HPMPO Transportation Advisory Committee (TAC)
Regular MeetingHigh Point, NC · April 26, 2022
Agenda
HIGH POINT URBAN AREA MPO
TRANSPORTATION ADVISORY COMMITTEE (TAC)
Agenda for the April 26, 2022 TAC Meeting
10:00 AM
Southern Theater & Event Center Meeting
18639 NC-109, Denton, NC 27239 Location
Ethics Statement
In accordance with the State Government Ethics Act, it is the duty of every TAC member to avoid
conflicts of interest. Does any TAC member have any known conflict of interest with respect to any
matters coming before the TAC today? If so, please identify the conflict and refrain from any
participation in the particular matter involved.
Public Comment Period
Action Items
1. Consideration of the March 22nd TAC meeting minutes. (Martha Wolfe) Page 1
2. Consideration of amendments to the 2020-2029 MTIP. (John Hanes) Page 8
Information Items
3. STIP Format and P7.0 Schedule Update (Andrew Edmonds) Page 13
Agency Reports
4. NC Board of Transportation Report (Mike Fox)
5. Division Engineer’s Reports
• Division 7 (Wright Archer) Page 42
• Division 8 (Patrick Norman) Page 46
• Division 9 (Pat Ivey) Page 47
6. Federal Highway Administration Report (Suzette Morales)
7. NCDOT Transportation Planning Branch Report (Michael Abuya)
8. NCDOT Integrated Mobility Division (Alex Rotenberry)
9. Public Transportation Reports
High Point Transit System (Angela Wynes)
Davidson County Transportation (Richard Jones)
RCATS (Tawanna Williams)
PART (Scott Rhine)
Next TAC Meeting
May 24, 2021
TAC
Meeting
Meeting Date 4/26/2022 Agenda Item No. 1
Action Requested Approve
Section Tab
Consideration of the March 22nd TAC meeting minutes. (Martha Wolfe)
Information Summary Attachments Yes No
The complete meeting minutes are in your packet as Attachment 1.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
1
MINUTES
TRANSPORTATION ADVISORY COMMITTEE
March 22, 2022
TAC MEMBERS PRESENT: Martha Wolfe, Doug Hunt, Richard McNabb, Fred
McClure, Larry Ward, Darryl Frye, Andrew Perkins, Jay Wagner, James Upchurch, Lynn
Reece, Suzette Morales
TCC MEMBERS PRESENT: Stephen Robinson, Bryan Kluchar, Fred Haith, Michael
Abuya, Mark McDonald, Greg Venable, Jason Miller, Roger Jones, Chuck George, Pat
Ivey, Scott Rhine
MPO Staff: Gwen Ford, Andrew Edmonds, Tabatha J’Arrante
OTHERS PRESENT: Jim Myers, Karel Van Der Linden
RECORDING STAFF: Microsoft Teams
Reading of the Ethics Statement: Martha Wolfe read the Ethics Statement.
Public Comment Period: No comments.
Action Items
Item 1: Consideration of the January 25th TAC meeting minutes.
Greg Venable made corrections to the last meetings minutes.
Motion by: Larry Warlick
Seconded: Darrell Frye
Vote:
For: Unanimous
Against: None
Item 2: Public Hearing for the 2022-2023 Unified Planning Work Program
(UPWP).
No motion made. Martha Wolfe closed the public hearing.
Motion by:
Seconded:
Vote:
For: Unanimous
Against: None
2
Item 3: Consideration of approval of the HPMPO Self Certification process.
Greg Venable reported every year, prior to adoption of the Unified Planning Work
Program, the MPO is required to certify its planning process and its compliance with
various federal regulations including the Clean Air Act, the Civil Rights Act, the
Americans with Disabilities Act, and the federal transportation authorizing legislation.
The certification states that the MPO is following all federal requirements and is carrying
out its planning process in the appropriate manner. The resolution is a prerequisite for
adoption of the UPWP. A copy of the resolution is included in your packet.
Motion by: Larry Warlick
Seconded: Richard McNabb
Vote:
For: Unanimous
Against: None
Item 4: Consideration of approval of the 2022-2023 Unified Planning Work
Program (UPWP).
Greg Venable reported the UPWP is the MPO’s annual budget and work plan. It lists the
planning tasks that staff expects to perform and the work products that we expect to produce
during the fiscal year. Our fiscal year runs from July 1st through June 30th of next year Each
major division includes several line items under which the MPO can perform work. Each line
item includes explanatory text describing the customary work items for the line item, the
rationale for performing the work, how much money we plan to spend on the line item and
the work products that the MPO expects to produce during the upcoming year. The UPWP
also includes a series of tables showing the sources of the funds used, the amount of federal
funds used, the amount of the local match, and total expenditures for each line item from
each funding source.
The Draft UPWP was out for a thirty (30) day review and comment period. A copy of
the resolution is included in your packet.
Motion by: Doug Hunt
Seconded: Larry Warlick
Vote:
For: Unanimous
Against: None
Item 5: Consideration of amendments to the 2020-2029 MTIP.
Greg Venable reported STIP Modification P-5722 Norfolk Southern, Kimberly Clark in
Lexington. Delay construction from FY 23 to FY 24 to allow additional time for planning
and design.
3
STIP Additions B-5723, SR 1158 (Jackson Lake Rd), replace bridge 400054 over
Richland Creek in High Point. Programmed to reflect latest bridge prioritization.
Motion by: Larry Warlick
Seconded: Darrell Frye
Vote:
For: Unanimous
Against: None
Item 6: Consideration of approval of an amendment to the 2021-2022 UPWP.
Andrew Edmonds reported additional transit funding has been allocated to the High Point
MPO by NCDOT. The current 2021-2022 UPWP needs to be amended to reflect these
additional 5303 transit planning funds. A copy of the amendment UPWP task item table
is included in your packet along with a copy of the amendment resolution.
Motion by: Larry Warlick
Seconded: Richard McNabb
Vote:
For: Unanimous
Against: None
Item 7: Recognition of Mark McDonald.
Greg Venable reported a special recognition for Mark McDonald for his years of service
as City of High Point Director of Transportation and HPMPO TCC Chair. A resolution
was presented.
