War Memorial Stadium Advisory Board
Regular MeetingHampton, VA · June 7, 2021
Minutes
Peninsula Stadium Authority Minutes June 7th, 2021
The meeting was called to order by Jim Wilson, Chair. Others in attendance
included: Frank Feagan, Brenda Stokes, Sallie Marchello, Jim Goodbody,
Randy Price, Wayne Gomes, Lola Perkins and Linda Williams from the Board.
Absent from the meeting were: Kiufordis Khasidis and David McCauley. In
attendance from Community Baseball was Henry Morgan. Also in attendance
was Honorable Mayor Tuck.
The May 3rd Minutes were approved by Randy, seconded by Frank and
accepted by the Committee.
The Treasurers report was presented with checks written for Design Services
and a Plaque leaving a balance of $109,912.12.
FY22 Budget for the PSA will be $99,500 with payments at 50% in 6 month
periods.
During the past few months there have been many discussions related to the
Batters Eye, replacement options or repair, pole repair and installation of
chain link fabric to replace existing black screen material. The Pilots would
like the PSA to pay for Batters screen repair work which includes removal and
disposal of existing black fabric material on the top two rows and repair the
entire framework to support the new fabric. Install two rows of 6 ft high, 9
gauge, 2 inch black coated wire on existing black vinyl post and install green
Permahedge in the weave of the new chain link fence. Cost of labor and
materials is $17,382.00. Sallie made a motion to approve the Batters Eye
Project at a cost of $17,382.00, seconded by Linda and approved by the
Committee.
Elevator Company Maintenance Agreement – Henry presented the
Committee with a description of two maintenance plans that Otis Elevator
Company offers. One is a Maintenance Plan which is a full preventative
maintenance contract that includes regular time equipment related service
calls, annual testing, parts needing replacement due to normal wear and tear,
etc. ($219.50/month) The other is a Service Plan that is similar but excludes
parts replacements and the full load testing. ($148.50\month) The existing
contract expires on June 30th.
Sallie motioned to have a phase approach:
1) Have the City of Hampton take it over entirely
2) Piggy back on the City’s Maintenance Contract
3) Ask Otis Elevator Co. for a 60 day grace period in order to investigate the
best course of action
4) Go ahead with the Otis Service Contract
Randy seconded the motion and it was approved by the Committee.
Building Dedication follow-up comments – everyone felt that it went well.
Proposed Restroom work – Jim has not received an update from the City
about the inspection that was done to upgrade the restrooms with touchless
equipment. He will get back with us on that at our next meeting.
Lightning Protection – AAA Electric Co., under the City’s contract, is handling
this project. As soon as they are available to start the project they will begin
the work.
Entry-Way Building Warranty Work Report – Jim has not received yet, he will
present it to the Committee at our next meeting.
Baseball Barricade Proposal and Gates – Jim is trying to get more proposals
and the work will probably not be done until the Fall.
Clubhouse Work Proposal – Jim is working on getting Henry and Hank
together with the Architects in order to finish the report so that it can be
presented to City Council.
Lola presented the Committee with a copy of a “Cooperation Agreement” to
review. The Committee needs to review the document and decide if they
want to establish a Fiscal Agent Relationship with the City. We will follow up
in July.
Next month we will elect next years Officers for the Committee.
Jim presented the Committee with a list of Future Projects that we need to be
thinking about and discuss at our next meeting.
The meeting was adjourned by Jim W. Our next meeting will be Monday, July
12th.
Agenda
Peninsula Stadium Authority
June 7, 2021
AGENDA
Our Meeting will be in the indoor Batting Cage of the new Entry-way Building.
Call meeting to order.
Approval of the May 3, 2021 meeting Minutes.
Review of the Treasurers Report.
FY22 Budget for the P.S.A. will be $ 99,500. Payments at 50% in 6-month periods.
Discussion on the Dedication of the new Entry-way Building.
Project Discussion Updates:
● Proposed Fence Work & Batters Eye
● Safety Signs
● Proposed Restroom Work in old Restrooms
● Entry-Way Building Warranty Work Report
● Baseball Barricade Proposal
● Lighting Protection
● Clubhouse Work Proposal
Discussion of Establishing Fiscal Agent Relationship with City.
Election of Officers next Month
Update on Insurance Policy for 2021 & 2022
Prepare to Discuss Fall Projects in August and September
New Business
Our Next Meeting will be July 12th. This is the second Monday of the Month.
The First Monday is July 5th which I believe will be a holiday with the 4th of July
falling on Sunday.