Idaho Falls Redevelopment Agency
Regular MeetingIdaho Falls, ID · December 21, 2023
Minutes
IDAHO FALLS REDEVELOPMENT AGENC Y
P.O. BOX 50220
IDAHO FALLS, ID 83405
December 21, 2023 Regular Meeting Minutes Council Chambers
Call to Order: Lee Radford called the meeting to order at 12:00.
Members Present: Lee Radford, Kirk Larsen, Tom Hally, Brent Thompson
Members Absent: Chris Harvey, Jon Walker, Terri Gazdik
Also Present: Wade Sanner, Executive Director; Ann Peterson; Brad Cramer; Megan Conrad,
Esq. (via Teams); Renee Magee (via Teams) and interested citizens.
1. Modification to Agenda. None.
2. Approval of Minutes November 16, 2023. Thompson moved to accept the Minutes for
November 16, 2023, Hally seconded the motion, and the motion passed unanimously.
3. Approval of Expenditures and Finance Report.
Lee Radford presented the Finance Report dated December 21 2023. In the River commons
Area: $100.00 to Rebecca Thompson for transcription of Minutes; $1,850.00 to Renee Magee for
feasibility report for Yellowstone Project; $2,805.00 to Elam and Burke for legal services; $1,
650.00 to City of Idaho Falls for Administrative Services; $2,600.00 to RAI. In Eagle Ridge
$2,491.00 to Elam and Burke for legal services; $200.00 to the City of Idaho Falls for
Administrative Services. In Jackson Hole Junction $200.00 to the City of Idaho Falls for
Administrative Services.
Larsen moved to approve the Finance Report dated December 21, 2023, Thompson
seconded the motion and the motion passed unanimously.
4. Approval of Task Order #4 Authorizing Brad Cramer to Prepare an Updated Economic
Feasibility Study for the First Amendment to the Eagle Ridge Urban Renewal Plan
Deannexing Certain Parcels from the Revenue Allocation Area.
Radford indicated that this is the split that was agreed to move forward last month and it now
requires an economic feasibility study.
Conrad stated that there is a Consultant Agreement with Brad Cramer dated August, 2023.
Pursuant to that Agreement tasks orders can be issued to direct Cramer to do certain identified
scopes of work. Task Order #4 is related to the deannexation of parcels from the existing Eagle
Ridge Revenue Allocation Area. That scope of work to accomplish the deannexation is a Plan
amendment and there will need to be an updated economic feasibility study and that data will
look at the revenue allocation area proceeds to be accrued through the remaining life of the
District and the remaining projects within the remaining portion of the project area and that data
will provide transparency to the remaining years of the project area. The First Amendment will
start this effort and this is anticipated to be completed by the fourth Monday in July with the
updated Economic Feasibility Study being presented in February. The scope of work is estimated
to cost $6,000 at $130/hour. Conrad stated that because they are taking out of the District
potentially revenue generating parcels, they need an analysis to provide an updated projection of
what will be generated through the life of the District.
Thompson moved to approve Task order #4 Authorizing Brad Cramer to prepare an
Updated Economic Feasibility Study for the First Amendment of the Eagle Ridge Urban
Renewal Plan Deannexing Certain Parcels from the Revenue Allocation Area, Hally
seconded the motion. The motion passed unanimously.
5. Approval of Task Order #5 Authorizing Brad Cramer to Prepare Eligibility Report for
the Proposed Snake River West Project.
Conrad explained that pursuant to the Consultant Agreement, this Task Order #5 will direct
Brad Cramer to review the specific geographic area and determine if the parcels meet the
statutory conditions of deterioration that warrant the establishment of a revenue allocation area.
This is for the proposed Snake River West Area, which is the portion that is being deannexed
from the existing Eagle Ridge Project Area and the addition of adjacent property. This draft will
be available for January draft review and February meeting approval, and City Council approval
in March. Moving forward is contingent upon City Council. They have not done a second scope
related to the economic feasibility for the Snake River West, as this is the first phase establishing
a new project area. The estimated cost is $4,500 at $130/hour.
Radford confirmed that this is the new part, that will be apartments. Conrad agreed that it is the
new area.
Larsen asked if it is the 272 new apartments, Radford agreed.
Thompson moved to Approve Task Order #5 Authorizing Brad Camer to Prepare
Eligibility Report for the Proposed Snake River West Project, Larsen seconded the motion.
The motion passed unanimously.
6. Owner Participation Agreement with 2700 Boge Ave LLC Regarding the Proposed
Industrial Business Park Project Within the Stanley Boge Revenue Allocation Area.
