunities.
Director Stevens explained that the Housing Production Plan is intended to serve as a long-term
policy guide for addressing Gardner's housing needs while maintaining compliance with Chapter
40B requirements. He reviewed the City's existing inventory of affordable housing, demographic
trends, housing affordability data, and projected reductions in subsidized housing inventory as
affordability restrictions expire over time. The presentation emphasized the importance of
maintaining the City's Safe Harbor status while expanding housing opportunities for seniors,
veterans, individuals with disabilities, families, and other populations experiencing housing
insecurity.
Director Stevens further explained that many of the implementation strategies identified in the
plan complement initiatives the City has already begun, including recent zoning reforms,
redevelopment of existing properties, expanded housing rehabilitation efforts, and partnerships
Page 5 of 6
City of Gardner
Economic and Community Development Committee - Meeting of June 24, 2026
with regional housing organizations. He noted that restoring Community Development Block
Grant housing rehabilitation funding and strengthening partnerships with organizations such as
Habitat for Humanity of North Central Massachusetts would provide additional opportunities to
preserve and expand affordable homeownership.
Committee members discussed how the Housing Production Plan integrates with other recently
completed planning documents, including the Master Plan, Municipal Surplus Property Plan,
and zoning amendments. Director Stevens noted that these documents were intentionally
developed to complement one another and provide a coordinated framework for future
economic and residential development throughout the City.
The Committee received the presentation and placed the item on file.
Item 11869 – Municipal Surplus Property Plan Information and Discussion
Director Stevens next presented the Municipal Surplus Property Plan, explaining that the
document had previously been adopted by both the Planning Board and the City Council and
was being presented to the Committee for informational purposes. He reviewed the purpose of
the plan, which establishes a systematic process for identifying municipally owned properties
that may no longer serve governmental purposes and evaluating opportunities for
redevelopment, housing, economic development, conservation, or other public uses.
Director Stevens emphasized that the plan does not authorize the sale or disposition of any
specific parcel. Rather, it provides a decision-making framework to evaluate surplus properties
in a consistent and transparent manner while considering community needs, zoning,
infrastructure, environmental constraints, and long-term municipal objectives. The plan also
encourages coordination among City departments before any recommendation is made
regarding future disposition of municipal property.
Committee members discussed the value of maintaining an organized inventory of municipal
assets and agreed that the planning process would improve future redevelopment opportunities
by allowing the City to proactively evaluate parcels rather than responding on a case-by-case
basis.
The Committee received the informational presentation. No motions were offered, and no action
was taken.
VI. Adjournment
There being no further business before the Committee, the meeting adjourned.
Page 6 of 6
City of Gardner - Executive Department
Mayor Michael J. Nicholson
July 23, 2026
Hon. Elizabeth J. Kazinskas, Chair
And Economic and Community Development Committee Members
Gardner City Hall, Rm 121
95 Pleasant Street
Gardner, MA 01440
RE: June Waterford Community Center Update
Dear Madam Chair and Committee Members,
I hereby submit the July Update on the progress being made for the Waterford Community
Center.
Roof Repair and Solar Installation:
The Administration is holding a meeting with Solect Energy on a update for this project on
Tuesday, July 28, 2026.
Representatives from Solect Energy visited the Waterford Site to work on the design of their
behind the meter system that they are looking to install on the roof of the building. They are also
making an updated generation and savings report, similar to what was submitted to the City
Council when the roof was declared surplus for the purpose of installing a solar array so that we
can get a more accurate projection since it has been two (2) years since the first report was
generated.
Building Renovations, Senior Center, Concrete Ramps, Construction:
As a result of the recent inspection that found disturbed asbestos in the two-story wing of the
building, the City has been in conversations with the Massachusetts Department of
Environmental Protection (DEP) to decide the best path forward.
Interim Commissioner Jean has been working to find a contractor to perform the non-traditional
work plan (NTWP) to clean and remediate the asbestos that was disturbed, clean the location,
and get the area ready for its next phase of construction.
The area in which disturbed asbestos was found was in the two-story wing of the building, not in
other locations. As such, work being done in the other locations of the building is able to
continue.
To alleviate any future concerns of asbestos disturbance in the two-story wing, I have submitted
a proposal to the City Council to redeploy funds that have already been assigned to projects at
the Community Center to perform a full abatement and removal of all asbestos containing
materials (flooring and ceiling tiles) in the two-story wing, replace the floors and ceilings on the
first floor, and temporarily leaving the second story unfinished, since it is unable to be used due
to it not having an elevator.
This will alleviate any and all asbestos concerns for the future Senior Center location moving
forward. However, it will delay the Senior Center moving into the space until this work is
completed. But even with the delay, I believe it is in the best interest of the City to get this done
the right way now and not have to worry about it later.
