HPMPO Transportation Advisory Committee (TAC)
Regular MeetingHigh Point, NC · April 28, 2015
Minutes
Attachment 1
MINUTES
TRANSPORTATION ADVISORY COMMITTEE
April 28, 2015
TAC MEMBERS PRESENT:
Neal Grimes – Thomasville
Larry Warlick – Archdale
Fred McClure – Davidson County
Larry Ward – Denton
Cheryl McQueary – NCDOT Board Division 7
Bill Bencini – High Point
Keith Volz – Jamestown
TCC MEMBERS PRESENT: Greg Venable, Mark McDonald, Guy Cornman, Hemal
Shah, Bryan Fulbright, Chuck George, Roger Jones, Zeb Holden, Scott Rhine, Chuck
Smith, Diane Hampton, Jeff Loflin, Darius Sturdivant, Heidi Galanti, Ed Lewis, John
Gray, Wayne Davis, Gregg Errett, Angela Wynes, and Carrie Spencer.
OTHERS PRESENT: John Hanes (Transportation Planning), Randy McCaslin (High
Point), John Tippett (Consultant), Richard Atkins (Triad Transportation Partnerships)
RECORDING SECRETARY: Marianne Janiszewski, City of High Point
Item 1: Reading of the Ethics Statement.
Neal Grimes read the Ethics Awareness and Conflict of Interest Reminder. No one had
any conflicts.
Item 2: Public Comment Period
Neal opened up the public comment period. There were no speakers. Neal closed the
comment period.
ACTION ITEMS
Item 3: Consideration of the March 24, 2015 TAC meeting minutes.
There was no change to the minutes.
Motion by: Fred McClure
Seconded: Larry Warlick
Vote:
For: Unanimous
1
Attachment 1
Against: None
Item 4: Consideration of an amendment from NCDOT to the 2012-2018
Metropolitan Transportation Improvement Program (MTIP).
US 29 / US 70 / BUSINESS 85 SB, Replace bridges 400237 and 400242 over Deep
River in High Point. Revise project scope to include Bridge 400237.
Motion by: Larry Warlick
Seconded: Keith Volz
Vote:
For: Unanimous
Against: None
Item 5: Consideration of an amendment from Hi tran to the 2012-2018
Metropolitan Transportation Improvement Program (MTIP).
High Point Transit System would like to request an amendment to the FY2012
– FY2018 MTIP to allow Hi tran to add funding for our FY15-16 transit operating and
routine capital funding as well as add funding for replacement of half of the Para transit
fleet. The total for Para transit is $175,000, operating assistance $1,500,000, and routine
capital $258,000.
Motion by: Larry Warlick
Seconded: Fred McClure
Vote:
For: Unanimous
Against: None
Information Items:
Item 6: Presentation on A New Approach for Developing Local Government
Priorities.
John Tippit was a Transportation Planning Administration for the Hickory MPO for
several years. He gave a presentation on the above topic.
2
Attachment 1
Cheryl McQuery stated that NCDOT Board Members have access to a small pool of
money that they can spend however they choose. Cheryl represents five counties and she
tries to make sure that she spends money in every county. She gave examples of several
small projects she funded. The High Point MPO is covered by three Board Members so
there is an opportunity to draw upon some small amounts of money. Most times the
Division Engineer is contacted about a project who then in turn contacts Cheryl and
explains the project. They will then decide if it makes sense to spend this kind of money.
At the end of the year the money that is unspent is taken and put into the maintenance
fund. She advised Conover to reach out to the District Engineer and make certain that
that person is on the same page with you on all your projects because there are several
funds that are available. If the Board Member agrees to fund a project a paper is filled
out and sent up to Raleigh for approval and then when approved it will be put on the
board agenda for approval.
AGENCY REPORTS
Item 7: NCDOT Board of Transportation Report.
Cheryl McQueary reported that the General Assembly came up with a solution to the gas
tax but there is still no long term funding fix for NC transportation funds. Greg is
working on getting someone to come out and give a presentation on how funding is
handled in the state. A couple of weeks ago the Governor introduced two bond requests
and Division has two items on the bond. One would complete the Jamestown Bypass
which is a $48,000,000 dollar project, and the other project is NC 119 in Alamance
County, section B of the Mebane Bypass. This is a $17.8 million dollar project.
