Community Development Advisory Committee (CDAC)
Regular MeetingHot Springs, AR · November 12, 2020
Agenda
AGENDA
City of Hot Springs
Community Development Advisory Committee (CDAC)
VIRTUAL TELECONFERENCE
Thursday, November 12, 2020 at 1:00pm
1. Call to Order
2. Roll Call: Terry Kent, Leslie Ramsey, Kelly Thomason, Kelly Cowart, Alice Marshall
3. Approval of September 3, 2020 Meeting Minutes
4. New Business:
Michelle Sestili will present an overview of the Second CARES Act Amendment to the 2020 Annual Action
Plan. A copy of the proposed amendment can be downloaded at https://www.cityhs.net/563/Community-
Development or viewed in the lobby at City Hall, 133 Convention Blvd.
The City was awarded $254,473 in CDBG CARES Act (CV) funds, which were allocated to CV-
Healthcare Services ($126,825), CV-Homeless Assistance ($76,824) and CV-Meal Services ($50,824)
through a 2020 Annual Action Plan amendment earlier this year
FEMA grant funds have become available to pay for the planned CDBG-CV funded Health Care
Services such as PPEs, testing and medical supplies
CDBG-CV funding prohibits duplication of benefits when other funds are available
This amendment proposes reallocating the $126,825 from CV-Healthcare Services to:
o $100,000 CV-Rent Emergency Subsistence Payments
o $26,825 CV-Utility Emergency Subsistence Payments
Subsistence payments would be made directly to the property owner (landlord) and/or the utility
provider, not to the eligible household
To qualify, households have to demonstrate and certify that they have lost income, incurred
medical bills or experienced another hardship directly related to COVID-19. All other low- to
moderate-income CDBG income verification rules apply.
HUD currently allows up to 6 consecutive months of subsistence payments however, payments
beyond 3 months require a lead based paint test and abatement of any lead based paint found. It
is likely the City will provide payments for up to 3 consecutive months unless the HUD regulation is
waived in the future and the need for continued assistance exists.
CDBG statutes do not allow grantees to make payments to themselves including publicly owned
utilities such as water and sewer. Unless this HUD regulation is waived in the future, utility
subsistence payments will be limited to gas and electric.
Rental payments will not exceed HUD Fair Market Rates
Rent and utility payments will not duplicate other sources of funding including FEMA, state CDBG,
ESG, ESG-CV, unemployment, Section 8 and support provided through other organizations.
The CDC eviction moratorium ends on 12/31/2020. Rent and utility assistance has been identified
as the greatest unmet need to prevent widespread evictions and homelessness.
Ouachita Children’s Center received a HUD Emergency Solutions Grant (ESG) and is providing rent
and utility assistance to eligible households earning less than 50% area median income. CDBG can
bridge a gap for those earning between 51% to 80% area median income.
As moderator, Michelle Sestili will call on each CDAC member then resident participants for questions and
comments.
CDAC will publicly discuss and consider The Second CARES Act Substantial Amendment to the 2020 Annual
Action Plan to the Hot Springs Board of Directors with or without revisions, or remand to the CDBG
Administrator for substantial changes.
5. Old Business:
Michelle Sestili will provide updates on prior year CDBG projects
-----Funded-----
CV-3 $317,926 To be determined. Additional CARES Act funding
for the prevention of and response to COVID-19.
CV-1 Homeless Assistance $76,824 total allocation; $16,211.02 balance after
purchasing the homeless shower/restroom trailer and
supplies
CV-1 Health Services and Supplies $128,893 (CV & 2019 funds) To be reallocated
CV-1 Food/Meals Services and Supplies $50,824 meals on wheels/grab and go food services. RFP
