City Planning Commission
Regular MeetingLiberty Lake, WA · March 9, 2022
Minutes
PLANNING COMMISSION MEETING
& PUBLIC HEARING MINUTES
WEDNESDAY, MARCH 9TH, 2022
HELD REMOTELY
Planning Commission Members Present: Tim Olsen, Joe Mann, Stephen Ramirez, Richard
Siler, Dale Robbins, Dg Garcia, Conrad Band
Adjunct Member(s) Present: Jim Baumker
Absent: Richard Siler
Staff Present: Lisa Key, Amy Mullerleile, Jen Camp, Megan Abhold, & Michelle Binion
Call to Order: Meeting was called to order at 4:01.
Roll Call: A quorum of members was present.
Introduction of New Senior Planner Amy Mullerleile:
Amy Mullerleile introduced herself to the planning Commissioners; including her education, past
work history and how long she has lived in the area.
Review of Agenda & Approval of Minutes:
Commissioner Ramirez moved that the February 9th, 2022, minutes be approved, seconded by
Commissioner Tim Olsen. The motion carried unanimously.
Workshops:
2021 Annual Development Review – Megan Abhold
Megan Abhold presented on the 2021 Development Statistics for the City of Liberty Lake.
No follow up questions were asked.
2022 – 2027 Capital Facilities Plan Review – Lisa Key:
Lisa Key presented the 2022-2027 Capital Facilities Plan that was adopted by city council on
December 21st, 2021.
No follow up questions were asked.
Potential 2022 Annual Code & Comp Plan Amendment Cycle – Lisa Key:
Director Key discussed seven potential 2022 Annual Code and Comp Plan Amendments:
including zoning map updates, and the 2021 CVSD annexation.
Director Key also discussed revising garage and carport requirements for Manufactured Homes
in the R1 and R2 zones, as well as clarifying the definition of a Building Height.
Planning Commission Meeting Minutes Page 1|2
March 9th, 2022
Director Key also proposed updating the Parking Code Standards and permitting RV/Mini Storage
in Commercial zones as requested by Mayor Kaminskas. Amy discussed her background on
updating sign code amendments and the benefit of going through the process of initiating Sign
Code Amendments. Director Key added that the sign code amendment process would involve
businesses, sign companies, and the public.
Director Key also proposed Codifying SAPS in Development Code to increase transparency and
allowing the Development Code to be more accessible and understandable.
Privately Initiated Comp Plan & Development Code Amendments in 2022:
Director Key presented the proposed Code Amendment for the Industrial Zone (I) to allow for
personal service uses.
Questions were asked and answered.
Secretary’s Report:
Director Key discussed the Public Meetings Act and noted the Act will remain in effect until the
emergency is terminated. City council has the ability to have a hybrid scenario due to the Council
members having city issued laptops.
Planning Commissioner Reports:
Commissioner Garcia is taking a tour of the city Friday March 11th with Director Key to get a
better idea of what is being built into the city.
Director Key spoke on various ways in which the Planning Commissioners can have influence on
what comes into the city, mainly through Land Use Planning, and Comprehensive Plan &
Development Code Amendments.
Citizens Comments:
No citizen comments were made at this time.
Adjournment:
Commissioner Ramirez moved to adjourn the meeting, seconded by Commissioner Olsen which
carried unanimously. The meeting adjourned at 5:15 p.m.
Planning Commission Meeting Minutes Page 2|2
March 9th, 2022
Agenda
PLANNING COMMISSION MEETING AGENDA
WEDNESDAY, MARCH 9, 2022
4 P.M.
CITY HALL
HELD REMOTELY
PURSUANT TO GOVERNOR INSLEE’S ORDER 20-28 DATED MARCH 24, 2020 – ALL PUBLIC
MEETINGS WILL BE HELD REMOTELY.
