Contractor's Licensing Board and Registration
Regular MeetingHobart, IN · September 26, 2018
Minutes
CITY OF HOBART CONTRACTOR’S LICENSING BOARD
Meeting Minutes - September 26, 2018 at 6:00pm
Mr. Phil Gralik called the meeting to order at 6:01pm.
Roll Call: Members in attendance were: Mr. Phill Gralik, Ms. Maria Galka, Mr. Owen Stephens,
Mr. Dave Soderquist, and Mr. William Shearer.
Also in attendance were Mr. Mike Hannigan, Building Official and Elizabeth Ferba, Recording
Secretary.
Let the record show that Mr. Lino Maggio and Mr. Ed Power were not present at the meeting.
Pledge of Allegiance
Approval of Minutes: Mr. Stephens motioned to approve the minutes of the July 25, 2018
meeting as presented, seconded by Mr. Soderquist. All ayes, motion carried. (5-0)
Communications / Acceptance of Agenda: An error was discovered in the agenda showing a
previously used case number. The Agenda has been amended so that Danley’s Garage World is
2018-07 and Stash Construction Co. is 2018-08. Mr. Stephens motioned to approve the
amended agenda, seconded by Ms. Galka. All ayes, motion carried. (5-0)
OLD BUSINESS:
2018-05: Upscale Construction – Dan Kettwig
Complainant: Shane Hric, 1020 Lakeview Dr, Hobart, IN
Purpose: Follow-up from the July 25, 2018 Contractor’s License Board meeting.
This matter was tabled for today’s meeting to see if there had been any resolution to the
complaint. Mr. Hric has stated that the two homeowners have been working together to try to
resolve the issues without the cooperation of the Contractor. Mr. Soderquist motioned to table
this matter until the next meeting on January 23, 2019 to give all parties additional time to
work out their differences. Ms. Galka seconds. All aye, motion carried. (5-0)
1
NEW BUSINESS:
2018 - 07: Danley’s Garage World
Violation: Failing to call for required inspections
Purpose: Required to appear before the Contractor’s Licensing Board.
Bob Null, Building Inspector, is stating that the contractor has failed to call for their framing
inspections on at least two locations that they are aware of. Garages were built in 2017 and
permits have not been finaled. A representative of Danley’s was present and stated that he
was not familiar with the two jobs in question but was called in to take care of the matter. Mr.
Soderquist motioned to table this matter to the next meeting on January 23, 2019 to research
how many open permits Danley’s Garage World has. Danley’s Garage World must also call for
final inspections on the two known locations. Mr. Stephens seconded. All aye, motion carried.
(5-0)
2018 – 08: Stash Construction Co
Violation: Working without proper permits
Purpose: Required to appear before the Contractor’s Licensing Board.
Building Official, Mike Hannigan, brought Stash Construction before the board with the
complaint that they started working at a site before obtaining the proper permits. Josh Milton,
with Stash Construction, appeared and explained that the error was on their part. They started
the work before verifying in their office if permits were applied for. Mr. Soderquist motioned
to fine Stash Construction $300.00 for working without a permit and suspend the fine pending
no further violations within a year. Ms. Galka seconded. All aye, motioned carried. (5-0)
Ms. Galka motioned to adjourn the meeting. Mr. Shearer seconded. All aye, motion carried.
(5-0)
2
Agenda
Building Department
Code Enforcement
CONTRACTOR’S LICENSING BOARD MEETING
SEPTEMBER 26, 2018
COUNCIL CHAMBERS
6:00 P.M.
ROLL CALL
PLEDGE OF ALLEGIANCE
APPROVAL OF MINUTES OF JULY 25, 2018
ACCEPTANCE OF AGENDA
OLD BUSINESS:
2018-05 – UPSCALE CONSTRUCTION INC / COMPLAINT & BUILDING OFFICIAL
NEW BUSINESS:
2018-06 – DANLEY’S GARAGE WORLD / BUILDING INSPECTOR
2018-07 – STASH CONSTRUCTION CO / BUILDING OFFICIAL
NEXT CLB MEETING – JANUARY 23, 2019 AT 6:00PM
Get email alerts for Hobart
A daily email when new agendas and minutes are posted.