Mayor Wilson called the regular meeting of the City Council to order at 7:00 p.m. Members
present: Neid, Schrupp, Ziemer, Robeck and Alexander. Also present: City Administrator Mark
Larson, City Attorney Mark Ostlund, Finance Director Trippel, Assistant City Administrator
Ehrke, PWD’s Schreifels and Voigt, Police Chief Raiter, Fire Chief Scheidt.
PLEDGE OF ALLEGIANCE AND MOMENT OF SILENCE
CONSENT AGENDA
Councilor Ziemer entered the motion to approve the consent agenda as presented. Councilor
Schrupp seconded. All members voted in favor.
A. Approve the minutes of the regular meeting of August 6, 2018.
B. Approve the following building permits:
1. Glencoe Multi Family, 2905 14th St E; Plumbing Permit
2. Jim Raiter, 205 Fairway Circle, Rebuild Deck
3. Greg Wedin, 1703 Fairway Dr; Re-side
4. Curtis Templin, 1413 Elm Ave N; Re-roof
5. Paul Jensen, 1311 Armstrong Ave N; Window Replacement
6. Dave Palm, 1707 Louden Ave N; Window Replacement
7. Leif Hoklin, 116 12th St E; Plumbing Permit
8. Rich Westlund, 820 Sumac Lane; Plumbing Permit
9. Adam Jopp, 1120 Newton Ave N; Re-roof
10. Lynn Ackerson, 611 Chestnut St; Re-roof
11. Howard Ackerson, 1811 9th St E; Re-roof
12. Clark Christianson, 310 Wacker Dr; Window Replacement
13. Ron Ernst, 1028 13th St E; Re-roof
C. Approve the following book transfer:
1. $5,850 from General Fund to Tax Inc. #4, Braun Intertec Coding Error in 2016 per
State Auditor’s Office-Jason Nord
PUBLIC HEARINGS: None scheduled.
BIDS AND QUOTES:
A. 14TH STREET EXTENSION BIDS- RESOLUTION NO. 2018-23
John Rodeberg, SEH, presented the bids for the 2018 14th Street Extension Project. The
bids ranged from a high of $294,185.45 to a low of $254,759.71 for Option 1- the 41 foot
wide street. The Engineer’s estimate was $252,381.65 for this option. Option 1 was based
on extending the street at its current width of 41 feet, while option 2 was to transition to a
34 foot roadway width to reduce costs. The savings for the 34 foot width roadway was
nominal.
William Mueller & Sons, Inc. submitted the low bid and it is recommended to accept this
low bid and award it to this contractor.
Councilor Schrupp entered the following resolution and moved for its adoption:
RESOLUTION NO. 2018-23
ACCEPTING BID
WHEREAS, pursuant to an advertisement for bids for the construction of the 2018 14th Street
Extension, bids were received, opened and tabulated according to law, and the following bids
were received complying with the advertisement:
Option 1 Option 2
Contractor Amount Amount
Wm. Mueller & Sons, Inc. $254,759.71 $235,659.56
Hamburg, MN
Land Pride Construction $277,489.30 $244,922.30
Paynesville, MN
R & R Excavating, Inc. $278,545.24 $260,230.80
Hutchinson, MN
OMG Midwest, Inc. (dba Chard) $294,185.45 $271,690.34
Belle Plaine, MN
AND WHEREAS, it appears that Wm. Mueller & Sons, Inc. of Hamburg, Minnesota, is the lowest
responsible bidder,
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF GLENCOE,
MINNESOTA:
1. The mayor and city administrator are hereby authorized and directed to enter into a contract
with Wm. Mueller & Sons, Inc. of Hamburg, Minnesota, Minnesota, in the name of the City
of Glencoe, Minnesota, for the construction of the 2018 14th Street Extension, Option 1
amount only, according to the plans and specification therefore approved by the city council
and on file in the office of the city administrator.
2. The city administrator is hereby authorized and directed to return forthwith to all bidders the
deposits made with their bids, except that the deposits of the successful bidder and the next
lowest bidder shall be retained until a contract has been signed.
Councilor Neid seconded the motion. Upon a roll call vote all members voted in favor.
Whereupon said resolution was adopted and approved.
B. APPROVE PLANS AND SPECIFICATIONS AN SET BID OPENING FOR
WASTE WATER TREATMENT PLANT BY RESOLUTION 2018-24
Jessica Hedin, SEH, presented the plans and specifications for the Waste Water
Treatment Facility project. The plans were provided to the council electronically for
their review.
