• Redevelopment/Mariner’s Village PILOT
This Town Hall Meeting was recorded: 3-19-24 Town Hall Meeting Mariners Village Pilot
Presentation.mp4 (sharepoint.com)
John Cantalupo, Esq., Archer & Greiner, P.C.
David Weinstein, Esq., Archer & Greiner, P.C.
Sean McGowan, Esq., Greenbaum, Row, Smith & Davis, LLP
Ken Pape, Esq., Heilbrunn & Pape
Clay Perlman, Mariner’s Village and 357 W. Front Street
Erick Aguiar, Muni PILOT Solutions
John Cantalupo – Borough bond counsel, welcomed all to the meeting during which the Mariner’s
Village project will be discussed, as well as some general information about PILOTs and Mariner’s
Village PILOT, specifically. He explained the developers will give a presentation followed by a
presentation by the experts for the Borough who have analyzed the application. The meeting will
then be turned over for questions and answers.
Sean McGowan – redevelopment attorney and an expert in PILOTs, explained he will give a brief
presentation on what has happened, where we are, the PILOT that we are requesting, and the
benefits it is going to provide to allow the project to be built, as well as the benefits to the overall
community.
Kenneth Pape – represents Mariner’s Village and 357 W. Front Street, and began this process
about eight years ago with the governing body. In 2017, after a year’s worth of work, the properties
were designated an area in need of redevelopment and a redevelopment plan was negotiated. A
contract was drawn between the Borough and the developer, and the requirements were set forth
in that agreement, including 120 apartments, and an obligation to preserve and maintain the
marina. Since that agreement was entered into, we have completed most of the approvals, and
presented an application to the Borough Planning Board in 2018 for the approval of the apartment
building.
The second approval required by the redevelopment agreement was for the preservation of the
marina, and we have completed that process. Other approvals required included the Monmouth
County Planning Board subdivision approval, which was a difficult approval that took a couple of
years. It was coincidental with the condemnation that was going on with the bridge in front of the
property, and that slowed it down. We also had to go back to the County Planning Board for site
plan approval. Those approvals are complete and are in place. We had an obligation to do
extensions of water/sewer approvals. The water supply was determined by the Borough’s engineer
to be inadequate for the existing community, as well as for the proposed community. We had to
design a system that brought in new water lines, which has been reviewed by the Borough engineer.
A final review is outstanding. We also had to design a sanitary sewer system to service the
community which has gone through municipal review. The next step is to go to Bayshore
[Sewerage Authority]. The most difficult approval was the DEP’s CAFRA approval, which took
us almost four years, and was received earlier this month. We are very close to the end of the
approval process.
We also approached the Borough for a vacation of a portion of Washington Street, which was done
by ordinance. We also came before the governing body to review with them the PILOT that was
previously approved for this project four or five years ago, which was determined at that time by
both the Borough and developer to be a necessary element of the project. We are looking to modify
the PILOT. We are seven plus years into the approval process, and with the issuance of the CAFRA
permit, we are just about finished with the approvals.
Sean McGowan – talked a little bit more about the redevelopment process and the benefits that it
provides to a developer, as well as to the community. There has been a long-standing working
March 19, 2024
Keyport, NJ
Page |2
relationship between the Mariner’s Village folks and the Borough of Keyport for many years at
this point.
Many years ago, Keyport decided it would be most advantageous to designate the area as an area
in need of redevelopment. That means that qualified individuals, urban planners, professional
planners, take a look at property and decide if it meets certain criteria - those criteria generally
being blight, or similar type conditions, that are preventing the property from being redeveloped
by a developer without the aid of the redevelopment process. If the property qualifies as an area in
need of redevelopment, the governing body can adopt a resolution declaring that property an area
in need of redevelopment. That provides for two distinct benefits to both the municipality and the
developer. The first is the property becomes eligible for a redevelopment plan which is essentially
a zoning plan for that specific property that’s often negotiated between the municipality and the
redeveloper that provides for a project that both parties think can lift the property out of that “in
need of redevelopment” state. It’s a project that the municipality thinks will generally be beneficial
to the municipality, as well as a project that is feasible for a developer to build and will be an
economic success.
The second benefit that the redevelopment designation provides is that it makes the property
eligible for what is commonly known as a PILOT – a payment in lieu of taxation. The theory is
that the property is in need of redevelopment, yet it hasn’t been able to be developed under the
normal zoning code for a variety of reasons. In order to incentivize the development of the
property, the property is eligible for the PILOT. What that does is it provides certainty to the
redeveloper what the taxes are going to be moving forward, essentially removing a very large
variable from the equation as to whether the project is going to be economically feasible.
Due to the high cost of living in New Jersey, and the high cost of construction, PILOTS are
essentially a necessity when you’re building a project of such size and magnitude as this 120-unit
project. There are numerous amenities and parts of this project that are not always provided by a
developer, but because the property was eligible for a redevelopment plan, these are things that
Keyport negotiated had to be part of the project. The Mariner’s Village folks, who wanted to
provide a first-class project here in Keyport, agreed to these amenities: private-gated garage
parking, private storage room, common meeting areas, pool, gym, dog park, the marina will be
kept and improved, shuttle to nearby train station, and customized electric vehicles for utilization
by the residents around town. All of these amenities come at a large cost. That is why a PILOT is
generally necessary for a project such as this. Parking garages these days cost approximately
$25,000-$30,000 per space.
It’s just not economically feasible to build these projects if you have the uncertainty of what your
tax bill is going to be. In order to create the certainty, as well as a more economically feasible tax
payment, the developers and the municipalities negotiate the PILOT, which is documented through
a financial agreement. It generally provides for a slightly lower tax payment called an “annual
service charge” – but we will use the term “tax” here because it is familiar and they are incredibly
similar in their functions. The municipality will agree to receive a slightly lower tax payment in
exchange for the developer building a project on that property that has been designated an area in
need of redevelopment and lifting the property out of an area in need of redevelopment.
The theory, which has been proven throughout the state, is that a development such as this not only
will benefit the developer, but it benefits the town and everyone living in the town. This
development will provide two hundred new residents that are going to use the stores and businesses
here in Keyport. It is projected they will have about $100,000 in annual household income they’re
going to spend throughout town on restaurants. The developer is going to incur roughly $750,000
in annual operating expenses with a very large portion of that going to residents of Keyport and
surrounding towns. Statistics show that for every 100 units of construction, 161 jobs are created
and $2.2 million in taxes and other revenue for the local governments, for a total of $11.7 million
into the local economy.
