HPMPO Technical Coordinating Committee (TCC)
Regular MeetingHigh Point, NC · June 21, 2022
Agenda
HIGH POINT URBAN AREA MPO
TECHNICAL COORDINATING COMMITTEE (TCC)
Agenda for the June 21, 2022 TCC Meeting
2:00 PM – Third Floor Conference Room
High Point Municipal Building - City Hall
211 S. Hamilton Street, High Point
Action Items
1. Consideration of the April 19th TCC meeting minutes. (Greg Venable) Page 1
2. Recommendation to the TAC of amendments to the 2020-2029
MTIP.(John Hanes) Page 5
3. Recommendation to the TAC for approval of Section 5307 Funding Allocation.
(Andrew Edmonds) Page 8
Information Items
4. STIP Format and P7.0 Schedule Update (Greg Venable) Page 10
5. Bus and Bus Facilities Letters of Support (Andrew Edmonds) Page 11
6. Bipartisan Infrastructure Law Opportunities & Safe Streets For All
(Andrew Edmonds) Page 16
Agency Reports
7. NCDOT Division Reports
Division 7 (Stephen Robinson) Page 18
Division 8 (Bryan Kluchar) Page 23
Division 9 (Fred Haith) Page 24
8. NCDOT Transportation Planning Branch Report (Michael Abuya)
9. FHWA Report (Suzette Morales)
10. Public Transportation Reports
High Point Transit System (Andrew Edmonds)
Davidson County Transportation (Richard Jones) Page 27
RCATS (Tawanna Williams)
PART (Mark Kirstner)
Next TCC Meeting
August 16, 2022
TCC
Meeting
Meeting Date 6/21/2022 Agenda Item No. 1
Action Requested Approve
Section Tab
Consideration of the April 19th TCC meeting minutes. (Greg Venable)
Information Summary Attachments Yes No
The complete meeting minutes are in your packet as Attachment 1.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
1
MINUTES
TECHNICAL COORDINATING COMMITTEE
April 19, 2022
TCC MEMBERS PRESENT: Stephen Robinson, Bryan Kluchar, Fred Haith, Michael
Abuya, Mark Kirstner, Greg Venable, Jason Miller, Roger Jones, Chuck George, Angela
Wynes
TAC MEMBERS PRESENT: Suzette Morales (non-voting)
MPO Staff: John Hanes, Andrew Edmonds, Tabatha J’Arrante
OTHERS PRESENT: Kathy Vollert, Richard Jones, Paul Blanchard, Jerone Monroe,
Alex Rotenberry, Phillip Craver, Chip Vanderzee, Tawanna Williams, Tamara Njegovan
RECORDING STAFF: Microsoft Teams
Greg Venable called the meeting to order.
ACTION ITEMS
Item 1: Consideration of the March 15th TCC meeting minutes.
Andrew Edmonds requested a change on page 5 under High Point Transit System to
change from was awarded to was not awarded.
Motion by: Roger Jones
Seconded by: Stevie Cox
Vote:
For: Unanimous
Against: None
Item 2: Recommendation to the TAC of amendments to the 2020-2029 MTIP.
John Hanes reported that there was one modification to the 2020-2029 MTIP – P-5719C
Piedmont Corridor – acquire and refurbish 8 rail cars – delay in construction from FY22
to FY23. John also reported on several Statewide amendments.
Motion by: Scott Leonard
Seconded by: Fred Haith
Vote:
For: Unanimous
Against: None
2
Information Items
Item 3: Complete Streets Presentation (NCDOT Division Planning Engineers)
Stephen Robinson, Bryan Kluchar, and Fred Haith provided information on the NCDOT
Complete Street Update. The presentation focused on goals, evolution, implementation
challenges, guidance, and next steps.
Item 4: STIP Format and P7.0 Schedule Update
Andrew gave an update on the new format for the Draft 2024-2033 STIP. The new
format will be an excel spreadsheet for this TIP which will allow you to more easily sort
and find projects specific to you MPO. He also gave an update on the STIP schedule and
P7.0 project submittals.
Agency Reports
Item 5: NCDOT Division Reports
Division 7
Stephen Robinson reported that there is a delay on the Kivett Drive bridge. He also gave
a brief update on the South Main Street/US 29-70 interchange project.
Division 8
Bryan Kluchar reported there were no changes to what was in the packet. Greg asked
about discussions concerning a possible new interchange on I-85 at the Mohawk location.
Stevie Cox mentioned some of the concerns for Trinity with all of the new development
in the Trinity area and the need for transportation improvements. Phillip Craver with
Division 9 provided information on discussions and projects that may help with traffic
congestion in the area. Jerone Monroe added information on the schedule for the Finch
Farm Road project and also stated they are taking another look at the design for Finch
Farm Road and NC 62 as well as the ramps with I-85.
Division 9
Fred Haith had nothing to add from what was in the report in the packet. Fred mentioned
that everyone needs to look at the STIP presentations and he would provide information
to Greg to distribute. There will also be a TAC level presentation on the STIP as well.
3
Item 6: NCDOT Transportation Planning Branch Report
Michael Abuya had nothing to add to the report that is in the packet.
Greg asked for Alex Rotenberry with the Integrated Mobility Division to provide an
update even though he was not on the agenda.
Alex Rotenberry mentioned the Multi-modal Planning Grant Initiative and urged the
member jurisdictions to take advantage of the opportunity.
