Planning Commission Agendas & Minutes
Regular MeetingHampton, VA · July 9, 2015
Minutes
AT THE WORK SESSION OF THE HAMPTON PLANNING COMMISSION HELD IN THE LAWSON
CONFERENCE ROOM, 8TH FLOOR, CITY HALL, HAMPTON, VIRGINIA, ON THURSDAY, JULY 9,
2015, AT 3: 00 P. M.
Commissioners Tommy Southall, Gregory Williams, Teresa Schmidt, Vice -Chair
Andre McCloud, and Chairman Gaynette LaRue were present. Commissioners Carlton
Campbell and Mary Bunting were absent.
Chairman Gaynette LaRue opened the floor for discussion of the agenda items.
Secretary to the Commission Terry O' Neill stated two items on the agenda are
different from what is normally done: 1) Planning Commission Action No. 15 -00001 for
the construction of a pump station at 515 Bridge Street is required by the Ordinance to
come before the Commission for a review of the location and its impact. This Planning
Commission Action will have a staff report and there will be discussion, but it is not
required to go before the City Council; and 2) under New Business is the Planning
Commission Bylaws Amendment, read at the June Planning Commission meeting,
which will be immediately adopted if the Commission concurs with the changes.
Chairman Gaynette LaRue asked Vice -Chair Andre McCloud to chair the July
meeting as she was experiencing some vision issues.
Mr. O' Neill stated two of the public hearing items are related and
recommended they be heard concurrently with a separate action taken on each ( RZ
15 -00001 and UP 15- 00001).
Discussion was held on the Use Permit request for Hampton University ( Use Permit
Application 15- 00010) and that zoning regulations apply to it because it is a private
university. The campus predates the Zoning Ordinance and is not covered under one
Use Permit. Each time a new building is added a new Use Permit is required. Hampton
University has been approached about considering the adoption of a College and
University District designation to put the University under one Use Permit.
The Rezoning and Use Permit applications ( UP 15 -00001 and RZ 15 -0001) by Todd
Center, LLC for an E- Commerce Center are being requested by a different applicant
than a previously requested application for a near -by location. Mr. O' Neill explained
the current request is across the street from the former request and is not going into a
residential district.
City Planner Tolu Ibikunle stated the applicant had an independent traffic study
done on this location and a letter of support has been received from the Coliseum
Central Business Improvement District.
In response to questions regarding the pump station, City Planner Matt Smith
stated the building is larger than the one it will replace and measures have been taken
to handle odors and noise. The new station will handle a larger capacity than the
current station. Letters were received from residents concerned about the pump station
blocking the river view, but the site plan accommodates Downtown Master Plan
requirements and maintains the site corridor to the river. The proposed direction of the
building on the lot takes up less property frontage.
PC Worksession 20150709 Page 1
Senior Assistant City Attorney Bonnie Brown stated that it is for the Commissioners
to determine if this pump station request is consistent with the Master Plan.
In response to a question from Chairman LaRue, Mr. Smith stated the visual link
between the river and the neighborhood will be maintained and a walkway around
the water is still a possibility.
Mr. O' Neill explained that it is hard to answer questions about the walkway at this
time because it would depend on property acquisition. The focus at this time is on the
downtown waterfront. The pump station is required and there are EPA requirements for
HRSD and all communities. In order to meet the Federal law regulations the older
stations must be taken offline and replaced with newer and better stations.
In response to a question from Commissioner Southall, Senior Zoning Official
David Stromberg stated it is his belief the piers on the property are to be removed as
part of the site plan for the pump station.
There being no further business, the meeting was adjourned at 3: 26 p.m.
PC Worksession 20150709 Page 2
AT A PUBLIC HEARING AND REGULAR MEETING OF THE HAMPTON PLANNING
COMMISSION HELD IN THE COUNCIL CHAMBERS, 81H FLOOR, CITY HALL, HAMPTON,
VIRGINIA, ON THURSDAY, JULY 9, 2015 AT 3: 30 P. M.
I. CALL TO ORDER
Chairman Gaynette LaRue called the Planning Commission meeting to order.
Due to an issue with her vision, the Chairman turned the meeting over to Vice -Chair
Andre McCloud.
II. ROLL CALL
A call of the roll noted Commissioners Tommy Southall, Gregory Williams, Teresa
Schmidt, Vice -Chair Andre McCloud, and Chairman Gaynette LaRue were present.
Commissioner Carlton Campbell was absent. Commissioner Mary Bunting arrived at
3:58 p. m.
III. MINUTES
A motion was made by Commissioner Gregory Williams, seconded by
Commissioner Tommy Southall, to approve the minutes of the June 4, 2015 work session
and Planning Commission meeting. A roll call vote on the motion resulted as follows:
AYES: Southall, Williams, Schmidt, McCloud, LaRue
NAYS: None
ABST: None
ABSENT: Campbell, Bunting
IV PLANNING COMMISSION ACTION
A. Planning Commission Action No. 15- 00001: by HDR Engineering, Inc. to allow for
the construction of a pump station at 515 Bridge Street.
Secretary to the Commission Terry O' Neill reminded the Commissioners that the
City of Hampton Zoning Ordinance requires public utilities to come before the Planning
Commission for review to ensure they are in compliance with the Hampton Community
Plan ( 2006, as amended) to allow for evaluation and assessment of the potential
impact to surrounding property owners. This is not a public hearing item and therefore
the Commission is not required to entertain any public comment. If there is any public
comment it is done at the discretion of the Commission.
City Planner Matt Smith presented Planning Commission Action No. 15 -00001 by
HDR Engineering, Inc. to allow for the construction of a pump station at 515 Bridge
Street in the Victoria Boulevard neighborhood.
The Hampton Roads Sanitation District ( HRSD) owns and operates the Bridge
Street Pump Station ( BSPS) located at 4701 Victoria Boulevard. The BSPS was originally
placed into service in 1945 and has surpassed its designed service life. This application is
PCMinu[ es 20150709 Page 1
for the construction of a replacement pump station at 515 Bridge Street. Public utility
facilities are a permitted use in the DT -2 District subject to approval by the Planning
Commission.
The Hampton Community Plan ( 2006, as amended) provides policies calling for
well- designed public facilities that support growth, provide continuity of service, and
minimize negative environmental impacts. The proposed pump station supports these
policies set forth in the Community Plan. The current pump station is undersized and
does not meet current needs.
The appearance of the proposed pump station was designed to complement
the surrounding community. Its increased capacity will eliminate sanitary sewer
overflows. Operation of the pump station will be automated, requiring only periodic
maintenance and operational visits by HRSD staff. A continuously running two -stage
odor control system will be provided to minimize odors associated with the collection of
wastewater. The major mechanical equipment will be located inside the building and
will not contribute noise pollution to the surrounding area.
The applicant held a community meeting on April 21, 2015 at the Hampton
Yacht Club and approximately 25 members of the public attended; comments were
generally positive. Two letters with concerns regarding the pump station' s location
have been received since that meeting.
Staff recommends approval of Planning Commission Action No. 15- 00001.
In response to questions from Chairman LaRue and Commissioner Schmidt, Mr.
Smith stated plans show that a view corridor will be maintained to the river from Marrow
Street. The portion of the building in question will house the auxiliary generator. The
Yacht Club still owns the back portion of the property behind the proposed pump
station.
Rosalind Allen, 50 Linden Avenue, stated she lives on the corner of Linden
Avenue and Bridge Street. When sitting on her front porch one would not know she lives
across the street from the water, as it looks like she lives across the street from a junk
parking lot. The only view she and her next door neighbors have of the river is from the
backs of their homes. Her neighbor, Carolyn Cox, who was unable to be at this
meeting, submitted a letter requesting the pump station be moved slightly north which
would give a more expansive view of the water as opposed to two very narrow views.