After the project is finished, every 100 units will create 44 local jobs and put $2.6 million annually
into the economy. Even though the developer is going to receive the benefit of a slightly lower tax
payment, there are all of these benefits that have been proven through statistics throughout the
state of New Jersey as very good reasons to incentivize the developer to make the project
March 19, 2024
Keyport, NJ
Page |3
economically feasible to lift this property, which is so important to the Borough of Keyport due to
its location due to the marina, out of that need for redevelopment criteria.
Another benefit to the municipality is that, although the tax payment is slightly lower, typically,
your municipal taxes are divided between the municipality itself, the school board, and the county.
Every town has a different ratio, but in Keyport roughly 35% of each tax dollar gets paid to the
municipality. When the municipality adopts a PILOT, 95% of that revenue goes to the municipality
itself, rather than 35%. So, even though the overall tax payment from the developer is slightly
lower than it would be under ordinary taxation, the municipality itself is actually seeing more tax
dollars from the PILOT payment than they would receive otherwise under ordinary taxation. So,
then the question is, what about the school board. There have been many, many studies in the state
of New Jersey, generally by the Rutgers University Planning School, that show that new apartment
complexes such as this generally do not provide a lot of children to the school system. There are
some, but the apartments are not geared toward families and they’re not conducive to families
living in these apartments. Very often you will have a young married couple move in and have a
child, but once that child is approaching school age, they will go out and buy a house in the local
community or surrounding towns. There is an exception in the fact that some new apartment
buildings of this ilk do create school children, but they are in units that are designated to be
affordable housing units. This property has no affordable housing units that will be deed restricted.
Therefore, the statistics show that the number of school children at this property will be very
minimal. For 120 units, they might send three or four kids to the school system per year.
The property, as it is now, in 2023 you received about $13,000 in tax payments from the owners
of the property. If this project is not built, it will generally proceed at that $13,000 a year with
maybe some slight increases to the tax payments. Without the PILOT, that is what most likely will
occur because the building is not economically feasible, the developer will not be able to receive
a construction loan and the property will continue as-is. Versus the PILOT, where this project that
is being requested, will generate $403,000 in PILOT payments in year 3, and by year 20 we will
be $665,000 per year, with obvious increases in between years 3 and 20, and then beyond to year
25. It really is a financial windfall to the Borough of Keyport.
Lastly, in order to build this, it will take roughly $40 million in development and construction
costs. Often people will say that a developer needs a PILOT because they are not financially secure
enough to be able to build without it. That’s not how it works. In order to build a building like this,
999 times out of 1,000, the building is built through construction financing. In order to receive
construction financing in the state of New Jersey, lenders generally require that a PILOT be
provided. The variable of unknown taxation is just too much for construction lenders to bear.
They might lend the money, the building might get built, and then its economically infeasible and
the town will take the building and the lender will not receive their money back. So, it’s generally
required by construction lenders that financial agreements be entered into for buildings such as
this.
Keyport is not breaking new ground here. There have been hundreds, if not thousands, of
successful financial agreements entered into throughout the state of New Jersey. Princeton,
Westfield, South Orange, West Orange, Long Branch, Red Bank, Morristown, Boonton, Denville,
Florham Park, Chatham, Park Ridge, Robbinsville, Metuchen, Hoboken, to name a few, and a lot
of these places are places that have seen real renaissances over the last twenty years and they have
skillfully used the tools available to the municipality provided through the redevelopment laws to
their advantage. Twenty and thirty years on, they’ve seen the benefits and they’ve seen how
successful these programs can be. That is what the Mariner’s Village folks want to execute in
Keyport. They want to build this first-class building, they want to help the community, they want
to rebuild and maintain the marina for everyone in town.
John Cantalupo – thanked Sean McGowan and asked if Mr. Perlman could address rumors
regarding the developer’s commitment to the town and the project.
Sean McGowan – has worked with developers throughout the state of New Jersey and Clay and
his team have shown an absolutely uncommon dedication to this development. They have spent
$8 million to date trying to build this project and that is atypical. They are very dedicated to this
Borough.
March 19, 2024
Keyport, NJ
Page |4
Ken Pape – there’s no limit to the funding that’s available to Clay and his partners. The $8 million
is acquisition costs over the last few years. We were required to buy a number of houses. We were
required to buy the Endeavor House and lands where the property is going to be developed. All of
those were acquisition costs - money to buy properties. There were also the costs of going through
the approval process. Since 2017, when we really started working on all of the approvals, we’ve
never stopped. It’s been complex, and at times complicated, but we’ve never stopped. With the
DEP CAFRA permit in place, we’re now at the downhill end of the approval process.
Clay Perlman – thinks the number is closer is $10 million. We are the marina owners and are not
planning on selling the marina. We are not planning on selling the development. We’ve never
entertained it. We had a broker come to us at one point who listed it without my approval. I had
to reverse that and explain it. We’re not going anywhere. We’ve been here and we are not just
developers trying to flip, and this and that. The marinas are having difficulties in this town, they’re
not doing well. This project will put a shot in the arm of this marina. This marina will end up being
one of the nicest marinas around. It’s a common theme, Mariner’s Village, so everything looks the
same with the marina and the apartments. It’s like a PUD – a Planned Unit Development. The
commitment level is 100%.
Sean McGowan – wants to re-emphasize how important a milestone it is that the CAFRA permit
has come in. Flood levels are generally rising in the state of New Jersey and the DEP over the past
10 years has started really doing their due diligence on any development that occurs next to water
or in areas that may flood and it is now very challenging to receive permits for waterfront
development or in flood zones. The permit took so long not because of any deficiency of the
redeveloper, but simply because they are very difficult to get. A lot of developers would have said
this is going to take too long and its going to have a lot of holding costs and I’m not going to do
it. The Mariner’s Village team want to build this project and they hung in there. It’s a huge
milestone that the CAFRA permit was provided.
John Cantalupo – asked Ken Pape to describe further the original plan from 2014 to do single-
family homes and that the Borough government at that time came to Mr. Pape wanting to do an
area in need of redevelopment and undertake this project.
Ken Pape – there were informal discussions. Clay and his partners had come up with idea of
developing a portion of this property with more traditional single-family homes and when we sat
down with the Borough representatives, the Borough planner, the Borough special counsel, the
direction that we were steered in is exactly what you have in the redevelopment contract when it
was signed, specifically stating this building, this location, and this number of units.
John Cantalupo – and everything that you’ve been asked to do by the Borough, you’ve roughly
been saying since 2014, you guys have done. Describe that a little bit more, that this is not a project
that you brought, but that they asked you to do it.
