City Council
Regular MeetingHarrisonburg, VA · June 8, 2017
Minutes
409 S. Main Street
City of Harrisonburg Harrisonburg, VA 22801
Meeting Minutes - Final
City Council
Mayor Deanna R. Reed
Vice-Mayor Richard A. Baugh
Council Member Ted Byrd
Council Member George Hirschmann
Council Member Christopher B. Jones
Thursday, June 8, 2017 7:00 PM Council Chambers
School Board/City Council Joint Meeting
1. Roll Call
Present: 4- Mayor Deanna R. Reed, Vice-Mayor Richard Baugh, Council Member Ted Byrd
and Council Member George Hirschmann
Absent: 1- Council Member Christopher B. Jones
Also Present: 5- City Manager Kurt Hodgen, Deputy City Manager Ande Banks, Deputy City Clerk
Pam Ulmer, City Attorney Chris Brown and Police Chief Stephen Monticelli
Also Present: Andrew Kohen, Chair; Deb Fitzgerald, Vice-Chair; Brent Holsinger,
School Board Member; Lauren Penrod, School Board Member; Kaylene Seigle,
School Board Member; and Dr. Scott Kizner, Superintendent; Nick Swayne,
School Board Member was absent.
2. Pledge of Allegiance
Mayor Reed led the Pledge of Allegiance
3. Regular Items
3.a. Discussion on addressing the high school space issue
Mayor Reed stated this is the second discussion regarding recommendations from
the School Board.
Chairman Kohen stated on June 6, 2017 the School Board unanimously accepted
the recommendation from the space study committee to move forward in solving
the overcrowding problem at Harrisonburg High School (HHS) by erecting a
second high school. Chairman Kohen stated the School Board is respectfully
offering this recommendation to city Council and the School Board asked Council
to endorse this decision and allow the School Board to move forward. Chairman
Kohen also stated there was a second motion that was also approved
unanimously, which was a request that Council authorize the School Board to
evaluate potential site locations for a new high school. Chairman Kohen stated
City of Harrisonburg Page 1 Printed on 6/28/2017
City Council Meeting Minutes - Final June 8, 2017
the objective being to share the preferred site with Council through the Liaison
Committee process. Chairman Kohen stated the land study would include
preliminary civil engineering work to help determine if the site is viable and any site
challenges that may exist.
Mayor Reed stated this is the time to ask any questions Council or School Board
may have pertaining to the recommendation by the School Board.
Council Member Hirschmann stated he would like to know how the School Board
arrive at the $100M plus figure for the cost of the new high school.
Chairman Kohen stated the estimated figure was based on a prospectus prepared
for the School Board by VMDO Architects on the likely costs given the parameters
of the size of school and the timing of the erection of the building. Chairman
Kohen stated this figure is speculative in the sense that a lot of the dimensions
that go into determining the precise cost are unknown at this time. Chairman
Kohen stated these are best guesses being made about a number of different
dimensions of the final cost. Council Member Hirschmann asked if this figure is a
guess. Chairman Kohen stated it is an educated estimate.
Chairman Kohen stated there are representatives from VMDO Architects, Kelly
Callahan and Bryce Powell, are present for any questions Council may have
regarding the process by which they arrived at the broad based estimates.
Kelly Callahan stated the proposed costs estimation was from a combination of
state averages based on historical data provided by the Department of Education,
average facility size based on the number of students that will be housed in the
new building, the square foot per student, which is an average, and then
multiplying that by the average cost per square foot. Ms. Callahan stated those
calculations were then escalated based on professional estimators averaging the
percent of escalation that would happen in the construction industry moving
forward, which was 4.5% per year.
Board Member Penrod stated a couple of months ago, when VMDO presented to
the School Board, it was stated an exact number couldn't be calculated at that
time because of everything that goes into it, but for the School Board and city
Council purposes this was an educated guess, it doesn’t mean that if the budget
approved doesn’t meet the $100M figure the school can’t be built. Board Member
Penrod stated she understood there are ways to work within the budget. Mr.
Powell stated the other significant is identifying a site, which has a number of
unknowns relative to general site development and other aspects that would affect
the project, up or down depending on what type of site was selected. Mr. Powell
stated those variables included utilities, materials, etc. Board Member Penrod
stated those are unknowns but VMDO has a strong history of staying within the
budget.
Ms. Callahan stated the numbers are intimidating; however the last thing anyone
City of Harrisonburg Page 2 Printed on 6/28/2017
City Council Meeting Minutes - Final June 8, 2017
wants is to embark on a four year journey to construct something that is the right
thing to do, but then come up short on funding. Ms. Callahan stated the funds
would not need to be available immediately as construction wouldn ’t start for
almost another two years, which is the bulk of the spending. Ms. Callahan stated
there will be costs that occur in the beginning: fees to design, engineering and site
study.
