School Building Financial Sub Committee
Regular MeetingGardner, MA · January 5, 2022
Minutes
Gardner Elementary School
Financial Subcommittee
Meeting Minutes
Wednesday, January 5, 2022
Zoom Meeting
4:00 p.m.
Members Present
Dr. Mark Pellegrino, Superintendent of Schools; Jennifer Pelavin, School Committee Vice Chair;
Mark Hawke, Director of Finance and Operations; Robert Hankinson, Gardner Citizen & Former
City Engineer; Robert Swartz, School Committee Member.
Also Present
Dr. Steve Hemman, Special Projects Assistant to the Superintendent; Tim Alix, Senior Project
Manager, Colliers International; Matthew Dunn, Sr. Construction Representative, Colliers
International; Kristian Whitsett, Architect, Jones-Whitsett Architects; Joshua Cormier,
Purchasing Director, City of Gardner; Alan Minkus, OPM; Colliers International; Brenda Smith,
Administrative Assistant to the Superintendent; Recording Secretary.
Regrets
Wayne Anderson, Facilities Director; Margo Jones, Designer, Jones-Whitsett Architects, Mayor
Michael Nicholson, City of Gardner; Colin Smith, Executive Aide to the Mayor, City of
Gardner; Steve Rockwood, Community Member.
Call to order
Dr. Mark Pellegrino, called the meeting to order at 4:00 p.m.
Approve Minutes
Mr. Robert Hankinson moved to approve the minutes from the Financial Subcommittee Meeting
on December 1, 2021 at 4:01 P.M.
Seconded by Ms. Jennifer Pelavin Vote – so voted
Approve Bills & Orders,
No Bills & Orders to approve at this meeting
Report from OPM
Updates
Mr. Timothy Alix reviewed the budget to date with the committee. He reviewed them in detail and
feels overall we are doing great with finances.
Mr. Alix is asking the committee to make things as efficient as possible for approval for a certain
dollar value for the contractor to move forward without having to wait for approval at committee
meetings; stop & starting creates loss in time for contractors.
Mr. Mark Hawke motioned to (keep us on the July 15, completion date) the approval to make a
decision of $10,000.00 per occurrence before having to come to the committee for approval, and
do not need to notify us immediately, but will update us at next meeting.
Seconded by Ms. Jennifer Pelavin Vote – so voted
Mr. Alix, updated the situation with the window testing. The primary sealant wasn’t adhering
properly so additional testing has been done and a different caulking product used that did pass.
We will revisit again next week and hope all is set and passes with additional tests and issues are
resolved so mason will be able to continue their work.
Change Orders to date:
● Change Order 1- $222,206.07 was approved 3.17.2021
● Change Order 2 - $54,350.00 was approved 4.7.2021
● Change Order 3 - $81,982.23 was approved 5.19 2021
● Change Order 4 - $83,955.56 was approved 6.2.2021
● Change Order 5 - $81,046.34 was approved 7.21.2021
● Change Order 6 - $61,332.67 was approved 8.4.2021
● Change Order 7 - $65,002.00 was approved 9.1.2021
● Change Order 8 - $133,047.02 was approved 9.15.2021
● Change Order 9 - $120,300.04 was approved 10.6.2021
● Change Order 10 - $83,985.00 was approved 11.17.2021
● Change Order 11 - $297,156.00 was approved 12.1.21
● Change Order 12 - $123,058.46 for approval 1.5.2022
Mr. Kristian Whitsett, Architect, reviewed Change Order #12, with the committee.
Summary of Requests -
o CO#102 Added Electrical Equipment $ 2,201.00
o CO#169 Adjust for Utility Conflicts in Pearl Street $ 8,285.00
o CO#172 (Credit) for floor boxes in Media Center - $ 1,890.54
o CO#173 Unsuitable Soils at Pearl Street Entry $ 55,198.00
o CO#174 Changes to AVB at C Wing Entry (Not to exceed) $ 9,231.00
o CO#181 Change to AVB at C Wing Entry $ 1,332.00
o CO#184 Add AV Strobes to Calm Room Halls $ 1,884.00
o CO#185b Additional Parapet Insulation Changes $ 8,646.00
o CO#188 Exposed Pipes between Radiant Panels $ 1,788.00
o CO#189 Add Frame for Roof Hatch (Not to exceed) $ 5,912.00
o CO#191 Steel Supports at Clerestory Walls (Not to exceed) $ 8,214.00
o CO#192 Change Exterior Concrete Sealer (Not to exceed) $ 28,878.00
o CO#193 Add TP Holders to Contractor Scope $ 4,463.00
o CO#195 Change Know Box to Vault per GFD $ 1,640.00
o CO#199 Winter Conditions for Loading Dock Driveway Concrete $ 13,937.00
TOTAL $123,058.46
Mr. Robert Hankinson motioned to recommend approval of Change Order #12 minus CO#192 in
the amount of $123,058.46
Seconded by Mr. Robert Swartz Vote – so voted
Public Comment:
No comments
Executive Session:
No Executive Session
Next Meetings
Meeting dates for future GES Financial Subcommittee meetings;
Wednesday, February 2, 2022 @ 4:00 by Zoom
Adjourn
A motion was made by Mr. Robert Swartz and seconded by Ms. Jennifer Pelavin to adjourn the
meeting. The meeting adjourned at 4:45 p.m.
Agenda
Gardner Elementary School
Financial Sub Committee
Meeting Agenda
The meeting will be on Zoom with some members in person at
70 Waterford Street, Gardner, MA 01440
January 5, 2022
4:00 pm
Subject to the law passed and signed by the Governor on June 16, 2021, this meeting of the City of Gardner School Building Sub Committee will
be conducted via remote participation to the greatest extent possible. For this meeting, members of the public who wish to watch the meeting
may do so in the following manner: watching on the City of Gardner YouTube page. No in-person attendance of members of the public will be
permitted, but every effort will be made to ensure that the public can adequately access the proceedings in real time, via technological means.
In the event that we are unable to do so, despite best efforts, we will post on the City’s website an audio or video recording, transcript, or other
comprehensive record of proceedings as soon as possible after the meeting.
The matters listed are those reasonably anticipated by the Chair which may be discussed at the
meeting. Not all items listed may in fact be discussed and other items not listed may also be
brought up for discussion to the extent by law.
1. Call to order and attendance
2. Approve Minutes
a. Dec. 1, 2021
3. Approve Bills and orders
a. Colliers
b. Jones Whitsett
c. Allied Testing
d. Beacon Construction
e. Intertek Testing
4. Report from OPM
a. Updates
b. Change Orders
c. Window Testing
d. Change Order process
5. Report from Architects
a. Updates
b.
6. Old Business
a.
7. New Business
a.
8. Other Business to come before the Sub Committee
9. Public Comment
10.Next meeting dates: Feb. 2, 2022
11. Executive Session
12. Adjourn