Ken Pape – when we sat down with the people who were negotiating the redevelopment agreement,
we got to say yes to their requests. Anything that we were asked to do, we did. When we were
asked to design a water system that was going to be not only for this project but for the downtown
area, Clay said yes. When we were asked to do the same with sewer, Clay said yes. When we were
asked to do improvements out into the bay that would be open to the public, Clay said yes. We
were asked to add additional parking on our property for the general public, no benefit to the
project at all, Clay said yes. Whatever we were asked to do, we did.
John Cantalupo – the water and sewer restructure is all being done by you. You’re enlarging the
mains at your cost and handling all that yourselves at no cost to the Borough or the tax payers.
Ken Pape – we presented the entire project to the Planning Board. The Planning Board approved
it first as an apartment complex. We were required to return to the same Planning Board for the
marina, and we did. On at least an annual basis we report to the Planning Board exactly where we
are and coming up in May we’ll be doing it again.
John Cantalupo – when developers come forward with their financial application asking for a
PILOT, the Borough just doesn’t accept the numbers and all of the information provided by the
developer. We have to make sure we verify that information and critique it, and figure out if that
March 19, 2024
Keyport, NJ
Page |5
information is true and accurate. We have Erick Aguiar of Muni PILOT Solutions who will take
you through his analysis of what the developer has proposed and whether he believes, in his
professional opinion, this is a project that requires a PILOT in order to move forward and to be
constructive. We also have David Weinstein from Archer & Greiner, he’s my partner. He is the
redevelopment attorney here in town.
Erick Aguiar – was retained by the Borough to analyze the claim that this project could not be
done under conventional taxes. The scope of the analysis that was done by my company was to
analyze the 120-unit apartment building that was proposed by the developer and approved by the
Borough and determine if it is financially feasible under conventional taxes. Secondarily, to
analyze if the answer to that questions is no, this project is not financially feasible under
conventional taxes, analyze if the proposal put forward is a reasonable subsidy to provide the
developer that would facilitate the project.
First, we have to analyze the development costs. We have to analyze are those market costs or are
they potentially inflated to show that we are really struggling to build this project or not. We have
to analyze the debt and the equity structure. Are those terms typical of the current market?
Typically, in today’s world, to borrow to do a project like this the developer would come out of
pocket with about 40% of the project costs, and they would be financing about 60% of the project
costs. Is the interest rate that’s going to be used to finance the project the market interest rate,
because that would impact the project feasibility as well. Are the projected rents market rents, or
are they being underreported – anticipated vacancy and expense rates, same situation. After
analyzing all of these figures and determining if they are true market figures, or reasonably within
the market, we have to determine what would the project be valued at so at that point we can
determine what would conventional taxes actually be. We don’t know what conventional taxes
would be until we figure out what is the project actually worth. After we know what that number
is, we have to plug that into our analysis to figure out is this project financially feasible or not.
Currently, the assessment of the lot is $4.8 million in 2024. We don’t have a 2024 tax rate, so if
you apply the 2023 tax rate to the $4.8 million assessment, the taxes on this property are
approximately $106,000 per year. The local municipal portion of those taxes is 35.81%, so the
municipality would be collecting about $38,000. As far as the proposed project goes, the numbers
that were presented by the developer show $7.6 million in land equity. As for construction costs
for this type of development you would expect to see between $200 and $275 per square foot.
They are in line with that. They are presenting the cost at $220 per square foot. If this application
was showing $500 per square foot, it would raise a red flag. Ultimately, it would cost about $46
million projected to do this development. They are in line with the debt/equity structure. They
would be coming out-of-pocket with about $18.6 million of equity to put up front and then borrow
60% from banks.
There are two issues here compared to 2018. Number one, the construction costs have dramatically
increased. Number two, financing is now 8%. Back in 2018, it would have been much less than
8%. Borrowing $28 million at 8% would result in about $2.5 million annual debt service payment.
Back in 2018, that number was about $1.8 million. So, when you look at this same exact project
from 2018 through today, the debt service payment annually for the developer will be about
$700,000 higher than what it was initially proposed back in 2018. Of course, rents have changed
so you have to still go through the full analysis to determine is it financially feasible if rents have
gone up double or triple. Rents have certainly gone up, but not to the same magnitude that costs
have.
As part of the developer’s application, they presented certain rents for one-bedroom and certain
rents for two-bedroom units. That’s the bulk of where their income is coming from. There are
some other income items – parking premiums, unit premiums for units with views, etc., vending,
etc., but the majority of the income will come from the units. A key element that we have to look
at in our independent review is are the rents being proposed here in line with the market. At this
point, some of the numbers that were presented by the developer, in my independent analysis, are
going to differ. I don’t necessarily agree with the rents. I think that these rents of $2,000-$2,100
for one bedroom and $2,600 for two bedroom is probably too low in this current market for new
construction on the water. I revised the numbers in my analysis and for the one-bedroom I’m using
$2,250 and for the two-bedroom $2,900. That may still be light, but we have to be reasonable about
it. I analyzed rents and talked to realtors throughout the Bayshore area and these rents would be
March 19, 2024
Keyport, NJ
Page |6
typical for this size one-bedroom and two-bedroom units for new construction property.
Ultimately, when you add up all of the income, and you back out the typical vacancy which
typically runs 3%-5%, the effective gross income of this project annually when it’s stabilized will
be about $3.7 million.
Then I have to analyze the proposed expenses within the developer’s application and adjust those
accordingly to make sure those are in line with the market. Typically, for new construction
apartments, the expense ratio for operating expenses, not including taxes, is about 25%. This
analysis is running about 24% so that is in line with the market. The numbers that were put forth
in the developer’s application were slightly different – some things were higher and some things
were lower – but we believe were current market.
An important point to highlight here is the recycling and garbage removal costs. The developer
has expressed that they will be covering the recycling and garbage removal within this project and
I do not believe they will be seeking the Borough reimburse them. The most direct and quantifiable
cost associated with any new development would be garbage, recycling, and any snow removal.
The idea behind a development seeking reimbursement is that they are paying conventional taxes
and part of their taxes are supposed to include those services. As part of this application, the
developer is declaring that they will be covering the recycling and garbage removal costs.
Before we figure out what taxes would otherwise be, we have to figure out what would the value
of this property be. We have to go through all of the steps – what are the rents, what are the
expenses – and figure out what those numbers are. To walk you through the way that this would
be done on an apartment building – and this goes for every apartment building within the Borough
and within the county – this is how tax assessor analyze valuation of apartment buildings. You
have $3.7 million of gross income; you then have to back out the operating expenses, so you have
an NOI left here of about $2.9 million. You then have to capitalize that with what’s known as a
cap rate. This is a return of investment that apartment building investors are typically seeking.