The argument was that the water view needed to be preserved at the end of Marrow
Street, but that does not respect the only water view from Linden Avenue which is from
the back side of their homes. With the limited water view in that area they are
requesting the proposed structure be moved only slightly to the north.
Chairman LaRue stated it is her belief that the reason behind the location of the
structure on the lot was an effort to preserve the view from both Linden Avenue and
Marrow Street as one heads toward the water. There have been other proposals before
the Planning Commission and City Council that would have obstructed the views even
PCMinutes 20150709
Page 2
more than this proposed structure. A lot of things need to be considered in deliberation
and Ms. Allen' s concerns will be considered.
In response to a question from Commissioner Williams, Santino Granado, project
manager for Hampton Roads Sanitation District ( HRSD), 102 Burgundy Road,
Williamsburg ( home address) and 2389 G Avenue, Newport News ( business address),
replied that it would not be a problem to move the structure slightly north but the
building was placed in this location on the site plan in such a way as to not obstruct the
view from Marrow Street in accordance with the City' s plan. There is a view -shed that
comes off Marrow Street to the waterfront in accordance with the City of Hampton' s
development plans so that the building would not obstruct the view from Marrow Street
in any way.
Mr. O' Neill stated that it is identified in the Downtown Master Plan to try to
preserve the view corridors down each of the streets as a recommendation to preserve
those views as much as possible. Some of the views were already obstructed prior to
the Downtown Master Plan recommendation. This is an opportunity to work with HRSD
on the property. A previous proposal was a multi -family project that would have
occupied the entire frontage of the property so the Marrow Street view as well as other
views would have been gone. The Commissioners are in a tough position as there are
rarely perfect solutions to issues such as this one, but a reminder is that the action is up
to the Commissioners to judge how much this request is in compliance with the Plan
and that the Plan does identify the Marrow Street corridor view. HRSD has situated the
building to preserve that corridor view. The building originally was proposed to be
located further north but HRSD moved it to comply with the Downtown Master Plan.
Sr. Assistant City Attorney Bonnie Brown clarified that this action is not forwarded
to the City Council; it is only a Planning Commission action and the Planning
Commission is the last stop.
Commissioner Tommy Southall stated decisions are always difficult when
waterfront property and construction on waterfront property are dealt with. It is never
easy to please everyone. The Downtown Master Plan gives guidelines to these items
and as Commissioners they are charged to relate these issues to land use and
recognize current plans and guidelines. The applicant has worked with staff in trying to
accommodate the Downtown Master Plan by repositioning the building on the
property.
After discussion, the Commission approved the following resolution:
WHEREAS: the Hampton Planning Commission has before it this day a proposal by
HDR Engineering, Inc. and the Hampton Roads Sanitation District to
construct a sanitary sewer pump station at 515 Bridge Street ( LRSN
13004162);
WHEREAS: the proposed pump station will replace an existing pump station at
4701 Victoria Boulevard, which has surpassed its designed service life;
PCMIMAcs 20150709 Page 3
WHEREAS: the property is zoned Downtown Waterfront ( DT -2) District, which
allows public utility facilities subject to approval of the Planning
Commission;
WHEREAS: the Hampton Community Plan ( 2006, as amended) provides policies
calling for well- designed public facilities that support growth, provide
continuity of service, and minimize negative environmental impacts;
WHEREAS:
the Downtown Master Plan ( 2004, as amended) calls for maintaining
visual access to the water along specified view corridors;
WHEREAS: one member of the public spoke against the proposed location of the
pump station; and
WHEREAS: Planning staff recommends approval of this application.
NOW, THEREFORE, on a motion by Commissioner Tommy Southall and seconded by
Commissioner Teresa Schmidt,
BE IT RESOLVED that the Hampton Planning Commission approves Planning
Commission Action No. 15- 00001.
A roll call vote on the motion resulted as follows:
AYES: Southall, Williams, McCloud, Schmidt, LaRue
NAYS: None
ABST: None
ABSENT:
Campbell, Bunting
PUBLIC HEARING PROCEDURES
Mr. Terry O' Neill, Secretary to the Commission, read key points of the Hampton
Planning Commission Public Hearing /Comment Rules in order for the affairs of the
Commission to be conducted in a courteous and orderly manner.
V. PUBLIC HEARING ITEMS
A. Rezoning Application No. 15- 00001: by Todd Center, L. L. C., c/ o Tower Park
Corporation to rezone 3. 13+ acres at 1700 Todds Lane [ LRSN 30039041 and a
portion of LRSN 3003903 from Limited Commercial ( C -2) District to General
Commercial ( C -3) District with proffers, to facilitate the establishment of a mixed -
use development to include: office, retail, and self- storage to create an e-
commerce center. These properties are located at the edge of and within the
Coliseum Central Overlay ( 0-CC) District. This application accompanies Use
Permit Application No. 15 -00001 for the storage component of the proposal.
Approval of this application and the accompanying use permit application
would permit a combination of office, retail, and storage uses fully contained in
an enclosed building. The Hampton Community Plan ( 2006, as amended)
P( M{ nutes 20150709
N, ge n
recommends mixed -use development for this area. The Coliseum Central Master
Plan ( 2004) recommends mixed -use nodes, improved pedestrian connectivity
within shopping centers such as this one, and connections to the district.
B. Use Permit Acollcation No. 15- 00001: by Todd Center, L. L. C., c/ o Tower Park
Corporation to operate the self-storage component of the proposed mixed -use
development to include office, retail, and self- storage for the establishment of an
e- commerce center. The properties are located at 1700 Todds Lane [ LRSN
3003904] and a portion of LRSN 3003903. These properties are located at the
edge of and within the Coliseum Central Overlay (O -CC) District. This application
accompanies Rezoning Application No. 15 -00001 for all three proposed uses.
Approval of this application and the accompanying Rezoning Application No. 15-
00001 would permit a combination of office, retail, and self- storage uses fully
contained in an enclosed new building. The Hampton Community Plan ( 2006, as
amended) recommends mixed -use development for this area. The Coliseum
Central Master Plan ( 2004) recommends mixed -use nodes, improved pedestrian
connectivity within shopping centers such as this one, and connections to the
district.
City Planner Tolu Ibikunle presented Rezoning No. 15 -00001 and Use Permit
Application No. 15 -00001 by Todd Center, L. L.C., c/ o Tower Park Corporation to rezone
3. 13± acres at 1700 Todds Lane and a portion of LRSN 3003903 from Limited
Commercial ( C -2) District to General Commercial ( C -3) District with proffers, to
facilitate the establishment of a mixed -use development to include: office, retail, and
self- storage to create an e- commerce center and to also allow the operation of a self -
storage component for the establishment in one fully contained building. An e-
commerce center allows business owners within the internet retail industry a one -stop
shop to conduct their operation. Mixed -use is defined as development of two or more
compatible land uses within one parcel, one building structure, or on the same block.
The rezoning application is being brought forward with Use Permit Application
No. 15 -00001 to permit the self- storage component of this proposal. The Hampton
Zoning Ordinance permits office and retail uses in the current C -2 zoning district by
right, however, self- storage requires a rezoning to C -3 and also requires a use permit.
The properties are located in the western part of the city at the edge of the
Coliseum Centeral District and specifically in the Todds Center Shopping Center. To the
north of the subject property is Bethel Temple Church; east of the site is a strip of
commercial uses - Big Lots and Good Wood Furniture; south are properties that include
office and residential uses; and to the west is a vacant lot and other residential and
office uses. If the applications are approved the properties will become one single
parcel.
