Third Workshop on the Park Avenue Land Reduction (Road Diet) Project
Regular MeetingLake Park, FL · May 6, 2023
Minutes
Lake Park Town Commission, Florida
Third Public Workshop
Park Avenue Lane Reduction (Road Diet) Project
Saturday, May 06, 2023 at 9:00 AM
Commission Chamber, Town Hall, 535 Park Avenue, Lake Park, FL 33403
CALL TO ORDER
9:15 A.M.
SPECIAL PRESENTATION/REPORT:
1. Third Public Workshop Associated with the Park Avenue Lane Reduction (Road Diet) Project.
Public Works Director Roberto Travieso explained what was being presented. He introduced the
Commission and Town Manager John D’Agostino. Susan O’Rourke with O’Rourke Engineering &
Planning; Adam Swaney with Engenuity Group, Inc. and Hays Henderson with JMorton Planning made
a presentation (see Exhibit "A"). Project Manager John Wille explained next steps and timeline.
A member of the audience asked staff to address cars parking for extended periods of time on Park Avenue.
Ms. O’Rourke stated that staff would review enforcement for extended parking issues. Town Manager
D’Agostino explained that signage would be installed along Park Avenue and cars would be towed if they
do not follow the parking regulations. The member of the audience asked questions regarding the
bioswales maintenance and the type of trees being installed. Ms. O’Rourke stated that the Town would be
responsible for maintaining the bioswales. She explained that they would try to be consistent with the type
of trees planted along Park Avenue and there were opportunities to discuss trees during this session.
A member of the audience asked how the new drainage and bioswales were designed. Mr. Swaney
explained that the drainage would be below the bioswales. He stated that particular areas could be
identified on the map in the back of the room. Town Manager D’Agostino explained that there are
currently bioswales installed on Lake Shore Drive that are working effectively.
Mr. Scott Brown, 205 Park Avenue explained that there was a bus stop in front of his home. He noticed
that there was no cut-in for buses to pull back onto the road. He asked if buses would block the road when
dropping off or picking up passengers. Ms. O’Rourke explained that they are in conversation with Palm
Tran for solutions. The street would be designed to slow traffic, so they would not be installing cut-out
for buses to pull into while loading and unloading passengers. She stated that bus shelters was also being
discussed.
Commissioner Mary Beth Taylor asked if shade trees were being installed. Public Works Director
Travieso explained that fully grown trees would not be planted, therefore, it would take some time before
the trees offer shade. Commissioner Taylor asked if they would transplant trees into personal property.
Mr. Henderson explained that it would be a larger task to transplant trees due to responsibilities and
liabilities that come along with doing so. He explained that there would be many logistical issues to
Regular Commission Meeting May 06, 2023 Page 1
Third Public Workshop on the Park Avenue
Lane Reduction (Road Diet) Project
EXHIBIT A
Public Works Department
Saturday, May 6, 2023
Project Team
Members of the Town Commission
John D’Agostino – Town Manager
Roberto Travieso – Public Works Director
Susan O’Rourke, P.E. – Lead Engineer
Adam Swaney, P.E. – Civil Engineer
Hays Henderson, PLA – Landscape Architect
John Wille – Capital Projects Manager
Public Workshop Agenda
1. Introductions 8. Project Illustrations
2. Project Background 9. Implementation Timeline
3. What is a Road Diet? and Next Steps
4. Public Input on Design Elements
10. Q&A
5. Civil Design Plans
11. Table Discussions
6. Public Input on Landscape
7. Landscape Design Plans 12. Closing Comments
Project Background
SUSAN O’ROURKE, P.E.
Project Area
What is a Road Diet?
Reduction in the travel way
Enhancement of the Corridor
Balance of Needs in the Corridor
o Drainage
o Beautification
o Parking
o Other travel modes
Should Park Avenue be Reduced?
