Call to Order: Kristi called the meeting to order at 12:21 p.m.
Minutes: Ron made a motion to approve the December 23, 2021, minutes as
presented. Nathan seconded the motion. The motion carried unanimously.
Public Hearing:
VAR22-001:
The applicant, Janice Vosselman with Home Pro Service, located at 4820 E Comish Drive, Idaho
Falls, ID, spoke on behalf of the applicant Heather Steimlosk. Janice informed the Board that they were
seeking a Variance that would reduce the rear setbacks for an addition to the residence located at 2576
Waterford Lane, Idaho Falls, ID. She believes this variance has merits for the following reasons: It would
make access for the homeowner easier and keep the structure away from adjoining lots. If built to current
codes, neighbors would be looking at separate structures with twelve-foot ceiling heights and built as
close to the rear property line as possible. Therefore, it will make a greater visual impact to neighbors. By
approving the variance, it will allow for a structure to be built while preserving as much of the back yard
as possible. It is her argument that preservation of the feeling of the neighborhood is better accomplished
with the approval of the variance.
Naysha Foster presented the staff report for the Variance for relief of a setback for an addition to
the principal structure located at 2576 Waterford Lane, Idaho Falls, ID. She informed the Board that this
property was annexed and zoned R-1 in July of 1988 and that the plat was recorded in September 1988.
The R1 zoning designation continued through the years and did not change with the city-wide initiated
zone change. The lot size was and still is, in compliance with the R1 standards. The residence met the R1
setbacks at the time of constructions and meets the current R1 setbacks. Naysha stated that this lot is
approximately 9,245 square feet. The R1 lot size requirements are between 7,000 and 13,500 square feet
except for corner lots and cul-de-sac lots or other unusually shaped lots. Those lots may be larger than the
13,500 square feet. This lot size is consistent with other interior, non-cul-de-sac lots in the subdivision
and surrounding area. Cul-de-sac and corner lots average approximately 1,000 square feet larger than this
lot. The lot is not an unusual shape and there are no issues with topography. Two corner lots across
Waterford, 2545 and 2615 were both denied variances to reduce front setbacks in 1989. The R1 Zone has
a minimum rear setback requirement of 25 feet. The applicant wishes to construct a building addition that
would extend into the rear setback 16 feet leaving a 9-foot setback. There are currently no other lots in
this area that have structures that extend into the required rear setback. If the applicant were to detach the
proposed structure and build it as a standalone accessory structure the rear setback could be as little as
BOA Minutes 5-26-22 Page 1 of 4
Planning Division
Office (208) 612-8276
zero feet. The side yard setback would be a minimum of 6 feet. The proposed structure could be permitted
today as a detached structure with no need for a variance. Naysha said the staff has reviewed the variance
and finds that there is no undue hardship. There are no physical limitations that are unique to this
property, and setbacks for a detached structure can be met in accordance with section 11-3-4 of the
Zoning Ordinance. This application is not consistent with the Comprehensive Zoning Ordinance or the
Local Land Use Planning act. Therefore, staff recommends denial to the variance.
Daniel asked for clarification of structural setbacks.
There was no other Public Testimony. Kristi closed the public hearing
Board Discussion: Board discussed testimony sent to them by the public, one for and one against the
variance. Kristi said that they need to remember that they can only look at what the law
requires. In order to approve a variance, it must cause undo hardship or have physical
limitations on the property.
There was a short pause to the meeting due to video and audio issues.
The Board continued their discussion. Ron made a motion to approve the application.
There was no second. Kristi stated that they needed to be very careful about making a
recommendation that violates the law, and that approving this application would do so.
Mike Kirkham, Assistant City Attorney, informed the Board that one thing they would
need to do was put together some criteria on how the decision was made. So, when
making the decision you might think that if a variance causes an undue hardship, think of
what that is exactly. Kristi asked Ron to expand on how this variance fits the criteria. Ron
said he was in his car, and he did not have the paperwork with him. Ron stated that he
had that wrong in his mind and withdraws the motion. Daniel asked Mike Kirkham why
the setback requirements were the way they are. Mike informed the Board that Zoning
Codes were adopted by the city and this law needs to be followed by what code reads
now. Nathan made a motion to deny the variance. Ron seconded the motion. This motion
passed with a three to one vote.
Reasoned Statement: Kristi read the reasoned statement. Nathan made a motion to approve the
reasoned statement as read. Ron seconded the motion. Motion carried with a three to one
vote.
CUP22-003:
David Richardson, the applicant, and Water Superintendent for the City of Idaho Falls provided
some background information on the decision to move the location of the water tower. In 2015 the
Water Facility Plant identified the need to replace the existing water tower due to a variety of
conditions. To determine where the new tower was going to be built, they went out on a public
campaign to present the fact that the old tower needed to be replaced and a new tower needed to be
built. In April of 2019 they started a public campaign and from the inception of this staff has been
insistent that the city needs a one-million-gallon water tower for future growth. On November 3, 2021,
the Library Board approached the city and offered their parking lot as a location. This is City owned
property. The consultants reviewed the site and began doing design work. The city sent out notification
to property owners within 300 feet of the proposed plan and held three public meetings prior o the BOA
meeting. Five property owners were in attendance and their concerns were logged and addressed.
BOA Minutes 5-26-22 Page 2 of 4
Planning Division
Office (208) 612-8276
David explained the process and timelines of construction. He discussed parking prior to, during, and
after construction.
Kristi asked David if they had an estimation of how long the short-term road closures would be.