These days, the rate is about 5%. It could be a little bit higher or a little bit lower depending on the
investor’s motivations or the area, so things certainly change. The operating expenses do not
include taxes in the analysis for tax assessment. The reason for that is because the value of the
property and the taxes that its going to pay, they are interconnected. You can’t know one without
the other. You have to build the Borough’s tax rate into the cap rate. You would use 5% plus the
current, or the 2023 tax rate of 2.198 so that comes to 7.198 and you would capitalize the net
operating income with that essentially after all that boring talk the property would be valued for
tax assessment purposes at around $40 million. Forty million dollars would mean they would be
paying about $877,000 in taxes. The municipal portion of that is about $314,000.
Everything to this point was to determine is this financially feasible. Developers and their financers
have to look at any given project and do an analysis and this is the way that analysis is typically
done. It’s called an internal rate of return. You have to analyze what are the expenses coming out,
what are the costs going in over a certain time frame and develop what is the annualized rate of
return. Based on the numbers that were submitted and were analyzed independently and modified
accordingly, with the $877,000 taxes, which would only increment up over time as we all painfully
know, the annualized rate of return would only be 0.65%. At a 0.65% IRR, this would not be a
financially feasible project.
Under the PILOT, what’s being requested in year one 10.35% of effective gross income, they
would also pay the Borough a 2% administrative fee on top of that. So, when this is a stabilized
income stream when all of the units are rented out in a year or two, the PILOT payment, which is
the annual service charge payment, and the administrative fee would be approximately $400,000
($397,000). If you were to simply modify, changing nothing else but just change the cost, that
recurring cost that the developer would have annually from $877,000 to $397,000, suddenly the
project is cash flow positive from year one or year two. In addition to having a cash flow positive,
or better cash flows, the PILOT would give a better certainty as to what the largest operating cost
is on an annual basis. So that, too, would play into increasing the value of the property. Ultimately,
the net result of changing this number so the taxes going from $877,000 to about $400,000 would
result in an IRR, or an internal rate of return, more commonly for us an annual rate of return, of
7.67% This improves the projections, making the development a lot more feasible. To be clear,
7.67% is not a stellar return for this type of risk. Typically, developers these days are looking for
March 19, 2024
Keyport, NJ
Page |7
8%-12% IRR. Even under the PILOT that is being presented here, they’re not even hitting the 8%
level.
The first part of the analysis that was done independently was to determine could this be done
under conventional taxes or not. The last slide would tell absolutely not. The second part of the
scope of my analysis was to determine could the Borough get more money from the developer in
terms of higher percentages. My opinion is the answer is no. If these numbers came back and we
were at 12%, 13%, I think the developer would be able to ask for a better deal. I think that these
numbers are completely reasonable. Just to put it into perspective in our personal lives, what does
a 0.65% rate of return mean versus a 7.67% rate of return? If you were to invest $100,000 at 0.65%
and were to take that money out of the bank in ten years, that $100,000 would grow to about
$107,000. That’s not very impressive, you’re not even beating inflation. At 7.67%, that $100,000
would turn into about $209,000 by year ten, so that shows you the difference. When you put this
in terms of someone investing $20 million, that would only turn into $21.3 million in ten years at
a 0.65% rate of return, but at a 7.67% rate of return $20 million would grow into about $40 million
plus. That would certainly attract development, attract financing of development to a much greater
extent than something that basically you’re going to break even on, or less when you factor
inflation, and incur significant risk along the way.
Comparing the 2018 PILOT to the current PILOT, the modification that is being done here is really
insignificant. What is being requested is two things – what was initially requested was years one
through five the annual service charge rate would be 11%. That is being requested to be modified
to 10.35% instead of 11% for the first five years. That would affect the Borough by approximately
$25,000 per year, or about $125,000 over the span of the five years.
The second thing being requested is to extend the 25-year PILOT from 2018 to 30 years. The 30-
year would be done at a 14.65% of income.
Comparing what taxes are today versus what this would be under a PILOT and running it out over
30 years, the longer you go the more assumptions have to be made. Certainly, there is no guarantee
in year 30 that these are what the numbers would be, but you have to do the analysis so that you’re
comparing apples to apples.
In year one under the PILOT, the annual service charge and administrative fee, as mentioned
before, would be about $397,000. The taxes today are about $100,000. What would be retained by
the Borough under the PILOT agreement would be about $378,000 because you keep 95% of the
annual service charge and 100% of the 2% administrative fee. If the project were not developed,
of the $100,000 the Borough portion would only be about $38,000. The Borough revenue benefit
is about $340,000 in year one. If you run this out over 30 years making a number of assumptions
just increasing things at 2% etc., those numbers are about $18.8 million to the Borough under the
PILOT versus $1.9 million to the Borough under conventional taxes.
To explain the way that taxes work, all of the budget components – the county, the school, the
municipal – those are determined based on the revenue sources that any municipality would have,
minus their costs. The costs are always higher than the expenses in government. There’s always a
negative number – it’s the deficit. The deficit, which is known as the tax levy, is raised through
conventional property taxes. The way that those taxes get distributed is based on the assessments.
Having a higher assessment doesn’t necessarily mean your taxes are going to be higher because it
depends on how you change your assessment in relation to everybody else within the Borough and
it also depends on the actual dollar amount that has to be raised by all the various budget
components. When you have a PILOT agreement, it’s slightly different. You don’t pay
conventional taxes. What you pay is this annual service charge which is actually a revenue source
to the Borough. Looking at the way the tax rate was calculated in 2023, the county budget was $2
million, the school was $11.6 million, the municipality had to collect $8.1 million and, ultimately,
the total amount that had to be collected was $22.6 million in taxes. To determine the tax rate, you
have to take the $22.6 million and divide it by the value of the town, all of the assessments
combined, which is about $1.029 billion. Its very simple math, $22.6 million divided by $1.029
billion is your tax rate of 2.198%. Under a PILOT agreement, what would happen is the property
would be paying money toward the Borough. The Borough could then take that money and reduce
their municipal budget. Its different than conventional taxes where it wouldn’t be a ratable as your
March 19, 2024
Keyport, NJ
Page |8
house would be. They would be making a payment that would go directly toward the municipal
budget.
There is a lot of discussion about what would happen if the school collected the money as a PILOT
versus the Borough. It’s the same exact thing. You don’t share the school with any other towns so
it’s the same bucket of tax payers that are paying into the school that are paying into the municipal
budget. The math would be the same. One caveat there is that there is a lot of state aid that goes
toward schools. It’s not really clear if the school got more revenue sources like PILOT money if
there could be impacts to the state aid.
