Site Development Review Committee
Regular MeetingKalispell, MT · June 27, 2019
Minutes
SITE DEVELOPMENT REVIEW COMMITTEE SUMMARY
Thursday, June 27, 2019
Lower Level Conference Room
201 First Avenue East
ATTENDING:
Dave Dedman, Fire Chief Tim Falkner, Administrative Captain
Tom Jentz, Planning & Building Director Rick Parker, Building Plans Examiner
Jarod Nygren, Senior Planner (Acting Chair) Susie Turner, Public Works Director
GUESTS: James Freyholtz, Montana Department of Transportation; Christi & Kara with the Ivy
Building; and Margaret Davis, Resident
HEAR THE PUBLIC:
‘Margaret Davis, 160 Charlotte. I’m looking at the display of the site plan for the Gateway Center
and I’m hoping that the pedestrian accesses will be indicated from the apartments. (Also,) the
internal pedestrian walkways to the Gateway Center and the bus stop will be clearly marked and
agreed upon between the parties according to conditions 13A and 14 of the apartment PUD. Thank
you.”
PERFORMANCE BOND REMINDERS:
Silverbrook Phase 2A & Treeline Center – Public Works is working with both of these projects on
their Warranty Bonds per Turner. Nygren added that on Treeline Center, there is a little bit of
landscaping they are going to include.
FVCC (note from Sorensen) – nothing from Public Works.
OLD BUSINESS:
Gateway Community Center – 1203 Hwy 2 W; parking lot changes. Nothing new has been
received. This will be on the agenda for next week.
406 Dentistry – 1315 Hwy 2 W; remodel existing building/change of use from salon to office.
Public Works is waiting on their submittal regarding including the boulevard at Corporate and then
removing the dead-end section of sidewalk along the highway. This will be on the agenda for next
week.
CHS Fuel Station – 1355 Rail Park Drive. Turner noted that Public Works is working with the
engineer on this project and it is currently under review. This will be on the agenda for next week.
1
Ivy Building – 343 1st Ave W. Christi and Kara are not wanting to put the curb extension in, and the
extension of the sidewalk to come up to the public alley ROW. There is a driveway access out to 4th
from the parking area. With their retail business that delivers large trucks, they were thinking that
they could pull up in the alley, be able to pull into the driveway and pull out. Additionally, the fly
fishing business that they are leasing to people in the back, will be coming in in the early morning
with trucks and boats behind them to pick up clients and then head out. Without that access, they
would either be blocking the alley or blocking 4th Street or 1st Street West which are main
thoroughfares. The back space has historically been garages. This is one of the main reasons they
bought this building was for the delivery space. They want to create off-street parking for their
customers and be able to utilize the space in the back in a functional way for the City. Do they need
to call it a berth space so they can have deliveries come in there? They would like to keep the alley
clear for the Valley Bank drive-thru customers next door. They will put landscaping at the back of
the lot and the front area to make the building more attractive. This is a one-way alley that goes
north to south. They are creating another parking space in the front as they are moving the property
line back to the original property line. They will meet with Parker about the handicapped space.
Because this is a new project they need to meet our parking standards. Their curb cut was discussed.
The committee still wants the curb extended to the ROW. This will be on the agenda for next week.
Base Camp RV Park – 1000 Base Camp Rd; south side of Hwy 93 bypass - subdivision. Nygren
stated we received the MDT Permits. The entire package went to Council yesterday so they can at
least approve the Revised Preliminary Plat. The owner can then start the rest of that construction and
hope to be open by July 15th. Freyholtz stated MDT just received some updated plans for the trail.
Public Works has already looked at adding another two feet to a section. The Council will be
looking at the (Revised Preliminary Plat) Final Plat Monday night. There is an $800,000 +/- bond in
place for the rest of the work. There are three MOU’s that Public Works is reviewing and then they
will go to the City Manager this week for his signature. This will be on the agenda for next week.
Glacier Bank – 49 Commons Loop; remodel. Near hospital on Commons Loop. Their stormwater
is still outstanding with Public Works. Turner stated we also need to receive the tech memo for the
source water protection for the wells. This will be on the agenda for next week.
J2 – 115 W Wyoming; storage building mezzanine addition inside the new storage building. Their
after-the-fact plans do not represent what is out there. We are still waiting for updated plans. There
has not been a status update in the last few days. There are a number of fire issues, including storage
items that were not supposed to be there. The Building Code would require sprinklering to make it
safe, and the zoning would not allow those storage items to be stored there at all. Nygren noted that
the way the mezzanine was built, it is pretty much a second story and not a mezzanine. We are
waiting for new plans. They will need to put a 4” fire line in the building. This will be on the
agenda for next week.
NEW BUSINESS: None.
2
PLANNING OFFICE ITEMS:
New CUP – Nygren sent out a referral on this project for a 9-unit, multi-family project across from
the skate park on N Woodland Park Road for your comments. No official public comment has come
in yet. There is a Facebook page that was created by someone opposing the project with some
comments on it, but this is not considered “official public comments.” If you have any comments,
please give them to Nygren.
Pedestrian Plan – We will be doing a Work Session at the Planning Board.
Downtown TIF Policies – We had a Work Session on this and it was well received. We are going
to continue to work with the Urban Renewal Agency on an application process. The policies are
how the URA and Council would work with developers to basically give them back their tax money
for any public infrastructure improvements they do up to a certain amount. This could be applied to
the Ivy Building project.
OTHER REPORTS:
Meadows Edge – Freyholtz stated MDT approved the Approach Permit for Phase I. This will also
be going to Council for Final Plat.
The meeting was adjourned at 10:45 a.m.
Minutes transcribed by Kathy Nelson, Recording Secretary
cc: Police City Manager Fairgrounds MDOT
Bldg. Fire City Clerk City Airport
Planning Parks Comm. Dev. Public Works
3
Agenda
Planning Department
201 1st Avenue East
Kalispell, MT 59901
Phone: (406) 758-7940
Fax: (406) 758-7739
www.kalispell.com/planning
SITE DEVELOPMENT REVIEW COMMITTEE AGENDA
Thursday, June 27, 2019, 10:00 a.m.
Lower Level Main Conference Room
201 First Avenue East
(1) Hear the Public
(2) Performance Bond Reminders
(3) Old Business: Gateway Community Center – 1203 Hwy 2 W; parking lot changes
406 Dentistry – 1315 Hwy 2 W; remodel existing building/change of
use from salon to office
CHS Fuel Station – 1355 Rail Park Dr
343 1st Ave W Building – 343 1st Ave W (previously listed as Ivy
Building)
Base Camp RV Park – south side of Hwy 93 bypass/Base Camp Rd
Glacier Bank – 49 Commons Loop; remodel
J2 – 115 W Wyoming; storage building mezzanine addition
(4) New Business:
(5) Planning Office Items: Planning Board Agenda
(6) Other Reports:
Cc: City Manager Public Works MDOT City Airport Planning Dept
Bldg Dept. Fire Dept. Comm. Dev. Parks City Clerk
Police Dept. Fairgrounds
Get email alerts for Kalispell
A daily email when new agendas and minutes are posted.