Motion by: Larry Warlick
Seconded: Darrell Frye
Vote:
For: Unanimous
Against: None
Information Items
Item 8. STIP Delivery Update
Greg Venable reported there is a work group going on for the next TIP. There were five
different scenarios about how to fund projects and what to fund. Scenario 2 takes the
existing TIP projects from P3, P4, & P5 that were committed as well as anything that
4
would be let before FY 2026. They are going to offer a flexibility option to some of our
projects. If we have a project in our area that’s not in the first five years or isn’t
committed; we have the flexibility to switch projects around. It will still have to go out
for public review. Once the STIP is out then we can start working on our Metropolitan
Transportation Improvement Program.
Andrew Perkins added the 2.5% will be a reserve in the new STIP in order to make sure
we can fund all the projects in terms of going up and going down over the 10-year period.
Agency Reports
Item 9. NCDOT Board of Transportation Report
Andrew Perkins reported we continue to maintain the floor of 2 billion dollars based
upon the legislation requirements. We continue to have a very robust fund balance in the
overall program of about 1.5 billion dollars. We believe all the projects that are in the
current STIP after we have done our review and reestimating some of those projects; all
of them in there will in fact be fully funded through completion. We have one more
meeting to review all of the final data that has been put together by the work group and
the MPOs and RPOs throughout the state.
Item 10. NCDOT Division Reports
Division 7
Stephen Robinson reported the Jamestown Greenway has pushed out the completion date
to for a couple of months and expect it to be completed April of this year.
Division 8
Bryan Kluchar reported applications are open for bicycle and pedestrian planning grants.
A link has been provided in the chat of this meeting. You can also register for a webinar
held on April 5th in additions to a complete streets training session link will also be added
to the chat of this meeting.
Division 9
Pat Ivey reported project R-5737 which is the new interchange on US 29/70 at
Davidson-Davie Community College construction has begun and we have US 29/70
narrowed down to one lane in each direction. Motorist can expect that for the next
several years as we begin construction in earnest. This fall we will be moving both
directions of traffic into one direction as we begin construction on the new bridges that
will go over the interchange. Project 47796 which is the addition turn lane on the I-85
south bound ramp at Hwy 109 we anticipate this project will begin construction next
month. We are adding another turn lane at the bottom of the ramp to help reduce some of
the congestion that we are experiencing there.
5
Item 11. Federal Highway Administration Report.
Suzette Morales reported federal highways will be returning to the office on April 25th. In
November the Bipartisan Infrastructure Bill was passed it is also known as IIJA to some.
We will have funding for programs and new fundings as well. Some of these will be
formula funds, some of them will be discretionary. It is important look out for those
discretionary ones as they come up. One will be the electric charging stations, which have
the option of both discretionary and in formula take advantage of this program as they
come up. One area you can take advantage of is the portion where they will fund off
system bridges that are owned by municipalities. There is an option to have those bridges
funded at a 100%.
Item 12. NCDOT Transportation Planning Branch Report.
Michael Abuya had no updates.
Item 13. NCDOT Integrated Mobility Division.
Alex Rotenberry was not present.
Greg Venable made an introduction of Alex Rotenberry to TAC members.
Item 14. Public Transportation Reports
High Point Transit
Andrew Edmonds reported the Triad just finalized a technology RFP that will allow users
to track their buses between systems. We have four upcoming applications coming for the
bus and bus facility grant that we will be requesting a letter of support for the four
applications.
Davidson County Transportation
Richard Jones had no updates.
RCATS
Tawanna Williams reported everything is looking good in Randolph County. We are
looking at moving forward with some wonderful new projects with great possibilities.
Our numbers are starting to ramp back up.
PART
Scott Rhine reported the household survey related to our travel demand model; I reported
last month that was going in front of the City of Greensboro for contract award, but it has
6
been delayed and will be on the agenda in City of Greensboro in April. This is a little
behind, but hope to get it kicked off, because it’s a very important piece for data input for
the validity of the model.
Our overall work program and budget for our Piedmont Triad Reginal Model that has
gone through the technical committee and is included in the UPWP that you have already
approved. Our executive committee will be meeting the first of April and will be tied into
up coming budgets.
We have some route planning activities underway. Route 10 in Randolph County; we are
going through some planning process now and we have some follow up with local
community leaders for some public outreach and input. But we are planning on moving
forward with some expansion of that service into our up coming fiscal year.
7
TAC
Meeting
Meeting Date 4/26/2022 Agenda Item No. 2
Action Requested Approve
Section Tab
Consideration of approval of amendments to the 2020-2029 MTIP. (John Hanes)
Information Summary Attachments Yes No
The proposed amendments to the 2020-2029 MTIP for the High Point MPO are included
in you packet. Staff is recommending approval of the MTIP amendments.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
8
High Point
RESOLUTION
Archdale AMENDING THE 2020-2029 HIGH POINT METROPOLITAN
TRANSPORTATION IMPROVEMENT PROGRAM
WHEREAS, the Transportation Advisory Committee has reviewed the 2020-2029
Denton
Metropolitan Transportation Improvement Program and found an amendment is
necessary; and
Jamestown WHEREAS, the following amendments have been proposed:
Lexington
Thomasville
Trinity
Wallburg
Davidson
County
Forsyth
County
Guilford
County
Randolph
County
9
High Point
Archdale
Denton
Jamestown
Lexington
Thomasville
Trinity
Wallburg
Davidson
County
Forsyth
County
Guilford
County
Randolph
County
10
High Point
Archdale
Denton
Jamestown
Lexington
Thomasville
Trinity
Wallburg
Davidson
County
Forsyth
County
Guilford
County
Randolph
County
11
High Point
Archdale NOW THEREFORE, be it resolved by the Transportation Advisory Committee for the
High Point Metropolitan Planning Organization that the 2020-2029 Metropolitan
Transportation Improvement Program be amended as listed above on this the 22nd day of
March 2022.
Denton
A motion was made by TAC Member ______________and seconded by TAC
member _______________ and approved this the 26th day of April 2022.
Jamestown
_________________________
Martha Wolfe,
Lexington Chair, Transportation Advisory Committee
Thomasville
Subscribed and sworn to me this the 26th day of April 2022.
______________________________________
Trinity
Notary Public
My commission expires ______________________
Wallburg
Davidson
County
Forsyth
County
Guilford
County
Randolph
County
12
TAC
Meeting
Meeting Date 4/26/2022 Agenda Item No. 3
Action Requested Information
Section Tab
STIP Format and P7.0 Schedule Update (Andrew Edmonds)
Information Summary Attachments Yes No
The Strategic Prioritization Office of Transportation has announced a new format for the
upcoming May 2022 release of the Draft 2024-2033 STIP. The new STIP will be released
as an Excel format to improve the ease of organization and searchability.