Vice-Chairman Fitzgerald stated it is uncomfortable to talk about this without a
final price tag, but so many unknowns are still outstanding, and the School Board
is asking Council to approve the School Board to move forward and resolve the
unknowns, such as investigating land and estimated costs to prepare the site
chosen, and what a building on the site would look like. Vice-Chairman Fitzgerald
stated the School Board cannot move forward until we get the green light from
Council to look at land.
Chairman Kohen stated the School Board needs to know what the budget is in
order to accomplish the goal of constructing a second high school.
Mayor Reed asked Council if there is any question as to what the School Board is
asking for.
Vice-Mayor Baugh stated at the last city Council meeting on May 23, 2017 it was
discussed that at least looking at some real estate is a component for moving
forward, however, per a letter received by the city manager from the
superintendent, there is mention of preliminary civil engineering work to be done to
help determine if a site is viable. Vice-Mayor Baugh asked if this is a request for
funding.
Chairman Kohen stated yes, the School Board would like adequate funding to
conduct the appropriate consideration of possibilities for site acquisition as drive
by viewing of the sites would not provide answers needed to provide Council with a
firm estimate of construction costs without being evaluated by civil engineering.
Council Member Byrd asked if the School Board was looking for the option to take
physical control of land. Vice-chairman Fitzgerald stated no. Council Member
Byrd stated that normally physical control of the land takes place prior to any civil
engineering work. Vice-Chairman Fitzgerald stated leadership was advised of the
three step site selection process in order to select property that is viable. Council
Member Byrd stated that would then dictate what type of facility will be built .
Vice-Chairman Fitzgerald stated the process could take three months or so, ideally
land would be selected and purchased by the end of September 2017, in order to
stay on track with occupying in 2021. Council Member Byrd asked if the School
Board is requesting city Council purchase the land by September of 2017.
Vice-Chairman Fitzgerald stated the School Board is not committing anyone to a
particular timeline, but simply asking to move forward with the next step.
Vice-Mayor Baugh stated when the Skyline Pre-K project reached a similar point
and School Board identified sites, and discussed the pros and cons with Council
City of Harrisonburg Page 3 Printed on 6/28/2017
City Council Meeting Minutes - Final June 8, 2017
without any engineering involved at that point. Vice-Mayor Baugh stated his vision
for the next phase for this project would be similar and accepted that some funds
may need to be allocated for study.
Mayor Reed asked, for those that weren’t on Council or School Board during the
Skyline Pre-K project, if a Council Member could walk the group through the
process that took place then.
Vice-Mayor Baugh stated, at that time, the School Board looked at sites, reached
a conclusion as to their opinion of those sites, and then had a meeting with
Council to discuss their findings.
Vice-Chairman Fitzgerald stated she wasn’t sure if any pre studies were done on
the Skyline Pre-K site, however, there was quite a bit of unexpected subterranean
issues, with karsts features on the site that were not known ahead of the purchase
of the property. Further discussion took place on the Skyline Pre -K site selection
process.
Board Member Holsinger stated he is unclear as to what Council is asking of the
School Board. Council Member Byrd stated the School Board needs to present
Council with a plan. Board Member Holsinger stated the School Board has gone
through an extensive planning process for the best long term solution, taking over
two years, and most intensively over the past year, and came to a decision that a
second high school would be the best long term solution for the entire community .
Board Member Holsinger stated the School Board is in need of Council’s support
to continue with acquisition of land. Vice-Mayor Baugh and Council Member Byrd
disagreed, as the School Board does not need Council’s approval to proceed with
site selection, only site purchase.
Board Member Penrod asked Council if it would be helpful if the School Board
came to Council stating they have twelve sites, which are the top three and their
recommendations.
Vice-Mayor Baugh stated until he saw the engineering need, he thought the
School Board would be already working on site selection. Council Member Byrd
stated to do the engineering physical control of the land must be obtained.
Chairman Kohen stated in order to meet a time line to open a new high school by
2021 the experts are saying the site must be selected and purchased by
September 2017. Chairman Kohen stated he understands this process does not
happen overnight and is keenly aware that the longer this decision is pushed out
the more difficult and urgent the problem becomes. Chairman Kohen noted the
School Board has done their due diligence in studying the solution, to take the
next step, which is the location of this new school, therefore seeking Council ’s
endorsement to take that step.