It was recommended to adopt the resolution to approve the plans and specifications and
to set the bid opening for October 17, 2018 at 10:00 a.m.
Councilor Neid entered the following resolution and moved for its adoption:
RESOLUTION NO. 2018-24
APPROVING PLANS AND SPECIFICATIONS AND
ORDERING ADVERTISEMENT FOR BIDS
WHEREAS, pursuant to a resolution passed by the council on September 5, 2017, the consulting
engineer retained for the purpose has prepared plans and specifications for the construction of the
Glencoe Phosphorus Project, and has presented such plans and specifications to the council for
approval;
NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF GLENCOE,
MINNESOTA:
1. Such plans and specifications, a copy of which is attached hereto and made a part hereof,
are hereby approved.
2. The City Administrator shall prepare and cause to be inserted in the official paper an
advertisement for bids upon the making of such improvement under such approved plans
and specifications. The advertisement shall be published as required by law, shall specify
the work to be done, and shall state that bids will be received by the City Administrator
until 10:00 a.m. on Wednesday, October 17, 2018, at which time they will be publicly
opened in the council chambers of the Glencoe City Hall by the City Administrator and
engineer. Any bidder whose responsibility is questioned during consideration of the bid
will be given an opportunity to address the council on the issue of responsibility. No bids
will be considered unless sealed and filed with the City Administrator and accompanied by
a cashier’s check, bid bond, or certified check payable to the clerk for 5 percent of the
amount of such bid.
Councilor Ziemer seconded. Upon a roll call vote all members voted in favor whereupon said
resolution was adopted and approved.
REQUESTS TO BE HEARD:
A. VARIANCE PERMIT REQUEST PANTHER HEIGHTS 1ST ADDITION
The Planning Commission recommended to approve the variance permit request of Joe
Keller of Team Development, the owner of lots 5-20 of Block 1 of Panther Heights, to
build single family homes on lots designed originally for twin homes. No replat will be
needed for this request for these lots. The Planning Commission approved the request in a
5-0 vote at their last regularly scheduled meeting.
Discussion led to a motion to approve the variance permit request entered by member
Robeck, second by member Ziemer. All members voted in favor.
B. CEMETERY COMMISSION MEMBER APPOINTMENT TO OPEN POSITION
Motion to appoint Paula Bulau to the Cemetery Commission by member Schrupp, second
by member Alexander. All members voted in favor.
C. REQUEST BUFFALO CREEK WATERSHED DISTRICT CONTINUE WITH
NEXT PHASE OF EAST AND CENTRAL WATER MANAGEMENT PROJECT
The City Council will need to formally request that the Buffalo Creek Watershed District
continue with Phase 3 of the East and Central Water Management Plan as presented at
the August 6th council meeting.
Councilor Alexander entered the motion approving the recommendation to continue with
Phase 3 and that Mayor Wilson send a letter to BCWD formally requesting continuing on
with Phase 3. Councilor Neid seconded. All members voted in favor.
ITEMS FOR DISCUSSION:
A. CENTRAL STORM SEWER PROJECT
New schedule for the project has been worked out at a recent contractor’s meeting and
contractor will be pushed to stick to this schedule. St. Pius parking lot will be paved first
week in September.
ROUTINE BUSINESS:
PROJECT UPDATES: Hennepin Avenue Project – railing will be re-installed to
specifications.
ECONOMIC DEVELOPMENT; Construction has begun on the apartment complex in
Panther Heights subdivision.
Oak Leaf Playground ribbon cutting will be at 8:00 a.m. on Tuesday, August 28th.
PUBLIC INPUT: None
REPORTS: None
CITY BILLS; Motion to approve payment of the city bills entered by Councilor Schrupp,
second by Councilor Ziemer. All members voted in favor.
CLOSE MEETING FOR REAL ESTATE DISCUSSION; Motion to close the regular
meeting entered by Member Alexander, second by Member Schrupp. All members voted
in favor.
Motion to re-open the meeting by Councilor Robeck, second by Councilor Schrupp. All
members voted in favor.
ADJOURN: Motion to adjourn by Councilor Robeck, second by Councilor Schrupp. All
members voted in favor.
Get email alerts for Glencoe
A daily email when new agendas and minutes are posted.