School Building Financial Sub Committee
Regular MeetingGardner, MA · June 30, 2021
Minutes
Gardner Elementary School
Financial Subcommittee
Meeting Minutes
Wednesday, June 30, 2021
Zoom Meeting
4:00 p.m.
Members Present
Jennifer Pelavin, School Committee Vice Chair; Robert Swartz, School Committee Member;
Wayne Anderson, Facilities, Director; Robert Hankinson Gardner Citizen & Former City
Engineer; Joshua Cormier, Purchasing Director, City of Gardner;
Also Present
Alternate member, Mark Hawke, Director of Finance and Operations; Dr. Steve Hemman,
Special Projects Assistant to the Superintendent; Tim Alix, Project Manager; Matthew Dunn, Sr.
Construction Representative, Colliers International; Kristian Whitsett, Architect, Jones-Whitsett
Architects; Alan Minkus, OPM; Colliers International; Steve Rockwood, Community Member;
Brenda Smith, Administrative Assistant to the Superintendent; Recording Secretary.
Regrets
Dr. Mark Pellegrino, Superintendent of Schools; Margo Jones, Designer, Jones-Whitsett
Architects, Mayor Michael Nicholson, City of Gardner; Colin Smith, Executive Aide to the
Mayor, City of Gardner; Dr. Catherine Goguen, Chief Academic Officer, Gardner Public
Schools;
Call to order
Jennifer Pelavin, called the meeting to order at 4:01 p.m.
Approve Minutes
Mr. Robert Hankinson asked for a modification to the minutes, minutes did not express the level
of concerns that I tried to show at the meeting with change orders especially in the structure
realm. Correction to sentence should be.
“Mr. Hankinson expressed significant concern over the number of structural steel change orders
requested so far.”
Mr. Robert Hankinson moved to amend the minutes from the Financial Subcommittee Meeting
on June 2, 2021 at 4:02 P.M.
Seconded by Mr. Robert Swartz Vote – 4 yes
Mark Hawke abstained from voting
Mr. Robert Swartz moved to approve the minutes as amended from the Financial Subcommittee
Meeting on June 2, 2021 at 4:02 P.M.
Seconded by Mr. Robert Hankinson Vote – 4 yes
Mark Hawke abstained from voting
Approve Bills & Orders,
The following invoices were presented to the Financial Subcommittee:
• Allied Testing Laboratories, Inc. Invoice # 22664, dated June 19, 2021, in the amount of
$5,035.00
Mr. Swartz moved to approve Invoice #22664, from Allied Testing Laboratories., Inc.
Seconded by Mr. Hankinson Vote - so voted
● Jones-Whitsett Architects, Invoice #2021057, dated June 30, 2021; in the amount of
$118,186.50
Mr. Robert Swartz moved to approve Invoice #2021057 from Jones-Whitsett Architects.
Seconded by Mr. Robert Hankinson. Vote - so voted
● Bacon Construction Co., Inc. Invoice #7, dated June 30, 2021; in the amount of
$2,502,683.39
Mr. Whitesett shared that he had a few minor items under discussion that this amount might come
down a little, can we have it approved not to exceed the current amount $2,502, 683.39
Mr. Swartz moved to except the invoices of payment not to exceed $2,502.683.39 on Bacon
Invoice and the other Invoices will stand as presented.
Seconded for reason of discussion by Mr. Hankinson.
Vote – so voted
Mr. Robert Hankinson said, in my mind for this committee to have validity. “This committee needs
more time to review bills ahead of time, not getting an email five minutes before a meeting”. I
spend time studying these and go over each and everyone one. I will vote based on
recommendation of the team, but would like more time to review.
Dr. Steve Hemman, assured him he will, this was due to the early meeting of June 30, in the future
you will get them ahead of time.
Report from OPM
Updates
Mr. Tim Alix wanted to explain how we track the finances a little more than how we have in the
past in the propay system, and that we are on track with MSBA. A summary was shared with the
committee and details of the financial status report was reviewed and explained as to what was
paid and projected to be paid, but, not contracted yet. We track it all and submit for reimbursement
each month.
Mr. Hawke asked for confirmation on financial side, what’s talked about between the Architect,
OPM & Contractor, need to have a log of everything in case it comes up. Mr. Alix said, potential
exposure is all tracked, some is real some is rejected. We wanted to share with you the financial
discussions side after all the change orders that have come up, so all understand where we stand
and how we go about it.
Mr. Alix, reviewed and discussed the change orders list for change order number 5. Mr. Alix
explained how we tracked on the project this month that hadn’t showed up on the list. Design issue
or miscellaneous item in order to show how we get reimbursed or pay.