Sean McGowan – one thing I didn’t mention is that the PILOT is based on a percentage of the
revenues that the developer makes based on financial reports that need to be filed with the Borough
on a yearly basis. You mentioned that your projected rents are slightly higher that what was put in
the application. If you are correct, it just means higher annual service charge to the Borough versus
what was put on paper, correct?
Erick Aguiar – Exactly. What would be the determinative factor here in terms of what the PILOT
actually is whatever the rents actually are times the rate that’s in the PILOT agreement for that
particular year. If the rents are higher, as I would expect, the PILOT would be higher. If the rents
are lower, the PILOT would be lower. It’s all determined by what actually happens with the rent.
The market could change – it could get better, it could get worse. We analyze it by what today
looks like.
John Cantalupo – under this PILOT is the Borough receiving more money then they would under
conventional taxes for their portion?
Erick Aguiar – under a hypothetical scenario of taxes, if this project were to happen under
conventional taxes, the $378,000 that would be under the PILOT is certainly higher than what that
number is under conventional taxes. It would be $314,000 under conventional taxes. Keep in mind
that’s making the assumption that the project could happen under conventional taxes, which it
can’t. It’s kind of like a false hypothetical scenario because this project is not going to happen if it
has to pay conventional taxes.
John Cantalupo – so even with the PILOT the Borough is making more money than it would under
conventional taxes.
Erick Aguiar – correct.
The meeting is opened to the public at 6:10 PM for comments limited to five minutes per person.
Rose Araneo, 90 Division Street – asked if the previous PILOT was approved.
David Weinstein – you do have an ordinance that approved the PILOT in 2018 by the then-sitting
Borough council. If this amended PILOT is not voted on, that PILOT would still be effectively on
the books under the ordinance.
Rose Araneo – I just wanted everyone to understand that it was approved prior. This is only
changing the PILOT for the first five years and adding five years to the back.
David Weinstein – that’s correct.
Kathleen McNamara – there was an ordinance December of 2018 that put the PILOT in place.
Then in 2021 the financial agreement was canceled. Currently, to my knowledge, there is no
PILOT agreement in place.
David Weinstein – there is no signed agreement, that is a fair statement. In 2021, there was a
resolution, but there was not an ordinance. In order to remove an ordinance from the municipal
docket, it needs to be removed by ordinance. You can’t remove an ordinance by resolution.
March 19, 2024
Keyport, NJ
Page |9
Kenneth Pape – in the summer of 2021, when we received notice that the Borough had attempted
to rescind those agreements, we challenged that and pointed out the failure to provide the required
notice and, as a result of that, the rescission was rescinded by the end of the summer.
John Merla, 34 Broad Street – was at the meeting when the ordinance was passed and was at the
meeting when the resolution was passed. You’re correct in that the resolution didn’t nullify the
ordinance. What it did do was it eliminated the agreement, and that’s a matter of public record.
Ken, you stated there is a PILOT in place, but there is not a PILOT signed by the Borough of
Keyport. Is it true that in order to obtain a construction loan it is always good to have a PILOT in
place?
Sean McGowan – lenders are generally looking to see a PILOT when they are providing
construction funds on a project in New Jersey. There are definitely exceptions out there but,
generally speaking, it is a huge box that is checked when the lender is going through the checklist
to determine whether they want to issue a term sheet, whether there is a financial agreement in
place.
John Merla – as far as the Borough is concerned, are the Borough representatives aware that in
2018 that there was a verbal agreement with the school that the school would get a portion of that
PILOT. So if there’s a new PILOT, there’s a new agreement, correct?
David Weinstein – if there is an existing executed financial agreement under the existing
ordinance, that would still be in place. If the new amendment is adopted, the agreement presented
at that point in time would be the agreement.
John Merla – asked if the Borough professional used a PFAF, a PILOT financial agreement
forecast, to determine if this is better for the Borough.
Erick Aguilar – the scope of my analysis was specifically to determine is the project financially
feasible or not and what would a reasonable level of subsidy be to make the project financially
feasible.
John Merla – asked if approved, the PILOT is subject to a certified audit every year.
David Weinstein – yes, that’s a statutory requirement.
Peter Henning, 102 Main Street – was a school board member and questioned the student/unit ratio
and asked what are our alternatives if that doesn’t pan out. He asked about sanitation using landfill
and our public works and will that be written in the agreement. What is the impact on our police
department, parking, and traffic?
David Weinstein – the in lieu fee is to pay for municipal services in lieu of the taxes. There are
underlying services that any property owner utilizes. If you call the police, they’re going to come
out. They have the right to receive trash collection and be reimbursed for it. It was our
interpretation from what they presented that they were not seeking that reimbursement. We can
talk about that with the developer.
Robert Bergen, 16 Green Grove Avenue – thinks architecturally this is a much nicer project than
what you see being built today. These numbers are never going to be perfect. All the analysis you
heard tonight is what the town should be going through. I think the rents are a bit low. But any
project that comes with a rate of return of about 8% is probably exactly right today. You should
make sure in the agreement that they will maintain their own garbage collection. Make sure that
if the payments aren’t made, the Borough can foreclose on the property. Thinks this is a good
project for the Borough.
Michael Lane, 51 First Street – this is the second go-around on a presentation on why a PILOT is
a good idea. Asked how the last projections stand up as being good sense. Are you aware that the
Borough homes are reassessed every year? Do you have any insight into how much they have gone
up in the last five years?
March 19, 2024
Keyport, NJ
P a g e | 10
Erick Aguilar – the assessments certainly are changing, but that doesn’t mean that the taxes are
changing because of the assessments.
Mike Lane – the tax bills on a single-family home on the waterfront have gone up more than 6%
a year. The Harbor View condos are going to generate significantly more money than this massive
project based on your last PILOT.
Erick Aguilar – to clarify one point, the assessments changing are not cause for the taxes
increasing. If the taxes have gone up, that’s because the budgets have been changing. It’s not just
the municipal budget, it’s the school budget and the county budget. There have been changes to
open space fees. The taxes changing is a product of budgets, not a product of the changing
assessments. The assessments are simply a distribution mechanism of the tax levy.
Mike Lane – I want to be clear that it’s the tax bills that are going up. The Harbor View twenty-
four condo units on the waterfront are going to be paying significantly more into the municipal
budget than this project based on your last PILOT.
Kenneth Pape – that’s not true. The PILOT has a percentage of the rents that are paid to the
municipality. The rents are going to go up as market values go up. You’re looking at numbers that
are expressed in percentages, but they’re percentages of the rent. Just like you’re observing other
property’s taxes going up, you can expect that the PILOT is going to go up on an annual basis.