As you all are aware, the schedule for prioritization has gone through several changes. In
Summer 2021, the SPOT workgroup made a recommendation to the NCDOT Board that
they halt the P6.0 process. The attached presentation from the April 2022 Board of
Transportation outlines the next steps for the P7.0 process. Additional information is
provided in your packet and additional discussion at the meeting.
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
13
April 6, 2022
14
2024-2033 STIP Development Update
Connecting people, products and places safely and efficiently
Today’s Topics
• Review
• Outreach
• Format
• Next Steps / Schedule
• Discussion
2
15
Review
16
Workgroup Discussions
Overall Goals
• Develop trustworthy and dependable STIP (fiscally constrained)
• Produce 2024-2033 STIP using current STIP project list with transparent process
• Have an opportunity to fund new projects in P7 scoring (all 22 categories)
• Ensure process is grounded in state/federal requirements
4
17
2024-2033 STIP Funding Availability for Committed Projects
Statewide Mobility Regional Impact Division Needs
Available Available Programming Available Programming
Programming Status Region Division
Funding Funding Status Funding Status
$10.6B $3.36B Over A (D1 & D4) $647.5M $383.2M Over 1 $569.7M $129.5M Over
B (D2 & D3) $919.2M $391.2M Over 2 $569.7M $190.3M Over
C (D5 & D6) $1.78B $297.1M Over 3 $569.7M $77.3M Under
D (D7 & D9) $1.33B $596.7M Over 4 $569.7M $223.2M Under
E (D8 & D10) $1.67B $756.5M Over 5 $569.7M $172.4M Over
F (D11 & D12) $881.0M $455.7M Over 6 $569.7M $87.4M Under
G (D13 & D14) $676.1M $982.2M Over 7 $569.7M $65.4M Under
REG Total: $3.86B Over 8 $569.7M $85.3M Over
9 $569.7M $31.6M Under
10 $569.7M $68.8M Under
11 $569.7M $102.4M Under
Includes estimated funding from Infrastructure and
12 $569.7M $234.0M Over
Investment Jobs Act (IIJA)
13 $569.7M $325.7M Over
As of January 25, 2022. Available Funding reflects accounting for 3% inflation. Programming Status Amounts are
compared to 100% of budget.
14 $569.7M $88.2M Over 5
DIV Total: $706.9M Over
18
2024-2033 STIP Development
Only includes projects funded in 2020-2029 STIP
All existing projects selected for funding using one of two approaches:
1. Delivery Projects – programmed first
– Currently scheduled for CON in FY 2026 or before, ROW underway or has federal grant
2. P3-P4-P5 Evaluation (Seniority Approach) – programmed second
– Use highest scores from each cycle until each STI category budget is filled
Once Draft 2024-2033 STIP is developed, opportunity to swap projects
• Swaps must be agreed to by NCDOT and MPO/RPO(s)
• Cost of project(s) swapped in must be < 110% of cost of project(s) being swapped out
Anticipate release of Draft STIP later this spring 6
19
2024-2033 STIP Next Steps / Schedule
7
20
2024-2033 STIP Outreach
21
Outreach
STIP Outreach Sessions (Educational Webinars)
• Technical Staff – MPOs, RPOs, Local Government staff, etc.
• Local Officials – Commissioners, Councilmembers, Mayors, Managers, etc.
• Topics:
− Challenges NCDOT has experienced over the last few years
− Process of developing the 2024-2033 STIP
− Discuss specific opportunities for input
Public Involvement
9
22
2024-2033 STIP Format
23
2020-2029 STIP Format – Not User Friendly
11
24
2020-2029 STIP Format – Not User Friendly
12
25
2024-2033 STIP Format – Excel-based
13
Note: These are not actual projects. Data shown is for illustrative purposes only.
26
2024-2033 STIP Format – Filter to County
Filter to Division
14
27
2024-2033 STIP Format –
Search/Filter by Route (or any other field)
15
28
2024-2033 STIP Format -
Funded Projects that Will Not Be Reprioritized
16
29
2024-2033 STIP Format -
Funded Projects that Will Be Reprioritized
Unfunded Projects that Will Be Reprioritized
17
30
2024-2033 STIP Format –
Projects that Can Be Swapped
Projects to be Let in FY 2023
18
31
2024-2033 STIP Format –
Description/Details of Fund Sources
19
32
2024-2033 STIP Format – Print on 11x17
20
33
Next Steps / Schedule
34
2024-2033 STIP Next Steps / Schedule
Draft STIP released later this spring
• Spreadsheet of funded projects and schedules
• Decision on Project Prioritization Status timeframe
• Discussion on Workgroup recommendation (5 yrs) at May BOT meeting
STIP coordination meetings with MPO & RPOs as needed
Project swaps due to STIP managers by early Fall 2022 with agreement
by MPO/RPO and Division staff
Revised Draft STIP released by December 2022
Anticipated adoption of Final 2024-2033 STIP by BOT in Summer 2023 22
35
2024-2033 STIP Next Steps / Schedule
23
36
Prioritization Next Steps and Schedule
P7 Workgroup scheduled to begin Fall 2022
P7 will generate the 2026-2035 STIP
Anticipated P7 project submittal window: Summer 2023
Anticipated P7 quantitative scores and 2026-2035 Statewide Mobility
programming: Spring 2024
24
37
Discussion
38
PROGRAMMING
SPRING 2022 SUMMER 2023
NCDOT RELEASES WINTER 2022 BOARD OF TRANSPORTATION ADOPTS
DRAFT 2024‐2033 STIP NCDOT RELEASES REVISED DRAFT 2024‐2033 STIP FINAL 2024‐2033 STIP
Today
SPRING 2022 – FALL 2022 FALL 2022 WINTER 2022 – SPRING 2023 SUMMER 2023
STIP OUTREACH SESSIONS, DRAFT STIP PUBLIC COMMENT NCDOT REVISES DRAFT STIP PUBLIC COMMENT PERIOD AND NCDOT FINALIZES MPOS APPROVE TIPS AND FHWA
PERIOD, AND MPO/RPO COORDINATION MEETINGS DRAFT STIP 2024‐2033 STIP APPROVES FINAL 2024‐2033 STIP
PRIORITIZATION 7.0 SPRING 2023 SUMMER 2023
