School Building Financial Sub Committee
Regular MeetingGardner, MA · April 6, 2022
Minutes
Gardner Elementary School
Financial Subcommittee
Meeting Minutes
Wednesday, April 6, 2022
Zoom Meeting
4:00 p.m.
Members Present
Dr. Mark Pellegrino, Superintendent of Schools; Jennifer Pelavin, School Committee Vice Chair;
Mark Hawke, Director of Finance and Operations; Robert Hankinson, Gardner Citizen & Former
City Engineer; Robert Swartz, School Committee Member; Wayne Anderson, Facilities Director;
Also Present
Dr. Steve Hemman, Special Projects Assistant to the Superintendent; Tim Alix, Senior Project
Manager, Colliers International; Matthew Dunn, Sr. Construction Representative, Colliers
International; Kristian Whitsett, Architect, Jones-Whitsett Architects; Alan Minkus, OPM;
Colliers International; Joshua Cormier, Purchasing Director, City of Gardner; Brenda Smith,
Executive Assistant to the Superintendent; Recording Secretary.
Regrets
Margo Jones, Designer, Jones-Whitsett Architects, Mayor Michael Nicholson, City of Gardner;
Colin Smith, Executive Aide to the Mayor, City of Gardner; Dr. Catherine Goguen, Chief
Academic Officer; Steve Rockwood, Community Member.
Call to order
Dr. Mark Pellegrino, called the meeting to order at 4:00 p.m.
Approve Minutes
Mr. Robert Swartz moved to approve the minutes from the Financial Subcommittee Meeting on
March 2, 2022 at 4:01 P.M.
Seconded by Ms. Jennifer Pelavin Vote – so voted
Approve Bills & Orders
No Bills to approve this meeting
Report from OPM
Updates
Mr. Timothy Alix reviewed the Financial Status Report to date with the committee. We are in good
shape moving forward. We are still on our target date for opening July 15, 2022. Somethings are
delayed and other items coming in sooner than said it would be, all just working out.
Mr. Swartz questioned are we on National Grid power yet? Mr. Alix replied, mid-May. It is being
worked on. National Grid came out this week to pull their primary wires, Griffin Electric was
waiting on some equipment to pull secondary’s once primaries completed bringing everything in
from transformer, expecting Mid-May.
Site Update:
Mr. Matthew Dunn reviewed the recent site activity, great news is the transformer is in.
Each building moving right along taping, painting and doing trim in each classroom, building is
looking great.
Change Orders to date:
● Change Order 1- $222,206.07 was approved 3.17.2021
● Change Order 2 - $54,350.00 was approved 4.7.2021
● Change Order 3 - $81,982.23 was approved 5.19 2021
● Change Order 4 - $83,955.56 was approved 6.2.2021
● Change Order 5 - $81,046.34 was approved 7.21.2021
● Change Order 6 - $61,332.67 was approved 8.4.2021
● Change Order 7 - $65,002.00 was approved 9.1.2021
● Change Order 8 - $133,047.02 was approved 9.15.2021
● Change Order 9 - $120,300.04 was approved 10.6.2021
● Change Order 10 - $83,985.00 was approved 11.17.2021
● Change Order 11 - $297,156.00 was approved 12.1.21
● Change Order 12 - $99,701.46 was approved 1.5.2022
● Change Order 13 - $93,616.00 was approved 2.2.2022
● Change Order 14 - $71,237.00 was approved 3.2.2022
● Change Order 15 – $96,285.00 for approval 4.6.2022
Report from Architects
Mr. Kristian Whitsett, Architect, reviewed Change Order #15 with the committee in detail.
