School Building Financial Sub Committee
Regular MeetingGardner, MA · April 7, 2021
Minutes
Gardner Elementary School
Financial Subcommittee
Meeting Minutes
Wednesday, April 7, 2021
Zoom Meeting
4:00 p.m.
Members Present
Dr. Mark Pellegrino, Superintendent of Schools; Wayne Anderson, Facilities, Director; Jennifer
Pelavin, School Committee Vice Chair; Robert Hankinson Gardner Citizen & Former City
Engineer; Joshua Cormier, Purchasing Director, City of Gardner;
Also Present
Alternate member, Robert Swartz, School Committee Member; Dr. Steve Hemman, Special
Projects Assistant to the Superintendent; Alan Minkus, OPM; Colliers International; Tim Alix,
Project Manager; Matthew Dunn, Sr. Construction Representative, Colliers International; Craig
DiCarlo, Project Manager, Colliers International: Kristian Whitsett, Architect, Jones-Whitsett
Architects; James Trifiro, Deputy Chief of Police, City of Gardner; Steve Rockwood, Community
Member; Brenda Smith, Administrative Assistant to the Superintendent; Recording Secretary.
Regrets
Margo Jones, Designer, Jones-Whitsett Architects, Mayor Michael Nicholson, City of Gardner;
Colin Smith, Executive Aide to the Mayor, City of Gardner;
Call to order
Superintendent Pellegrino called the meeting to order at 4:01 p.m.
Approve Minutes
Mr. Wayne Anderson moved to approve the minutes from the Financial Subcommittee Meeting
on March 3, 2021 at 4:00 P.M.
Seconded by Mr. Robert Swartz Vote – so voted
Dr. Hemman, asked the committee if we could jump ahead to New Business while we had
Deputy Chief James Trifiro with us to talk about the Traffic Entrance design at the Pearl
Street Entrance:
Mr. Dunn spoke with the Building Commissioner and basically advised us we had to have an
issued permit, signage would be on state land and private property, so why? Bacon Construction,
would be willing to put up and take down the signage every day, but for the amount of time to do
this they would need to be paid for their services, which would overtime be too costly.
Dr. Hemman asked Deputy Chief if there was anyone we could talk to? Deputy Chief said, I had
a lengthy discussion with the City Engineer and Highway Department Superintendent before
today’s meeting. If I have this correct, you’re looking to put local commuters on notice to look for
construction zone in the area so to take caution. For signage I will talk with a local MA DOT Rep,
find out what we would need to keep them up during the permanently, temporary construction
process.
Dr. Hemman said, the abutter is at our meetings and he has no problem with us putting a sign up
on his property. Abutters name was shared and the Deputy Chief is going to talk with him along
with MA DOT and the Gardner Highway Department Superintendent. He will be back in touch
with Dr. Hemman as soon as possible with the outcome.
Dr. Hemman thanked Deputy Chief Trifiro for attending and his help. We have been working on
this for three weeks trying to figure it all out.
Dr. Hemman let the committee know Deputy Chief Trifiro is in charge of traffic. So this works
out well.
Approve Bills & Orders, No Full Committee held until April 28, 2021 Subcommittee has
approved to do so.
The following invoices were presented to the Financial Subcommittee:
● Strategic Building Solutions, LLC, dba Colliers International, Invoice #008921 dated
March 31, 2021; in the amount of $87,941.36
Mr. Robert Hankinson moved to approve Invoice #008921 from Strategic Building Solutions,
LLC, dba Colliers International.
Seconded by Mr. Robert Swartz Vote - so voted
● Jones-Whitsett Architects, Invoice #2021024, dated March 31, 2021; in the amount of
$111,710.25
Mr. Hankinson moved to approve Invoice #2021024 from Jones-Whitsett Architects.
Seconded by Mr. Swartz Vote - so voted
● Bacon Construction Co., Inc. Invoice #4, dated Mach 31, 2021; in the amount of
$865,368.67
Mr. Hankinson moved to approve Invoice #4 from Bacon Construction Co., Inc.
Seconded by Mr. Swartz Vote – so voted
• Allied Testing Laboratories, Inc. Invoice # 22215, dated March 27, 2021, in the amount of
$3,225.00
Mr. Hankinson moved to approve Invoice #22215, from Allied Testing Laboratories., Inc.
Seconded by Mr. Swartz Vote - so voted
Any Discussion on the motions:
Mr. Hankinson, my only question is, make sure the recent two invoices been reviewed and
approved.
Dr. Hemman responded, all invoices have been reviewed and approved, by the OPM & Architect.
Mr. Whitsett you have any comment? Mr. Whitsett, yes, all bills have been reviewed and approved.
Dr. Pellegrino replied, thank you for bring that up, good to have on record Mr. Hankinson.
Report from OPM
Updates-Mr. Timothy Alix reviewed the Financial Status Report, Summary of our budget with
approved transfers just to show our contingency with what was spent and where we are.
Mr. Alix discussed the change orders list, looking to potentially get the approval tonight.