The Planning Commission will participate via ZOOM. The public can participate via the
following:
• Sign up to provide Public Comment at the meeting via calling in
• Submit Written Public Comment Prior to 2 pm on March 9, 2022
• Join the Zoom Meeting
Questions or Need Assistance? Please contact Planning Commission Clerk Megan Abhold at
mabhold@libertylakewa.gov
1. Call to Order
2. Roll Call
3. GENERAL BUSINESS:
• Introduction of New Senior Planner Amy Mullerleile
• Review of Agenda
• Approval of Minutes from February 9th, 2022
4. WORKSHOPS:
• 2021 Annual Development Review – Megan Abhold
• 2022 – 2027 Capital Facilities Plan Review – Lisa Key
• Potential 2022 Annual Code & Comp Plan Amendment Cycle – Lisa Key
5. REPORTS:
• Secretary’s Report
• Planning Commissioner Reports
6. Citizens Comments
7. Adjournment
Next Meeting: April 13, 2022
PUBLIC COMMENT
If you wish to provide oral public comments or testimony during the Planning Commission
meeting, please register through this link:
https://us02web.zoom.us/j/87335590929?pwd=YzFORU1RNFptQ2E0d0NrdFE5UmFaZz09
WRITTEN PUBLIC COMMENTS
If you wish to provide written public comments for the upcoming council meeting, please
email your comments to mabhold@libertylakewa.gov by 2:00 p.m. the day of the
Planning Commission meeting and include all of the following information with your
comments:
1. The Meeting Date
2. Your First and Last Name
3. If you are a Liberty Lake resident
4. The Agenda Item(s) which you are speaking about
JOIN ZOOM MEETING
To view the meeting live via Zoom Meeting, join the Zoom web meeting:
Meeting Instructions:
To join the Zoom web meeting:
https://us02web.zoom.us/j/87335590929?pwd=YzFORU1RNFptQ2E0d0NrdFE5UmFaZz09
Dial In Phone Numbers:
• +1 253 215 8782 US (Tacoma)
• +1 669 900 6833 US (San Jose)
Meeting ID: 873 3559 0929
Password: 067420
PLANNING COMMISSION MEETING
& PUBLIC HEARING MINUTES
WEDNESDAY, FEBRUARY 9TH, 2022
HELD REMOTELY
Planning Commission Members Present: Tim Olsen, Joe Mann, Stephen Ramirez, Richard
Siler, Dale Robbins, Dg Garcia, & Conrad Band
Adjunct Member(s) Present: Jim Baumker
Absent:
Staff Present: Lisa Key, Megan Abhold, & Michelle Binion
Call to Order: Meeting was called to order at 4:02 p.m.
Roll Call: A quorum of members was present.
Introduction of All Planning Commission Members & Staff:
Each Planning Commission member introduced themselves to all members; including how long
they have lived in the area and information on their personal background.
Review of Agenda & Approval of Minutes:
Commissioner Mann moved that the November 10th, 2021 minutes be approved, seconded by
Commissioner Olsen. The motion carried unanimously.
2022 Meeting Schedule:
Commissioner Band moved that the proposed Planning Commission Meeting dates be
approved, seconded by Commissioner Robbins. The motion carried unanimously.
Selection of Design Review Committee Members:
Director Key if any Planning Commissioners were interested in participating in the Design Review
Committee.
Commissioner Mann presented an overview of the role of the Design Review Committee as well
as the amount of influence the members hold when reviewing plans.
Commissioner Olsen, Mann, & Ramirez are current members and informed the Commissioners
that they would like to continue being involved in the Design Review Committee. Commissioner
Garcia informed the Commission that she would like to be considered as an alternate for the
Design Review Committee.
Workshops:
2022 Work Program Discussion:
Planning Commission Meeting Minutes Page 1|2
February 9, 2022
Director Key discussed various work programs that the Planning Commissions have processed
since 2018 as well as work programs that Planning Commission would work on in 2022. Questions
asked and answered.
Status of Planning Commission Appointments for 2022
Director Key discussed the Planning Commission positions that will be open in January 2023.
Secretary’s Report:
• MTC Zone Change Public Hearing before City Council in March
• New Senior Planner to start March 1st
• Comprehensive Plan Periodic Update
o Commissioner Ramirez was curious to know if climate resiliency was related to
housing. Director Key noted that climate resiliency focused on energy efficiency
and environmental regulations and concerns.
o Commissioner Baumker questioned if the climate resiliency related to wildfires as
well. Director Key stated that it does. Commissioner Baumker asked if any
annexations were going to occur. Director Key stated that if any annexations were
to occur that it would only occur in the Urban Growth Areas.