Conrad went to page 25 of the OPA that shows the map of the Stanley Boge Project Area. North
Boulevard on the western boundary, north of union pacific, and Boge Ave, goes through the
project. Attachment 3 page 28 of the OPA shows where the project site is located on the
northern end of the project. There is a preliminary concept design showing a three phase build
out. This is a standard OPA form. The proposed eligible costs are centered around blasting,
excavation, and fill. Phase I will move forward and Phase II and III will be dependent on full
lease of Phase I. First Phase will commence in April 2024 (at earliest). They are working on
designs and will be submitting documents to the Planning Commission soon. Conrad will be
making changes to the draft OPA based on those changes. The reimbursement procedure on
Page 8 of the Agreement shows that the reimbursement doesn’t commence until CO for the
entire first phase of the private development, then there is completion of all Agency funded
eligible improvements, execution of the Confirmation of Reimbursement Form for the completed
scope of work, completion within a certain time period and the fact that the revenue allocation
proceeds from the first phase of the development are actually received by the Agency. There is
some lack of certainty as to whether they will mobilize and do all of the blasting and excavation
and fill for all three Phases at once or undertake each scope as they take on each Phase. The
reimbursement procedure will be on completion of the Agency Funded eligible improvements
related to the phase that is being undertaken. If they take all off the work contemplated for
blasting and excavation but only build Phase I, they are aware they might not be fully reimbursed
by the end of the district, so there is incentive to have all three phases built out quickly. The
developer had a question regarding planning cost. The MOU had estimated planning costs at
$38,000 and now that they are towards the end of the OPA negotiations, they will do an
accounting to determine actual planning costs and that will be memorialized in a confirmation of
reimbursement form and those planning costs are not reimbursed until there is taxable
development on the site. The planning costs are reimbursed at the same methodology as the
reimbursement obligation under the Agreement, if there is not private development on the site
the planning costs will not be reimbursed. All three phases built out are anticipated to be $11
million in new development taxable value, and the reimbursement rate is 75% of the TIF
generated from the site.
Radford confirmed that if they incur all of the blasting cost, but only build the first building they
will only get the revenue from one building. They could blast only what is needed for Phase I
and get revenue to cover that. Conrad stated that part of the comments and changes to the
Agreement will further outline the phased approach, and they could break out the eligible project
costs and do those by phase, and that concept needs to be better defined in the Draft OPA.
Thompson asked if the $38,000 is reimbursable up front when funds come in. Conrad stated that
the $38,000 will be less once they get through an internal audit and they will memorialize that
amount in the confirmation of reimbursement form. The costs are reimbursed using the same
methodology as the reimbursement of the reimbursement obligation of the actual eligible costs.
They will need CO on the first Phase and the Agency will have to be receiving revenue from the
development. Those costs will be first paid out because it will be the first confirmation of
reimbursement form, but if they do not move forward with development, they do not get paid for
the planning costs. Thompson confirmed that Engineering will approve hard costs that are
reimbursable per phase. Conrad agreed that as they move through their design and get better
numbers, they will have a better understanding of the costs. They are estimated at $885,000 and
that could go up or down based on the hard bids they get. Conrad stated that once they perform
the scopes of work they have to submit cost documentation and that is reviewed by City Staff for
commercial reasonableness, they make sure the costs were incurred.
Larsen asked if the first Phase ends up costing more than a third of the total, it doesn’t change the
grand total that can be reimbursed. Conrad agreed and stated that with this OPA they have to go
off of estimates, and it is a do not exceed amount that can be broken out in Phases. Conrad stated
that if their ultimate engineers estimates are higher they would have to come back to the Board
and ask for the Board to increase the OPA do not exceed amount.
Conrad stated that this is a draft and there will be changes and this will come back in January or
February.
7. RAI and Legislative Update. Conrad stated that RAI continues to receive success stories
that are being compiled and shared with certain organizations to help drive the conversation with
Legislators and others. There is likely going to be legislation that will impact urban renewal and
they are working to find replacements to the program. They are continuing to monitor.
Hally stated that it is election year, and these ideas take time, so he thinks a lot of the things that
are controversial will drift and not pass. Conrad agreed and there is a drive to have this be a
shorter session and it is hard to know the timing on when legislation will be addressed.
Hally moved to adjourn the meeting, Thompson seconded the motion passed unanimously.
Kirk Larsen will now be the City Council.
Hally stated that someone will be appointed, and he has been on City Council for 20 years. He
has been on the Board for 1.5 decades.
Thank you for your service, Tom Hally
Next Regular Meeting: January 18, 2024.
Radford adjourned the meeting at 12:30 p.m.
Respectfully Submitted: Beckie Thompson
Get email alerts for Idaho Falls
A daily email when new agendas and minutes are posted.