Item 7: FHWA Report
Suzette Morales reported on the changes to the definitions of urban areas. There are a lot
of comments received and now FHWA has decided on that definition. Over the next 6 to
8 months, they are reviewing all urban areas. There is a schedule available online. There
is also a notice of funding opportunity (NOFO) for infra/mega/rural grant.
Alex Rotenberry asked about the MUTCD updates. Suzette has not seen any updates for
that. Greg mention to the TCC that our boundary will more than likely change when our
urbanized area is determined.
Item 8: Public Transportation Reports
High Point Transit System
Andrew Edmonds reported that we submitted a request to our Congressional
Representatives for an earmark for a new transfer hub. As part of that request, we asked
for a letter of support from the MPO which Greg provided.
Davidson County Transportation
Richard Jones stated that Davidson County Transportation are still working on their
submittal to become a direct recipient for FTA funding.
RCATS
No report from RCATS.
PART
Kyle Laird gave an update on ridership. PART is conducting surveys to try and help
identify who is taking advantage of the PART service. He also gave an update of
Community Viz and how that will be used moving forward for our Socio-Economic data
the goes into the Travel Demand Model.
4
TCC
Meeting
Meeting Date 6/21/2022 Agenda Item No. 2
Action Requested Recommendation
Section Tab
Recommendation to the TAC for approval of amendments to the 2020-2029 MTIP.
(John Hanes)
Information Summary Attachments Yes No
The proposed amendments to the 2020-2029 MTIP for the High Point MPO are included
in you packet. Staff is recommending approval of the MTIP amendments.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
5
High Point
RESOLUTION
Archdale AMENDING THE 2020-2029 HIGH POINT METROPOLITAN
TRANSPORTATION IMPROVEMENT PROGRAM
WHEREAS, the Transportation Advisory Committee has reviewed the 2020-2029
Denton
Metropolitan Transportation Improvement Program and found an amendment is
necessary; and
Jamestown WHEREAS, the following amendments have been proposed:
Lexington
Thomasville
Trinity
Wallburg
Davidson
County
Forsyth
County
Guilford
County
Randolph
County
6
High Point
Archdale
Denton
Jamestown
Lexington
Thomasville
NOW THEREFORE, be it resolved by the Transportation Advisory Committee for the
High Point Metropolitan Planning Organization that the 2020-2029 Metropolitan
Transportation Improvement Program be amended as listed above on this the 28th day of
Trinity June 2022.
A motion was made by TAC Member ______________and seconded by TAC
Wallburg member _______________ and approved this the 28th day of June 2022.
_________________________
Martha Wolfe,
Davidson
County
Chair, Transportation Advisory Committee
Forsyth
County Subscribed and sworn to me this the 28th day of June 2022.
______________________________________
Notary Public
Guilford
County
My commission expires ______________________
Randolph
County
7
TCC
Meeting
Meeting Date 6/21/2022 Agenda Item No. 3
Action Requested Recommendation
Section Tab
Recommendation to the TAC for approval of Section 5307 Funding Allocation.
(Andrew Edmonds)
Information Summary Attachments Yes No
Attached is a letter to the NCDOT Integrated Mobility Division requesting Section 5307
Funds for operations, capital, and planning activities. More information will be provided
at the TCC Meeting.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
8
May 25, 2022
Mr. Ryan Brumfield, PE
Director
Integrated Mobility Division (PTD, Bike, Ped)
North Carolina Department of Transportation
1550 Mail Service Center
Raleigh, NC 27699-1550
Dear Mr. Brumfield,
On behalf of the High Point Urbanized Area Metropolitan Planning Organization, I would like to
request that FFY22 Section 5307 funds apportioned to the High Point Urbanized Area be
allocated to recipients in the UZA. The maximum amount of Section 5307 funds available to
each municipality to support operating, capital, and planning activities is identified below.
Guilford County $ 100,000.00
Davidson County $ 300,000.00
PART $ 900,000.00
High Point $ 2,884,618.00
$ 4,184,618.00
If you have any questions, please contact Greg Venable at 336-883-3310.
Sincerely,
Martha Wolfe
TAC Chairman
c: Greg Venable, Interim Transportation Director, City of High Point
Andrew Edmonds, Transportation Planner, City of High Point
Richard Jones, Transportation Manager, Davidson County
Scott Rhine, Executive Director, Piedmont Authority for Regional Transportation
Angela Wynes, Transit Manager, City of High Point
Irma Zimmerman, Transportation Supervisor, Guilford County
9
TCC
Meeting
Meeting Date 6/21/2022 Agenda Item No. 4
Action Requested Information
Section Tab
P7.0 Update (Greg Venable)
Information Summary Attachments Yes No
Update on the P7.0 Process.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
10
TCC
Meeting
Meeting Date 6/21/2022 Agenda Item No. 5
Action Requested Information
Section Tab
Bus and Bus Facilities Letters of Support (Andrew Edmonds)
Information Summary Attachments Yes No
On March 7, 2022, Federal Transit Administration announced $372 million available for
Fiscal Year 2022 grants to help transit agencies purchase and rehabilitate buses, vans, and
related equipment and build bus facilities. This FY 22 opportunity was part of a larger
package in competitive grant funds to help modernize bus fleets and facilities across the
country, including $1.1 billion to help transit agencies purchase or lease low- or no-
emission vehicles that use advanced technologies to help improve air quality and combat
climate change.
