Board of Park Commissioners
Regular MeetingHobart, IN · September 10, 2018
Minutes
Board of Park Commissioners
Meeting Minutes of
September 10, 2018
Call to Order: Mrs. Galka called the meeting to order at 6:00 p.m. followed by the recitation of
the Pledge of Allegiance.
Roll Call: Commissioners in attendance: Mrs. Galka, Mr. Kara, Mrs. Sills, and Mr. Wengel.
Also present: Common Council representative Mr. Huddlestun, Park Board Secretary Ms.
Montes, Park Director Mrs. Goodpaster
Approval of Agenda: There was an addition to the agenda by Mrs. Goodpaster regarding
Brickie Bowl under new business. Motion by Mr. Wengel, seconded by Mr. Kara, to approve the
agenda with the addition. All aye, motion carried. (4-0)
Approval of Minutes: There were a couple typos to the minutes. Motion by Mrs. Sills, seconded
by Mr. Kara, to approve the minutes of the Regular Meeting of August 13, 2018. All aye,
motion carried. (4-0)
Approval of Register of Claims: Mr. Wengel questioned a claim for picnic table frames. Mrs.
Goodpaster stated that is less expensive to by the frames for the picnic tables and put them
together, then it is to buy a whole picnic table. Mrs. Sills commented on the cost of the bands
being more expensive compared to last year cost. Mrs. Lopez stated that the bands where a little
more expensive because they are better known in the area and attract a bigger crowd to the
festival. Motion by Mrs. Sills, seconded by Mr. Wengel, to accept the register of claims as
presented. All aye, motion carried. (4-0)
Approval of Bond Proceeds Claims List: Mrs. Galka questioned claims from BF&S regarding
ADA Access Site Plan Development. She was under the impression that the bill was already
paid. Mr. Dammarell explained that May and Early July was up to date, however, after meeting
with Mrs. Goodpaster some of the work was put on hold due to some changes to the project
regarding the direction they were going with the parks and there were some donations made by
Ozinga.
A discussion was held regarding the Lake Front Project questioning the high amount. Mr.
Dammarell explained the bond proceeds claims list in which shows the contract sums with
change orders on how the contractor calculates the payment application and also how the
schedule of values is calculated against the original contract. Dr. Dammarell stated that everyone
feels very confident in regard to the work that was done with the underground to prevent any
issues that they had in the past. Motion by Mr. Kara, seconded by Mrs. Sills, to approve the bond
proceeds list as presented. All aye, motion carried. (4-0)
Correspondence: There was no correspondence.
Superintendent’s Report: Mrs. Goodpaster reported that the Lakefront had a completion date
of September 21, but that is not the case anymore. However, she did have a discussion with Mr.
Dammarell so they can come up with a completion date and so that the contractor can be held
responsible for a completion date. The Gazebo railing is up and complete. The next step is
getting the wall stained and once that is done the rest of the railing can go right on top of the
wall. Once the staining and railing is done, landscaping will go in right after. Mrs.Galka
questioned why the contractors are taking so long to finish the project. Mr. Dammarell explained
that originally the contract had a completion date in April, due to do the project taking a much
longer time than expected, we are working on a completion date with the contractor which will
give them leverage in order to get the work done.
A discussion followed explaining that the problem is coming from the contract going behind the
completion date due to the underground issues that came up. Mr. Dammarell stated that LaPorte
Construction is a capable contractor. However, they had a window of time where they had no
work going on and crews available to work, but running into the underground issues threw their
work schedule off course and as a result of that they had other jobs that came about and they
were not able to stay on task while waiting for some of the issues that came about.
The Splash pad is closed for the season. It was kept open during Labor Day weekend and the
people enjoyed it. The Summer Markets are finally finished and all our part-timers are back in
college.
The Lakefront Festival was taken over by Hobart Events this year by Mrs. Lopez. Mrs. Lopez
reported that the festival was a good turnout. She passed out a preliminary graph of the budget
and all expenses that the Lakefront Festival took in. Mrs. Lopez stated that every year they count
on $6,000 donations. However, this year they didn’t receive any donations but after looking back
and cutting out some of the things to prior years she still was able to profit over $5,000 more
than last year’s festival. She mentioned that this was the second year that Lakefront festival has
taken over the beer garden and has been a huge success. The beer garden is the most profitable as
the graph shows is where most of the revenue comes from. Mrs. Lopez reported that giving back
to the community is important, so all the tips that were raised each night went to a non-profit
organization. She also bumped all the tips to the hundred dollars for each organization. Friends
of Robinson were given $200, Little League was given $500, Soccer Club was given $300 and
Food Pantry was also given $300. Mrs. Lopez mentioned that the Dam Duck race and the
Cardboard Regatta went well. There were a total of seven registered Cardboard boats. Overall
was an excellent event. Mrs. Lopez also mentioned that next Hobart Events will also be taking
over the Dam Duck race next year. She has been working very closely with the Hobart
Community foundation for years and they have agreed to gift it to Hobart events to take over.
