Board of Works
Regular MeetingLafayette, IN · October 22, 2024
Minutes
BOARD OF PUBLIC WORKS AND SAFETY
MINUTES
October 22, 2024
Regular Session:
The Board of Public Works and Safety met in regular session on Tuesday, October 22, 2024 at 9:00 a.m. in the
Common Council Chambers. Members present were: Gary Henriott, Cindy Murray, Ron Shriner and Eric Rody.
Absent: Amy Moulton
Jacque Chosnek, City Attorney, was present at the meeting.
President Henriott called the meeting to order.
The Pledge of Allegiance was given to the flag of our Country.
MINUTES
Mr. Rody moved for approval of the minutes from the October 15, 2024 regular meeting. Mrs. Murray seconded.
Passed.
NEW BUSINESS
Engineering
Contract- Quotes: Small Concrete Projects
President Henriott stated that this item will be tabled. Mr. Shriner moved to table this item. Mrs. Murray
seconded. Tabled.
Notice to Proceed- Quotes: Small Concrete Projects
President Henriott stated that this item will be tabled. Mr. Shriner moved to table this item. Mrs. Murray
seconded. Tabled.
Permission to Advertise-Structure Demolition at 11 N. 13th Street
Jason Burks, Engineering, presented to the Board and recommended approval of a Permission to Advertise for the
Structure Demolition at 11 N. 13th Street. Publications are set to run on October 25 and November 1, 2024 with
the bid opening on November 12, 2024. Ms. Chosnek stated that this property went before the Lafayette Hearing
Authority 18 months ago with an order for demolition. Ms. Chosnek stated that this property will come before the
Board again in two (2) weeks for consideration of the 60-day waiting period. Mr. Rody moved for approval. Mr.
Shriner seconded. Passed.
Parks Department
Change Order #1-McCaw Park Improvements, Phase 2
Jon Miner, Parks Department, presented to Board and recommended approval of Change Order #1 for McCaw
Park Improvements, Phase 2 with JR Kelly Corporation. The change order is for additional cost for remediation
work to stabilize the soils beneath the two pickleball courts, the basketball court and areas of the walking trail.
The change order is an increase in the amount of $107,010.00 which brings the revised contract amount to
Board of Public Works and Safety
October 22, 2024
Page 2
$2,910,010.00. The change order also includes an increase of eighty (80) days to the contract time. Mr. Miner
stated that the remainder of the work will be completed according to the timeframe outlined in the original
contract. The new date of final completion will be June 4, 2025. Mr. Miner answered questions from the Board.
Mr. Shriner moved for approval. Mr. Rody seconded. Passed.
CLAIMS
Jeremy Diehl, Controller, presented for Board approval of Claims in the amount of $7,143,031.00. President
Henriott asked if there were any further questions and there were none. Mrs. Murray moved for approval. Mr.
Rody seconded. Passed.
Time: 9:07 a.m.
BOARD OF PUBLIC WORKS AND SAFETY
Gary Henriott s/s
President
ATTEST: Mindy Miller Riehle s/s
Mindy Miller Riehle, 1st Deputy Clerk
Minutes written by Mindy Miller Riehle, 1st Deputy Clerk
*A digital audio recording of this meeting is available in the Lafayette City Clerk’s Office or online at
http://www.lafayette.in.gov/agendacenter. **A list of all permits issued for the preceding week is available at
http://www.lafayette.in.gov/DocumentCenter/Index/375
Get email alerts for Lafayette
A daily email when new agendas and minutes are posted.