July 26, 2022
Regular Session:
The Board of Public Works and Safety met in regular session on Tuesday, July 26, 2022 at 9:00 a.m. in the
Common Council Chambers. Members present were: Gary Henriott, Amy Moulton, Ron Shriner and Norm
Childress. Absent: Cindy Murray
Jacque Chosnek, City Attorney, was also present.
President Henriott called the meeting to order.
The Pledge of Allegiance was given to the flag of our Country.
MINUTES
Mr. Childress moved for approval of the minutes from the July 19, 2022 regular meeting. Mrs. Moulton seconded.
Passed.
BIDS UNDER ADVISEMENT
Utility Emergency Repairs Program for 2022-2023
President Henriott stated that this item will remain under advisement.
NEW BUSINESS
Purchasing
Recommendation for Award-RFP’s for Lafayette Public Safety Center Signage Fabrication and Installation
Dennis Carson, Economic Development Director, presented to the Board and recommended approval of a
Recommendation for Award for the RFP’s for Lafayette Public Safety Center Signage Fabrication and Installation
with Huston Signs. Mr. Carson stated that RLR Associates, Inc developed the specifications for the signage and
they have reviewed both proposals received and recommended Huston Signs. Mr. Carson explained to the Board
that the proposal amount was not the only factor when determining the company to award the contract. Mr.
Shriner moved for approval. Mrs. Moulton seconded. Passed.
Contract- RFP’s for Lafayette Public Safety Center Signage Fabrication and Installation
Mr. Carson presented to the Board and recommended approval of a Contract for the RFP’s for Lafayette Public
Safety Center Signage Fabrication and Installation with Huston Signs in the amount of $215,170.00. Mr.
Childress moved for approval. Mrs. Moulton seconded. Passed.
Notice to Proceed- RFP’s for Lafayette Public Safety Center Signage Fabrication and Installation
Mr. Carson presented to the Board and recommended approval of Notice to Proceed for the RFP’s for Lafayette
Public Safety Center Signage Fabrication and Installation. The project is set to begin today. Mr. Shriner moved
for approval. Mrs. Moulton seconded. Passed.
Board of Public Works and Safety
July 26, 2022
Page 2
Lafayette Renew
Contract-Guaranteed Savings Contract Proposal for Miscellaneous WWTP Improvements
Brad Talley, Renew Superintendent, presented to the Board and recommended approval of a Contract for the
Guaranteed Savings Contract Proposal for Miscellaneous WWTP Improvements with Bowen Engineering in the
amount of $1,809,000.00. The project addresses the replacement and rehabilitation of the critical infrastructure
including raw sewage pump discharge valve replacement, aeration tank gate replacement and final clarifier
actuator replacement, effluent pump station gate replacement, gravity belt thickener pump replacement; and PLC
replacement. Discussion ensued regarding the aging issue of the current and replacement equipment; and the
guaranteed savings contract process. Steve Nutt, Bowen Engineering, answered questions from the Board
regarding the Department of Local Government Finance submissions and metrics of the project. Mrs. Moulton
moved for approval. Mr. Childress seconded. Passed.
Notice to Proceed- Guaranteed Savings Contract Proposal for Miscellaneous WWTP Improvements
Mr. Talley presented to the Board and recommended approval of a Notice to Proceed for the Guaranteed Savings
Contract Proposal for Miscellaneous WWTP Improvements. The project is set to begin today with the substantial
completion of June 26, 2023 and the final completion of July 26, 2023. Mr. Shriner moved for approval. Mrs.
Moulton seconded. Passed.
Permission to Advertise-7th Street Storm Sewer Project
Mr. Talley presented to the Board and recommended approval of a Permission to Advertise for the 7th Street
Storm Sewer Project. This project consists of installation of approximately 450 feet of storm sewer, coordination
of utilities, storm inlets and drainage structure reinstatements, structures, drainage features, surface restoration,
connection to existing structure, modifications to existing infrastructure, maintenance of flow, and other
appurtenances. The project also includes surface restoration for disturbed areas, including street resurfacing,
trench repair, sidewalk replacement; and reseeding of affected area. The publications are set to run on July 29 and
August 5, 2022 with the bid opening on August 23, 2022. Mrs. Moulton moved for approval. Mr. Childress
seconded. Passed.