High Point Transit System requested letters of support for four project applications that
were submitted May 31, 2022. These projects include the Five Points Transfer Hub, an
operator training facility, an addition to the maintenance facility, and a new vehicle to
replace aging fleet.
All four of these projects have been identified in the Metropolitan Transportation
Improvement Program.
Copies of the letters of support have been attached to the agenda for your reference.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
11
12
13
14
15
TCC
Meeting
Meeting Date 6/21/2022 Agenda Item No. 6
Action Requested Information
Section Tab
Bipartisan Infrastructure Law Opportunities & Safe Streets For All (Andrew Edmonds)
Information Summary Attachments Yes No
The Bipartisan Infrastructure Law includes billions of dollars in competitive funding
available to cities, towns, and municipalities across dozens of new and existing programs.
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
16
TCC
Meeting
Meeting Date 6/21/2022 Agenda Item No. 7-10
Action Requested Information
Section Tab
MPO Reports
Information Summary Attachments Yes No
Agenda Item 7
Division Reports
Agenda Item 8
NCDOT Transportation Planning Division Report
Agenda Item 9
FHWA Report
Agenda Item 10
Public Transportation Reports
TCC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
17
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO - UNDER DEVELOPMENT
Estimated
TIP/WBS # Description Let/Start Date Completion Cost Status Project Lead
Date
EB-5519 Lydia greenway trail from Jamestown municipal building to Jul. 2019 8/31/22 $1,198,415 LAP, Under Construction, Contract Donnie Huffines
50035.3.1 York Leigh Road (Non-System) in Jamestown 4/30/22 Administered by Town of Jamestown
SS-4907CN Install All-Way Stop with flasher and radius improvements on Dec. 2019 8/31/22 $90,000 Radius improvements completed, Dawn McPherson
48759.1.2 SR 1113 (Kivett Drive) at SR 1145 (Riverdale Drive) east of Jun. 2022 Traffic materials pending acquisition - Derek Dixon
48759.2.1 High Point Materials have been ordered -
48759.3.1 Construction underway - Pavement
markings and sign installation
scheduled for 6/30/22
SS-6007P Bridge #57 on SR 1113 (Kivett Drive) over Reddick's Creek - 7/1/22 10/31/22 $36,000 Planning and design activities Bobby Norris
49423.1.1 Install bridge approach guardrail with MASH compliant end 5/13/22 8/31/22 underway
49423.3.1 units
SS-4907CF Install traffic signal with pedestrian count down heads at the Mar. 2022 9/30/22 $120,000 Signal plans not complete, MA w/City of Dawn McPherson
48252.1.1 intersection of SR 1278 (University Parkway) and Davis Jun. 2022 High Point executed. Poles arrived
48252.2.1 Avenue (non-system) in High Point. Traffic signal to be 8/23/2021. Construction underway -
48252.3.1 supported by metal strain poles. Poles have been installed and
pavement markings and final signs
remain to be completed.
SS-6607AC Installation of 2 lines of trailing approach bridge guardrail at Jul. 2022 Sep. 2022 $33,000 Planning and design activities Bobby Norris
49824.1.1 Bridge #400196 on SR 1193 (Baker Road) over US 29-70 in Jun. 2022 Aug. 2022 underway
49824.2.1 High Point.
49824.3.1
SS-6207B Installation of Thermoplastic Lane Arrows to emphasize the 6/15/22 8/15/22 $8,000 Final inspection completed 6/6/22 Dawn McPherson
50317 one-way direction on SR 1300 (West Green Drive) at Jacobs
Place, Tomlinson Street, and South Lindsay Street.
U-6018 Improve interchange at NC 62 and I-85 and realign 4/18/23 FY2026 $12,300,000 Planning and design activities Rob Weisz
47163.1.1 intersections along NC62 at SR 1154 (Kersey Valley Road) underway, ROW acquisition underway
47163.2.1 and SR 1162 (Weant Road) in Archdale
47163.3.1
18
Page 1 HPMPO Jun. 2022
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO - UNDER DEVELOPMENT
Estimated
TIP/WBS # Description Let/Start Date Completion Cost Status Project Lead
Date
U-4015A Widen SR 1556 (Gallimore Dairy Road) to multilanes from NC 5/16/23 FY2025 $6,600,000 Planning and design activities Brian Ketner
35013.1.4 68 to Airpark East in Greensboro underway, coordinate with U-5974,
35013.2.4 ROW acquisition underway
35013.3.4
U-4758 Improvements to Johnson Street/Sandy Ridge Road from 12/19/23 FY2026 $45,700,000 Planning and Design activities Laura Sutton
40251.2.1 Skeet Club Road to I-40 underway, Public meeting 8/14/18 -
40251.3.1 ROW underway
B-5723 Replace Bridge 54 over Richland Creek on SR 1158 (Jackson 11/19/24 FY2026 $3,237,000 Planning and design activities Rob Weisz
45679.1.1 Lake Road) underway
45679.1.2
45679 2 1
I-5712 Interchange improvements at I-40/US 421 and SR 1850 12/15/26 FY2029 $14,500,000 Planning and Design activities Laura Sutton
50126.1.FS1 (Sandy Ridge Road) in Greensboro. Sandy Ridge Road underway, Coordinate with U-4758 & U-
50126.2.1 widening to Cider Road 6045
50126.3.1
U-5974 Upgrade NC 68 to Superstreet from SR 1523 (Hickswood 7/18/28 FY2030 $48,100,000 Planning and design activities Brian Ketner
45962.1.1 Road) to SR 1556 (Gallimore Dairy Road) in High Point underway, coordinate with U-4015A
45962.2.1
45962.3.1
U-6121 Widen SR 1541 (Wendover Avenue) from NC 68 (Eastchester 11/21/28 FY 2031 $27,300,000 Planning and design activities Brian Ketner
48605.1.1 Drive) in High Point to SR 1541 (Guilford College Road) in underway
48605.2.1 Greensboro.
48605.3.1
19
Page 2 HPMPO Jun. 2022
North Carolina Department of Transportation 6/10/2022
Active Projects Under Construction - Guilford Co.