• Change Order 1- $222,206.07 was approved 3.17.2021
• Change Order 2 – $54,350.00 presented 4.7.2021
o CO#8.1 Radiant panels $ 1,679.00
o CO#15 Transom to door $ 493.00
o CO#22 C Wing Steel $ 1,808.00
o CO#23 Retaining Wall Foot $ 3,852.00
o CO#27 Know Box and Smoke Beam $ 8,084.00
o CO#28 Vest B002 Lights $ 1,026.00
o CO#30 Skylight Sizes $ 1,882.00
o CO#31 Connector Steel $ 3,272.00
o CO#33 Stair 1 Landings $ 1,548.00
o CO#34 Water at Catherine $ 7,774.00
o CO#35 FRP door XA400 $ 1,557.00
o CO#36 Add Lite to Door B105A $ 318.00
o CO#37 C Wing Roof Slope Changes $ 3,530.00
o CO#43 Open Rock Allowance #2 $17,527.00
• Total for Change Order #2 $ 54,350.00
Mr. Anderson suggested we wait to approve CO#1 Fence at Wall, he discussed the new proposed
fence, we do not have increased height yet. Would like to wrap this all in together as one. Mr. Alix
said, we do have the time we can wait to do the one change on all fencing. Mr. Swartz conquered.
Ms. Pelavin agrees makes sense we will remove. Removed CO#1 from Change Order #2 list until
next meeting.
Mr. Anderson also asked to put in anther stub for water, so when building a concession stand we
are all set. Mr. Anderson asked if we could double the number on CO#34? Mr. Alix will need to
review with Contractor and see what the new amount would be. In condition that the amount does
not exceed what we have down on CO#34 we will approve the doubled amount tonight. Committee
agreed.
Mr. Wayne Anderson moved to approve Change order # 2. In the amount of $54,350.00
Seconded by Ms. Pelavin
Vote - so voted
Site Reports
Mr. Dunn informed committee they completed the first culvert today. Quite the structure, things
are moving along well. Building Inspector was by today, he’s good with everything. Conservation
will be coming through to see our work next.
Office trailers have arrived on site; it will take two weeks to power up then we can occupy. One
trailer for OPM, and one for Bacon Construction.
Mr. Alix asked, Mr. Anderson to meet up with Mr. Dunn and go over where they would like the
second water tap to go. Then they can talk to Bacon Construction about it. Mr. Anderson said,
tomorrow I will be in touch to review the location.
Report from Architects
Updates:
Mr. Whitsett shared future traffic flow at the school crossing, reviewed proposed plans with the
committee on how the flow would go through out the school zone.
• Turning left
• Turning right
• Flashing lights
• Speed limit signs
• Crosswalk
• Pedestrian’s crosswalk.
Will review with Police Department. And will bring back up at full committee on April 28, 2021
Other Business
Public Comment
Executive Session
No Executive Session
Next Meetings
New Information- Site Visit - Full GES Building Committee meeting will be held on
Wednesday, April 28, 2021@ 3:30. We will meet at Dunn Pond Parking lot to have a short
meeting (30 minutes), and to sign waivers, we go in at our own risk. All committee members
going on job site will need to sign a waiver to tour job site. If you don’t want to tour you do not
need to.
In case of bad weather, the meeting will take place as scheduled on April 28, 2021 by Zoom at
our 4:00 normal time.
Meeting dates for future GES Financial Subcommittee meetings;
Wednesday, May 5, 2021 @ 4:00 by Zoom
Adjourn
A motion was made by Ms. Jennifer Pelavin and seconded by Mr. Robert Swartz to adjourn the
meeting. The meeting adjourned at 4:447p.m.
Agenda
Gardner Elementary School
Financial Sub Committee
Meeting Agenda
April 7, 2021
Virtual (On-Line) Meeting -- Zoom Meeting
4:00 pm
Pursuant to Governor Baker’s March 12, 2020 Order Suspending Certain Provisions of the Open Meeting Law, G.L. c. 30A, §20, and the
Governor’s March 15, 2020 Order imposing strict limitation on the number of people that may gather in one place, this meeting of the City of
Gardner School Building Committee will be conducted via remote participation to the greatest extent possible. For this meeting, members of
the public who wish to watch the meeting may do so in the following manner: watching on the City of Gardner YouTube page. No in-person
attendance of members of the public will be permitted, but every effort will be made to ensure that the public can adequately access the
proceedings in real time, via technological means. In the event that we are unable to do so, despite best efforts, we will post on the City’s
website an audio or video recording, transcript, or other comprehensive record of proceedings as soon as possible after the meeting.
The matters listed are those reasonably anticipated by the Chair which may be discussed at the
meeting. Not all items listed may in fact be discussed and other items not listed may also be
brought up for discussion to the extent by law.
1. Call to order and attendance
2. Approve Minutes
a. March 3 2021
3. Approve Bills and orders
a.
4. Report from OPM
a. Updates
b. Site Report
5. Report from Architects
a. Updates
b. Report on Change Orders
c.
6. Old Business
a.
7. New Business
a. Change Orders-vote to recommend to Building Committee
b. Traffic Entrance design Pearle Street entrance
8. Other Business to come before the Sub Committee
9. Public Comment
10.Next meeting dates: May 5, 2021
11. Executive Session
12. Adjourn
Attachments:
Join Zoom Meeting
https://us02web.zoom.us/j/83653466403
Get email alerts for Gardner
A daily email when new agendas and minutes are posted.