Contract Reduction #1-Pearl River Lift Station CSO Storage Facility
Mr. Talley presented to the Board and recommended approval of a Contract Reduction #1 for the Pearl River Lift
Station CSO Storage Facility with Bowen Engineering. The contract reduction encompasses project cost savings
associated with value engineering of manhole materials of construction, storage pipe route modification and
impact on ground water dewatering and treatment system, reduction in soil hauling and disposal by reusing
excavated soils on site and fixed fee reduction. The contract reduction is a deduction in the amount of
$738,000.00 which brings the revised contract amount to $10,964,120.00. Mr. Childress moved for approval. Mr.
Shriner seconded. Passed.
Engineering
Contract-Cason Street and 22nd Street Curb and Sidewalk Improvements
Dave Griffee, Engineering, presented to the Board and recommended approval of a Contract for the Cason Street
& 22nd Street Curb and Sidewalk Improvements with Dixon Constriction in the amount of $83,743.00. Mr.
Board of Public Works and Safety
July 26, 2022
Page 3
Griffee stated that this project will add sidewalk, curb ramps and curbs on the west side on 22nd Street along
Murdock Park and on the south side of Cason Street along the frontage of the new booster station. Mr. Childress
moved for approval. Mrs. Moulton seconded. Passed.
Notice to Proceed- Cason Street and 22nd Street Curb and Sidewalk Improvements
Mr. Griffee presented to the Board and recommended approval of a Notice to Proceed for the Cason Street & 22nd
Street Curb and Sidewalk Improvements. This project is set to begin today. Mr. Shriner moved for approval. Mrs.
Moulton seconded. Passed.
Change Order #1-2021 Dover Estates Handicap Ramps and Street Repair Project
Mr. Griffee presented to the Board and recommended approval of Change Order #1 for the 2021 Dover Estates
Handicap Ramps and Street Repair Project with Dixon Construction. The change order is an increase in the
amount of $46,224.00 which brings the revised contract amount to $287,764.00. The change order includes a
change in scope for additional and replacemens of damaged concrete curbs and approaches. Mrs. Moulton moved
for approval. Mr. Childress seconded. Passed.
Economic Development
Historic Demolition Permit-1214 Cincinnati Street (Porch Only)
John Collier, Economic Development, presented to the Board and recommended approval of a Historic
Demolition Permit for 1214 Cincinnati Street Porch Only. Mr. Collier stated that Dann Keiser, Lafayette Historic
Preservation Officer, determined that the loss of the original porch roof would adversely affect the character of the
national historic district. Mr. Keiser recommended upholding the 60-day waiting period. Mr. Shriner moved to
uphold the 60-day waiting periods. Mrs. Moulton seconded. Passed.
CLAIMS
Jeremy Diehl, Controller, presented for Board approval, Claims in the amount of $570,537.01. President Henriott
asked if there were any further questions and there were none. Mrs. Moulton moved for approval. Mr. Childress
seconded. Passed.
MISCELLANEOUS
Special Event Request-LPD National Night Out
L.T. Randy Sherer, Police Department, presented to the Board and recommended approval of a Special Event
Request for the LPD National Night Out to be held on August 2, 2022 from 3:00pm-6:00pm on Wallace Avenue
from Main Street to entrance of Arni’s Pizza. Mr. Shriner moved for approval. Mr. Childress seconded. Passed.
Time: 9:22 a.m.
BOARD OF PUBLIC WORKS AND SAFETY
Gary Henriott s/s
President
Board of Public Works and Safety
July 26, 2022
Page 4
ATTEST: Mindy Miller Riehle s/s
Mindy Miller Riehle, 1st Deputy Clerk
Minutes written by Mindy Miller Riehle, 1st Deputy Clerk
*A digital audio recording of this meeting is available in the Lafayette City Clerk’s Office or online at
http://www.lafayette.in.gov/agendacenter.
**A list of all permits issued for the preceding week is available at
http://www.lafayette.in.gov/DocumentCenter/Index/375
Get email alerts for Lafayette