prepared for release
2018 Home Buyer Education Classes $4,969 balance. Next class November 14, 2020 with
limited seating. 372-2611 to register
2020 Spot Blight Nuisance Abatement $25,621.02. 8 structures. Bids opened 10/26. Contract to
be awarded pending contractor DUNS/SAM registration
2019 RA Psychle 4C Elderly & Disabled Lawn $8,619.74 balance for youth landscape certifications.
Care and Youth Landscape Mentorship Program Program launched 8/14. Refer low- to moderate income
elderly and disabled Hot Springs residents in need of lawn
care to:
HotSprings4C@gmail.com and cc:
msconsulting@outlook.com
Malvern Avenue Gateway Improvement Project $141,241.56 Bid opening 11/16/2020
2018 & 2020 Garden Street Sidewalk & ADA $51,899.64 Survey complete. Bid opening 11/23/2020
2019 Dell & Ravine Sidewalk & Drainage $42,121 In progress
Improve
2019 Park Avenue Sidewalk & ADA Accessibility $42,132 In progress
2019 Bus Shelter at Ouachita Behavioral Health $11,000. Concrete pad complete. Shelter to be installed.
Reallocate Bus Shelter to Indiandale Plaza on Concrete pad poured by Engineering Dept. Shelter to be
Malvern installed.
2019 Crosswalk on Malvern to Silver Street $11,680 ARDOT consultation in progress.
2019 Habitat for Humanity 115 Watt Street $2,750 balance for water line relocation. In progress.
2019 Habitat for Humanity Garland Avenue $9,000 retaining wall removal and grading for ADA access.
Habitat for Humanity Lot Acquisition $15,000 Environmental review in progress for potential
lots.
2020 Bell Street Sidewalk Phase II $10,000 10/26 bid rejected. New bid opening 11/23/2020.
Off Cycle Infrastructure Improvements $35,418.52 Projects to be identified.
2020 Home Buyer Education, Credit Counseling, $25,000 Request for proposals to be prepared and released
Refinance and Foreclosure Avoidance Services by end of year
2020 John Lee Webb House Brick Masonry & $60,000 Environmental review in progress.
Ancillary Roofs
2020 Cedar Street Sidewalk & ADA Phase III $10,261 Funded.
2020 Jefferson Street Sidewalks & ADA $31,510 Bid opening 11/23/2020
2020 Whittington Avenue Drainage $44,850 Environmental Review to be completed
Improvements
2020 Chelsea Street Sidewalks & ADA $40,800 Environmental Review to be completed
2020 Creek Street Sidewalks & ADA $32,343.75 Environmental Review to be completed
Accessibility
2020 Park Avenue at Tom Ellsworth Sidewalk, $38,875 Environmental Review to be completed
ADA & Drainage Improvements
-----Completed in 2020-----
CV-Homeless Assistance Shower/Restroom Delivered 10/6/2020. First used at free COVID testing day
Trailer, ULV Cold Fog Sprayer with disinfectant 11/4/2020
cleaner, hoses and electrical supplies
2019 Bus Shelter on Hobson near Lacey Installed 9/21/2020
2018 & 2019 Linden Park Bathroom Installed 9/9/2020
Replacement
2019 Arbor Street Sidewalk & ADA Accessibility Completed 8/25/2020
2019 Cedar Street Sidewalk & ADA Phase II Completed 8/12/2020
2019 Hobson & Linwood Sidewalk & ADA Completed 7/16/2020
2018 OCC Roof Replacement (1:1+ matching) Completed 6/29/2020
2017 OCC Fire Escape Door (1:1+ matching) Completed 1/27/2020
2017 OCC Staircase (1:1 matching) Completed 1/27/2020
Habitat for Humanity 206 Boaz Home dedicated on 1/25/2020
Home Buyer Education February 1, 2020 class with 22 participants
October 17, 2020 class with 7 participants
Spot Blight Nuisance Abatement 111 Cypress, 130 Gibson, 110 Liberty, 207 Ostego, 324
Ozark, 207 Texas, 621 Crescent, 512 Crescent, 333
Ridgeway, 409 Apex, 213 Meadow, 114 Francis
Bus Shelter on Central near Crestwood Installed in February
Bus Shelter on Hobson at Charteroak (Ouachita Installed in February
Children’s Center)
Bus Shelter on Highrise Circle (Housing Installed in February
Authority)
David F. Watkins Memorial Park CDBG Phase II sidewalks and amphitheater completed.
Parks Dept installed trees, benches, lighting, playground
with rubberized safety base
As moderator, Michelle Sestili will call on each CDAC member then resident participants for questions and
comments.
6. Community Announcements
7. Adjournment
Get email alerts for Hot Springs
A daily email when new agendas and minutes are posted.