Contract TIP Number Location Description Contractor Name Resident Contract Bid Availability Completion Work Start Estimated Progress Completion
Number Engineer Amount Date Date Date Completion Schedule Percent
Date Percent
C203256 U-3615B SR-1820 (SKEET CLUB RD) FROM EAST OF SR-1818 APAC - ATLANTIC INC Hayes, PE, $30,898,017.15 3/2/2015 3/29/2019 5/20/2015 7/1/2022 99.9 99.9
(JOHNSON ST) TO WEST OF NC-68 (EASTCHESTER DR) IN THOMPSON ARTHUR Meredith
HIGH POINT. DIVISION
C204071 U-5169 I-74/US-311 AND NC-68 (EASTCHESTER DR) BRANCH CIVIL INC Snell, PE, $22,481,354.65 7/30/2018 1/28/2021 9/14/2018 6/30/2022 100 94.07
INTERCHANGE IMPROVEMENTS. William H
C204096 U-2525C GREENSBORO EASTERN LOOP FROM US-29 NORTH OF ES WAGNER COMPANY Julian, Jason $120,471,182.82 4/30/2018 11/20/2022 5/7/2018 7/21/2023 80.64 93.37
GREENSBORO TO SR-2303 (LAWNDALE DR). LLC/SMITH-ROWE LL R
C204103 U-2412A SR-1486/SR-4121 (GREENSBORO/HIGH POINT RD) FROM BRANCH CIVIL INC Lorenz, PE, $55,963,119.69 7/30/2018 12/28/2021 9/12/2018 10/20/2023 91.7 88.89
US-311 BYPASS TO WEST OF SR-1480 (VICKREY CHAPEL Kris
RD).
C204150 U-5896 US-29/US-70/I-85 BUSINESS, SR 1009 (S. MAIN ST.) IN HIGH BOGGS CONTRACTING, Lorenz, PE, $25,325,396.73 3/28/2022 2/28/2025 4/23/2022 2/28/2025 4.7 2.28
POINT AND BRIDGE #147 OVER US-311 ON US-29/US-70/I- INC Kris
85 BUSINESS
C204371 U-2581BA US-70 (BURLINGTON RD) FROM WEST OF SR-3045 (MT APAC - ATLANTIC INC Snell, PE, $11,125,538.10 7/1/2020 4/30/2022 7/1/2020 7/31/2022 100 90.21
HOPE CHURCH RD) /SR-2819 (MCLEANSVILLE RD) TO THOMPSON ARTHUR William H
EAST OF SR-2826 (BIRCH CREEK RD) DIVISION
C204499 R-4707 INTERCHANGE OF US 29 AND SR 4771 (REEDY FORK APAC - ATLANTIC INC Hayes, PE, $46,382,713.04 6/2/2021 10/28/2024 6/7/2021 10/28/2024 30 21.5
PARKWAY) THOMPSON ARTHUR Meredith
DIVISION
C204626 RESURFACE 1 SECTION OF NC 87, 1 SECTION OF NC 49 FSC II LLC DBA FRED Lorenz, PE, $4,639,570.37 6/3/2021 11/1/2022 6/28/2021 11/1/2022 52.1 15.36
AND 21 SECTIONS OF SECONDARY ROADS SMITH COMPANY Kris
C204665 U-5754 US-29/US-70/US-220 (O'HENRY BLVD.) FROM I-40/I-85 BUS. BRANCH CIVIL INC Lorenz, PE, $5,144,885.00 3/15/2022 3/14/2023 4/25/2022 3/14/2023 18.1 7.25
TO SOUTH OF FLORIDA ST. IN GREENSBORO. Kris
DG00490 AST TREATMENT OF 26 SECONDARY ROADS IN CAROLINA ROAD Lorenz, PE, $832.311.02 4/1/2021 10/30/2021 4/8/2021 6/30/2022 100 97.46
GUILFORD COUNTY SOLUTIONS LLC Kris
DG00512 RESURFACE 43 VARIOUS STATE ROUTES SHARPE BROTHERS A Hayes, PE, $2,562,749.29 7/1/2021 11/1/2022 7/1/2022 11/1/2022 51 89.73
DIVISION OF VECELLIO & Meredith
GROGAN INC.
Page 1 of 3
20
North Carolina Department of Transportation 6/10/2022
Active Projects Under Construction - Guilford Co.