City of Harrisonburg Page 4 Printed on 6/28/2017
City Council Meeting Minutes - Final June 8, 2017
Vice-Mayor Baugh noted the School Board does not need Council’s approval to
look at sites, it doesn’t hurt to communicate with community development, but a
general blessing, if needed by the School Board, Council provides it.
Board Member Holsinger stated that is helpful.
Council Member Byrd stated in order for Council to make a decision regarding
timing a total package cost must be presented to Council, so a best estimated
guess to inform the citizens of the costs can be presented to the public and
determination of when and if this project can be done.
Mayor Reed stated Council is ok for the School Board to go forward at this point.
Vice-Mayor Baugh stated the letter from the superintendent states it perfectly,
“The School Board also unanimously adopted a motion to request that the City
Council authorize the School Board to evaluate potential site locations for a new
high school. The objective would be to share their preferred site to the City Council
through the Liaison Committee process.” Vice-Mayor Baugh stated there are two
asks, one to move forward with evaluating potential site locations, the other being
funding for civil engineering.
Council Member Byrd stated the second ask should be brought back to Council
once preferred sites have been determined.
Board Member Holsinger stated the last five minutes of this conversation have
been helpful, much more than the first 10 minutes, and feels better about the
conversation.
Council Member Byrd stated for the School Board to go through the initial process,
but Council has not said a new high school will be built, but Council needs a true
representation of the costs of such a project so the citizens are aware and see if
that is the direction they want to go. Council Member Byrd stated Council ’s job is
to be fiscally responsible while balancing the other side of city operations for their
five year plan of approximately $140M. Council Member Byrd stated if the School
Board wants a budget and a time line, Council has to have good numbers.
Board Member Holsinger stated the School Board has good ball park figures,
based on qualified estimates, which should be enough to have community
conversations.
Mayor Reed stated the School Board has completed a very thorough process but
it will also be a very thorough process with Council, hence the reason for Council
being careful of what is being discussed.
Chairman Kohen stated everyone one needs to be careful, and asks that Council
be mindful of the fact that the School Board was not ignoring the fiscal
dimensions, which is why the School Board consulted with the city’s bond counsel
City of Harrisonburg Page 5 Printed on 6/28/2017
City Council Meeting Minutes - Final June 8, 2017
about capacity of the city to borrow sufficient funds to erect a building that would
be within the ballpark ranges of those given based on state averages, size, etc.
Board Member Penrod stated she feels that for the School Board to be effective
on planning this project, it is helpful to have input and instruction from Council .
Further discussion took place regarding communication between the School Board
and the Liaison Committee and next steps.
Council Member Byrd asked that since the fiscal issues will fall on Council, if, for
some reason Council doesn’t go with the School Board’s recommendation, does
the School Board have a plan B. Chairman Kohen stated there is no plan B .
Council Member Byrd suggested the School Board not put all their eggs in one
basket and have a plan B and C. Board Member Holsinger stated all plans would
be contingent upon funding, so until funding is determined alternate plans can ’t be
made.
Board member Seigle asked if the School Board and city Council have ever done
the studies together on capital projects. Council Member Byrd stated Council
Member Jones was part of the space committee and Vice-Mayor Baugh and
Mayor Reed along with the city manager are on the School Liaison Committee .
Board Member Penrod asked if there was anything Council would like the School
Board to know or provide to Council, to help this process go smoothly. Council
Member Byrd stated once Council discusses further, he is sure there will be
questions. Further discussion took place on how the two bodies interact and
communicate.
Mayor Reed asked if both bodies were clear on how to proceed. All members
responded positively.
Mayor Reed noted the next Liaison Committee Meeting will be held on June 21st,
2017.
4. Adjournment
At 7:55 p.m., there being no further business and on motion adopted, the meeting
was adjourned.
________________________ ________________________
DEPUTY CITY CLERK MAYOR
City of Harrisonburg Page 6 Printed on 6/28/2017
Agenda
409 S. Main Street
City of Harrisonburg Harrisonburg, VA 22801
Meeting Agenda - Final
City Council
Mayor Deanna R. Reed
Vice-Mayor Richard A. Baugh
Council Member Ted Byrd
Council Member George Hirschmann
Council Member Christopher B. Jones
Thursday, June 8, 2017 7:00 PM Council Chambers
School Board/City Council Joint Meeting
1. Roll Call
2. Pledge of Allegiance
3. Regular Items
3.a. Discussion on addressing the high school space issue
4. Adjournment
City of Harrisonburg Page 1 Printed on 6/6/2017
Get email alerts for Harrisonburg
A daily email when new agendas and minutes are posted.