BOARD OF TRANSPORTATION APPROVES P7 SUBMITTAL WINDOW
P7 WORKGROUP RECOMMENDATIONS OPENS
FALL 2022
P7 WORKGROUP KICKS OFF
FALL 2022 – SPRING 2023 SUMMER 2023 – FALL 2023
P7 WORKGROUP DEVELOPS RECOMMENDATIONS P7 PROJECT SUBMITTAL WINDOW
FALL 2023
P7 SCORING BEGINS
39
TAC
Meeting
Meeting Date 4/26/2022 Agenda Item No. 4-9
Action Requested Information
Section Tab
MPO Reports
Information Summary Attachments Yes No
Agenda Item 4
NCDOT Board of Transportation Report
Agenda Item 5
Division Reports
Agenda Item 6
FHWA Report
Agenda Item 7
NCDOT Transportation Planning Division Report
Agenda Item 8
NCDOT Integrated Mobility Division
Agenda Item 9
Public Transportation Reports
TAC Vote: Motion Second
By:__________________ By:_______________________
Vote: For_______________________ Against________________________
40
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO - UNDER DEVELOPMENT
Estimated
TIP/WBS # Description Let/Start Date Completion Cost Status Project Lead
Date
EB-5519 Lydia greenway trail from Jamestown municipal building to Jul. 2019 4/30/22 $1,198,415 LAP, Under Construction, Contract Donnie Huffines
50035.3.1 York Leigh Road (Non-System) in Jamestown Administered by Town of Jamestown
SS-4907CN Install All-Way Stop with flasher and radius improvements on Dec. 2019 Jun. 2022 $90,000 Radius improvements completed, Dawn McPherson
48759.1.2 SR 1113 (Kivett Drive) at SR 1145 (Riverdale Drive) east of Traffic materials pending acquisition - Derek Dixon
48759.2.1 High Point Materials have been ordered -
48759.3.1 Construction underway - Rock
encountered during drilling -
Supplemental Agreement in process
SS-6007P Bridge #57 on SR 1113 (Kivett Drive) over Reddick's Creek - 5/13/22 8/31/22 $36,000 Planning and design activities Bobby Norris
49423.1.1 Install bridge approach guardrail with MASH compliant end 1/1/22 6/1/22 underway
49423.3.1 units
B-5353 Replace Bridge 147 over SR 1009 (South Main Street) on US 2/15/22 FY2024 $3,450,000 Combined let with U-5896, Contract Laura Sutton
46067.1.1 29/70 and I-85 Business in High Point execution underway
46067.2.1
46067.3.1
U-5896 Reconstruct interchange at US 29 / US 70 / Business 85 and 2/15/22 FY2024 $12,400,000 Combined let with B-5353, Contract Laura Sutton
44674.1.1 SR 1009(South Main Street) in High Point execution underway
44674.2.1
44674.3.1
SS-4907CF Install traffic signal with pedestrian count down heads at the Mar. 2022 Jun. 2022 $120,000 Signal plans not complete, MA w/City Dawn McPherson
48252.1.1 intersection of SR 1278 (University Parkway) and Davis of High Point executed. Poles arrived
48252.2.1 Avenue (non-system) in High Point. Traffic signal to be 8/23/2021. Construction underway -
48252.3.1 supported by metal strain poles. Poles have been installed and
pavement markings and final signs
remain to be completed.
SS-6607AC Installation of 2 lines of trailing approach bridge guardrail at Jun. 2022 Aug. 2022 $33,000 Planning and design activities Bobby Norris
49824.1.1 Bridge #400196 on SR 1193 (Baker Road) over US 29-70 in underway
49824.2.1 High Point.
49824.3.1
41
Page 1 HPMPO Apr. 2022
NCDOT DIV 7 PROJECTS LOCATED IN HPMPO - UNDER DEVELOPMENT
Estimated
TIP/WBS # Description Let/Start Date Completion Cost Status Project Lead
Date
SS-6207B Installation of Thermoplastic Lane Arrows to emphasize the 6/15/22 8/15/22 $8,000 Planning and design activities Dawn McPherson
50317 one-way direction on SR 1300 (West Green Drive) at Jacobs underway
Place, Tomlinson Street, and South Lindsay Street.
U-6018 Improve interchange at NC 62 and I-85 and realign 4/18/23 FY2026 $12,300,000 Planning and design activities Rob Weisz
47163.1.1 intersections along NC62 at SR 1154 (Kersey Valley Road) underway, ROW acquisition underway
47163.2.1 and SR 1162 (Weant Road) in Archdale
47163.3.1
U-4015A Widen SR 1556 (Gallimore Dairy Road) to multilanes from NC 5/16/23 FY2025 $6,600,000 Planning and design activities Brian Ketner
35013.1.4 68 to Airpark East in Greensboro underway, coordinate with U-5974
35013.2.4
35013.3.4
U-4758 Improvements to Johnson Street/Sandy Ridge Road from 12/19/23 FY2026 $45,700,000 Planning and Design activities Laura Sutton
40251.2.1 Skeet Club Road to I-40 underway, Public meeting 8/14/18 -
40251.3.1 Preliminary ROW underway
B-5723 Replace Bridge 54 over Richland Creek on SR 1158 (Jackson 11/19/24 FY2026 $3,237,000 Planning and design activities Kevin Fischer
45679.1.1 Lake Road) underway
45679.1.2
I-5712 Interchange improvements at I-40/US 421 and SR 1850 12/15/26 FY2029 $14,500,000 Planning and Design activities Laura Sutton
50126.1.FS1 (Sandy Ridge Road) in Greensboro. Sandy Ridge Road underway, Coordinate with U-4758 & U-
50126.2.1 widening to Cider Road 6045
50126.3.1
U-5974 Upgrade NC 68 to Superstreet from SR 1523 (Hickswood 7/18/28 FY2030 $48,100,000 Planning and design activities Brian Ketner
45962.1.1 Road) to SR 1556 (Gallimore Dairy Road) in High Point underway, coordinate with U-4015A
45962.2.1
45962.3.1
U-6121 Widen SR 1541 (Wendover Avenue) from NC 68 11/21/28 FY 2031 $27,300,000 Planning and design activities Brian Ketner
48605.1.1 (Eastchester Drive) in High Point to SR 1541 (Guilford underway
48605.2.1 College Road) in Greensboro.
48605.3.1
42
Page 2 HPMPO Apr. 2022
North Carolina Department of Transportation 4/4/2022
Active Projects Under Construction - Guilford Co.