Contract TIP Number Location Description Contractor Name Resident Contract Bid Availability Completion Work Start Estimated Progress Completion
Number Engineer Amount Date Date Date Completion Schedule Percent
Date Percent
DG00513 REPLACE BRIDGE #235 OVER BIG ALAMANCE CREEK ON SMITH-ROWE, LLC Hayes, PE, $1,675,367.75 6/21/2021 10/25/2022
SR 1005 (ALAMANCE CHURCH ROAD) Meredith
DG00515 AST TREATMENT OF 34 SECONDARY ROADS IN WHITEHURST PAVING CO. Lorenz, PE, $749,755.28 7/1/2021 6/30/2021 4/25/2022 6/30/2022 61.9 73.14
GUILFORD COUNTY INC. Kris
DG00524 R-5787-G INSTALLATION OF ADA COMPLIANT CURB RAMPS AT ATLANTIC CONTRACTING Lorenz, PE, $717,704.25 6/1/2021 4/14/2023 7/26/2021 4/14/2023 19.9 78.64
R-5787-H VARIOUS ROUTES COMPANY, INC. Kris
DG00527 HS-2007C INSTALLATION OF THERMOPLASTIC PAVEMENT MARKING TMI SERVICES INC. Cvijetic, PE, $1,358,289.72 8/16/2021 11/19/2021 5/18/2022
LINES ON VARIOUS SECONDARY ROUTES Bojan
DG00531 RESURFACE SR 1001 (CHURCH STREET) - 3 SECTIONS, SHARPE BROTHERS A Hayes, PE, $2,780,006.94 7/8/2021 7/7/2022 8/12/2021 7/7/2022 60 96.13
SR 2714 (RED CEDAR ROAD) AND SR 2748 (SPRINGWOOD DIVISION OF VECELLIO & Meredith
CHURCH ROAD) GROGAN INC.
DG00533 MILLING, RESURFACING AND PAVEMENT MARKINGS ON I- BLYTHE CONSTRUCTION Lorenz, PE, $2,989,292.45 7/8/2021 7/7/2022 9/20/2021 7/7/2022 73.4 65.14
85 BUS/US 29/US 70, NC 150 AND VARIOUS SECONDARY INC. Kris
ROADS
DG00545 REPLACE PIPE #40 ON SR 2930 (BETHEL CHURCH ROAD) BOGGS CONTRACTING, Cvijetic, PE, $346,396.50 6/16/2022 2/15/2023 6/16/2022
IN GUILFORD COUNTY INC Bojan
DG00551 R-2413A(L) LANDSCAPE PLANTING ALONG I-73 FROM BRYAN BLVD. COUNTRY BOY Lorenz, PE, $593,953.15 12/20/2021 6/19/2023 3/21/2022 6/19/2022 28.2 20.77
TO US 220 LANDSCAPING INC. Kris
DG00552 R-2413C(L) LANDSCAPE PLANTING ALONG US 220 FROM I-840 TO NC GOLDSTAR PROJECT Lorenz, PE, $119,464.76 12/20/2021 6/19/2023 3/4/2022 6/19/2023 81.2 79.18
65 GROUP LLC Kris
DG00555 REPLACE PIPE #402221 ON SR 3426 (SHERATON PARK C2 CIVIL LLC Cvijetic, PE, $529,396.00 3/7/2022 12/1/2022 3/7/2022 5/31/2022 52 57.09
ROAD) IN GUILFORD COUNTY Bojan
DG00572 REPLACE BRIDGE #25 OVER POLE CAT CREEK ON SR RE BURNS & SONS CO. Lorenz, PE, $1,285,359.02
1105 (EAST STEEPLE CHASE ROAD) INC. Kris
Page 2 of 3
21
North Carolina Department of Transportation 6/10/2022
Active Projects Under Construction - Guilford Co.
Contract TIP Number Location Description Contractor Name Resident Contract Bid Availability Completion Work Start Estimated Progress Completion
Number Engineer Amount Date Date Date Completion Schedule Percent
Date Percent
DG00576 AST RETREATMENT ON 50 SECONDARY ROADS IN WAUGH ASPHALT INC. Lorenz, PE, $811,504.54 5/9/2022 6/30/2023
GUILFORD COUNTY Kris
Page 3 of 3
22
Randolph County - High Point MPO - Active Projects - Division 8--June 2022
Contract # or Completion
Route Description Let Date Contractor Project Admin. Project Cost Notes
WBS # or TIP # Date
DH00327 Various Upgrade Intersections to comply with 7/13/2021 4/30/2022 Eastern Cary Fine $247,107 Project 74% complete
R-5788GA, GB Americans with Disabilities Act (ADA) Earthscapes (336) 318-4020
using TA Funds
HI-0002 I-85 Randolph Co. Pavement Rehab - from I-85/NC 109 in 4/19/2022 10/15/2023 Blythe Michael Ricketts $13,384,387 Project just starting
Thomasville to SR 1009 (South Main St) in Construction Inc. (910) 773-8033
Archdale
17BP.8.R.136 SR 1557 (Morris Rd) Replace Bridge No. 54 over unnamed 3/23/2021 9/27/2022 APAC Cary Fine $910,339 Project 91% complete
DH00325 tributary of the Uwharrie River (336) 318-4020 Now open to Traffic
Randolph County - High Point MPO - Upcoming Projects - Planning & Design, R/W, or not started - Division 8- June 2022 Initial Draft STIP in RED
Contract # or Completion
Route Description Let Date Contractor Project Admin. Funds Needed Notes
WBS # or TIP # Date
U-3400 SR 1577 / SR 1004 Widening from SR 1567 (Robbins Country 11/18/2025 TBD TBD Jeff Stroder $38,626,000 Right of Way 1/2023 FY 2023
(Archdale Road) Rd) to US 311 (Main Street) in Archdale FY 2026 (910) 773-8034 Public Meeting held 2/27/18
U-5308 SR 1547 (Finch Farm Rd) Widening from south of SR 3106 Kennedy 6/17/2025 TBD TBD Jeffrey Teague $35,462,000 Right of Way in progress
Rd to NC 62 FY 2025 (910) 773-8025 Public Meeting held 3/29/2018
2nd Public Meeting 11/29/18