Additionally, Chief Lagoy spoke with the State Fire Marshall about the need for sprinklers at the
facility. The Fire Marshall informed Chief Lagoy that based on the current usage of the site,
sprinklers are not yet required under the fire code. While they may be required in the future, we
have not hit that threshold yet.
With that said, I also believe it to be in the best interest of the City to plan to install sprinklers in
the building within the next five (5) to ten (10) years. As such, my proposal that was submitted to
the City Council also includes funding to run a water line from the street into the building so that
when the sprinkler system is being ready to be installed, the line is already in the building.
The funding for this project will also delay work on the concrete ramps into the building,
however, the plans for the resurfacing of the parking lot are still moving forward.
Our next update meeting with DEP is scheduled for Tuesday, July 28th, 2026.
Gardner Farmers Market:
The Gardner Farmers Market continues to have their Farmers Market planned for the third (3rd)
Saturday of every month on the front lawn of the Community Center.
The next Farmers Market is taking place on Saturday, August 15th with a theme of “Preserving
the Harvest.”
We have coordinated with the Department of Public Works to make sure the lawn is mowed in
conjunction with all markets that are planned for the site.
Disability Commission:
There are no updates on this topic since the below update was submitted last month.
We are still in conversations with the Disability Commission on getting them a space to increase
their outreach opportunities in the Community Center. These details are still very preliminary but
are moving forward in conversations.
Gardner Educational Television (GETV):
GETV has moved into their new space at the Community Center.
Director Josti and Director O’Keefe successfully reset the station to be able to use the same IP
addresses and have all computer access that is needed to operate the station.
Xfinity Comcast is still in the process of making their final connections to the station to allow it
to go back on the air. Until that final connection is made, the regular Channel 8 stream will be
down. However, we anticipate that this final connection will be made by Comcast sometime by
the end of next week (Friday, July 31).
Mount Wachusett Community College also donated three workstation desks for the new TV
Station that have been set up and are being used by the GETV Staff members. A donation request
vote will be submitted to the City Council shortly.
Growing Places and Gardner Community Action Committee (CAC)
Interim Commissioner Jean has set up meetings with both Growing Places and the CAC to go
over a comprehensive look of the work that needs to be done in their spaces.
For the Gardner CAC this involves the work needed to be done with their kitchen construction
and final approvals needed for them to open in the space.
For Growing Places, this involves the work needed to be done with the recent building
improvements approved by the City Council with the generator and condenser.
Hive Athletics:
Hive Athletics is a new soccer and volleyball league that was started by the Palabra Miel
Evangelical Church that opened at the former St. Joseph’s Church on Pleasant Street. They
practice at Wilder Field on Wednesdays and have games on Saturdays.
They are open to members of the community to play in the league as well.
They have the space reserved through the City’s regular park use reservation form and are paying
for the port-o-potties on site privately.
Respectfully Submitted,
Michael J. Nicholson
Mayor, City of Gardner
July 2026
Department Quarterly Update
Department of Community Development & Planning
Staffing
During specifically the last month, it is well known by this committee that the
Department of Community Development & Planning has experienced significant
staffing challenges following the departures of both the Assistant Director and the
Conservation Planning Agent. Despite these vacancies, the department has
continued to prioritize maintaining service levels and project oversight to
minimize impacts on ongoing initiatives and avoid delays to the numerous
projects, reviews & reports, and boards and commissions supported by the
department, including the Planning Board, Gardner Redevelopment Authority,
Conservation Commission, and CDBG Steering Committee.
Recruitment for the Assistant Director position has progressed, and a preferred
candidate has been identified. The hiring process is currently awaiting certain
internal reviews that exist with the HR department before an offer can be
finalized. While these reviews are ongoing, the vacancy continues to place
additional demands on existing staff and departmental operations.
Upcoming Projects
• Rear Main – South Side
• Waterford Street Community Center (Senior Center Asbestos
Abatement) – CDBG Project
*Previously Waterford Community Center (Fire System Electrical Upgrades)
• Social Service Provider Grants – CDBG Project
Rear Main – South Side
• Project Status: Awarded and Contract Signed
• Amount: $3,500,000.00 (FY25 HousingWorks Infrastructure
Grant Program)
• Description:
The City had split the development of the Rear Main parcels into two
separate projects. This half will include the remaining parking for the lot
and include bringing underground utilities to the site of what will be a
private development.
Current Work:
Discussions with Realty Income have continued as the owner of a necessary parcel
of the project site, and have gone through many iterations of possible ownership,
land sale, ground lease, future purchase options, etc. We are still reviewing the
best possible way to move forward with this project and obtain the site ownership
necessary to see through the vision for the eventual development.