Contract TIP Number Location Description Contractor Name Resident Contract Bid Availability Completion Work Start Estimated Progress Completion
Number Engineer Amount Date Date Date Completion Schedule Percent
Date Percent
C203256 U-3615B SR-1820 (SKEET CLUB RD) FROM EAST OF SR-1818 APAC - ATLANTIC INC Hayes, PE, $30,898,017.15 3/2/2015 3/29/2019 5/20/2015 4/30/2022 99.8 99.8
(JOHNSON ST) TO WEST OF NC-68 (EASTCHESTER DR) IN THOMPSON ARTHUR Meredith
HIGH POINT. DIVISION
C203433 I-5110 FUTURE I-73 FROM EXISTING SR-2085 (JOSEPH M BRYAN FLATIRON Smith, Brian $176,550,000.00 5/7/2014 4/25/2017 5/7/2014 4/30/2022 100 99.95
I-5110A BLVD) / AIRPORT PKWY INTERCHANGE TO SOUTH OF US- CONSTRUCTORS INC - V
R-2413A 220 NEAR HAW RIVER. BLYTHE DEVELOPMENT
CO JOINT VENT
C204071 U-5169 I-74/US-311 AND NC-68 (EASTCHESTER DR) INTERCHANGE BRANCH CIVIL INC Snell, PE, $22,481,354.65 7/30/2018 1/28/2021 9/14/2018 9/30/2022 100 95.23
IMPROVEMENTS. William H
C204096 U-2525C GREENSBORO EASTERN LOOP FROM US-29 NORTH OF ES WAGNER COMPANY Julian, Jason $120,471,182.82 4/30/2018 11/20/2022 5/7/2018 7/14/2023 78.9 81.17
GREENSBORO TO SR-2303 (LAWNDALE DR). LLC/SMITH-ROWE LL R
C204103 U-2412A SR-1486/SR-4121 (GREENSBORO/HIGH POINT RD) FROM BRANCH CIVIL INC Lorenz, PE, $55,963,119.69 7/30/2018 12/28/2021 9/12/2018 10/20/2023 90.5 85.9
US-311 BYPASS TO WEST OF SR-1480 (VICKREY CHAPEL Kris
RD).
C204371 U-2581BA US-70 (BURLINGTON RD) FROM WEST OF SR-3045 (MT APAC - ATLANTIC INC Snell, PE, $11,125,538.10 7/1/2020 4/30/2022 7/1/2020 4/30/2022 99.4 84.91
HOPE CHURCH RD) /SR-2819 (MCLEANSVILLE RD) TO THOMPSON ARTHUR William H
EAST OF SR-2826 (BIRCH CREEK RD) DIVISION
C204465 RESURFACE 1 SECTION OF US 29 AND 21 SECTIONS OF BLYTHE CONSTRUCTION, Lorenz, PE, $3,884,488.85 4/1/2021 7/1/2022 7/9/2021 3/31/2022 100 99.98
RAMPS AND LOOPS FOR US 29 INC Kris
C204499 R-4707 INTERCHANGE OF US 29 AND SR 4771 (REEDY FORK APAC - ATLANTIC INC Hayes, PE, $46,382,713.04 6/2/2021 10/28/2024 6/7/2021 10/28/2024 25.9 15.31
PARKWAY) THOMPSON ARTHUR Meredith
DIVISION
C204626 RESURFACE 1 SECTION OF NC 87, 1 SECTION OF NC 49 FSC II LLC DBA FRED Lorenz, PE, $4,639,570.37 6/3/2021 11/1/2022 6/28/2021 11/1/2022 52.1 15.36
AND 21 SECTIONS OF SECONDARY ROADS SMITH COMPANY Kris
C204665 U-5754 US-29/US-70/US-220 (O'HENRY BLVD.) FROM I-40/I-85 BUS. BRANCH CIVIL INC Lorenz, PE, $5,144,885.00 3/15/2022 3/14/2023
TO SOUTH OF FLORIDA ST. IN GREENSBORO. Kris
DG00462 REHAB. BRIDGES 264, 288, 260, 543 IN GUILFORD COUNTY ELITE INDUSTRIAL Snell, PE, $967,383.15 8/1/2019 1/1/2020 9/13/2021 4/30/2022 100 94.36
AND BRIDGE 031 IN ORANGE COUNTY PAINTING INC William H
43
Page 1 of 3
North Carolina Department of Transportation 4/4/2022
Active Projects Under Construction - Guilford Co.
Contract TIP Number Location Description Contractor Name Resident Contract Bid Availability Completion Work Start Estimated Progress Completion
Number Engineer Amount Date Date Date Completion Schedule Percent
Date Percent
DG00480 U-2412B(L) LANDSCAPE PLANTING ALONG GATE CITY BLVD FROM SR MOTS LANDSCAPING & Hayes, PE, $175,647.50 9/1/2019 12/31/2021 9/9/2019 12/31/2021 100 100
4121 (EAST MAIN ST) TO SR 1546 (GUILFORD COLLEGE LAWNS LLC Meredith
ROAD)
DG00490 AST TREATMENT OF 26 SECONDARY ROADS IN GUILFORD CAROLINA ROAD Lorenz, PE, $832.311.02 4/1/2021 10/30/2021 4/8/2021 4/30/2022 100 97.46
COUNTY SOLUTIONS LLC Kris
DG00493 REPLACE PIPE #2134 ON SR 2835 (MCKNIGHT MILL ROAD) HUNTING CREEK Snell, PE, $374,444.44 7/8/2021 9/9/2021 7/8/2021 4/30/2022 82.5 99.69
APPROX. 0.1 MILE SOUTH OF INTERSECTION WITH SR CONSTRUCTION INC William H
2732 (HINES CHAPEL ROAD)
DG00512 RESURFACE 43 VARIOUS STATE ROUTES SHARPE BROTHERS A Hayes, PE, $2,562,749.29 7/1/2021 11/1/2022 7/1/2022 11/1/2022 16.37 21.1
DIVISION OF VECELLIO & Meredith
GROGAN INC.