David said that the roads would be closed for a couple of weeks but for one week at a time as work
demands. Kristi then asked if the trees that will be lost will be transplanted or replaced. David said four
trees will be removed, but others will be planted in different areas. Daniel asked about the closure of
the library parking lot. David said they will keep the parking lot open as much as possible, only closing
when works demands.
Naysha Foster presented the staff report for the Conditional Use Permit (CUP) for an Elevated
Water Tank for the City of Idaho Falls. She informed the Board that this property was platted in 1918 as
part of the original townsite. It was originally developed as commercial. The land was cleared, and the
library was constructed in 1977. In May of 2019, the property was rezoned to the Form Based Code.
Prior to that it was zoned CC, Central Commercial. The CUP is to construct a Public Service Facility, more
specifically an elevated water tank for the City of Idaho Falls. The Form Based Code defines water
treatment and storage as Utility and Infrastructure. Utility and Infrastructure uses are permitted but are
required to obtain a Conditional Use permit in all subdistricts. The General A subdistrict does have
standards for Utility and Infrastructure uses. It does not require any type of screening, fencing or height
restrictions. Naysha said that David Richards, Director of the Water Division, conducted a neighborhood
meeting on April 26, 2022, at the Idaho Falls Public Library as required by the Comprehensive Zoning
Code. Two other meetings were held for the general public. She said that the elevated tank will be
approximately 185 feet tall, with a welded-steel elevated tank of 75 feet in diameter with approximately
38-foot-wide concrete support pedestal and will be in the south-east corner of the library parking lot.
The proposed location of the elevated water tank will only eliminate one parking stall. Parking standards
will still be in compliance with 95 parking stalls for the library after construction. Landscaping in the
parking area will also increase by approximately 1,350 square feet. The city is proposing an 8-foot
wrought iron security fence around the tank. Naysha informed the Board that staff has reviewed the
CUP and finds that it complies with the Form Based Code and requirements of a CUP and recommends
approval as presented without additional conditions.
Daniel asked what the capacity of the water tank would be and what the lifespan of the water
tower is. David Richards said that the tank holds one million gallons and the anticipated life span it
eighty to one hundred years.
Kristi explained to the public that they are here regarding this application and not the location of
the water tower. She asked the public to not repeat testimony and written testimony has been turned
in, please do not repeat it.
Jed Campbell, 410 W. Broadway, is concerned about the domino effect of people who use all
day parking across the street during construction.
Beth Swanson, 1065 Ada, stated that the Library Board has enthusiastically approved this
location.
Mike Murdock, 2915 S. Boulevard (also owner of 152 and 152 ½ Park), is concerned that he was
never contacted and has properties that boarder the project. He stated that David called him once on
BOA Minutes 5-26-22 Page 3 of 4
Planning Division
Office (208) 612-8276
the phone to tell him about the public meetings. People are talking about the code for the trees, what
about the code for the water tower? Mike asked to hand out the building code that he printed out.
Naysha informed him that it was to late to turn in written testimony and that if he wanted it on the
record, he would need to read it. Mike asked how it can be too late if he did not know about the
meeting? Naysha told him he was contacted by telephone, and he attended the neighborhood meeting.
Kristi explained that they are there to discuss the Conditional Use Permit and the conversation needs to
pertain to that alone. Mike said they are talking about parking on Park Ave. and recommended they go
down there about 8:00 am and try to find a parking spot. Mike said he looked up the International
Building Code and Kristi explained that is not what is under discussion at today’s meeting. Naysha told
him that they were there to discuss the site itself not the building of the water tower. Mike said he
thinks that the site itself with the tower hanging over it right next door to his apartment that he rents to
his granddaughter is important if the tower falls over and kills her. Kristi said we are not here for
speculation; we are her for any comment you have about the Conditional Use Permit. Naysha explained
to Mike that the Board is there to set conditions on the property if needed not to discuss construction or
the structure. Kristi told Mike that the BOA has no control over building codes. Mike said that the code
states that a one-million-gallon water tank must be built 1000 feet from any building that can be open
to the public. Mike explained that what is being addressed is out of the International Building Code and
what is in front of the Board today is if the proposed use is allowed in the Zoning Code. The Board needs
to look and see if there are any conditions that should be imposed to minimize adverse impacts for the
community. Mike said you can not park anyone on the east side of Park Ave during construction. He said
most people that work downtown park here.
Howard Arthur, Cliff Street, disagrees with the location of this project. He said that this site is a
textbook perfect, extreme example, for a ground level terrorist event. Kristi told him the Board is not
there for that purpose. She told him to keep his comments to the use of the property. Howard said that
the use of the property was somewhat glazed over by the Water Department. He said that tower holds
one million gallons of water, one gallon of water weighs 8.3 pounds, so that is eight million three
hundred thousand pounds of water. That is four thousand one hundred and fifty tons in an elevated
position above a parking lot and the library. If the site were to receive a significant seismic event the
weight of the water and the tower would determine the future of anything. It would destruct and
Howard thinks that needs to be taken into consideration. Kristi told Howard that she’s sure this is taken
into account during the construction and building phase.
There was no other Public Testimony. Kristi closed the public hearing.
Board Discussion: There was no additional discussion by the Board. Nathan made a motion to approve
the application as presented. Ron made a motion to second. The motion passed
unanimously.
Reasoned Statement: Kristi read the reasoned statement. Nathan made a motion to approve the
reasoned statement as read. Daniel seconded the motion. Motion carried unanimously.
Adjourn: Kristi adjourned the meeting at 1:23p.m.
Respectfully Submitted,
Ann Peterson, Recording Secretary
BOA Minutes 5-26-22 Page 4 of 4
Get email alerts for Idaho Falls
A daily email when new agendas and minutes are posted.