The site is currently zoned C -2 ( Limited Commercial District) and is covered by
the Coliseum Central Overlay District ( OCC). Some of the surrounding properties are
zoned C -2 ( Limited Commercial District) and R -11 ( Single Family Residential) with a few
properties zoned C -1 ( Neighborhood Commercial). The future land use plan calls for
mixed -use development for the subject property and the surrounding area.
Page 5
PCMfnutes 20150709
As part of the rezoning application the applicant has proffered eleven
conditions with other standard conditions attached to ensure quality development.
These proffers include: adherence to the site plan review process; stormwater; and
other City codes and ordinances. There is a subdivision clause in the proffer agreement
to ensure the two parcels become one. The proposed development must be in
substantial conformance with the conceptual site plan which includes the landscape
buffer and an enhanced sidewalk. Building materials have also been proffered. The
proposed building is three stories high with retail, self- storage, and office space. All
three uses will work in tandem together. The self- storage component cannot be any
larger than 75 percent of the total building square footage to ensure a true mixed -use.
As part of the accompanying use permit application for the self- storage
component, there are five conditions that ensure the proposed land use action is
executed properly; these conditions include: a non -transferable clause; surveillance;
compliance to applicable laws; nullification; and a revocation clause.
There are several City policies that support this proposal. This propsal exempliflies
a true mixed -use development because it ensures that the office, self- storage, and
retail will all work in tandem together. Another City policy encourages strengthening
older commercial areas such as the Todd Center Shopping Center. The applicant has
made a great effort to add additional retail options which will continue the longevitiy of
this shopping center. If approved this structure could serve as a small business incubator
and be a facility to nurture and provide support services for small businesses like office
space and self- storage for multiple small businesses.
The subject properties are within the Coliseum Central Master Plan ( 2004, as
amended) and specifically within the Power Plant Initiative Area. The Coliseum Central
Master Plan encourages mixed -use development; pedestrian connectivity; and
exploring innovative ways to maintain competitive edge. There is a clear alignment
with what the City' s plans reflect, as well as what this proposal is trying to achieve. This
proposal is a mixed -use development which meets the policies and future land use
goals described in the Hampton Community Plan ( 2006, as amended) and Coliseum
Central Master Plan ( 2004, as amended).
The applicant held a community meeting on April 13, 2015 at the Sentara
Careplex. No one from the community was in attendance.
Staff recommends approval of Rezoning Application No. 15 -00001 with 11
proffered conditions and Use Permit No. 15 -00001 with five conditions.
Raymond Suttle, Jr., Attorney with Blechman, Woltz and Kelly, 701 Town Center
Drive, Newport News, and Bobby Freeman, the developer and principal of Todd Center
came before the Commission.
Mr. Suttle stated he would like to thank those on the Planning staff and City
Attorney' s staff who have helped with this process.
PCMinutes 20150709
Page 6
Mr. Suttle explained that as stated in the staff report the reason for the rezoning
of the property is because of the self-storage component of this mixed -use
development. Everything else required has been complied with and a traffic impact
study was done with no significant impact to occur with this development. The
Coliseum Central Business Improvement District ( CCBID) submitted a favorable
recommendation.
Two important things from the staff report are that this proposal creates a mixed -
use with a different dynamic from anything else in Hampton Roads and it is consistent
with the Master Plan.
Bobby Freeman, president of Tower Park Corporation and this particular property
stated he and Mr. Suttle met with staff months ago and he would also like to thank the
staff. An unusual concept was thrown out to the Planning staff and they embraced it,
asked a lot of questions, and asked a lot of the right questions to get this project where
it is today. Mr. Freeman asked those present how many of them had bought something
on the internet in the past week. If this question had been asked ten years ago one
might have asked " what is that Internet thing ?" Internet sales have grown 20% a year
for the last five years and that is increasing by a higher percentage every year. The old
dynamic of goods being purchased from brick and mortar stores is dramatically
changing. That does not mean the stores are going away it just means buying and
buying decisions are being done in a different way. The real estate supporting this
structure is about to change. An example given was buying first edition books and that
the old charming bookstores no longer exist. These stores now live on the internet. At
the other end of buying on the internet has someone accepting an order. That seller
may be at home in his pajamas, at an office, or desk in his den. This person needs a
place to store his inventory: i. e. garage, storage unit, or somewhere else. Over 50% of
Amazon sellers and most of the people selling on line are not huge companies, they are
mom & pop" services. These people need someplace to work, store their goods, and
a way to ship those goods. What this proposal does is a new idea for real estate. It has
taken one piece of real estate and rolled these three things into one building. An
internet seller could sit in one of the applicant' s offices, click on the computer to take
an order, walk downstairs to pick up the inventory out of storage, and then walk
downstairs again to take it to the shipping place. Each process is still independent. A
person driving down Todds Lane could just pull in, park, and go to the UPS location.
One could just rent office space and not use any other service. One living in the
neighborhood could just want to store their items. The applicant is betting that after
paying rent for the storage and not touching it, this person will want to sell their " stuff ".
Another of the applicant' s components is that there will be an eBay sales center
where, for a fee, pictures will be taken, the item( s) placed on line, and sold for this
person. It is the applicant' s belief that their proposal is a response to the people,
whether an occasional seller or a full time seller. This proposal contains small offices -
300 to 500 square feet - with leases that can be as short as 30 days or extend for years.
This time of technology changes faster than one can keep up with and the applicant
has tried to develop a business model that anticipates what the e- sellers need and look
at the broader community for the different component parts with hope that the seller
will continue to use and overlap one, two, or three of these pieces of the puzzle.
PCMlnutes 20150709 Page 7
The belief is that this is a tremendous incubator business opportunity and they will
be marketing to those people who currently sit at home in their pajamas, getting in their
car to get their product out of their storage space, and then going to a shipping
location. The idea is to bring these people to this building and help them grow. Mr.
Freeman stated he knows of no other product like this in the State of Virginia and it is his
belief that this concept will attract people from and market to people all over Hampton
Roads.
In response to a question from Commissioner Southall, Mr. Freeman stated it is his
belief it will take four to six months to finalize plans and then about a year to build.
In response to a question from Chairman LaRue, Mr. Freeman stated the building
is approximately 90,000± square feet. The finished space is 50,000 square feet of
storage, 20,000± square feet of office space, and the eBay and retail areas are about
2,500 square feet. Seventy -five percent of the building is storage and 25 percent is
office.
David Duxbury, 907 Thames Drive, stated the rezoning of the property was the
reason behind his concerns. His questions about resident' s concerns have been
answered. His other question was about removal of the fuel tanks and the property
being brought back to EPA standards.
In response to a question from Vice -Chair McCloud, Ms. Ibikunle stated that a
community meeting had been held and no one from the community attended even
though notification had been sent out to the surrounding properties.
Commissioner Bunting stated the location of the previous request for a self -
storage facility was on the opposite side of the intersection which was literally adjacent
to homes which is somewhat different from this requested location. Those residents who
spoke at the prior hearing were adjacent to that particular location.
Ms. Ibikunle stated the previous site in question that had opposition to its request
had a different property owner, a different applicant, and was a different site from this
current application and location. The only residential property adjacent to this current
location is Bethel Temple Church. Bethel Temple was notified of this hearing and had no
comments.
In response to a question from Commissioner Williams, Ms. Ibikunle stated any
environmental issues will be addressed during the site plan process. The site plan
process will not begin until after this application goes before City Council and is
approved.
Mr. Freeman stated all the tanks would have to be removed and the soil
sampled, but that is part of the process in taking the property back to its original state.