DG00513 REPLACE BRIDGE #235 OVER BIG ALAMANCE CREEK ON SMITH-ROWE, LLC Hayes, PE, $1,675,367.75 6/21/2021 10/25/2022
SR 1005 (ALAMANCE CHURCH ROAD) Meredith
DG00515 AST TREATMENT OF 34 SECONDARY ROADS IN GUILFORD WHITEHURST PAVING CO. Lorenz, PE, $749,755.28 7/1/2021 6/30/2021
COUNTY INC. Kris
DG00524 R-5787-G INSTALLATION OF ADA COMPLIANT CURB RAMPS AT ATLANTIC CONTRACTING Lorenz, PE, $717,704.25 6/1/2021 4/14/2023 7/26/2021 4/14/2023 41 63.89
R-5787-H VARIOUS ROUTES COMPANY, INC. Kris
DG00527 HS-2007C INSTALLATION OF THERMOPLASTIC PAVEMENT MARKING TMI SERVICES INC. Cvijetic, PE, $1,358,289.72 8/16/2021 11/19/2021
LINES ON VARIOUS SECONDARY ROUTES Bojan
DG00531 RESURFACE SR 1001 (CHURCH STREET) - 3 SECTIONS, SR SHARPE BROTHERS A Hayes, PE, $2,780,006.94 7/8/2021 7/7/2022 8/12/2021 7/7/2022 60 96.13
2714 (RED CEDAR ROAD) AND SR 2748 (SPRINGWOOD DIVISION OF VECELLIO & Meredith
CHURCH ROAD) GROGAN INC.
DG00533 MILLING, RESURFACING AND PAVEMENT MARKINGS ON I- BLYTHE CONSTRUCTION Lorenz, PE, $2,989,292.45 7/8/2021 7/7/2022 9/20/2021 7/7/2022 73.4 65.14
85 BUS/US 29/US 70, NC 150 AND VARIOUS SECONDARY INC. Kris
ROADS
DG00551 R-2413A(L) LANDSCAPE PLANTING ALONG I-73 FROM BRYAN BLVD. COUNTRY BOY Lorenz, PE, $593,953.15 12/20/2021 6/19/2023 3/21/2022
TO US 220 LANDSCAPING INC. Kris
44
Page 2 of 3
North Carolina Department of Transportation 4/4/2022
Active Projects Under Construction - Guilford Co.
Contract TIP Number Location Description Contractor Name Resident Contract Bid Availability Completion Work Start Estimated Progress Completion
Number Engineer Amount Date Date Date Completion Schedule Percent
Date Percent
DG00552 R-2413C(L) LANDSCAPE PLANTING ALONG US 220 FROM I-840 TO NC GOLDSTAR PROJECT Lorenz, PE, $119,464.76 12/20/2021 6/19/2023 3/4/2022
65 GROUP LLC Kris
DG00555 REPLACE PIPE #402221 ON SR 3426 (SHERATON PARK C2 CIVIL LLC Cvijetic, PE, $529,396.00 3/7/2022 12/1/2022 3/7/2022 12/1/2022 17.5 10.97
ROAD) IN GUILFORD COUNTY Bojan
45
Page 3 of 3
Randolph County - High Point MPO - Active Projects - Division 8--April 2022
Contract # or Completion
Route Description Let Date Contractor Project Admin. Project Cost Notes
WBS # or TIP # Date
DH00327 Various Upgrade Intersections to comply with 7/13/2021 4/30/2022 Eastern Cary Fine $247,107 Project 74% complete
R-5788GA, GB Americans with Disabilities Act (ADA) Earthscapes (336) 318-4020
using TA Funds
17BP.8.R.136 SR 1557 (Morris Rd) Replace Bridge No. 54 over unnamed 3/23/2021 7/20/2022 APAC Cary Fine $910,339 Project 69% complete
DH00325 tributary of the Uwharrie River (336) 318-4020 Now open to Traffic
Randolph County - High Point MPO - Upcoming Projects - Planning & Design, R/W, or not started - Division 8--April 2022
Contract # or Completion STIP Project
Route Description Let Date Contractor Project Admin. Notes
WBS # or TIP # Date Cost
U-3400 SR 1577 / SR 1004 Widening from SR 1567 (Robbins Country 11/18/2025 TBD TBD Jeff Stroder $38,626,000 Right of Way 1/2023
(Archdale Road) Rd) to US 311 (Main Street) in Archdale (910) 773-8034 Public Meeting held 2/27/18
U-5308 SR 1547 (Finch Farm Rd) Widening from south of SR 3106 Kennedy 6/17/2025 TBD TBD Jeffrey Teague $39,808,000 Right of Way in progress
Rd to I-85 in Trinity Extend northern (910) 773-8025 Public Meeting held 3/29/2018
limit to NC 62 2nd Public Meeting 11/29/18
U-5770 I-85 / SR 1993 Interchange Improvements 4/15/2025 TBD TBD Jeff Stroder $30,150,000 Right of Way 4/2022
(South Main Street) Frontage Road Alternative Selected (910) 773-8034 Public Meeting 11/30/17
Newsletter Mailed 6/8/18
U-5864 SR 1595 (Surrett Drive) 3-lane widening from I-85 to SR 1300 (W. 8/15/2028 TBD TBD Greg Davis $55,063,000 Right of Way 6/2024
Fairfield Rd. /Guilford Co.) in Trinity, (910) 773-8022 Public Meeting held 6/13/19
Archdale, and High Point
U-6191 NC 62 Modernize roadway between SR 3252 10/17/2028 TBD TBD Greg Davis $15,500,000 Right of Way 10/2026
(Surrett Dr) in Trinity to SR 1009 (N. Main (910) 773-8022
St) in Archdale
HI-0002 I-85 Randolph Co. Pavement Rehab - from I-85/NC 109 in 4/19/2022 TBD TBD Michael Ricketts $14,700,000
Thomasville to SR 1009 (South Main St) in (910) 773-8033
Archdale
46
High Point MPO
Transportation Update
April 1, 2022
Project
T.I.P. No. Description Let Date Completion Date Status Construction Cost Contractor Comments
Administrator
PROJECTS UNDER CONSTRUCTION
Little Mountain Builders began work April 19, 2021,
upgrading various wheelchair ramps and sidewalks to new
R-5789F
ADA standards. All new installation has been completed in
44919.3.7 Little Mountain
ADA Ramps at Various Locations in Davidson, Davie, Kelly Seitz, PE Rowan County, and crews are currently performing punch list
R-5789G March 1, 2021 March 31, 2022 62% Complete $2,524,367 Builders of Catawba
Forsyth and Rowan Counties (704)630-3200 work. Contractor has 3 crews working in Denton, along with
44919.3.8 County, Inc
Winston Salem. Kernersville, King, Lewisville, and Lexington
(DI00235) have been completed. Estimated project completion is July
29, 2022.