Item 8: Division Engineer’s Reports.
Division 7
Ed Lewis reported that the Traffic Signal Revision project on Main St., English Rd. is
90% complete. The plans are under review for the traffic signal revisions at Kivett Dr.
and Dillon Rd./Triangle Lake Rd. The High Point Rd. project is 63% complete on work
and 59% complete on the schedule. There are utility relocations under way on the Skeet
Club Rd. project The contract has been awarded to APAC –Atlantic, Thompson Arthur
Division. The design is in progress on the US 311 and NC 68 interchange. They are
planning a workshop later this fall. The utilities have been moved and grading has
begun on the realignment project at Groomtown Rd. and NC 62. There are 12 design-
build bridge projects on the list. Work has started earlier this month on the bridge at
Groomtown Rd. We are expecting about a 120 day closure. There are two other bridge
projects that are currently under construction, one at Lexington Ave. over Bouldin
Branch, and the other on Model Farm Rd. over Richland Creek.
Division 8
Jeff Loflin reported on the list of projects in the draft STIP. Some adjustments have been
made to the project schedule. The I-85 improvement project in Randolph County is
scheduled to be completed in mid-May. The resurfacing program is currently under way.
Some of the utilities have been relocated on the Braxton Craven Rd. bridge replacement
3
Attachment 1
project but some of the bridge funding is in flux so this project is on hold until the
construction funding on bridge projects is determined in July.
Division 9
Diane Hampton reported that they had a good public meeting on April 21 on the MPO
projects process. There were approximately 20 members of the public along with about
20 DOT members. There are several rail and bridge projects under way. The pavement
rehabilitation, bridge preservation, and upgrade to interstate standards project on
Business 85 is 70% complete. The bridges over Swearing Creek will be replaced.
Division 9 recently had a noise wall meeting in which the local community was invited to
come out and see what the noise walls look like. They are waiting on the results of their
ballots to decide whether the noise wall will be put in near the high school project. The
widening of NC8 (Winston Rd.) will be let in FY 2019.
Item 9: Triad Air Awareness.
No one was here.
Item 10: NCDOT Transportation Planning Branch Report.
Hemal Shah reported that based on guidance from FHWA PL (planning funds) cannot be
used to prepare the NEPA document. Planning funds can be used for preliminary
engineering up to 15% of its cost. This language was updated and approved UPWP for
FY 2016 as a technical correction and there was no change in the dollar amount.
Item 11: Hi tran Report
Angela Wynes reported that they are wrapping up their short range transit plan and are
presenting the final draft to council on Thursday afternoon. Council will have a chance
to review all of the input from the public, sounding board, steering committee, as well as
the recommendations that they would like to see over the next five years.
Item 12: PART Report
Scott Rhine stated that the air quality conformity process is on schedule. They will be
going in with a generation of their model activities in May. If everything works fine they
will be moving into their division of air quality work. PART is working with the MPO to
set up at a future meeting to present the freight enhancement study that they have been
working on this current fiscal year. They had some federal highway administration
research funds that were used for this study. This project has been completed. It is
designed to incorporate more freight into the planning process. There will be a
groundbreaking and naming ceremony event on May 13 for the PART Intermodal
Transportation Center honoring Congressman Howard Coble.
Item 13: Other Business
Chuck Smith reported that Jamestown has been awarded two major sidewalk projects.
The town agreed to sign the Municipal Agreement in July, 2014. One project is a $1.2
million dollar pedestrian bridge and sidewalk project and the other is a $150,000 of state
and federal funding for both of these projects. It has taken eight months to get the
4
Attachment 1
municipal agreements back which left them with four months to complete the design
work and testing. They had to spend town funds to start the design process and testing
and are hoping to get reimbursed for those expenditures. Mr. Smith is asking the TAC
for a letter of support to request and extension of the June 30,2015 date out
approximately 2-3 months to allow them to get comments back from DOT and the
railroad.
Motion by: Keith Volz
Seconded: Larry Warlick
Vote:
For: Unanimous
Against: None
The next meeting in May may be cancelled or postponed. Greg will set out an email.
There was no other business. The meeting was adjourned.