• Change Order 1- $222,206.07 was approved 3.17.2021
• Change Order 2 - $54,350.00 was approved 4.7.2021
• Change Order 3 - $81,982.23 was approved 5.19 2021
• Change Order 4 - $38,095.56 was approved 6.2.2021
• Change Order 5 - $84,860.00 presented 6.30.2021
o CO#24 A Wing Mesh Platform $ 12,674.00
o CO#51 Joist Substitute at AG $ 4,859.00
o CO#52 Art Wall Floor Lighting $ 13,329.00
o CO#63 A-Wing Eave and Rake Support $ 17,092.00
o CO#64 C-Wing Eave and Rake Support $ 7,797.00
o CO#73 Change B Wing Admin Window $ 2,182.00
o CO#74 Change lighting in C204 $ 2,594.00
o CO#79 Thicker Sun Control Devices $ 7,530.00
o CO#80 Furred out wall at Stair 5 $ 1,262.00
o CO#87 Material for Kitchen Hood Duct $ 1,464.00
o CO#89 A Wing Bathroom Heaters $ 956.00
o CO#92 Changes to Handrail $ 13,121.00
o CO#95 Credit Fire Alarm Hoist Way Vents $ - 958.66 (credit)
• Total for Change Order #5 $ 84,860.00
Mr. Whitsett just wanted to point out the items on the shared document, the items that have lines
through them have been officially rejected. Money to increase structural steel issues that have
come up we need to review; we don’t agree with at this time. We want the committee to be aware
of this, we will meet with them next week and keep you posted.
Mr. Hankinson asked to make two comments;
#1 Thank you for looking out for our interests, don’t take anything I say as criticism.
#2 Tim, please explain, you used the three remaining structural items out there necessary, because
what was carried vs what was required resulted in change order? Expand upon that, who decided
what was carried vs what is required in the construction document?
Mr. Tim Alix, responded, the structural engineer we rely on for that, and a couple of these, what
was happening was in the drawing process the distances between the joist may be different in
certain areas to be able to carry cross over spans and still get the support.
Mr. Hankinson, so the supplier is questioning the structural engineer? Mr. Alix responded, there
is always a give and take, need to move things around for coordination, adjustment in the pitch of
the roof, allowances of mechanical some of those things some aren’t defined in the design, roof
top unit’s, basis for design from one manufacture, submit something that was different, and some
modification, there’s coordination that needs to take place. Mr. Hankinson, I really appreciated
that explanation Tim, and the notes on the side explaining it, I appreciate that.
Dr. Hemman brought up the change in doors from – Wood to Maple? Natural Birch was specified.
Some of these doors look great, some that have hardwood are very “stripey” We asked for a change
to maple and were told that this is the price difference. We would prefer maple, but defer to the
committee. White birch is even more than maple for some reason, with the current building
materials shortage. All options are higher than maple. Any difference in longevity of doors was
asked, no, both hardwood. There is a 16 week lead time on doors so need to get the order in.
Committee agrees to stay with the original Natural birch wood.
Mr. Robert Hankinson moved to authorize Change Order #5 not to exceed the amount of
$84,860.00
Seconded by Mr. Mark Hawke Vote - so voted
Report from Architects
Updates: Mr. Whitsett updated the committee on the fantastic drone sites, very excited to share
at Full Committee meeting.
Other Business
Mr. Hankinson would like to thank Wayne Anderson, on all the work done in getting the beam
signed.
Mr. Swartz would like to Thank Matt Dunn, for the weekly reports and pictures, he takes the
right picture at the right time, very impressed gives a good sense on what’s going on at the
school site.
Public Comment
Executive Session
No Executive Session
Next Meetings
Meeting dates for future GES Financial Subcommittee meetings;
Wednesday, August 4, 2021 @ 4:00 by Zoom
Adjourn
A motion was made by Mr. Robert Swartz and seconded by Mr. Mark Hawke to adjourn the
meeting. The meeting adjourned at 5:04 p.m.
Agenda
Gardner Elementary School
Financial Sub Committee
Meeting Agenda
The meeting will be on Zoom with some members in person at
70 Waterford Street, Gardner, MA 01440
June 30, 2021
4:00 pm
Subject to the law passed and signed by the Governor on June 16, 2021, this meeting of the City of Gardner School Building Sub Committee will
be conducted via remote participation to the greatest extent possible. For this meeting, members of the public who wish to watch the meeting
may do so in the following manner: watching on the City of Gardner YouTube page. No in-person attendance of members of the public will be
permitted, but every effort will be made to ensure that the public can adequately access the proceedings in real time, via technological means.
In the event that we are unable to do so, despite best efforts, we will post on the City’s website an audio or video recording, transcript, or other
comprehensive record of proceedings as soon as possible after the meeting.
The matters listed are those reasonably anticipated by the Chair which may be discussed at the
meeting. Not all items listed may in fact be discussed and other items not listed may also be
brought up for discussion to the extent by law.
1. Call to order and attendance
2. Approve Minutes
a. June 2, 2021
3. Approve Bills and orders
a. Colliers
b. Jones Whitsett
c. Allied Testing
d. Beacon Construction
4. Report from OPM
a. Updates
b. Site Report
c. Report on Change Orders---Vote to Approve
5. Report from Architects
a. Updates
b. Report on working Groups
6. Old Business
a.
7. New Business
a.
8. Other Business to come before the Sub Committee
9. Public Comment
10.Next meeting dates: August 4, 2021
11. Executive Session
12. Adjourn