U-5770 I-85 / SR 1993 Interchange Improvements 4/15/2025 TBD TBD Jeff Stroder $21,034,000 Right of Way in progress
(South Main Street) Frontage Road Alternative Selected FY 2025 (910) 773-8034 Public Meeting 11/30/17
Newsletter Mailed 6/8/18
U-5864 SR 1595 (Surrett Drive) 3-lane widening from I-85 to SR 1300 (W. 8/15/2028 TBD TBD Greg Davis $33,864,000 Right of Way 6/2024 FY 2026
Fairfield Rd. /Guilford Co.) in Trinity, FY 2029 (910) 773-8022 Public Meeting held 6/13/19
Archdale, and High Point
U-6191 NC 62 Modernize roadway between SR 3252 10/17/2028 TBD TBD Greg Davis $22,800,000 Right of Way 10/2026 FY 2027
(Surrett Dr) in Trinity to SR 1009 (N. Main FY 2029 (910) 773-8022
St) in Archdale
23
High Point MPO
Transportation Update
June 1, 2022
Project
T.I.P. No. Description Let Date Completion Date Status Construction Cost Contractor Comments
Administrator
PROJECTS UNDER CONSTRUCTION
Little Mountain Builders began work April 19, 2021,
upgrading various wheelchair ramps and sidewalks to new
R-5789F
ADA standards. All new installation has been completed in
44919.3.7 Little Mountain
ADA Ramps at Various Locations in Davidson, Davie, Kelly Seitz, PE Davidson, Davie, and Rowan Counties. Contractor currently
R-5789G March 1, 2021 March 31, 2022 85% Complete $2,524,367 Builders of Catawba
Forsyth and Rowan Counties (704) 630-3200 has 2 crews performing replacements in Winston Salem.
44919.3.8 County, Inc
Other locations in Forsyth County that have been completed
(DI00235) are Kernersville, King, and Lewisville. Estimated project
completion is the end of July 2022.
Milling, Resurfacing, and Shoulder grading of (18)
2021CPT.09.02.20291 Availability date Blythe Construction, Jeb Smith, PE
sections of Secondary routes in Davidson County, February 16, 2021 October 28, 2022 $4,150,985 Contractor plans to begin work in mid-June.
(C204604) May 3, 2021 Inc (704) 630-3220
totaling 28.6 miles
Whitehurst paving scheduled to start AST on May 12, 2022.
2022CPT.09.11.20292 Asphalt Surface Treatment (AST) in Davidson County - Whitehurst Paving Jeb Smith, PE
September 22, 2021 October 14, 2022 0% Complete $1,740,522 The Contractor is anticipated to be completed by end of June
(DI00253) Various Secondary Routes – 78 Sections Co. (704) 630-3220
2022.
2021CPT.09.26.20292 Polyurea Pavement Markings on I-285/US 52 from SR JP Couch, PE Project was awarded on March 22, 2021. Project is 75%
February 10, 2021 TBA 75% Complete $228,300 TMI Services, Inc.
(DI00245) 1147 (Old Salisbury Rd) to NC 8, North of Lexington (336) 747-7800 complete
Replace Bridge #459 on SR 2160 (Smith Ave) over Triangle Grading & Jeb Smith, PE The project is substantially complete ICT No. 1 on May 5,
17BP.9.R.33 June 23, 2021 July 31, 2022 56% Complete $400,000
Charles creek in Davidson County. Paving, Inc (704) 630-3220 2022 and waiting on vegetation establishment.
Contractor is currently waiting for delivery of corrugated
Replace Culvert #564 on Unnamed Creek and replace aluminum pipe culverts and headwalls, prior to mobilizing to
17BP.9.C.14 Chatham Civil Larry Shaver
Culvert #504 on Branch of Cabin Creek at SR 2522 August 25, 2021 December 16, 2021 0% Complete $920,485 Handy Road. Tenative start date has been pushed from mid-
17BP.9.C.13 Contracting, LLC (336) 249-6255
(Handy Rd) in Davidson County. March to May 2022. Contractor needs to recieve materials
for waterline construction before work can begin.
Lane closures alternate throughout throughout the project, as
R-5737 the Contractor works to build crossovers for future traffic
Convert at grade intersection to Interchange on US Larry Shaver
50195.3.1 October 19, 2021 February 28, 2026 7% Complete $25,893,075 Smith-Rowe patterns. Clearning and grubbing, drainage, and erosion
29/70/I-85 Bus at SR 1798 (Old Greensboro Rd) (336) 249-6255
(C204399) control are the current operations until the detour work is to
begin next month.
TRP began construction March 15 and has completed all
W-5809A Install Rumble Strips on NC 109 from SR 2067 TRP Construction Kelly Seitz, PE work under the contract. Crews are currently finishing up
October 27, 2021 TBD 99% Complete $374,464
48954.3.2 (Lambeth Rd) to the Northern Denton Municipal Limits Group, LLC (704) 630-3200 punch list items. Expected project completion is the end of
May.
Welcome-Arcadia Rd at the bridge over Reedy Creek has
Replace Bridge #63 on SR 1472 (Welcome Arcadia Larry Shaver been closed and detours are set in place. The bridge will be
17BP.9.R.57 February 9, 2023 July 29, 2022 0% Complete $858,581 Smith-Rowe, LLC
Rd) over Reedy Creek in Davidson County. (336) 249-6255 demolished and rebuilt by the end of the summer. Completion
date set at July 29, 2022.
Replace Bridge #230 on SR 2250 (Becks Church Rd) Eastern Structures, Daniel Dagenhart
17BP.9.R.79 April 27, 2022 TBD 0% Complete $1,234,179 Division Let - Design in progress.
over Pounder Fork Creek in Davidson County. LLC (336) 747-7800
High Impact Low Cost Project - Construction began in late
Construct additional left turn lane on I-85 South Bound April 6, 2022 Under Kevin Hedrick, PE April with the removal of existing traffic island, grading of
47796 TBD $358,000 State Forces
Exit Ramp at NC 109 in Thomasville (State Forces) Construction (336) 224-3200 curb and the grading for the pavement widening. The initial
phase of work is progressing.
24
Page 1 of 3
High Point MPO
Transportation Update
June 1, 2022
Project
T.I.P. No. Description Let Date Completion Date Status Construction Cost Contractor Comments
Administrator
PROJECTS UNDER DEVELOPMENT
Raleigh Let - Final Plans recieved There will likely be a
B-5765
Replace Bridge #115 on SR 1711 (Gumtree Rd) over ROW Acquisition Kevin Fischer, PE delay in availability for the contractor to begin work; this will
45721.3.1 August 16, 2022 TBD $3,850,000 TBD
WSSB RR in progress (919) 707-6514 allow time for railroad coordination and acquiring materials
(C204385)
for the project.
Raleigh Let - Approved to move forward with PE. Reinitiation
B-5773 Replace Bridge #25 on SR 3346 (S. Main St) over ROW Acquisition Ryan Newcomb, PE
January 20, 2026 TBD $3,250,000 TBD meeting held March 2022. Working on scope and fee for
45729.3.1 WSSB RR in Lexington (Combine let with BR-0015) Jan. 15, 2025 (336) 747-7800
additional PE work.
PROJECTS UNDER DEVELOPMENT
B-5777 ROW Acquisition Ryan Newcomb, PE Raleigh Let - Approved to move forward with PE. Working
Replace Bridge #58 on NC 109 over US 64 January 16, 2024 TBD $1,850,000 TBD
45733.3.1 Jan. 15, 2023 (336) 747-7800 on scope and fee for PE. PE work has started.
*Schedule based on Approved 2020-2029 STIP - Raleigh
Let - Coordinate with B-5785. Division is currently working
on a feasibility study for this bridge replacement and how this
B-5779 Replace Bridge #118 on US 29NB/64EB/70EB over SR ROW Acquisition Ryan Newcomb, PE will work with the overall interchange. PE was authorized to
April 15, 2025 TBD $4,061,000 TBD
45735.3.1 3346 (N Main St) in Lexington April 19, 2024 (336) 747-7800 restart in January 2021. We will be coordinating with the
STIP and Feasibility group to determine how to proceed with
the bridge project. Working on scope and fee for PE. NTP
issued. PE work has started.
*Schedule based on Approved 2020-2029 STIP - DDRL
B-5783 Replace Bridge #164 and Bridge #168 on US 29/70/I- Planning/Design Ryan Newcomb, PE
May 16, 2023 TBD $5,778,000 TBD Let - Approved to move forward with PE. 25% plans
45738.3.1 85 Bus over NSRR in Progress (336) 747-7800
complete. 65% plans complete.
B-5785 Replace Bridge #121 and Bridge #122 on US 29/70/I- ROW Acquisition Daniel Dagenhart Raleigh Let - Coordinate with B-5779. Approved to move
February 17, 2026 TBD $4,000,000 TBD
45740.3.1 85 Bus over Leonard Creek Feb. 16, 2025 (336) 747-7800 forward with PE.
B-5787 ROW Acquisition Connie James, PE
Replace Bridge #29 on NC 49 over NC 109 January 20, 2026 TBD $2,000,000 TBD Raleigh Let. - Approved to move forward with PE.
45741.3.1 Jan. 15, 2025 (336) 747-7800
Replace Bridges #67 and #68 over SR 1192 (W. 5th
BR-0015 ROW Acquisition Kevin Fischer, PE
Ave) on US 29/70/ I-85 Business in Lexington November 21, 2023 TBD $6,200,000 TBD Raleigh Let - Approved to move forward with PE.
67015.3.1 Nov. 22, 2022 (919) 707-6514
(Combine let with B-5773)
Raleigh Let. Approved to move forward with PE. Working on
BR-0016 Replace Bridge #150 over SR 2123 (Kanoy Rd) WB on ROW Acquisition Ryan Newcomb, PE
January 20, 2026 TBD $5,175,000 TBD scope and fee for PE. Scope and fee approved. PE work has
67016.3.1 I-85 Bus in Thomasville Jan. 19, 2025 (336) 747-7800
started.
BR-0140 Replace Bridges #87 and #89 0n US 29/70/I-85 Bus ROW Acquisition Ryan Newcomb, PE Raleigh Let - New - In development. Working on scope and
September 16, 2025 TBD $6,800,000 TBD
67140.3.1 over WSSB Railroad Jan. 22, 2024 (336) 747-7800 fee for PE. NTP issued. PE work has started.
*Schedule based on Adjusted 2020-2029 STIP - DDRL -
Pavement Rehabilitation on I-85 from US 29/52/70/I-85 Combine I-5950 and I-5951 - This project will include bridge
I-5950 Planning/Design Matt Jones, PE
Bus to N of SR 2205 (Old US 64) and from NC 109 to September 20, 2022 TBD $14,740,000 TBD preservation in this corridor, STIP description will be updated
45897.3.1 in Progress (336) 747-7800
Randolph County Line (Includes I-5951) to reflect this. Construciton estimate will be updated once
adjusted.
*Schedule based on Adjusted 2020-2029 STIP - DDRL -
R-4734 Widen NC 109 to multilanes from NC 109 in Denton to Post Year ROW Acquisition Ryan Newcomb, PE *The PE work for this project has been temporarily
TBD $132,096,000 TBD
38954.3.1 I-85 in Thomasville Jan., 2040 Jan. 21, 2028 (336) 747-7800 suspended.* Express design update in progress to revise
project estimate.
U-5757 Widen NC 8 (Winston Rd) to multi-lanes from 9th St to ROW Acquisition Ryan Newcomb, PE
July 18, 2023 TBD $8,800,000 TBD *Schedule based on Adjusted 2020-2029 STIP - DDRL -
54035.3.1 SR 1408 (Biesecker Rd) in Lexington in progress (336) 747-7800
25
Page 2 of 3
High Point MPO
Transportation Update
June 1, 2022
Project
T.I.P. No. Description Let Date Completion Date Status Construction Cost Contractor Comments
Administrator
PROJECTS UNDER DEVELOPMENT
BP9-R001
Replace Bridge #469 on SR 2183 (Fisher Ferry Rd) ROW Acquisition Daniel Dagenhart
BP9.R001.3 May 24, 2023 TBD $1,300,000 TBD Division Let - Approved to move forward with PE.
over North Hamby's Creek in Davidson County May 20, 2022 (336) 747-7800
formerly 17BP.9.R.16)
BP9-R003
Replace Bridge #286 on SR 2545 (Slate Mine Rd) over ROW Acquisition Daniel Dagenhart
BP9.R004.3 August 16, 2023 TBD $1,400,000 TBD Division Let - Approved to move forward with PE.
Beaverdam Creek in Davidson County. July 16, 2022 (336) 747-7800
(formerly 17BP.9.R.74)
BP9-R006
Replace Bridge #246 on SR 2351 (Flat Swamp Rd) ROW Acquisition Daniel Dagenhart
BP9.R006.3 February 14, 2024 TBD $900,000 TBD Division Let - *Approved to move forward with PE.
over Lick Creek in Davidson County Jan. 14, 2023 (336) 747-7800
(formerly 17BP.9.R.92)
STATE FORCES CONSTRUCTED PROJECTS
Re-align intersection of SR 2184 (Cedar Lodge Rd) Matt Jones, PE High Impact Low Cost Project - Project released to move
47795 April 2023 TBD In development $372,000 State Forces
and Liberty Drive (NS) in Thomasville (336) 747-7800 forward. Let date under review.
COMPLETED PROJECTS
This project widened NC 150 to install a left turn lane into
W-5709C Becky Hill Rd. Country Boy Landscaping is the contractor.
Construct left turn lane on NC 150 at SR 1435 (Becky Country Boy Kelly Seitz, PE
44855.3.3 July 26, 2021 November 24, 2021 99% Complete $500,584 Contractor began construction August 16, 2021; and the new
Hill Rd) - Safety Improvements. Landscaping (704) 630-3200
DI00222 turn lane was opened November 21, 2021. The project
completion date is June 19, 2022.
26
Page 3 of 3
DCTS June 2022 MPO Update
May Rider Statistics. 62.27% increase in riders over May 2022. Best month we have had
since reinstatement of our Deviated Fixed Routes. Increase of 35 riders per day from April
2022.
FTA Direct Recipient. The process of becoming a Direct Recipient of the FTA continues.
We have been working through FTA responses to our submission of required documents/
worksheets. IMD goal is for the process to be complete by June 30, 2022.
Demand Response Transportation Providers RFP. Current third-party contracts for De-
mand Response transportation providers expire on October 31, 2022. Work on the RFP has
begun and will be launched on August 1, 2022.
Rita Winegar NCPTA Driver of the Year. DCTS Bus Operator Rita Winegar received the
NCPTA Driver of the Year award at this years NCPTA Conference. Rita goes above and be-
yond in caring for the riders.
May 2022
Route Riders % Ave/Day
RED 1,465 15.49% 70
GREEN 1,749 18.49% 83
BLUE 3,899 41.22% 186
ORANGE 2,167 22.91% 103
Thomasville Saturday 179 1.89% 45
Totals 9,459 100.00% 487
May 2021
Route Riders % Ave/Day
RED 982 16.85% 49
GREEN 1,038 17.81% 52
BLUE 2,324 39.87% 116
ORANGE 1,430 24.53% 72
Thomasville Saturday 55 0.94% 14
Totals 5,829 100.00% 302
+/- from previous year 62.27%
27