Milling, Resurfacing, and Shoulder grading of (18)
2021CPT.09.02.20291 Availability date Blythe Construction, Jeb Smith, PE
sections of Secondary routes in Davidson County, February 16, 2021 October 28, 2022 $4,150,985 Contractor plans to begin work in mid-June.
(C204604) May 3, 2021 Inc (704)630-3220
totaling 28.6 miles
The date of availability is April 11, 2022. Whitehurst paving
2022CPT.09.11.20292 Asphalt Surface Treatment (AST) in Davidson County - Whitehurst Paving Jeb Smith, PE
September 22, 2021 October 14, 2022 0% Complete $1,740,522 scheduled to start April 22, 2022. The Contractor is
(DI00253) Various Secondary Routes – 78 Sections Co. (704)630-3220
anticipated to be completed by Oct. 14, 2022.
Project was awarded on March 22, 2021 with a completion
2021CPT.09.26.20292 Polyurea Pavement Markings on I-285/US 52 from SR Availability date JP Couch, PE
February 10, 2021 TBA $228,300 TMI Services, Inc. date of 06/14/2021. No work has begun on this project as of
(DI00245) 1147 (Old Salisbury Rd) to NC 8, North of Lexington March 22, 2021 (336)747-7800
10/25/2021.
Replace Bridge #459 on SR 2160 (Smith Ave) over Triangle Grading & Jeb Smith, PE ICT No. 1 anticipated completion is mid April, 2022. The
17BP.9.R.33 June 23, 2021 July 31, 2022 56% Complete $400,000
Charles creek in Davidson County. Paving, Inc (704)630-3220 project is anticipated completion date by end of July 2022.
Contractor is currently waiting for delivery of corrugated
Replace Culvert #564 on Unnamed Creek and replace aluminum pipe culverts and headwalls, prior to mobilizing to
17BP.9.C.14 Chatham Civil Larry Shaver
Culvert #504 on Branch of Cabin Creek at SR 2522 August 25, 2021 December 16, 2021 0% Complete $920,485 Handy Road. Tenative start date has been pushed from mid-
17BP.9.C.13 Contracting, LLC (336)249-6255
(Handy Rd) in Davidson County. March to April 2022. Contractor needs to recieve materials
for waterline construction before work can begin.
The inside lanes of SB and NB are closed through the
R-5737
Convert at grade intersection to Interchange on US Larry Shaver project, as the Contractor works to build crossovers for future
50195.3.1 October 19, 2021 February 28, 2026 0% Complete $25,893,075 Smith-Rowe
29/70/I-85 Bus at SR 1798 (Old Greensboro Rd) (336)249-6255 traffic patterns. Also, clearing and grubbing operations are
(C204399)
underway.
Project availibility is March 15, 2022. A preconstruction
W-5809A Install Rumble Strips on NC 109 from SR 2067 TRP Construction Matt Jones, PE
October 27, 2021 TBD TBA $374,464 conference was held February 17, 2022. Contractor plans to
48954.3.2 (Lambeth Rd) to the Northern Denton Municipal Limits Group, LLC (336)747-7800
begin work March 1, with all operations at night.
Pre-Construction Meeting held March 24, 2022 with
anticipated construction to being April 4th. Welcome-Arcadia
Replace Bridge #63 on SR 1472 (Welcome Arcadia Larry Shaver
17BP.9.R.57 February 9, 2023 January 25, 2023 0% Complete $858,581 Smith-Rowe, LLC Road scheduled to be closed on April 4th. The roadway will
Rd) over Reedy Creek in Davidson County. (336)249-6255
be reopened once the work is subtantially complete.
Substantial completion date is July 29, 2022.
PROJECTS UNDER DEVELOPMENT
Raleigh Let - Right-of-way acquisition to begin - 75% plans
B-5765 received. Division and Central staff are working toward the
Replace Bridge #115 on SR 1711 (Gumtree Rd) over ROW Acquisition Kevin Fischer, PE
45721.3.1 June 21, 2022 TBD $3,850,000 TBD June 2022 let date. There will likely be a delay in availability
WSSB RR in progress (919)707-6514
(C204385) for the contractor to begin work; this will allow time for
railroad coordination and acquiring materials for the project.
Raleigh Let - Approved to move forward with PE. Reinitiation
B-5773 Replace Bridge #25 on SR 3346 (S. Main St) over ROW Acquisition Ryan Newcomb, PE
January 20, 2026 TBD $3,250,000 TBD meeting held March 2022. Working on scope and fee for
45729.3.1 WSSB RR in Lexington (Combine let with BR-0015) Jan. 15, 2025 (336)747-7800
additional PE work.
B-5777 ROW Acquisition Ryan Newcomb, PE Raleigh Let - Approved to move forward with PE. Working
Replace Bridge #58 on NC 109 over US 64 January 16, 2024 TBD $1,850,000 TBD
45733.3.1 Jan. 15, 2023 (336)747-7800 on scope and fee for PE. PE work has started.
47
Page 1 of 3
High Point MPO
Transportation Update
April 1, 2022
Project
T.I.P. No. Description Let Date Completion Date Status Construction Cost Contractor Comments
Administrator
PROJECTS UNDER DEVELOPMENT
*Schedule based on Approved 2020-2029 STIP - Raleigh
Let - Coordinate with B-5785. Division is currently working
on a feasibility study for this bridge replacement and how this
B-5779 Replace Bridge #118 on US 29NB/64EB/70EB over SR ROW Acquisition Ryan Newcomb, PE
April 15, 2025 TBD $4,061,000 TBD will work with the overall interchange. PE was authorized to
45735.3.1 3346 (N Main St) in Lexington April 19, 2024 (336)747-7800
restart in January 2021. We will be coordinating with the
STIP and Feasibility group to determine how to proceed with
the bridge project. Working on scope and fee for PE.
