Village Board
Regular MeetingHilton, NY · March 23, 2017
Minutes
Village Board
Meeting Minutes of
March 23, 2017
Present: Mayor Lee, Trustees, Burritt, Zabelny
Village Manager/Clerk, Shari Pearce
DPW Superintendent, Mike McHenry
Code Enforcement Officer, Mike Lissow
Deputy Clerk, Amy Harter
Absent Trustee Gates, Village Treasurer, Maryalice Edwards
Guests: Robert Pistilli, Keith Brown
Mayor Lee called the meeting to order at 5 p.m. with the pledge of allegiance followed by a
moment of silence.
Shari Pearce explained that an issue has arisen regarding the lighting fixtures throughout the
Community Center. One employee felt strongly that the fixtures are potentially hazardous. After
several conversations among the staff, Shari sought the opinion of someone within the
community that is knowledgeable in facility maintenance. He suggested contacting RG&E to
inquire about grant opportunities.
RGE offers a Small Business Energy Efficiency Program, which everyone pays for on their bill.
The purpose of the program is to evaluate buildings energy usage. Shari met with Mr. Robert
Pistilli, Energy Service Representative from Lime Energy Services. A visual inspection was
conducted of the entire building. He recommends replacing or retrofitting each light fixture with
LED lighting throughout the building. The existing fixtures are oil filled ballasts that can leak
without warning; Mr. Pistilli noted a leaking fixture is dangerous. The fixtures themselves are
not hazardous if there is not a leak. An inspection was done at the DPW building. Mike
McHenry is recommending the inside and outside fixtures need replacing.
Mr. Pistilli explained replacing the fixtures to increase efficiency is a benefit for all. This would
reduce the strain to the aging power grid. The cost savings to the Village in future lighting
charges is estimated at 71% annually. The estimate payback is between 14-20 months. RG&E
offers a contribution to offset the costs of the replacement of the fixtures.
1
The proposal states the cost for the total Community Center project is $61,788.45, RGE’s
contribution is $37,397.10, and the Village cost is $24,391.35. The total cost for the DPW
project is $34,089.58. RG&E’s contribution is $12, 908.49 and the Village’s is $21,181.09. The
payback is estimated at approximately 2-3 years.
Resolution to approve the Energy Efficiency Proposal for the Community Center for a cost of
$24,391.35. The monies are to come from the refund of the Worker’s Compensation Program.
Motion made by Trustee Burritt, seconded by Trustee Zabelny, carried 4-0.
Resolution to approve the Energy Efficiency Proposal for the DPW Building for a cost of
$21,181.09. The monies are to come from the DPW Savings Account. Motion made by Trustee
Burritt, seconded by Trustee Zabelny, carried 4-0.
There being no further business the meeting was adjourned at 6:00 p.m.
Respectfully Submitted,
Amy Harter, Deputy Clerk
2