Special Session of Council
Special MeetingGreenville, PA · August 21, 2006
Minutes
MINUTES OF A SPECIAL MEETING
OF GREENVILLE BOROUGH COUNCIL
HELD IN THE COUNCIL CHAMBERS
ON MONDAY, AUGUST 21, 2006 AT 6:30 P.M.
1. Call to Order – Council President Longiotti called the meeting to order at 6:30 p.m.
2. Roll Call - Pete Longiotti, Council President
David Henderson, Council Vice President
Pamela Auchter, Councilor
Robin Douglas, Councilor
Henry M. Mueller, Councilor
Theodore E. Jones, Councilor
Jasson Urey, Councilor
Richard H. Miller, Mayor
Also present, Ryan T. Eggleston, Borough Manager
3. New Business
a. Streetscape Phase II
The meeting was held to discuss entering an agreement with the Pennsylvania Department
of Transportation for acceptance of the $1,722,600 award of Transportation and
Community System Preservation Program funds. This project was slated for 2008 but a
vote was held by the MPO to move Phase II to 2006. Council President Longiotti
explained that a 20% match would be required by the borough in order to enter into the
agreement with PennDOT. The 20% match figure of $430,650 is based on the total
project cost of $2,153.250.
Don Hall, from the Oil City office of Penn DOT, fielded questions regarding the required
match. He stated the borough was not required to accept the total project amount. He said
that signing the Penn DOT agreement was to agree to the project, a smaller project could
be done for a reduced cost. He also clarified that this funding was project specific and
could not be used for anything else. Council President Longiotti asked Mr. Hall how
much time the borough had to sign the agreement with Penn DOT, he stated he felt up to 6
months but stressed the sooner the better, especially if the project is to continue on this
year. Mr. Hall also said it is legal to NOT re-bid the project when you are making
changes to the work order.
Paul Rosak, EGG, spoke about the Phase II plans stating the original plans for the whole
project were from Water Street to South Mercer Street. When the project was scaled
back, the area included South Mercer Street to the RR tracks. He stated there would be
some work to re-package the design for Phase II, he would need to take a thorough look at
it.
1
John Rusnak, HRG Engineering, suggested a meeting with “key people” at the Oil City
Penn DOT office, after the Labor Day holiday would be most productive to establish an
exact cost and discuss different scenarios for this project. It was agreed this meeting
could be held at the Greenville Borough office.
John Combine, general contractor, briefly spoke. He stated his crew would be
“demobilizing” in approximately 4 to 5 weeks. Mr. Combine stressed there will be price
increases next year. He confirmed the proposed project from the RR tracks to the west
side of the borough building is 506 feet.
President Longiotti confirmed the borough can only match a total project cost of
$1,250,000 with the 20% match being $250,000.
No action was taken at this meeting.
4. Adjournment
Councilor Jones moved, seconded by Councilor Mueller, to adjourn the meeting. The
council then went into an executive session.
Respectfully submitted,
Ryan T. Eggleston
Borough Secretary