Summary of Requests -
o CO#148 Add Thresholds to Select Alum Doors $ 2,601.00
o CO#152 Change to GFRC Pattern to Meet Design Criteria (Excluding this CO)
-$24,081.00 (Denied)
o CO#217 Add Tile to West Wall of Kitchen (Denied) $ 4,267.00
o CO#218 Add Quarry Tile to Floor of Walk-in Cooler $16,417.00
o CO#224 Fur Out Two B-Wing Walls $ 789.00
o CO#226 Relocate Custodial Sink B200A $ 1,483.00
o CO#236 Divide Workshop into Multiple Rooms $42,753.00
o CO#237 Add Edging Between Pavers & Asphalt (Not to exceed) $ 3,166.00
o CO#238 Add Tile & Graphic to Art Wall $10,441.00
o CO#243 Add Curb Between Pavers & Asphalt $ 4,772.00
o CO#247 Provide HVAC Valves to Isolate Each Building $11,467.00
o CO#249 Add Soffit in A317 $ 1,967.00
o CO#251 Change Sealant at A-Wing Windows (Denied) - ($16,803.00)
o CO#252 Modify Water Closets at Tile Trim $ 4,955.00
o CO#254 Delete chip and seal asphalt coating -($5,038.00)
o CO#256 Relocate letter from Canopy Wall (Not to Exceed) $ 3,143.00
o CO#257 PR-75 Swing Set Changes -($ 3,204.00)
o CO#259 Increase Type B Sign Size $ 573.00
TOTAL $ 96,285.00
Discussion on the Change Order# 152
Mr. Robert Hankinson voiced his opinion. I really object to this, in my experience I would say the
words of the specification which say it needs to be attached takes precedence over a typical detail
and I just feel this is just one more example of the contractor trying to pick up what he left on the
table.
Mr. Wayne Anderson added, did the bid specification say that you are going to need to fastened
each panel 3 times to the building? Mr. Whitsett replied, no, we didn’t give them any numbers just
said all necessary wall enforcements.
Mr. Dunn, replied, we did give them wind load information.
Mr. Hankinson noted, I really appreciate Mr. Whitsett’s input, but, would like to hear from Mr.
Alix.
Mr. Alix explained indetail and said my recommendation is not to except it, direct them to do the
work and if they want to do it under protest bring it up as an issue at the end of the project, we
have specific guidelines in our contract how to go about doing it if need be.
Mr. Hankinson noted he depends on the OPM; we have no working relationship with the contractor
I depend on you to make that known.
Mr. Mark Hawke noted to reach out to the contractor and let them know it was denied, they bid
this and if they didn’t know they should have asked questions.
Mr. Mark Hawke motioned to recommend approval of Change Order #15 excluding CO#152
bringing the amount of $96,285.00
Seconded by Ms. Jennifer Pelavin Vote – so voted
New Business
Mr. Hemman asked the committee to think about the Time Capsule placement, we need to prepare
an area and make a decision where it will go. It will be brought up to the full committee next
meeting.
Mr. Hemman also noted having no bills this meeting I need to make a request of 3 people to sign
bills before our next meeting. Mr. Swartz nominated the Finance Committee of the GES Building
Committee, Jenn Pelavin, Robert Swartz, and Wayne Anderson to do it. All agreed that is fine.
Public Comment:
No comments
Executive Session:
No Executive Session
Next Meetings
Meeting dates for future GES Financial Subcommittee meetings;
Wednesday, May 4, 2022 @ 4:00 by Zoom
Meeting date for next GES New Building Committee Meeting has been changed due to April
vacation to April 27, 2022 @ 4:00 by Zoom
Adjourn
A motion was made by Ms. Jennifer Pelavin and seconded by Mr. Robert Swartz to adjourn the
meeting. The meeting adjourned at 4:54 p.m.
Agenda
Gardner Elementary School
Financial Sub Committee
Meeting Agenda
The meeting will be on Zoom with some members in person at
70 Waterford Street, Gardner, MA 01440
April 6, 2022
4:00 pm
Subject to the law passed and signed by the Governor on June 16, 2021, this meeting of the City of Gardner School Building Sub Committee will
be conducted via remote participation to the greatest extent possible. For this meeting, members of the public who wish to watch the meeting
may do so in the following manner: watching on the City of Gardner YouTube page. No in-person attendance of members of the public will be
permitted, but every effort will be made to ensure that the public can adequately access the proceedings in real time, via technological means.
In the event that we are unable to do so, despite best efforts, we will post on the City’s website an audio or video recording, transcript, or other
comprehensive record of proceedings as soon as possible after the meeting.
The matters listed are those reasonably anticipated by the Chair which may be discussed at the
meeting. Not all items listed may in fact be discussed and other items not listed may also be
brought up for discussion to the extent by law.
1. Call to order and attendance
2. Approve Minutes
a. March 2, 2022
3. Approve Bills and orders
a. Colliers
b. Jones Whitsett
c. Allied Testing
d. Beacon Construction
e. Intertek Testing
4. Report from OPM
a. Updates
b. Budget Status
c. Construction updates
5. Report from Architects
a. Updates
b. Change Orders
c. Vote Change Orders
6. Old Business
a.
7. New Business
a.
8. Other Business to come before the Sub Committee
9. Public Comment
10.Next meeting dates: May 4, 2022
11. Executive Session
12. Adjourn