*Schedule based on Approved 2020-2029 STIP - DDRL
B-5783 Replace Bridge #164 and Bridge #168 on US 29/70/I- Planning/Design Ryan Newcomb, PE
May 16, 2023 TBD $5,778,000 TBD Let - Approved to move forward with PE. 25% plans
45738.3.1 85 Bus over NSRR in Progress (336)747-7800
complete. 65% plans complete.
B-5785 Replace Bridge #121 and Bridge #122 on US 29/70/I- ROW Acquisition Daniel Dagenhart Raleigh Let - Coordinate with B-5779. Approved to move
February 17, 2026 TBD $4,000,000 TBD
45740.3.1 85 Bus over Leonard Creek Feb. 16, 2025 (336)747-7800 forward with PE.
B-5787 ROW Acquisition Connie James, PE
Replace Bridge #29 on NC 49 over NC 109 January 20, 2026 TBD $2,000,000 TBD Raleigh Let. - Approved to move forward with PE.
45741.3.1 Jan. 15, 2025 (336)747-7800
Replace Bridges #67 and #68 over SR 1192 (W. 5th
BR-0015 ROW Acquisition Kevin Fischer, PE
Ave) on US 29/70/ I-85 Business in Lexington November 21, 2023 TBD $6,200,000 TBD Raleigh Let - Approved to move forward with PE.
67015.3.1 Nov. 22, 2022 (919)707-6514
(Combine let with B-5773)
Raleigh Let. Approved to move forward with PE. Working on
BR-0016 Replace Bridge #150 over SR 2123 (Kanoy Rd) WB on ROW Acquisition Ryan Newcomb, PE
January 20, 2026 TBD $5,175,000 TBD scope and fee for PE. Scope and fee approved. PE work has
67016.3.1 I-85 Bus in Thomasville Jan. 19, 2025 (336)747-7800
started.
BR-0140 Replace Bridges #87 and #89 0n US 29/70/I-85 Bus ROW Acquisition Ryan Newcomb, PE Raleigh Let - New - In development. Working on scope and
September 16, 2025 TBD $6,800,000 TBD
67140.3.1 over WSSB Railroad Jan. 22, 2024 (336)747-7800 fee for PE.
*Schedule based on Adjusted 2020-2029 STIP - DDRL -
Pavement Rehabilitation on I-85 from US 29/52/70/I-85 Combine I-5950 and I-5951 - This project will include bridge
I-5950 Planning/Design Matt Jones, PE
Bus to N of SR 2205 (Old US 64) and from NC 109 to August 16, 2022 TBD $14,740,000 TBD preservation in this corridor, STIP description will be updated
45897.3.1 in Progress (336)747-7800
Randolph County Line (Includes I-5951) to reflect this. Construciton estimate will be updated once
adjusted.
*Schedule based on Adjusted 2020-2029 STIP - DDRL -
R-4734 Widen NC 109 to multilanes from NC 109 in Denton to Post Year ROW Acquisition Ryan Newcomb, PE
TBD $132,096,000 TBD *The PE work for this project has been temporarily
38954.3.1 I-85 in Thomasville Jan., 2040 Jan. 21, 2028 (336)747-7800
suspended.*
U-5757 Widen NC 8 (Winston Rd) to multi-lanes from 9th St to ROW Acquisition Ryan Newcomb, PE
July 18, 2023 TBD $8,800,000 TBD *Schedule based on Adjusted 2020-2029 STIP - DDRL -
54035.3.1 SR 1408 (Biesecker Rd) in Lexington in progress (336)747-7800
Replace Bridge #230 on SR 2250 (Becks Church Rd) ROW Acquisition Daniel Dagenhart
17BP.9.R.79 April 27, 2022 TBD $750,000 TBD Division Let - Design in progress.
over Pounder Fork Creek in Davidson County. Complete (336)747-7800
BP9-R001
Replace Bridge #469 on SR 2183 (Fisher Ferry Rd) ROW Acquisition Daniel Dagenhart
BP9.R001.3 May 24, 2023 TBD $1,300,000 TBD Division Let - Approved to move forward with PE.
over North Hamby's Creek in Davidson County Jan. 24, 2022 (336)747-7800
formerly 17BP.9.R.16)
BP9-R003
Replace Bridge #286 on SR 2545 (Slate Mine Rd) over ROW Acquisition Daniel Dagenhart
BP9.R004.3 August 16, 2023 TBD $1,400,000 TBD Division Let - Approved to move forward with PE.
Beaverdam Creek in Davidson County. July 16, 2022 (336)747-7800
(formerly 17BP.9.R.74)
48
Page 2 of 3
High Point MPO
Transportation Update
April 1, 2022
Project
T.I.P. No. Description Let Date Completion Date Status Construction Cost Contractor Comments
Administrator
PROJECTS UNDER DEVELOPMENT
BP9-R006
Replace Bridge #246 on SR 2351 (Flat Swamp Rd) ROW Acquisition Daniel Dagenhart
BP9.R006.3 February 14, 2024 TBD $900,000 TBD Division Let - *Approved to move forward with PE.
over Lick Creek in Davidson County Jan. 14, 2023 (336)747-7800
(formerly 17BP.9.R.92)
STATE FORCES CONSTRUCTED PROJECTS
Re-align intersection of SR 2184 (Cedar Lodge Rd) Matt Jones, PE High Impact Low Cost Project - Project released to move
47795 May 30, 2022 TBD In development $372,000 State Forces
and Liberty Drive (NS) in Thomasville (336)747-7800 forward. Let date under review.
Construct additional left turn lane on I-85 South Bound Kevin Hedrick, PE High Impact Low Cost Project - Project released to move
47796 April 6, 2022 TBD In development $358,000 State Forces
Exit Ramp at NC 109 in Thomasville (336)224-3200 forward.
COMPLETED PROJECTS
This project widened NC 150 to install a left turn lane into
W-5709C Becky Hill Rd. Country Boy Landscaping is the contractor.
Construct left turn lane on NC 150 at SR 1435 (Becky Country Boy Kelly Seitz, PE
44855.3.3 July 26, 2021 November 24, 2021 99% Complete $500,584 Contractor began construction August 16, 2021; and the new
Hill Rd) - Safety Improvements. Landscaping (704)630-3200
DI00222 turn lane was opened November 21, 2021. The project
completion date is June 19, 2022.
49
Page 3 of 3