Commissioner Bunting stated this project is very exciting and she applauds Mr.
Freeman for the innovative thinking and wanted to publicly thank him. This particular
PCMinutes 20150709
Page 8
concept makes so much sense in how shopping is going and puts Hampton in the
forefront of something very exciting. The building does not scream storage and looks
like an office building. The integration of the storage, the eBay center, and the shipping
is something to be really proud of and she is glad Mr. Freeman is looking to invest in
Hampton.
City of Hampton Traffic Engineer Marty Wilson responded to Commissioner
McCloud' s question that any traffic issues that may be the result of the building being
located on a corner lot will be addressed during the site plan process.
Mr. O' Neill stated the site plan process will have requirements for this site and
some of the traffic dynamics might actually improve because the ingress and egress will
be placed further back from the intersection.
Mr. Freeman responded to a question from Commissioner Schmidt that there will
be access to the project from both sides of the intersection.
After discussion, the Commission approved the following resolutions:
Rezoning Application No. 15 -00001
WHEREAS: by Todd Center, L. L. C., c/ o Tower Park Corporation to rezone 3. 13±
acres at 1700 Todds Lane [ LRSN 3003904] and a portion of LRSN
3003903 from Limited Commercial ( C -2) District to General
Commercial ( C -3) District with proffers, to facilitate the
establishment of a mixed -use development to include: office, retail,
and self- storage to create an e- commerce center;
WHEREAS: The rezoning application is being brought forward in conjunction
with Use Permit Application 15 -00001 to permit the self- storage
component of this proposal. In the Hampton Zoning Ordinance,
office and retail are permitted by -right in C -2; however, self- storage
is not, thus requiring the rezoning to C -3 and approval of a use
permit. As a result, the two applications are tied together and the
decisions on both the rezoning and use permit applications, while
independent in vote, should reflect each other;
WHEREAS: approval of this application and the accompanying use permit
application would permit a combination of office, retail, and
storage uses fully contained in an enclosed building. The Hampton
Community Plan ( 2006, as amended) recommends mixed -use
development for this area. The Coliseum Central Master Plan ( 2004)
recommends mixed -use nodes, improved pedestrian connectivity
within shopping centers such as this one, and connections to the
district. The mixed use category encourages developments of two
or more compatible land uses, such as live /work, retail /office,
residential /retail, tourist attractions /community facilities, and light
industrial /residential as the primary uses within one parcel, building
PCMlnutes 20150709 Page 9
structure, or the same block. In this area of Coliseum Central it
means combining land uses compatible in character and scale of
development;
WHEREAS:
A rezoning to General Commercial [ C -3] District solely for the
establishment of a self- storage facility would allow for a land use in
this particular area of the city not supported by the Hampton
Community Plan ( 2006, as amended); however, this proposal is a
mixed -use development which meets the policies and future land
use goals described in the Community Plan and Coliseum Central
Master Plan, ( 2004, as amended).
WHEREAS:
there are eleven ( 11) proffered conditions attached to this rezoning
that, among other things, limit the site to the three proposed uses:
office, retail, and storage uses. To achieve a true mixed -use
development, the applicant has proffered a condition that limits
the self- storage to no more than 75% of the building' s area. Other
proffered conditions include: combining the two subject properties
into one single parcel, building elevations or drawings that achieve
the highest quality architectural standards, a landscaped buffer,
and other standard conditions to ensure quality development of
the proposal;
WHEREAS:
there was one member from the public who spoke. The individual
had questions pertaining to the proposal and did not speak in
support or opposition of the applications;
WHEREAS:
Planning staff recommends approval of this use permit application.
NOW, THEREFORE, on a motion by Commissioner Teresa Schmidt and seconded
by, Commissioner Gaynette LaRue;
BE IT RESOLVED that the Hampton Planning Commission approves Rezoning
Application No. 15 -00001 with eleven ( 11) conditions.
A roll call vote on the motion resulted as follows:
AYES:
Southall, Williams, McCloud, Schmidt, Bunting, LaRue
NAYS: None
ABST: None
ABSENT: Campbell
Use Permit Application No. 15- 000001
WHEREAS: by Todd Center, L. L. C., c/ o Tower Park Corporation to operate the
self- storage component of the proposed mixed -use development
to include office, retail, and self-storage for the establishment of an
e- commerce center. The properties are located at 1700 Todds
PCMmutes 20150709
Page 10
Lane [ LRSN 3003904] and a portion of LRSN 3003903. These
properties are located at the edge of and within the Coliseum
Central Overlay (O -CC) District;
WHEREAS: This use permit application accompanies Rezoning Application No.
15 -00001 for all three proposed uses. Approval of this use permit
application and the accompanying Rezoning Application No. 15-
00001 would permit a combination of office, retail, and self- storage
uses fully contained in an enclosed new building. In the Hampton
Zoning Ordinance, office and retail are permitted by -right in C -2;
however, self- storage is not, thus requiring the rezoning to C -3 and
approval of a use permit. As a result, the two applications are tied
together and the decisions on both the rezoning and use permit
applications, while independent in vote, should reflect each other;
WHEREAS: The Hampton Community Plan ( 2006, as amended) recommends
mixed -use development for this area. The Coliseum Central Master
Plan ( 2004) recommends mixed -use nodes, improved pedestrian
connectivity within shopping centers such as this one, and
connections to the district. The mixed use category encourages
developments of two or more compatible land uses, such as
live /work, retail /office, residential /retail, tourist
attractions /community facilities, and light industrial /residential as
the primary uses within one parcel, building structure, or the some
block. In this area of Coliseum Central it means combining land
uses compatible in character and scale of development;
WHEREAS: there are five ( 5) conditions attached to this use permit application
for self-storage. The conditions ensure the use permit only applies to
the subject properties and cannot be transferred to another site,
the safety and welfare of patrons by requiring surveillance
cameras, compliance of all applicable laws, and other standard
conditions to ensure adherence to all of the use permit
requirements;
WHEREAS: there was one member from the public who spoke. The individual
had questions pertaining to the proposal and did not speak in
support or opposition of the applications;
WHEREAS: Planning staff recommends approval of this use permit application.
NOW, THEREFORE, on a motion by Commissioner Teresa Schmidt and seconded
by, Commissioner Gaynette LaRue;
BE IT RESOLVED that the Hampton Planning Commission approves Use Permit
Application No. 15 -00001 with five ( 5) conditions.
A roll call vote on the motion resulted as follows:
PCMinutes 20150709 Page 11
AYES:
Southall, Williams, McCloud, Schmidt, Bunting, LaRue
NAYS: None
ABST: None
ABSENT: Campbell
C. Rezoning Application No. 15- 00002: by Shervonne Banks to rezone . 2+ acre at
1204 E. Pembroke Ave. ( LRSN 12000782) from General Commercial ( C -3) District to
Neighborhood Commercial ( C -1) District without proffered conditions to operate
a respite care facility. The Hampton Community Plan ( 2006, as amended)
recommends commercial use for this area.
City Planner Matt Smith presented Rezoning Application No. 15 -00002 by
Shervonne Banks to rezone . 2+ acre at 1204 E. Pembroke Avenue from General
Commercial (C -3) District to Neighborhood Commercial ( C -1) District without proffered
conditions to operate a respite care facility.
The applicant is requesting a rezoning from C -3 to C -1 to operate a respite care
facility in a vacant medical office building near the corner of E. Pembroke Avenue and
E. Mercury Boulevard. The facility will offer services such as meals, medication
management, supervision, and transportation on a short-term basis to ambulatory
adults.
This request is for a rezoning without proffered conditions. While the applicant is
proposing to operate a respite care facility, approval of this rezoning application would
allow any use permitted in the C -1 District on this site.