Sean McGowan – generally, there are two ways to decrease the burden of tax bills on the property
owners. You can cut services, which no one likes, or you can develop. It’s indisputable that if this
building is built, there will be significantly more municipal revenue provided from this property
than if the project was not built. That increased revenue will help to reduce the increases in taxes
that all other property owners are facing every year.
Kenny Schwartz, 52 Broad Street – sometimes it’s hard to fathom how fantastic the town is. This
is a beautiful project. I pay in town $300,000 a year in taxes. This project is more than money. It
says something about the town, that we are worth it to have something that’s world class.
Jack Straub, 235 Main Street – I understand there is an issue regarding where the pier is extended
out all the way to the east that there is a problem with fire department access. The owner was asked
to put in a standpipe that the fire department would have access to in the event of a fire and the
owner has declined to do that.
Kenneth Pape – the firefighting system that we were requested by the board to put in is part of the
design. What is there is permitted and the commitment that was made by the applicant was to
incorporate it into the approval. The Construction Board of Appeals stated we are in compliance.
Al Litwak, 60 Walnut Street – What is the impact if you decide five or six years down the road to
sell the units to the people living there. Are the setbacks still in place, does it carry through?
Sean McGowan – nothing would change as far as any of the development approvals. They run
with the land. When it comes to the financial agreement, typically it requires the approval of the
municipality and it needs to be assigned to an urban renewal entity that has the same profit
limitations as any urban renewal entity such as this. In order to receive a PILOT, you need to apply
to the Department of Community Affairs to become what is called an “urban renewal entity.”
PILOTS can only be given to entities that have “urban renewal” in their name. In order to become
an urban renewal entity, you are agreeing that your profits will be limited as per the long-term tax
exemption statute. Very often, people think that developers that receive PILOTs are receiving a
windfall. I hope this presentation tonight shows that that is not the case. As further prevention to
the “windfall” is the long-term tax exemption statute which specifically limits the profits that a
developer can receive under a PILOT. That is the purpose of having to submit the audited financial
statements every year. One, so the Borough can make sure they are getting the percentage of the
revenue that they negotiated, but also so the Borough can ensure that the developer is not exceeding
that profit threshold.
David Weinstein – if the current owner decides to sell an individual unit that would be a completely
different financial structure and under the statute we couldn’t do that.
March 19, 2024
Keyport, NJ
P a g e | 11
Anthony, 167 Second Street – have known Clay for a couple of years now. He has a lot of big
dreams and is a guy who will move mountains to get what he wants done. I’ve seen it over the
years as my family have been customers at his marina how much it’s improved from years back.
If this project gets approved, I know he will run it well.
Robert Bergen – we want to see the downtown thrive. This project is going to generate economic
activity that you wouldn’t get from a much smaller project. The analysis for how taxes are
calculated on a project like that, it’s not what the property would sell for it’s what the income
stream is over a long period of time.
Cathleen Reilly, 261 Main Street – asked if the pier is fire safe.
Kenneth Pape – there was a full trial. There was a hearing by fire commissioners.
Vicky Flynn – there was a settlement and a finding of a violation that they were to remediate.
Requested an update from the attorney and will share.
Jack Straub – my understanding is the judge decided it was a construction issue and not a fire issue.
Is that dock safe – does it meet all fire codes or whatever are necessary?
Kenneth Pape – the determination was there were no violations.
Mike Lane – if you build a building that requires fire suppression, you can’t move people into the
building until the fire suppression is available. Our fire bureau has said that they cannot fight a fire
more than 90 feet from the end of the pier. Are you going to allow boats past the point where our
firefighters can fight a fire? People live on the boats 24/7 in the summertime.
Elmer J. Graham, Jr. – Mr. Perlman has been at this for a long time. I think it’s going to help our
Borough. I think it’s an excellent project.
John Cantalupo – that concludes our Town Hall. Thank you all for coming.
REGULAR COUNCIL MEETING
CALL TO ORDER: 7:14 PM
SUNSHINE LAW NOTICE: Read by Municipal Clerk
Minutes of the Workshop Meeting of the Mayor and Council, Borough of Keyport, held on the
above date in Borough Hall Council Chambers, Keyport, NJ, pursuant to the Annual Notice on file
with the Borough Clerk forwarded to the Asbury Park Press, and Newark Star Ledger and posted
on the Bulletin Board in accordance with the Open Public Meetings Act, P.L.1975, c.231.
ROLL CALL:
Members present: Councilmember Brady, Councilmember Gross, Councilmember McNamara,
Councilmember Peperoni, Councilmember Reilly, Council President Vecchio,
Mayor Araneo
PLEDGE OF ALLEGIANCE/MOMENT OF SILENCE
COMMITTEE REPORTS
(Councilmember is lead or co-lead liaison of Committees in bold)
Councilmember Brady: Environmental, Recreation/Senior Center, Fire/First Aid/OEM,
Municipal Alliance, Green Team
• Environmental Commission – provided updates on Atlantic Shores offshore wind
capstone project, invasive species, and dune development and maintenance. Next
meeting is Monday, March 25th; Cedar Street Clean Ocean Action beach cleanup April
13th.
• Recreation – Easter egg hunt was last weekend; thanked Nicki Francis, Mary Holtz,
Nancy Jones, Mayor Araneo, and Sofia Lamberson; considering Blue Claws event and
planning summer events for kids; date for Senior Prom; will provide night out for high
school seniors; I Love Keyport Day is May 18th with a rain date of May 19th.
March 19, 2024
Keyport, NJ
P a g e | 12
• MAC – attended the March meeting but there was no quorum,
• Both groups looking for volunteers.
Councilmember Gross: KBBC, Public Works/Water-Sewer, Recreation/Senior Center,
Redevelopment
• Public Works – conducted pothole repairs, street sweeping, and water meter readings.
Thanked DPW for everything they do.
Councilmember McNamara: Finance/Grants, Cannabis, Green Team, Police, NPP
• Finance and Grants – work continues on the budget process; unable to present the budget
until the solid waste contract is in place towards the end of April; received a Boardwalk
Preservation Fund award through DCA which will compliment other funds; attended the
NJ League of Municipalities Budgeting for Municipal Officials seminar with
Councilmember Brady and Mayor Araneo; requested 5-year tax abatements be topic at
the April workshop meeting.
• Cannabis – provided an update on the appeal by the Highway retail location; Premo
officially has an annual license; the Green and Gold trial is rescheduled for March 22nd.