Plan Commission Report: Nothing under Plan Commission
Common Council Report: Mr. Huddlestun reported that school ground breaking will take place
September 20th at 5:00 p.m.
School Board Report: Nothing under School Board Report
Old Business: Noting under Old Business
New Business: Consideration of Lake George Wall and Walkway Project Change Order #9
Mr. Dammarell provided information regarding change order #9 for the cost of $15,366.30. This
change order is for additional lighting and electrical. The majority of items are items to repair
existing light pole bases and replace missing existing light pole items. Midwestern Electric is the
subcontractor performing the work and has discovered that some of the existing light poles in the
park were missing lenses and lamp holders and has replaced them to allow the existing light
poles to function properly. They also repaired exciting anchor bolts and pole base covers and
extended several existing pole bases to correct the light pole elevations in reference to the new
sidewalk. All of the work saved money by not having to replace the existing light poles or bases
and anchor bolts. Also included in the change order are four new light poles. The new poles will
be the same light poles in Festival Park. Motion by Mr. Kara, seconded by Mrs. Sills to accept
change order #9. All aye, motion carried. (4-0)
Brickie Bowl: There was a whole discussion regarding the Brickie Bowl Project. Kelly
Goodpaster, Mayor and City Engineer are all in agreement in moving forward in getting Brickie
Bowl functional and safe for the public. Mrs. Goodpaster stated that they would be moving
forward to pave the top area giving it the final look using asphalt paving and some areas using
color concrete in some area to would differentiate what is ADA and what is not. Mrs. Goodpaster
stated that the whole plan for Brickie Bowl needs to be revisited and come up with a good solid
plan for it, however in the mean while having the paving done it will at least be safe and
functional for the upcoming events. Mrs. Goodpaster also stated that some of the funding would
come from the Mayor, parks and bond. Mr. Wengel makes a move, and seconded by Mr. Kara
not to exceed of 36,000 dollars for the Brickie Bowl Project. All Aye, motion carried.
Announcements: Cooley Priestly president of The Friends of Robinson Lake. Mr. Priestly wants
to take Robinson to the next level and he states that working as a team it can happen. He
expressed that by improving Robinson Lake it will also improve the City of Hobart. They many
events as in annual picnics, kayaking, fishing events where they proved crafting, dip netting for
the pond creatures. They have also done some planting work on the shoreline project.
He thanked Mrs. Lopez for the $200 donation to the Friends of Robinson Lake organization. He
also thanked Park Department Mrs. Goodpaster for allowing them to use the Park Department
dump truck to haul dirt away. The Park Department and the Friends of Robinson have a great
line of communication.
Mr. Priestly comes forward to the Park Board Commissioners with a wish list in extending the
parking out. He expresses that the parking lot is not big enough especially when there is fishing,
kayaking, and biking going on at the same time. He would love to see new playground
equipment for the kids. Nicer restrooms, states that the restrooms are beat up pretty bad. He
would like to see a large gazebo that as a photographer he can vision beautiful outdoor weddings
out by the Lake. He also would like help with the shore line project, 200 ft of work has been
done now and would like to get some help with the project so that it can become more stable. He
also would like to see repairs to the culverts and establish proper drainage. Discussion followed
in regard to the parking lot and restroom. Mrs. Galka mentioned that is something to get the city
engineer involved with between the culverts and the parking.
Adjournment: Motion to adjourn by Mrs. Sills, seconded by Mr. Wengel. All aye, motion
carried. (4-0)
________________________________________________
____________________________________________
____________________________________________
____________________________________________
Agenda
AGENDA
THE REGULAR MEETING OF THE CITY OF HOBART
PARKS AND RECREATION DEPARTMENT
Hobart City Hall, 414 Main Street, 2nd Floor Council Chambers
September 10, 2018 at 6:00 p.m.
CALL TO ORDER / PLEDGE TO THE FLAG
ROLL CALL
APPROVAL OF AGENDA
APPROVAL OF MINUTES Regular Meeting of August 13, 2018
APPROVAL OF REGISTER OF CLAIMS
APPROVAL OF BOND PROCEEDS CLAIMS LIST
CORRESPONDENCE
SUPERINTENDENT REPORT
PLAN COMMISSION REPORT
COMMON COUNCIL REPORT
SCHOOL BOARD REPORT
OLD BUSINESS:
NEW BUSINESS: Consideration of Lake George Wall and Walkway Project Change Order #9
ANNOUNCEMENTS
ADJOURNMENT
Get email alerts for Hobart
A daily email when new agendas and minutes are posted.