The Hampton Community Plan ( 2006, as amended) recommends commercial
use for the site. The Community Plan also provides policies promoting compatibility
among different land uses, evaluation of land use proposals from the neighborhood
perspective, protection of existing residential neighborhoods, and support for small
businesses.
In evaluating the proposal, staff felt that applying the C -1 District to this parcel
not only met the needs of the applicant, but also supported the objectives and policies
of the Community Plan better than the current C -3 zoning. Uses allowed in the C -1
District are considered neighborhood- serving and are generally more compatible with
nearby residences than the more intense uses allowed in the C -3 District.
A community meeting was held on May 27, 2015 and no one from the public
attended.
Staff recommends approval of Rezoning Application No. 15 -00002.
Shervonne Banks, 274 Mockingbird Lane, stated she is a professional
gerontologist who lives in Hampton, went to Hampton University, and worked as a
community advocate for adult protective services at Hampton Social Services for seven
years.
PCMinutes 20150709 Page 12
As a community resident in the city of Hampton she noticed when she had to be
a caregiver there were not a lot of quality options offered in the city of Hampton for
caregivers who could have caregiver stress or burnout. A lot of facilities within the
jurisdiction have a lot of different caveats for those caregivers who would like to have
time for themselves for a day or two, or even seven days. It was difficult for Ms. Banks
during the six years she helped take care of her mother.
One of the things Ms. Banks thought about was to find a prime location where
individuals could take a loved one to receive quality care from licensed professional
nurses under the standards of VDSS ( Virginia Department of Social Services), and be fed
while under care.
Ms. Banks stated she has 9+ years in geriatrics and currently runs an adult day
care center in another jurisdiction that has 150 participants. She is trying to bring an
upscale respite home to Hampton where caregivers can bring their loved ones for a
short term break. Respite is short term care and people can drop their loved ones off for
a few hours or up to seven days to allow for a few hours break for themselves.
Any accommodations that the building may need will be done. Along with the
installation of a fire suppression system, a " wander guard" system has been installed to
deter those who may wander off. The building is being upgraded and safety is a
number one priority.
In response to a question from Commissioner Williams, Ms. Banks stated the
system being put in place is a " wander guard" system by BADA and it is placed on the
entrances and exits to prevent residents from leaving the premises unattended. The
residents will have an electronic device on their person during their temporary stay and
the doors at the entrances and exits will automatically lock if the person wanders
toward those exits. This particular building is considered a micro -community so there are
no more than three people needing care at any one time to allow for one -on -one
attention.
In response to questions from Commissioner Southall, Ms. Banks stated that
patients may come to the facility for two hours to 7 days and that there will be only
three patients at one time.
In response to a question from Commissioner Schmidt, Ms. Banks stated they are
licensed by the Virginia Department of Health for personal care and employ 18
individuals on staff and four of those are registered nurses. They will also go to an
individual' s home.
In response to a question from Vice -Chair McCloud, Mr. O' Neill stated this
request is to downzone the property from C -3 ( General Commercial) to C -1
Neighborhood Commercial) which is probably a better fit with the neighborhood.
Mr. Smith replied further to Vice -Chair McCloud' s question that the subject
property has C -3 properties to the east and residential properties to the west, but in
evaluating the proposal it was found that this is a better and more compatible use with
PCMinutes 20150709 Page 13
the residential zoning. The C -3 district does allow for heavier commercial uses, but that is
not what those sites are currently being used for.
Mr. O' Neill stated during the Phoebus Master Plan update this was one of the C -3
areas along with areas in Phoebus that were identified and questioned. Given the
modern uses out there the question posed was if the C -3 zoning along this portion of E.
Mercury Boulevard was appropriate.
This is something to be looked into and any observations and recommendations
would be brought back to the Commission as a comprehensive rezoning at a later
date.
There were no speakers from the public.
After discussion, the Commission approved the following resolution:
WHEREAS:
the Hampton Planning Commission has before it this day a
proposal by Shervonne Banks to rezone . 2+ acre at 1204 E.
Pembroke Avenue ( LRSN 12000782) from General Commercial ( C-
3) District to Neighborhood Commercial ( C -1) District without
proffered conditions;
WHEREAS: Shervonne Banks intends to operate a respite care facility on this
site;
WHEREAS: the Hampton Community Plan ( 2006, as amended) recommends
commercial use for the site, and also provides policies promoting
compatibility among different land uses, evaluation of land use
proposals from the neighborhood perspective, protection of
existing residential neighborhoods, and support for small businesses;
WHEREAS: no one from the public spoke for or against this proposal; and
WHEREAS: Planning staff recommends approval of this application.
NOW, THEREFORE, on a motion by Commissioner Gaynette LaRue and seconded
by Commissioner Gregory Williams,
BE IT RESOLVED that the Hampton Planning Commission recommends to City
Council approval of Rezoning Application No. 15 -00002 without
proffered conditions.
A roll call vote on the motion resulted as follows:
AYES:
Southall, Williams, McCloud, Schmidt, Bunting, LaRue
NAYS: None
ABST: None
ABSENT: Campbell
PCMinutes 20150709 Page 14
D. Use Permit Application No. 15- 00010:
by Hampton University to operate a
university facility, specifically a student resource center, at 65 Marshall Avenue,
which is defined as the portion of the Hampton University main campus ( LRSN
12001034) beginning on the south side of Marshall Avenue beginning at the
northwest corner of the Hampton National Cemetery ( LRSN 12001094) extending
southwest along Marshall Avenue 135' to the intersection of Marshall Avenue and
Orchard Road, then south -southeast along the east side of Orchard Road 85',
then east -northeast 145' to the property line, then 130' north -northwest, returning
to the starting point on Marshall Avenue. The property is zoned One Family
Residence ( R - 13) District, which permits universities with an approved use permit.
The Hampton Community Plan ( 2006, as amended) recommends public /semi-
public land use for this area.
Chief Planner Michael Hayes presented Use Permit Application No. 15 -00010 by
Hampton University to operate a university facility, specifically a student resource
center, at 65 Marshall Avenue, which is defined as the portion of the Hampton University
main campus beginning on the south side of Marshall Avenue at the northwest corner
of the Hampton National Cemetery extending southwest along Marshall Avenue 135' to
the intersection of Marshall Avenue and Orchard Road, then south -southwest along the
east side of Orchard Road 85', the east -northeast 145' to the property line, then 130'
north -northwest, returning to the starting point on Marshall Avenue.
This is a request to construct a new building that would contain a computer lab,
an auditorium classroom, and offices in support of tutorial services at Hampton
University. The University is referring to this endeavor as a student success center and
wishes to locate it on the main campus.
The property is zoned One Family Residence ( R - 13) District, which permits
colleges and universities with an approved use permit. Hampton University' s main
campus precedes the Zoning Ordinance and is grandfathered as a use. The campus
does not have an active use permit and therefore a new use permit must be sought for
each new use or building added to the campus. Even though located in a residential
district there are no single family uses in this area; it is either university property or
cemetery property.
The Hampton Community Plan ( 2006, as amended) recommends public /semi-
public land use, which includes schools, colleges, and universities. The Community Plan
also recognizes the importance of preparing Hampton citizens for future success and
having well -prepared and educated citizens being an economic development asset.
Mr. Hayes stated the city of Hampton values education and values Hampton
University as a great resource and asset in providing education. By having Hampton
University as part of the City of Hampton we are able to retain some of the best and
brightest minds that Hampton has to offer, and attract some very bright people.
Hopefully some will choose to stay after school and invest in businesses.
Four conditions are attached to this application: the use permit pertains to this
specific site; operations are limited to office and education space; the site
PCMlnutes 20150709 Page 15
development will have to adhere to the concept plan; and the nullification clause that
is typical of a use permit.
The structure is a one -story 3, 500 square foot building. It will not impact parking
and it will have plenty of accessible parking.
Staff recommends approval of Use Permit Application # 15 -00010 with 4
conditions.
In response to a request by Chairman LaRue, Mr. Hayes explained that while
Hampton University is a historic, older university, the main campus was in existence prior
to the Zoning Ordinance. The ordinance now requires a use permit in relation to
colleges or universities going into residential districts. When the University and its
buildings first came about and many of the buildings were first established there was no
use permit requirement and therefore there was no use permit for the campus. As
changes occur and new buildings come into play a use permit is now required.
In response to a question from Commissioner McCloud, Mr. Hayes stated the
student resource center is being specifically designed to provide a small amount of
office space and provide a place for tutoring, a small classroom /auditorium space,
and a computer lab. Mr. Hayes is not certain how that center complements or how it is
different from what occurs in the library.
Bob Miller, consulting engineer for MSA and representative for the University,
stated the University has taken the opportunity to provide a success center. This center
will provide a facility where a student is given the opportunity to go somewhere and
have someone mentor and coach them and help with graduate school. The computer
lab is another resource for the mentoring process. The staff will be able to help the
students from getting a job to working on graduate studies.
Randall Hardy, Director of the Hampton University Physical Plant, explained the
site would be located in the middle of the campus and that the location is a great one.
There were no speakers from the public.
After discussion, the Commission approved the following resolution:
WHEREAS: the Hampton Planning Commission has before it this day a
proposal by Hampton University for university use at 65 Marshall
Avenue [ LRSN 120010341;
WHEREAS: 65 Marshall Avenue is part of the main campus;
WHEREAS: the property is zoned One Family Residence ( R - 13) District, which
allows for the operation of universities subject to approval of a use
permit;
PCMinutes 20150707 Page 16
WHEREAS: Hampton University' s main campus was established prior to the
zoning ordinance so any new university use requires an approved
use permit;
WHEREAS: the Hampton Community Plan ( 2006, as amended) recommends
public /semi -public use for this site, which includes institutional uses,
such as schools and universities, as well as support for education;
WHEREAS: four ( 4) conditions are attached that limit the location of the use,
further define the use to an academic and office building, and
ensure site development will be in accordance with the submitted
concept plan and building elevations; and
WHEREAS: no one from the public spoke to this application;
NOW, THEREFORE, on a motion by Commissioner Tommy Southall and seconded
by Commissioner Mary Bunting,
BE IT RESOLVED that the Hampton Planning Commission recommends to City
Council approval of Use Permit Application No. 15 -0010, subject to
four (4) conditions.
A roll call vote on the motion resulted as follows:
AYES: Southall, Williams, McCloud, Schmidt, Bunting, LaRue
NAYS: None
ABST: None
ABSENT: Campbell
VI. COMMUNITY DEVELOPMENT DIRECTOR' S REPORT
A. Project updates:
a. Coliseum Central Master Plan update
Mr. O' Neill stated that City Planner Tolu Ibikunle will present the Coliseum Central
Master Plan Update process which is getting toward the final turn on this effort. Work is
being done to finalize the draft. Most of the public input and community feedback
portion of the process has been concluded. These are not final recommendations, but
a glimpse of where things stand and what direction it is going.
City Planner Tolu Ibikunle stated the Coliseum Central Master Plan update
process began with gathering data from the community. Work was done with Urban
Design Analysis ( UDA) and market analysis to help facilitate the public process.
Some ideas received from the community were tried and people were given an
opportunity to look at the various concepts online and give feedback. Several
community meetings and stockholder meetings with property owners were held. The
P( Winules 20150709 Page 17
options were refined to help develop strong concepts and things are moving forward
for adoption of the final plan in the fall of this year.
The current plan was adopted by City Council in 2004. There have been many
changes since 2004 including a market crash in 2008. Demographics and lending have
changed. One change has been in the way people shop with the internet; however
there is still room for restaurants and box retail. Commercial properties are being
repositioned so they can keep up with market demands. Repositioning of
underperforming hotels is being done to ensure visitors have quality hotels to stay in
while in Hampton. More people are looking for walkable urban districts to work and
live in. There is also a demand in this market for apartments and townhomes.
Some of the development activities since 2004 are the Peninsula Town Center,
which includes the Chapman - a residential community that commands one of the
highest rents on the Peninsula and is leasing at 99 %; the H2O townhome development;
the Sentara Careplex Fitness Center; and the Boo Williams Sportsplex.
With design principals it is important to focus on organizing land use in terms of
the scale of the development and to cluster the compatible uses and character. An
example of this is the Coliseum and the Convention Center. Other design principles are
to integrate residential and commercial uses into mixed use developments as in
Peninsula Town Center; create dense and connected pedestrian friendly activity
centers; strengthen the retail market; create new public streets and sidewalks to
connect areas; develop and connect open space within the district.
Some recommendations for the Coliseum North Initiative Area where Peninsula
Town Center is located are to improve signage; gateway elements; outdoor events;
new housing; new hotel on site; and new restaurant and retail buildings.
Riverdale Shopping Plaza is also located in Coliseum North and some of the
recommendation there is to make it a mixed -use district; add residential and office
space; add retail along Mercury Boulevard; and improve street connections in the
center.
Mr. O' Neill stated that the street connections referred to in the drawings and on
the maps are represented as principle concepts of what it could look like but not
literally what will be done. It just shows an example of a way to connect streets and
sidewalks.
In response to a question from Chairman LaRue, Mr. O' Neill stated that from a
Planner and urban design perspective streets are viewed almost like veins and arteries
in the body. Ideally streets should connect but sometimes other things get in the way. It
is a give and take process.
The ideas for the Coliseum South Initiative Area, where a portion of it is known as
the Hospitality Corridor, are to have a convention quality hotel on the former Best
Products site; reposition under -performing hotels; and incorporate new restaurants and
more multi -family residential.
PCMinutes 20150709 Page 18
Along Saville Row the ideas are to redevelop the Langley Federal Credit Union
LFCU) site; obtain new retailers; convert Saville Row into a pedestrian oriented street;
new street connections; and add additional multi -family residential.
Mr. O' Neill explained that City staff met with LFCU upon their request to help with
ideas on their site as they rethink their presence at this location. They own their current
office site and most of the wooded area behind. Collaboration has been done
between the City and LFCU on how to re- develop their site.
The Crossroads Initiative area ideas include a Grand Central Park meeting space
where visitors and residents can enjoy the outdoors; adding additional convention
quality hotels, more amateur sports facilities; a Festival Park for outdoor special events;
and office space.
In response to a question from Commissioner Williams, Ms. Ibikunle stated the
idea of a potential splash park is still an idea in the development of a sports park.
The Power Plant Initiative Area consists of larger box retailers ( Bass Pro, BYs and
Lowes) and there is an opportunity to include new residential communities.
In meeting with representatives from the Sentara Careplex Hospital located in
the Sentara Initiative Area it was expressed that there is a need for additional housing in
close proximity for hospital personnel who may be in their residency, working long,
strenuous hours and who may not have time to go home if they live out of the area.
The Coliseum Drive extension will begin at the Hampton Roads Center Parkway
and extend further north. Also available in this area is space for additional offices that
could support the Careplex.
The next steps for this process are to refine the concepts and ideas that were
received and present a final concept in the early fall.