• Green Team - Explore the Bayshore program was held on February 28th with a
presentation on horseshoe crabs; two signs were given to the Borough to post about not
disturbing horseshoe crabs.
• Attended information session regarding events to recognize the 250th anniversary of the
American Revolution.
Councilmember Peperoni: Planning Board, Recycling, Health/Registrar/Construction/Fire
Bureau/Code Enforcement/Zoning, Redevelopment, Harbor Commission
• Read the Board of Health treasurers report.
• Read the construction office report.
• Angie’s seeing-eye dog was attacked in August and had to be given up.
Councilmember Reilly: Fire/First Aid/OEM, Police, Municipal Alliance, Finance/Grants,
Cannabis
• No update from Fire. No update from MAC since there was no meeting quorum.
• Read First Aid calls for service report, police calls for service report, and report from
Chief Torres.
• St. Patrick’s parade is scheduled for the upcoming weekend.
• Thanked police, first aid, and fire.
Council President Vecchio: Harbor Commission, NPP, Public Works/Water-Sewer
• Harbor Commission – Snapper contest finalized for September 7th; new kiosk is up and
running (at the boat ramp) and looking at adding signage; damaged railing repair is closer
to completion; focused on working buoys. Request for Proposals are on this agenda.
• NPP – provided Beach Park project update.
Mayor Araneo: Library, Planning Board, KBBC, Green Team, Cultural/Civic, Mayors
Wellness Campaign
• KBBC – six new businesses opened and ribbon cuttings will be scheduled: Legacy Auto
Customs, Aangara Indian Cuisine, Garden State Barbershop, Brinia's Sazon restaurant,
Smokey’s Doggy Café which was a changeover, and Any Way You Wine It; the first
KBBC event, Spring Shop and Hop, was successful; new Highway 36 sign needs NJ
DOT approval to be installed; change in treasurer for short period; Susan Montanti was
elected treasurer.
• The NJ League of Municipalities Finance and Budget workshop was very informative.
• Attended Recreation Easter egg hunt.
• Met with Hazlet Mayor, Borough Administrator, and Councilman Peter Terranova,
liaison to the schools, to discuss feasibility study for school regionalization. Hazlet is not
interested at this time.
• Met with Congressman Pallone’s office to discuss additional funding for the waterfront.
• Performed 24th wedding ceremony.
• Highlight of the past two weeks was reading to Mrs. Guttman’s 3rd grade class.
March 19, 2024
Keyport, NJ
P a g e | 13
Mayor Araneo wanted it noted for the record that the governing body can hear statements made
by audience members at council meetings. A recent comment heard was “who elected that idiot
in?” and the answer is the residents of Keyport. The governing body hears everything on the
dais. Kids are taught not to bully but there are adults doing the same thing, and it’s disgusting.
Mayor Araneo advised Mr. Lane that she will respond to his request for status updates on a
number of items at the next meeting.
Motion to table resolutions R2024-110 through R2024-113, until the governing body holds a
workshop meeting on tax abatements in April.
MM: Vecchio 2nd: McNamara
Roll Call: Ayes: Brady, Gross, McNamara, Peperoni, Reilly, Vecchio
Nays:
Absent:
Abstain:
Motion to add resolution R2024-126, Authorizing Execution of Lease of Borough Property with
the Keyport Garden Club for Use of the Community Garden, to the agenda.
MM: Vecchio 2nd: Reilly
Motion to approve resolution R2024-126.
MM: Peperoni 2nd: Vecchio
Motion to table resolution R2024-126.
MM: Brady 2nd: Gross
Roll Call: Ayes: Brady, Gross, McNamara
Nays: Peperoni, Reilly, Vecchio, Mayor Araneo
Absent:
Abstain:
On the motion to approve resolution R2024-126:
Roll Call: Ayes: Peperoni, Reilly, Vecchio, Mayor Araneo
Nays: Brady, Gross, McNamara
Absent:
Abstain:
Motion to table resolution R2024-117.
MM: Reilly 2nd: Peperoni
Roll Call: Ayes: Brady, Gross, McNamara, Peperoni, Reilly, Vecchio
Nays:
Absent:
Abstain:
Councilmember McNamara questioned why R2024-126 was a walk-on resolution without an
opportunity for public comment.
Councilmember Brady noted she received R2024-126 update only hours before this meeting.
Council President Vecchio doesn’t want R2024-126 to be postponed further; wants the Garden
Club to be able to garden.
PUBLIC COMMENTS
The Meeting was opened to the public for comments on agenda items only.
Opened: 7:39 PM Motion by Peperoni, Carried by Gross. Ayes by all present.
Peter Henning, 102 Main Street – suggested a moment of silence for former Keyport teacher
Sherry Hill who passed away on March 14th and is a great loss. A moment of silence was held at
the Mayor’s request.
George Walling, 54 Second Street – disappointed R2024-126 was added last minute; hinders
transparency.
March 19, 2024
Keyport, NJ
P a g e | 14
John Merla, 34 Broad Street – thanked the mayor and council for considering the PILOT.
Thinks the garden club compromise needs to move forward. Asked about R2024-106 audit
recommendations concerning trust fund reserves, and the Borough Administrator responded.
Expressed concerns about the Municipal Alliance not having a quorum, and urged volunteers to
come together for the cause.
Susan Montanti, 110 Warren Street – believes taxes are atrocious but expressed concerns about
R2024-110 through R2024-113 being tabled. She previously worked on Raritan Cove and
believes and it’s problematic to not honor promised abatements.
Elmer J. Graham, Jr., 22 St. Peters Place – asked for an explanation of R2024-104, which the
Borough Administrator provided.
George Walling – commented that the MODIV data for 266 Van Dorn shows an abatement.
Ed Carew – asked for an explanation of R2024-107 and why the reduction/chemical control
grant would use chemical treatments. The Borough Administrator responded that chemical
treatments wouldn’t be used, but the trees of heaven/paradise would be removed to reduce the
population, in shared services with the County whereby the grant would be a reimbursement.
There is one tree at the library, which the administrator specified will be removed. Mr. Carew
said he received a letter from Victoria Thompson stating chemicals are not sprayed by
helicopters. They are spraying dumps formula that effects three insects in the larval stage, only
where there is no tidal flow.
Bill Shadel, 62 Division Street – acknowledged not knowing that Council President reached out.
Conveyed it’s not [the club’s] fault there wasn’t a sit-down to come to an agreement months ago
instead of it being approved as it just was. Displeased with the high cost of the lease.
There being no further comments, the Meeting was closed to the public.
Closed: 8:01 PM Motion by Peperoni, Carried by Reilly. Ayes by all present.