Waterford Street Community Center (Senior
Center Asbestos Abatement) – CDBG Project
*Previously Waterford Community Center (Fire System Electrical Upgrades)
• Project Status: Reallocation Being Reviewed for Applicability
• Amount: $122,000.00 (FY25 CDBG)
• Description:
Project to abate the asbestos in the ceiling and floor tiles in the area for
the Senior Center’ identified in Tighe & Bond’s 2024 feasibility study. The
mayor asked for these funds previously allocated to the Fire Electrical
System to be reallocated here to complete the area’s abatement.
Current Work:
Notice has been sent to EOHLC on the request for reallocation from the electrical
service to asbestos abatement, it has been indicated from their team that the
project would be eligible. We are currently in progress with obtaining expected
beneficiary numbers, the full scope of work, detailed budget estimates, ERR
package, etc. to send over to HLC to move forward with this reallocation.
Social Service Providers – CDBG Project
• FY2024 CDBG Social Service Grants
– Gardner Athletic Program – User Fee Scholarship – $15,000.00
– Voices of Truth – Domestic Violence Prevention – $12,000.00
– Gardner Community Action Committee – Food Program – $16,000.00
• FY2025 CDBG Social Service Grants
– Gardner Athletic Program – User Fee Scholarship – $15,000.00
– Voices of Truth – Domestic Violence Prevention – $12,000.00
– MVOC Veterans Assistance – $20,000.00
– Gardner Community Action Committee – Food Program – $30,000.00
• FY22/23 CDBG Social Service Grants
– Gardner Community Action Committee – Food Program - $110,830.00
– MVOC Veterans Assistance – $38,215.00
Ongoing Projects
• Rear Main – North Side
• South Gardner Village Center Utility Upgrades
• Downtown Phase V – CDBG Project
• Greenwood Memorial Pavilion Construction – CDBG Project
• Master Plan Update
• Hazard Mitigation Plan (HMP)
• Housing Production Plan (HPP)
• Municipal Surplus Property Plan
• Downtown Mobility Plan
• Gardner Municipal Surplus Property Plan
Rear Main – North Side
• Project Status: Project Ongoing (Substantial Completion by
August 31, 2026)
• Amount: $4,100,000.00 (FY23 MassWorks Infrastructure
Program)
• Description:
Improved available parking for the downtown area, water feature, green space, splash pad, and
movement of the existing utilities for Main Street businesses currently present on their existing access
road underground.
Current Work:
Pavilion completed, asphalt and pavers complete, majority of work on site has been completed. The
contractor team is currently completing alternate work (landscaping, chain link fence for cell tower, etc)
while awaiting National Grid and Verizon to schedule their work related to the project and see through
the removal of the existing utility poles.
Electrical subcontractor is also awaiting National Grid for the delivery and installation of transformers to
be able to continue relevant work on site.
South Gardner Village Center Utility Upgrades
• Project Status: Project Ongoing
• Amount: $1,480,000.00 (FY26 MassWorks MWIP Grant)
• Description:
The City plans to utilize these funds to overhaul utility wires underground
in the South Gardner Village Center. This initiative is a critical component
of a broader community revitalization effort that is aimed at enhancing
not only the area’s visual appeal, but supporting residential development
and fostering sustainable economic growth.
Current Work:
The team at Tighe & Bond has completed the surveying work for this
project and is currently awaiting National Grid to complete the Right of
Way (ROW) information so their design can continue.
Greenwood Memorial Pavilion Construction –
CDBG Project
• Project Status: Project Bid, Preconstruction Meeting Scheduled
• Amount: $719,342.51 (FY24 CDBG)
• Description:
FY24 CDBG funds originally designated for the demolition of the School
Street School will be used to construct a memorial pavilion on the site of
the former Greenwood Pool facility.
Current Work:
This project was bid out to Diversified Construction Services. We will be having
the preconstruction meeting with the contractor and engineering team on July 30.
Downtown Phase V – CDBG Project
• Project Status: Public Bid in Progress
• Amount: $340,000.00 (FY25 CDBG)
• Description:
Upgrades to the current pedestrian infrastructure on Willow Street
between Main Street and Pleasant Street. Upgrades will include new
crosswalks, sidewalks, curbing, street lighting upgrades, and accessibility
improvements.
Current Work:
The city convened relevant departments to review the proposed design of
the improvements and reconstructed crossings between Willow and Main
Street on June 11. The public bid for this project is open and is ending on
8/5.
Master Plan Update
• Project Status: Plan Completed and Adopted
• Amount: $122,000.00
$90,000.00 (FY24 Community Planning Grant), $32,000.00 (EEA Planning
Assistance Grant) *see HPP Plan
• Description:
The City is undergoing updating its Master Plan for the first time since 1975.