In response to a question from Chairman LaRue, Ms. Ibikunle explained where
the walking /riding trail and Grand Central Park area are to be located in the
Newmarket Creek area.
Mr. O' Neill stated that the first of the three sections of the Central Park project
that Council has given an approval to start on begin at the Air Power Park at LaSalle
Avenue and Mercury Boulevard down to Armistead Drive, across Armistead Avenue to
Freeman Drive, behind the H2O townhomes and Freeman Drive, through the Coliseum
Complex and up to Pine Chapel Road. Staff is currently working on the preliminary
design.
b. Dutch Dialogues Report
Mr. O' Neill stated a " teaser" presentation was given to City Council regarding
the Dutch Dialogues that occurred two weeks ago. A more in -depth briefing and
PC Minutes 20150709 Pnke 19
worksession will be given to City Council at a later date on the outcome and any future
steps that may come from these discussions.
If the Commission desires to explore this subject in more detail, staff will give
another briefing.
City Planner Matt Smith presented a briefing on the Dutch Dialogues, which is a
series of workshops, came as a response to Hurricane Katrina. A Planning and
Architectural firm in New Orleans saw that the Dutch had the only comprehensive
solutions to flooding stormwater problems. They got in touch with the Dutch Embassy
and organized a workshop. Similar workshops have been held and this was the second
true Dutch Dialogue session held in the Hampton Roads area. One reason Hampton
Roads was chosen as a location is because the area has flooding and sea level rise
issues and is one of the most vulnerable locations on the East Coast. An attraction to
the Dutch is that they saw an opportunity and the region is being proactive with the
issue.
The workshop was held over a five day period. Some of the Dutch people were
there along with key participants. There were three days of workshops and the two sites
that were visited were in Hampton and Norfolk. The report went out to City Manages in
the area, elected officials, and members of the public.
Participants included staff from Hampton and Norfolk along with representatives
from the Army Corps of Engineers, State offices, non -profits, local universities, and firms.
There were a lot of the right people there to discuss the issue. The most important
groups were the globally recognized experts and disciplines related to water
management such as engineering, architecture, landscape architecture, and
planning. A lot of these experts volunteered their time to come help out with these
issues. These experts brought serious resources to Hampton Roads.
Separated into three teams they focused on the region as a whole and on the
big picture items as how the jurisdictions could work better together on this topic. One
group was devoted to an area in Norfolk. Called the Tidewater District they focused on
St. Paul' s Quadrant, Harbor Park, and the Chesterfield Heights neighborhood in Norfolk.
The third group was the Newmarket Creek group who focused on the watershed in
Hampton and Newport News. This last team included staff from both cities.
Hampton is a built -out city and it is important to take advantage of the resources
it has. One of the observations that came out of these sessions is that the Dutch thought
Hampton had its back to Newmarket Creek instead of taking advantage of what the
Creek has to offer. The Dutch looked at the Creek and broke it into three sections: the
narrow creek, the residential creek, and the bay creek. They felt strongly that the water
management solutions are single purpose. In the broad conceptual realm Newmarket
Creek and Mercury Boulevard could work together to connect the important areas of
Newport News and Hampton from the border to the Coliseum, through downtown
Hampton, Hampton University, and to Ft. Monroe.
P( M IlUtes 20150709
Page 20
Part of the focus was on how Newmarket Creek could provide benefit to specific
sites. At Net Center and in Newmarket South, Newmarket Creek takes a difficult path as
it runs into a dam and is routed under Mercury Boulevard and is then piped around the
shopping center. This causes a lot of problems and actually causes the shopping center
parking lot ( Newmarket South) to flood. An idea was to restore the Creek to a more
natural function it could be the spur development and an amenity and centerpiece of
a transformation in this area.
The next steps are to look at and process the Dutch recommendations, evaluate
current activities; hold a detailed discussion with City Council in August; and explore
partnerships with other cities.
Mr. O' Neill stated this was a five day work session, but a lot of work went into it
prior to this session. City Planner Matt Smith and Gayle Hicks from Public Works
represented the City of Hampton and did the majority of the work and logistics behind
the scenes. They made this a unique opportunity for the City of Hampton.
c. Designation of Urban Development Areas
Mr. O' Neill stated that Lucy Stoll would present a pre- briefing of the amendment
regarding Urban Development Areas to give the Commissioners a general idea of the
concept of the language involved and why the amendment was to be done. A formal
plan will be brought back in a month or so.
City Planner Lucy Stoll presented a proposal on Community Plan Amendment
No. 022 -2015 to the Hampton Community Plan, ( 2006, as amended) which will include
Urban Development Areas. This is an area where population growth and development
are more appropriate at a denser level or it is an area that has previously been
developed and is ripe for redevelopment or infill development.
The reason for including urban development areas in the Hampton Community
Plan ( 2006, as amended) began in 2014 when the State General Assembly passed
House Bill 2 ( HB2) which acknowledged that in all levels of government transportation
funding is very limited. With that in mind HB2 is trying to ensure limited funds are
allocated wisely and create a system for funding certain transportation projects. It will
create a transparency for those projects that are selected based on economic
development, accessibility, and congestion mitigation among other things. This gives
everyone an idea of how their projects stack up against others in the State.
With the HB2 passage, Hampton Roads has been allocated $80 million over the
next six years that Hampton can compete for to fill the gap funding for possible eligible
projects such as Central Park ( Newmarket Creek); upgrade of Old Buckroe Road, and
the Coliseum Drive extension.
Before these projects can be submitted the State needs to see that Hampton' s
project needs address a need in the statewide plan. The State' s plan is Vtrans 2040
Multimodal Plan. The State focuses on airports, freight, and much larger scale
transportation needs. Hampton focuses on transit, its roads, pedestrians, and cyclists.
PCMinutes 20150709
Page 21
The State' s plan breaks down the projects into corridors of statewide significance
regional networks; and urban development areas.
The corridors of statewide significance are the most intuitive. These are the
largest conduit of people and goods. These cover travel between states and regions:
interstates; ports, and freight lines. For Hampton it is the 1 - 64 corridor.
The regional networks are primarily for travel throughout our region ( Hampton
Roads). The focus is more on economic activity and job accessibility and how people
access their jobs. A good example is Magruder Boulevard which is a major corridor with
research and development parks; offices; and Langley Air Force Base.
Urban Development Areas are areas appropriate for infill and denser
development that need access to water, sewer and transportation systems and need
to go with " traditional neighborhood" design. Mixed -use is a big tenant of " traditional
neighborhood" design and requires things like sidewalks and crosswalks for good
pedestrian and bicycle circulation; narrower streets; and buildings built closer together.
Localities are the only entities that can submit UDA projects and these projects
must be designated by localities in their comprehensive plan.
In order to make the Community Plan amendment changes staff have worked
with Public Works, regional planning organizations, and the State to come up with our
best locations. With the addition of Ft. Monroe Hampton has come up with seven areas
that are consistent with the Master Plan. The amendment will include text and maps to
identify the UDAs.
The included text will cover a lot of what has been presented: definition of
Urban Designated Areas; background on House Bill 2 and the process; and how this fits
with State objectives. A new Transportation Policy will be developed that will state that
information for the Community Plan in a condensed form.
Maps will be provided to show the corridors of statewide significance ( 1- 64, 1- 664,
CSX railways) and regional networks. Hampton does not get to choose what these
statewide significance or regional networks are. Hampton is giving input and working
with consultants to put this together. The reason Urban Developments are important is
that Hampton gets to make the final call as long as it matches up with the legislation.
The regional networks that have come out are the Magruder Corridor and the
Hampton University and VA Regional Medical Center employment spot.
The Urban Development Areas being proposed are the six Master Plan areas and
Ft. Monroe.