CONSENT AGENDA
(All resolutions listed hereunder are considered to be routine in nature and will be enacted in
one motion. Any person may request that an item be removed for separate consideration.)
R2024-102 Payment of Bills Listed on the March 8, 2024 Bills List
R2024-103 Payment of Bills Listed on the March 19, 2024 Bills List
R2024-104 Resolution of the Borough of Keyport, County of Monmouth, New Jersey,
Permitting the Transfer of 2023 Budget Appropriation Reserves Pursuant to
N.J.S.A. 40A:4-59
R2024-105 Governing Body Certification of the Annual Audit
R2024-106 Approving the Corrective Action Plan for the 2022 Municipal Audit
R2024-107 Authorizing a Grant Application to the New Jersey Department of Agriculture,
Spotted Lanternfly Program – 2024-2026 Spotted Lanternfly Reduction/Chemical
Control Treatment Grant
R2024-108 Approving the Borough of Keyport, County of Monmouth, Emergency
Operations Plan
R2024-109 Authorizing the Borough of Keyport to Release the Security Deposit Provided by
A Canoe to You, LLC for the Lease of the Keyport Waterfront Boathouse
R2024-110 Approving a Five-Year Tax Abatement for 5 Raritan Cove in the Borough of
Keyport
R2024-111 Approving a Five-Year Tax Abatement for 9 Raritan Cove in the Borough of
Keyport
R2024-112 Approving a Five-Year Tax Abatement for 10 Raritan Cove in the Borough of
Keyport
R2024-113 Approving a Five-Year Tax Abatement for 266 Van Dorn Street in the Borough
of Keyport
R2024-114 Authorizing the Issuance of a Social Affair Permit for the Keyport Yacht Club
(Garden Walk Fundraiser)
R2024-115 Authorizing the Issuance of a Social Affair Permit for the Keyport Yacht Club
(Raine Foundation Fundraiser)
March 19, 2024
Keyport, NJ
P a g e | 15
R2024-116 Authorizing the Issuance of a Social Affair Permit for the Keyport Yacht Club
(Bill Volk Regatta/Raine Foundation Fundraiser)
R2024-117 Authorizing the Issuance of a Social Affair Permit for David Gibson Memorial
Fund – Food Truck Festival
R2024-118 Approving the Request of the Keyport Fire Department’s 2024 Fair Committee
Chairperson for Exclusive Use of Fireman’s Park for the Annual Fireman’s Fair
R2024-119 Authorizing Keyport Fire Department to Use Fireman’s Park Parking Lot for
Annual Inspection
R2024-120 Resolution of the Mayor and Council of the Borough of Keyport Confirming the
Selection of Volunteer Firefighter of the Fire Department for Life Membership
R2024-121 Authorizing Knights of Columbus St. Joseph Council #3402 to Solicit Donations
on a Public Roadway
R2024-122 Amending Resolution #2024-66 Authorizing the Borough’s Participation in the
Clean Ocean Action 39th Bi-Annual Spring and Fall Beach Sweeps
R2024-123 Awarding the Waterfront Park Food Service Concession for the 2024 Season and
Authorizing Execution of Concession Lease Agreement with Funnee Girl Dogs LLC
R2024-124 Awarding the Waterfront Park Boathouse Concession of Non-Motorized
Watercraft for the 2024 Season and Authorizing Execution of a Concession Lease
Agreement with Paddle Share LLC
R2024-125 Authorizing the Award of Contract to V&C Hartley Fishing LLC for the
Operation of a Charter and/or Party Boat Service
R2024-126 Authorizing Execution of Lease of Borough Property with the Keyport Garden
Club for Use as a Community Garden (added to agenda during council meeting)
APPROVAL OF RESOLUTIONS
Motion to approve resolutions R2024-102 through R2024-125, except for R2024-110 through
R2024-113 and R2024-117, on the Consent Agenda.
MM: Reilly 2nd: Peperoni
Roll Call: Ayes: Brady, Gross, McNamara, Peperoni, Reilly, Vecchio
Nays:
Absent:
Abstain:
APPROVAL OF MEETING MINUTES
December 19, 2023 Regular Meeting (tabled March 5, 2024)
January 1, 2024 Reorganization Meeting
MM: Brady 2nd: Gross Ayes: all present Nays:
INTRODUCTION OF ORDINANCES
1. Ordinance – Amending the Salary Ordinance
The Clerk read the Ordinance by Title: ORDINANCE OF THE BOROUGH OF
KEYPORT, COUNTY OF MONMOUTH, NEW JERSEY, ESTABLISHING SALARIES
AND WAGES FOR DESIGNATED OFFICIALS AND EMPLOYEES OF THE BOROUGH
OF KEYPORT
1a. Motion to introduce:
MM: Peperoni 2nd: Brady
Roll Call: Ayes: Brady, Gross, McNamara, Peperoni, Reilly
Nays:
Absent:
Abstain: Vecchio
1b. Motion authorizing the Clerk to publish the Ordinance as introduced in the Asbury Park
Press for a public hearing:
MM: Peperoni 2nd: Gross Ayes: all present Nays:
REPORTS
1. Municipal Clerk’s Report for February 2024
2. Tax/Water/Sewer Collector’s Report for February 2024
3. Board of Health Treasurer’s Report for February 2024
4. Building Department Report for February 2024
March 19, 2024
Keyport, NJ
P a g e | 16
5. Municipal Court Report for February 2024
MM: Peperoni 2nd: Gross Ayes: all present Nays:
PUBLIC COMMENTS
The Meeting was opened to the public for comments.
Opened: 8:03 PM Motion by Peperoni, Carried by Reilly. Ayes by all present.
John Merla – regarding the proposal for grass cutting and lawn maintenance services, asked
about the maintenance of Cedar Street and Main Street ball fields, given there was a
Memorandum of Understanding (MOU) with the school for maintenance of the fields. The
Borough Administrator responded that there is no current MOU, the bid specifications were
discussed with DPW, and this will be discussed with the awardee to be included in the contract
rather than the RFP.
Elmer J. Graham, Jr. – stated he was pleased with the Town Hall meeting prior to the governing
body meeting. Noted his support for We Care Adult Care. Mentioned American Legion Post
#23, which meets the first Thursday of each month at 7:30pm.
Carol Grabowski, 48 Walnut Street – the light is out at the end of Walnut Street.
Michael Lane – asked Mayor Araneo about following up with her regarding his top six items.
Closed: 8:10 PM Motion by Peperoni, Carried by Reilly. Ayes by all present.
ADJOURNMENT
Motion to Adjourn
MM: Peperoni 2nd: Reilly Ayes: all present Nays: