War Memorial Stadium Advisory Board
Regular MeetingHampton, VA · February 3, 2020
Minutes
Peninsula Stadium Authority Minutes February 3rd, 2020
The meeting was called to order by Jim Wilson, Chair. Others in attendance
included: Randy Price, Jim Goodbody, Frank Feagan, Wayne Gomes, Brenda
Stokes, David McCauley, Lola Perkins and Linda Williams. Attending from
Community Baseball was Henry Morgan. We had a special visit by Mayor Donnie
Tuck.
The January Minutes were approved by Randy, seconded by Jim G. and approved
by all.
No changes to the Treasurers report since our last meeting.
Jim W. met with Tracy Joyner, Insurance Manager with Towne Insurance, last
week in regards to updating the insurance policy for the Stadium. Jim had several
questions that Tracy was not able to answer and therefore a new representative
has been assigned to the Stadium policy. The new account representative for our
policy will be Trevor Topping. He is familiar with Stadium insurance policies and
will be working up a new quote. Trevor will be getting in touch with Jim to go
over the insurance details and Joe Sanders, Risk Management Officer for the City
of Hampton, will be with Jim for this meeting. Jim W. and Joe also met with Nora
Pierce, Virginia Risk Sharing Assoc., ( she is with a firm that the City of Hampton
deals with) to get a second opinion about the insurance policy.
Jim W. met with City Officials on Jan. 23rd to discuss his concerns about the
delays on the New Building. Asst. City Manager, Brian Deprofrio, was also there
and will be following up with Public Works and Richie-Curbow Construction to
find out what some of the concerns were surrounding the delays. The delays
have caused a delay relating to Community Baseball LLC. leasing and negotiations
with the Apprentice School. The New Building is supposed to be completed in
March. During the meeting Jim asked if the City could address the standing water
situation on the 3rd Base side, on the Plaza in front of the concession stand. Jim
took some pictures to share with them. They will follow up with Ron Sterling,
Senior City Engineer.
Outfield fence work has been completed and waiting for the final invoice from
Rosenbaum.
Fence top and centerfield padding-Henry has not received the estimate yet,
should be getting it in the next couple of days. He will be able to share that with
us at our next meeting.
Jim met with the Pilots in regards to batting cage improvements. They are
waiting on some concrete to be poured in order to finish it up.
Henry is also looking into some estimates to replace the washer and dryer in the
locker room. He will get those to us at our next meeting.
Frank and Jim G. met with Henry to discuss the Tiki Tavern. Frank gave us an
estimate of $27,335 for the foundation, walls, floor, roof & gutters. This does not
include the electrical work. With the electrical work, the estimate is around
$30,000. He does not have any drawings at this time. Randy motioned for the
Sub-Committee to proceed with the preliminary drawings and necessary
information needed in order to get the work permit from the City of Hampton.
Brenda seconded that motion and it was approved by the Committee.
Jim W. asked us to think about Inside Stadium needs. We need to focus on
completing the needs involving the baseball players and referees in order to make
our Stadium attractive to visiting teams. He mentioned the 1st Base side needs to
upgrade the locker room and restrooms with ADA accommodations’ and Family
facilities. More discussions on this topic at the next meeting.
No New Business to discuss.
Meeting was adjourned by Jim W.
Our next meeting will be on March 2nd.
Agenda
Peninsula Stadium Authority
February 3, 2020
Noon, War Memorial Stadium Conference Room
AGENDA
Approval of the January 6, 2020 Minutes
Review of the Treasurer’s Report
Update on our meetings with the Insurance policy and efforts to update our current policy.
Update on the Entryway Building. Please note; in a meeting with City of Hampton Officials on
Thursday January 23rd the Peninsula Stadium Authority express their major concern on the
delays we have experienced with the construction of this building and the problems this has
created for the P.S.A and the Peninsula Pilots. They will follow up on this.
P.S.A has requested the City of Hampton to address the standing water on the third base plaza
side by the concession stand after heavy rains.
Outfield Fence work has been completed, approval of the Pilots to process the Payment.
Discussion on the proposal of the new Third base Plaza Area.
Winter Projects Discussion for Funding. Possible pending items:
Fence Top cover with line pole covers and padding
Items still required in the Batting cage area
Washer & Dryer for the Locker room
Concession Items for the new building.
Update on the Budget request for next year.
New Business
Next meeting will be Monday March 2nd. At the stadium