A meeting of the Board of Public Works was called to order by Chair Thiele on Monday, October 6,
2025, at 6:00 P.M.
Members present: Antoine, DeCoster (Zoom), Eggleston, Kilgas, Schell, Schumacher, and
Thiele.
Absent & Excused: Moore.
Also present: Mayor Penterman, Attorney Greenwood, DPW/Eng. Neumeier, Com. Enrich. and Rec.
Director Vosters, Mark. and Com. Manager Fencl, Fire Chief Carrel, HR Director Hodge, Police Chief
Graff, Street Superintendent Van Gompel, Dir. of Plan. and Com. Dev. Kittel, Fin. Dir. Van Rossum,
and interested citizens.
Motion by Eggleston, seconded by Kilgas to excuse the absent member.
All Ald. Present voted aye.
Motion carried.
1. Correspondence – none.
2. Discussion Topics.
a. Authorization to submit a State Trunk Highway Connection Application for a public road
at/across from Morningside Drive on STH 55.
The Director of Public Works/City Engineer is requesting authorization to submit a State Trunk
Highway(STH) Connection Application for a public road at/across from Morningside Drive on STH
55, on behalf of the city. The application submitted to the Wisconsin Department of
Transportation (WisDOT) is required for access as the project area is under WisDOT permitting
authority. This means the city is asking WisDOT to allow a public roadway connection at this
location. The authorization to submit an application is not an approval of any design elements,
however, the reviewing parties agree that a roundabout would be the approved traffic control
treatment if this intersection is installed for this development. Authorization to submit the
application would allow the City and KASD to start working with WisDOT on a formal design for
the intersection, including pedestrian accommodations. After the design process and with DOT
approval, an access permit would allow for the street connection to be constructed if City BPW
and Common Council direction to do so. As part of the preliminary WisDOT review of this
connection, a Traffic Impact Analysis (TIA) was required. A TIA is a detailed look at the proposed
development with proposed roadway connections and the impacts that the development traffic
could have on several surrounding roads and intersections.
Alders thanked the Director of Public Works/ City Engineer, Neumeier, for all the documents
provided for this project. Alders also agreed that a Public Informational Meeting should be held
during the design process, prior to a final design being considered by the city. Alder Kilgas
expressed concerns with pedestrian safety with the new middle school going near the proposed
roundabout. KASD Director of Operations and Finance, Chris McDaniel, explained the proposal for
a pedestrian tunnel underneath Highway CE. Alders expressed concerns about the timeline of this
project and would feel more comfortable moving an application forward after public comments
have been received and a listening session has been held.
Motion made by Antoine, seconded by Kilgas to authorize the Director of Public Works/City
Engineer to submit a State Trunk Highway Connection Application to WisDOT for a public road
at/across from Morningside Drive on STH 55 contingent on a public informational forum prior to
the submission of the application.
Roll call vote: Antoine- aye, DeCoster- aye, Eggleston- aye, Kilgas- aye, Schell- aye, Schumacher-
nay, and Thiele- nay.
Motion carried.
b. Ahlstrom/Red Hills Landfill Updates.
Ahlstrom staff were not present but Director of Public Works/ City Engineer, Neumeier, stated he
would pass along any questions or concerns to them.
c. Recommendation for Bids on Project 8-25 Sanitary and Storm Sewer CIPP Installation.
The Engineering Department has reviewed and analyzed the bid received from Visu-Sewer on
September 9th, 2025, at 4:00pm for the 8-25 Sanitary and Storm Sewer CIPP Installation Project. The
Engineering Department only received one bid and compared it against the Engineer’s estimate that
was put together prior to bid opening. The Engineer’s estimate is compiled utilizing previous years’
prices and adjusted for inflation and changes in work descriptions. The received bid was
$2,092,499.50 for the work, a number much higher than anticipated. The Engineer’s estimate for the
project was $1,386,397.00. This high bid is due to some very extensive work that would have been
required for one of the main items on the project, along with some deadlines that the contractor did
not feel comfortable meeting. The Engineering Department will be making alterations to the project
scope and plans to rebid the project to receive more competitive pricing.
Motion made by Schell, seconded by Schumacher to reject all bids for Project #8-25, Sanitary and
Storm Sewer CIPP Installation, and authorize the Engineering Department to seek bids for Project
#8-25R, Sanitary and Storm Sewer CIPP Installation.
All Ald. Present voted aye.
Motion carried.
d. Recommendations for Disposal Site.
The continued concern about staff safety and non-compliant dumping at the Municipal Disposal site
has brought staff and board members to consider operational changes. Providing an alternative
disposal for Disposal Site users if refuse and recycling services were removed was a direction from
this board. With the winter holidays being the highest producer of residential waste, providing a drop-
off option of household garbage and recyclables for Disposal Site users seems to be the best fit. The
city can also provide the same drop-off option in the spring before large and irregular collections
resume in April. Drop-off dates would be Tuesday, January 6 from 7:15am-6pm and Tuesday, March
3 from 7:15am-6pm. These dates would be slightly adjusted each year and advertised in the city
calendar along with Facebook and the city website. Residents can always bring excess garbage and
recycling to the Outagamie County Recycling and Solid Waste Drop-off site Monday-Friday 7am-
3:30pm and Saturday 7am-12pm. With the removal of the garbage and recycling containers from the
Disposal Site, the city can provide compost for free to residents that have valid access to the site.
This material would be managed and available to residents in the same manner as the wood chips
offered at the site.
Motion made by Eggleston, seconded by Antoine to direct staff to remove the garbage and
recycling services from the Municipal Disposal Site on January 2, 2026, advertise the service
changes, provide and advertise the two drop off dates, and update waste ordinance 11.11 to
reflect the changes to the Municipal Disposal Site.
All Ald. Present voted aye.
Motion carried.
e. U.S. Army Corps of Engineers Right of Entry for Construction - Bicentennial Ct.
Motion made by Kilgas, seconded by Schumacher to authorize Mayor Penterman to enter into an
agreement with the U.S. Army Corps of Engineers for Right of Entry for construction on
Bicentennial Court.
All Ald. Present voted aye.
Motion carried.
f. Riverside Park/Pool Hill - Easement to Kaukauna Utilities.
The City and Kaukauna Utilities are moving towards the final steps to facilitate the expansion of the
water treatment facility at Riverside Park and the new plant on the top of Pool Hill. The Site plans have
been reviewed, the needed CSM has been reviewed with the next step being to finalize the needed
easements. These easements are necessary to facilitate access, construction, and long-term
maintenance of the upgraded filtration systems.
Motion made by Schumacher, seconded by Schell to approve the easements as presented and
direct the mayor to sign the required documents to record the easements.
All Ald. Present voted aye.
Motion carried.
3. Adjourn.
Motion made by Antoine, seconded by Eggleston to adjourn.
All Ald. Present voted aye.
Motion carried.
Meeting adjourned at 7:14 pm.
Kayla Nessmann, Clerk
Agenda
BOARD OF PUBLIC WORKS
City of Kaukauna
Council Chambers
Municipal Services Building
144 W. Second Street, Kaukauna
Monday, October 06, 2025 at 6:00 PM
AGENDA
In-Person and Remote Teleconference via ZOOM
1. Correspondence.
2. Discussion Topics.
a. Authorization to submit a State Trunk Highway Connection Application for a public road
at/across from Morningside Drive on STH 55.
b. Ahlstrom/Red Hills Landfill Updates.
c. Recommendation for Bids on Project 8-25 Sanitary and Storm Sewer CIPP Installation.
d. Recommendations for Disposal Site.
e. U.S. Army Corps of Engineers Right of Entry for Construction - Bicentennial Ct.
f. Riverside Park/Pool Hill - Easement to Kaukauna Utilities.
3. Adjourn.
NOTICES
Notice is hereby given that a majority of the City Council will be present at the meeting of the Board
of Public Works meeting scheduled for Monday, October 6, 2025 at 6:00 P.M. to gather information
about a subject over which they have decision making responsibility.
IF REQUESTED THREE (3) DAYS PRIOR TO THE MEETING, A SIGN LANGUAGE INTERPRETER WILL
BE MADE AVAILABLE AT NO CHARGE.
MEETING ACCESS INFORMATION:
You can access this meeting by one of three methods: from your telephone, computer, or by an app.
Instructions are below.
To access the meeting by telephone:
1. Dial 1-312-626-6799
2. When prompted, enter Meeting ID 234 605 4161 followed by #
3. When prompted, enter Password 54130 followed by #
To access the meeting by computer:
1. Go to http://www.zoom.us
2. Click the blue link in the upper right hand side that says Join a Meeting
3. Enter Meeting ID 234 605 4161
4. Enter Password 54130
5. Allow Zoom to access your microphone or camera if you wish to speak during the meeting
To access the meeting by smartphone or tablet:
1. Download the free Zoom app to your device
2. Click the blue button that says Join a Meeting
3. Enter Meeting ID 234 605 4161
4. Enter Password 54130
5. Allow the app to access your microphone or camera if you wish to speak during the meeting
*Members of the public will be muted unless there is an agenda item that allows for public
comment or if a motion is made to open the floor to public comment.*
Get email alerts for Kaukauna
A daily email when new agendas and minutes are posted.