Park Avenue demand is for two-lane now
and in the future
Speed Limit: 25 MPH, School Zone: 20 MPH
History of excessive speeds and traffic
accidents—requires mitigation
Previous Public Input
Definitely Needed Somewhat Needed Not needed
22%
Multimodal Path 44%
33%
44%
Wide Sidewalk w/ Street Furniture/Landscaping 56%
89%
Protected Sidewalk 11%
33%
Bike Lanes on Street 11%
56%
Previous Public Input
Definitely Needed Somewhat Needed Not needed
56%
Median in Center of Street 11%
33%
33%
Painted Centerline 33%
33%
44%
On Street Parking 33%
22%
56%
Bio-Swales 33%
11%
Previous Public Comments
Consider a phased-in approach to complete project
Include latest safety and lighting technology; paint new lines
Do not change the existing lighting
Add security cameras
Bike lane should not be between travel lanes and street parking
Improve school zone markings
Prefer multi-use path than dedicated bike lanes
Need protected crosswalks
60% Design Plans (Typical Blocks)
SUSAN O’ROURKE, PE
ADAM SWANEY, PE
Preliminary Layout
Preliminary Layout
Previous Public Input – Landscape
HAYS HENDERSON, PLA
Previous Public Input – Landscape
CANOPY TREE PREFERENCE
Bulnesia, 15%
Live Oak, 46%
Gumbo Limbo,
39%
Previous Public Input – Landscape
PALM TREE PREFERENCE
Sabal Coconut
5% 0%
Foxtail
18%
Royal
50%
Date
27%
Previous Public Input – Landscape
SMALL TREE PREFERENCE
Gieger Tree Green
Dahoon Holly 0% Buttonwood
9% 0%
Japanese
Blueberry
18%
Tabebuia
73%
Previous Public Input – Landscape
SHRUBS & GROUND COVER
PREFERENCE
Muhly Gtass
13% Society Garlic
Thryallis
13% 35%
African Iris
15%
Coontie
24%
Previous Public Input – Landscape
BIOSWALE PLANTING PREFERENCE
Mulhy Grass
19% Coontie
25%
Milkweed
19%
Tickseed
18%
Sage
19%
Landscape Design Plans (Typical Blocks)
HAYS HENDERSON, PLA
Landscape Plans
Landscape Plans
Project Design Illustrations
HAYS HENDERSON, PLA
Park Avenue, between 4th Street and 5th Street (East View)
Park Avenue, between 6th Street and 7th Street (East View)
Implementation Timeline & Next Steps
JOHN WILLE, CAPITAL PROJECTS MANAGER
Implementation Timeline & Next Steps
Project Team will:
Analyze public input for potential inclusion in project’s design
Develop 90% design plans
Continue to investigate and leverage grant funding opportunities to support
project implementation
Final Workshop proposed for Spring 2024
Possible implementation during Calendar Years 2024/2025
Questions & Comments
Table Discussion
DURATION: UP TO 1 HOUR
Table Discussion
1. Discuss available maps/table arrangements
2. Property Owners/Tenants are encouraged to locate their property on
the maps and discuss concerns with members of the design team
Table 1: Full complete civil plan (driveways, on-street parking, etc.)
Table 2: Full Landscape Plan
Connect with Us!
New Service Request Portal
o Request Service
o Report Issues
(561) 657-3918
publicworks@lakeparkflorida.gov
SCAN AND
BOOKMARK
ME!
Agenda
Third Public Workshop
Park Avenue Lane Reduction (Road Diet) Project
Saturday May 6, 2023, 9:00 AM – 12:00 PM
Commission Chambers, Town Hall
Meeting Agenda
Facilitator: Roberto Travieso, Director of Public Works
WELCOME/OPENING COMMENTS ROBERTO TRAVIESO
INTRODUCTIONS
PRESENTATIONS SUSAN O’ROURKE, P.E.
ADAM SWANEY, P.E.
HAYS HENDERSON, PLA
IMPLEMENTATION TIMELINE/NEXT STEPS JOHN WILLE
Q&A ROBERTO TRAVIESO
TABLE DISCUSSION ROBERTO TRAVIESO
SUSAN O’ROURKE, P.E.
ADAM SWANEY, P.E.
HAYS HENDERSON, PLA
JOHN WILLE
CLOSING COMMENTS JOHN D’AGOSTINO