This project will include reviewing past planning efforts, existing conditions,
and gathering public input. The goal is to provide a vision of the community’s
future and a roadmap on how to get there. We’ll be focusing on six key
planning areas in the development of this master plan: housing, economic
development, land use, transportation, open space & recreation, and historic
& cultural resources.
Current Work:
Plan was presented to the Planning Board at its meeting on May 12, 2026 and
was subsequently adopted.
Housing Production Plan (HPP)
• Project Status: Plan Completed and Adopted
• Amount: $32,000 (EEA Planning Assistance Grant)
• Description:
The City has expanded its Master Plan through this grant to create
numerical goals to address affordability of housing, allow a wider variety
of homes in the city, identify municipal property to be used for housing,
how we can meet the region-wide needs for housing, among other
components.
Current Work:
Plan was presented to the Planning Board at its meeting on June 9, 2026
and was subsequently adopted. It was presented to the Finance
Subcommittee on June 9, 2026 and to the City Council on June 15, 2026
and was subsequently adopted.
Gardner Municipal Surplus Property Plan
• Project Status: Plan Completed and Adopted
• Amount: $50,000 (FY26 Massachusetts One Stop for Growth)
• Description:
This project created a city-wide Surplus Property Plan that repositions vacant,
underused public parcels as catalysts for housing, jobs, and equitable investment.
The plan will inventory surplus sites, assess constraints and opportunities, engage
stakeholders, and deliver a clear roadmap for strategic reuse aligned with
Gardner’s planning goals, market conditions, and commitment to sustainable,
inclusive growth.
Along with the plan, this project incorporated a market feasibility study looking at
the current market conditions in Gardner and the feasibility of creating different
kinds of housing, commercial spaces, etc. from the perspective of developers.
• Current Work:
The plan was presented to the Finance Subcommittee on June 9, 2026 and to the
City Council on June 15, 2026 and was subsequently adopted.
Hazard Mitigation Plan (HMP)
• Project Status: Project Ongoing (Extension Granted Until
10/31/2026)
• Amount: $90,000.00 (FY25 Community Planning Grant
Program)
• Description:
The City is undergoing updating its first individual HMP as we’ve
previously relied on the regional Montachusett HMP for how to address
hazards and extreme weather events.
Current Work:
All chapters for this plan are completed and have been in review by
MEMA and FEMA for both completeness and a thorough look through our
engagement process for required stakeholder feedback & outreach.
Downtown Mobility Plan
• Project Status: Contract Awarded to City, RFP Bid in Progress
• Amount: $1,253,000.00 (RAISE Grant)
• Description:
The project will address active transportation infrastructure, multimodal
transit options, a neighborhood-scaled mobility hub, last-mile
connectivity, and parking infrastructure. The project will also include the
planning, engineering, and preparation for bid-ready documents for a 4-
story parking garage on West Street located in the Downtown area.
Current Work:
The City completed its bid process and received two responses to the RFP,
the RFPs are being critiqued against the comparative criteria included
with the proposals to decide on the contractor being chosen. Aim for this
to be completed early-mid next week.
North Central Pathway Phase II
• Project Status: Grant Awarded, State Contract Signed
• Amount: $250,000.00
$200,000.00 (FY26 MassTrails Grant), $50,000.00 (Required Match, Municipal
Capital Funds)
• Description:
This phase of the project would oversee the planning for the remainder of the
nature trail past Park Street through to Route 140.
Current Work:
The city received its grant award notice and state standard contract on June
25, 2026, and the signed contract and authorized signatory listing on July 8,
2026. Currently awaiting the returned endorsed contract and Notice to
Proceed (NTP).
A public design hearing was advertised and held virtually by MassDOT on June
16, 2026, as required, to go over the remaining design of the trail and answer
questions from the public.
Keyes Road Culvert Replacement
• Project Status: Full Project Cost Awarded by MassDOT
• Amount: $2,014,230.00 (Community Culvert Grant Program)
• Description:
Construction for the replacement of the Keyes Road culvert into a full bridge
that serves Wilder Brook and the 60+ household residential neighborhood
that relies on the crossing as its only form of access to the rest of the City. The
culvert is in critical condition and is at risk of failing and implementing a
bridge in its place will improve the community’s reliance on the infrastructure
and the ecological health of the Brook and stream area.
Current Work:
After being awarded the full project amount, the department is having Tighe
& Bond move forward with the project’s bidding and construction services.
The City Auditor is in progress with creating the account to hold these
awarded funds.
Get email alerts for Gardner
A daily email when new agendas and minutes are posted.