Administration Committee
Regular MeetingGrantsburg, WI · January 8, 2024
Minutes
The Village Administration Committee met on Monday, January 8 at 4:30 p.m. in the Village Board room,
316 Brad Street S, Grantsburg, WI 54840.
Present: Chairman/President Terrance Kucera
Trustee Greg Peer
Trustee Hank Java
Others: Clerk/Treasurer Sheila Meyer
DPW John Erickson
Chief Mitch Olson
Kim Hallberg, Nicki & Ben Peterson, Damon Johnson – Grantsburg Watercross
Greg Marsten – Burnett County Sentinel
Brent Blomberg
President Kucera called the Administration Committee Meeting to order at 4:30 p.m. The Pledge of
Allegiance was recited.
Memory Lake Aquatic Management Plan Grant update
The committee chose to move this agenda item later in the meeting until all Watercross members that had
planned to attend were present to discuss.
Water towers
DPW Erickson informed the committee that an inspection was done on the North Water tower in 2023 that
resulted in repair recommendations costing over $400,000. He indicated that the South Water tower required
inspection in 2024 and would like to have that completed prior to moving forward with any recommendations
for the North Water tower in hopes that the projects could be combined if work is also needed on the South
Water tower. The committee discussed that DPW Erickson did not need to approach the committee for
approval for agency required items costing less than the $10,000 threshold. The committee asked to have
DPW Erickson return when repair recommendations are available for both towers to review.
Motion by Trustee Java second by Trustee Peer to approve DPW Erickson to schedule State of
Wisconsin (DNR, DOT, etc) required items without prior Village Board approval. Motion carried.
Memory Lake Aquatic Management Plan Grant update
Clerk/Treasurer Meyer explained the Village received notice from SEH that the DNR grant review board felt
that the application did not fit in the Comprehensive Planning for Lakes and Watersheds category which had
a $25,000 maximum grant award but could fit in the Surface Water Planning category with only a $10,000
maximum grant award. Originally the Watercross group agreed to pay $10,000 towards the project, the Village
agreed to pay SEH to submit the grant and would borrow $10,000 with the grant portion covering the
remaining costs. Now with only $10,000 maximum grant potential, there is a $15,000 deficit that would need
to be covered. SEH verified the Village’s grant application was submitted to the Comprehensive Planning for
Lakes and Watersheds category as directed by Austin Dehn WI DNR regional Water Quality Bureau
specialist, but the grant review board had final say. The Village had the option to pull the grant application or
keep it submitted under the new category, the Village chose to submit under the new category. Any project
costs incurred prior to the grant award would not be eligible for grant coverage. The Watercross group asked
the Village to get bids from other engineering firms for the Aquatic Plant Management Plan and to verify with
SEH what the cost of an update Comprehensive Lake Management plan would be. The group verified that
without this Aquatic Plant Management Plan, mechanical plant cutting and dredging could not be done. The
committee asked Clerk/Treasurer Meyer to check with another firm for prices on lake management plans,
follow up with SEH on the long-term plan and costs, and allowed the Watercross group to work with the Tribe
to relocate the wild rice. The committee will inform the Watercross group as updates become available. No
motions made.
Water Main – State Rd 70 E
DPW Erickson informed the committee that he would like to contact an engineering firm to develop plans
and a cost estimate to replace the watermain on State Rd 70 between Johnson St and Russell St S. DPW
Erickson explained this section of main has had at least one main break each year for the past five years which
is far more than any other main in town. He would like to begin planning now so a project could coincide
with Wisconsin Department of Transportation’s Highway 70 re-surfacing project set for the year 2028. No
motions made.
The meeting was adjourned at 5:08 p.m.
Allison Longhenry
Deputy Clerk/Treasurer
Agenda
Village of Grantsburg
316 South Brad Street
Grantsburg, WI 54840
Administration Committee Meeting
Monday, January 8, 2024 4:30 p.m.
Village Board Room, 316 S. Brad Street
Agenda
The Village Board of Trustees will discuss the following items and may take action as
needed:
1. Call to Order; Roll Call; Pledge of Allegiance
2. Memory Lake Aquatic Management Plan Grant update
3. Water towers
4. Water Main – State Rd 70 E.
5. Adjournment
Sheila Meyer, Clerk/Treasurer
** Appearance times/agenda order may change at the discretion of the Committee Chair**
Posted: January 4, 2024 Village of Grantsburg website www.villageofgrantsburg.gov; Village Office 316 South
Brad Street; Community Center 315 South Robert Street; Grantsburg Public Library 415 S. Robert Street
316 South Brad Street, Grantsburg, WI 54840 715/463-2405 Fax: 715/463-5555
Website: www.villageofgrantsburg.gov Email: office@villageofgrantsburg.gov
Get email alerts for Grantsburg
A daily email when new agendas and minutes are posted.