By aligning Hampton' s goal with the State goals it opens Hampton up to be
more competitive with transportation funding. With limited funds there will be more call
for accountability for where monies are spent. It is important for Hampton to get its foot
in the door at the ground level as everything is building up.
Page 22
PCMinutes 20150709
The project submission period begins in August and goes through October. Plans
are to come back before the Commission in August and to City Council for adoption in
August.
VII, NEW BUSINESS
A. Planning Commission Bylaws Amendment
Sr. Assistant City Attorney Bonnie Brown stated the By -law is about weather
cancellations. If it needs to be read again she stated she would read the proposed By-
law again.
As there were no questions, Vice -Chair McCloud entertained a motion.
A motion was made by Commissioner Schmidt, and seconded by
Commissioner Williams, that the By -laws Amendment regarding weather cancellations
be approved.
A roll call vote on the motion resulted as follows:
AYES: Southall, Williams, McCloud, Schmidt, LaRue
NAYS: None
ABST: None
ABSENT: Campbell, Bunting
Vice -Chair McCloud stated the Youth Planner Report is not on the agenda but
there is a written report in the Commission packet. Youth Planner Bryauna Kralik is on a
college tour and could not be at the meeting.
VIII. ITEMS BY THE PUBLIC
There were no items by the public.
IX. MATTERS BY THE COMMISSION
There were no matters by the Commission.
X. ADJOURNMENT
There being no further business, the meeting was adjourned at 5: 48 p.m.
Respectfully submitted,
Terry ' Neill
Secretary to the Commission
PCMinu[ es 20150709 Page 23
APPROVED BY:
McCloud -—
PCMinu[ es 20150709 - _ Page 24
Agenda
PLANNING COMMISSION
CITY OF HAMPTON, VIRGINIA
CHAIR: Gaynette LaRue
VICE-CHAIR: Andre McCloud
COMMISSIONERS: Mary Bunting, Carlton Campbell, Teresa V. Schmidt,
Thomas Southall, Gregory Williams
WORK SESSION
July 9, 2015 @ 3:00 PM – City Hall, Lawson Conference Room, 8th Floor
I. Questions about agenda items
MEETING AGENDA
July 9, 2015 @ 3:30 PM – City Hall, City Council Chambers, 8th Floor
I. Call to Order
II. Roll Call
III. Minutes of the June 4, 2015 Planning Commission Meeting
IV. Planning Commission Action
A. Planning Commission Action No. 15-00001: by HDR Engineering, Inc. to allow for the
construction of a pump station at 515 Bridge Street. Staff Contact: Matt Smith, 757-727-6077 or
mssmith@hampton.gov.
V. Public Hearing Items
A. Rezoning Application No. 15-00001: by Todd Center, L.L.C., c/o Tower Park Corporation to
rezone 3.13+ acres at 1700 Todds Lane [LRSN 3003904] and a portion of LRSN 3003903 from
Limited Commercial (C-2) District to General Commercial (C-3) District with proffers, to
facilitate the establishment of a mixed-use development to include: office, retail, and self-
storage to create an e-commerce center. These properties are located at the edge of and
within the Coliseum Central Overlay (O-CC) District. This application accompanies Use Permit
Application No. 15-00001 for the storage component of the proposal. Approval of this
application and the accompanying use permit application would permit a combination of
office, retail, and storage uses fully contained in an enclosed building. The Hampton
Community Plan (2006, as amended) recommends mixed-use development for this area. The
Coliseum Central Master Plan (2004) recommends mixed-use nodes, improved pedestrian
connectivity within shopping centers such as this one, and connections to the district. Copies
of documents or information concerning this proposal may be obtained from the Community
Development Department, located in Hampton City Hall, 22 Lincoln Street, 5 th Floor, or from
Tolu Ibikunle, 757-728-5237 or tibikunle@hampton.gov.
B. Use Permit Application No. 15-00001: by Todd Center, L.L.C., c/o Tower Park Corporation to
operate the self-storage component of the proposed mixed-use development to include
office, retail, and self-storage for the establishment of an e-commerce center. The properties
are located at 1700 Todds Lane [LRSN 3003904] and a portion of LRSN 3003903. These
properties are located at the edge of and within the Coliseum Central Overlay (O-CC) District.
This application accompanies Rezoning Application No. 15-00001 for all three proposed uses.
Approval of this application and the accompanying Rezoning Application No. 15-00001 would
permit a combination of office, retail, and self-storage uses fully contained in an enclosed new
building. The Hampton Community Plan (2006, as amended) recommends mixed-use
Page 1 of 2
development for this area. The Coliseum Central Master Plan (2004) recommends mixed-use
nodes, improved pedestrian connectivity within shopping centers such as this one, and
connections to the district. Copies of documents or information concerning this proposal may
be obtained from the Community Development Department, located in Hampton City Hall, 22
Lincoln Street, 5th Floor, or from Tolu Ibikunle, 757-728-5237 or tibikunle@hampton.gov.
C. Rezoning Application No. 15-00002: by Shervonne Banks to rezone .2+ acres at 1204 E.
Pembroke Ave. (LRSN 12000782) from General Commercial (C-3) District to Neighborhood
Commercial (C-1) District without proffered conditions to operate a respite care facility. The
Hampton Community Plan (2006, as amended) recommends commercial use for this area.
Copies of documents or information concerning this proposal may be obtained from the
Community Development Department located in Hampton City Hall at 22 Lincoln Street or
from Matt Smith, 757-727-6077 or mssmith@hampton.gov.
D. Use Permit Application No. 15-00010: by Hampton University to operate a university facility,
specifically a student resource center, at 65 Marshall Avenue, which is defined as the portion
of the Hampton University main campus (LRSN 12001034) beginning on the south side of
Marshall Avenue beginning at the northwest corner of the Hampton National Cemetery (LRSN
12001094) extending southwest along Marshall Avenue 135’ to the intersection of Marshall
Avenue and Orchard Road, then south-southeast along the east side of orchard road 85’, then
east-northeast 145’ to the property line, then 130’ north-northwest, returning to the starting
point on Marshall Avenue. The property is zoned One Family Residence (R-13) District, which
permits universities with an approved use permit. The Hampton Community Plan (2006, as
amended) recommends public/semi-public land use for this area. Copies of documents or
information concerning this proposal may be obtained from the Community Development
Department located in Hampton City Hall at 22 Lincoln Street or from Mike Hayes, 757-728-5244
or mdhayes@hampton.gov.
VI. Community Development Director’s Report
A. Project updates:
a. Coliseum Central Master Plan update – Donald Whipple
b. Dutch Dialogues Report – Matt Smith
VII. New Business
A. Planning Commission Bylaws Amendment – Bonnie Brown
VIII. Items by the public
IX. Matters by the Commission
X. Adjournment
Protocol for Public Input at Planning Commission Meetings:
Hampton Planning Commission meetings are open to the public. The public is invited to attend meetings
and to observe the work and deliberations of the Planning Commission. The public may also address the
Planning Commission on public hearing items by signing up to speak. Public hearing sign-up sheets will be
available until the specific item is reached during the course of the meeting. Speakers will be recognized in
the order in which they sign up and are asked to state their name and address, to limit their comments to 3
minutes, and to avoid repeating comments made by previous speakers.
As a courtesy to others during the meeting,
please turn off cellular telephones or set them to vibrate.
CITY OF HAMPTON
COMMUNITY DEVELOPMENT DEPARTMENT
PLANNING & ZONING ADMINISTRATION DIVISION
22 LINCOLN STREET, 5TH FLOOR
HAMPTON, VA 23669
757-727-6140
Page 2 of 2