• Agenda items for March Planning Commission Meeting were discussed.
Planning Commissioner Reports:
• N/A
Citizens Comments:
Citizen Greg Cronin was curious to know the update to Stonehill Development and who the new
developer is. Director Key stated that Lennar Homes was to be giving a presentation to City
Council on March 1st and provided additional information regarding the status of the plats.
Greg inquired about Temporary Signage and the allowance of certain signs in right-of-ways.
Director Key informed Greg that only public event A-Boards are permitted and if an individual
notices a sign that is within the right-of-way to call Public Works and it will be removed.
Greg asked if the Planning Commission Meetings would be recorded and if videos would be
posted of the Planning Commission Meetings on the website. Director Key stated that the present
Planning Commission Meeting was being recorded and will be uploaded to the website.
Greg inquired about the new hire to the Police Department who has drone experience. Inquired if
drone surveillance is possible for the RV park to monitor individuals who overstay. Director Key
stated that the RV Park is located on private property and that would likely not be permissible
without a search warrant.
Adjournment:
Commissioner Mann moved to adjourn the meeting, seconded by Commissioner Olsen which
carried unanimously. The meeting adjourned at 5:25p.m.
Planning Commission Meeting Minutes Page 2|2
February 9, 2022
2022 -2027
Capital Facilities Plan
As Adopted December 21, 2021
Table of Contents
Page
Executive Summary…………………………………………………………………………………….... 1
Glossary of Funding Acronyms…………………………………………………………..………….. 3
Transportation & Pedestrian Projects………………………………………………….…………. 5
Parks & Public Facilities……………………………………………………………………….…………. 11
Equipment & Technology…………………………….………………………………………………… 13
Projects by Others………………………………………………………………………………………….. 17
Unfunded Projects…………………………………………………………...…………………………… 23
2022 -2027 ADOPTED
CAPITAL FACILITIES PLAN
EXECUTIVE SUMMARY
The City of Liberty Lake Capital Facilities Plan is a planning document that is adopted annually
and appended to the City of Liberty Lake Comprehensive Plan by reference. The document
reflects the plan for the City of Liberty Lake’s capital investments, including both new projects
and asset management investments, envisioned to be implemented over the next 6 years. 2022
proposed capital investments are reflected in the City of Liberty Lake Proposed 2022 Budget,
which is being reviewed and will be adopted concurrently with the Capital Facilities Plan. Any
amendments made by City Council to the Capital Facilities Plan in year 2022 will also need to be
amended in the City of Liberty Lake Proposed 2022 Budget.
Funding investments for 2022 in the proposed 2022-2027 Capital Facilities Plan (CFP) are
summarized below:
2022 Proposed Capital Investments
Kramer Parkway Overpass & Roadway Extension $2,300,000
Trailhead Clubhouse, Driving Range & Parking $8,000,000
Public Works Building & Final Site Improvements $1,080,000
Library Facility Upgrades $100,000
Public Art $34,000
Grant-funded Infrastructure Projects:
• Kramer Pkwy Partial Reconstruction1 $1,520,000
• Technology $373,360
• Stormwater Master Plan $200,000
Traffic Operational Improvements:
• Legacy Ridge/CV Signal $650,000
• CV Operational Improvements Design $135,000
• Design – Appleway / CV Blvd Intersection Improvements $40,000
• Solar-powered flashing speed limit sign $5,500
Annual Street Maintenance Allocation $100,000
Project Development- Streets 2 $100,000
Trails & Pedestrian Pathways $380,000
Parks / Public Facilities Maintenance Projects $613,700
Essential Equipment (New & Replacement) $424,300
TOTAL CAPITAL INVESTMENT, 2022 $16,055,860
1Funding decision in November; Project needs to proceed regardless of the outcome
2Contingency fund for design in the event of roadway failure
City of Liberty Lake 2022 – 2027 Capital Facilities Plan 1
As Adopted December 21, 2021
All cost estimates within this proposed CFP reflect the full cost of design, ROW acquisition (where
applicable), construction, inspection, and contingency. This CFP was developed utilizing the
adopted 2021-2026 Capital Facilities Plan, with modifications as based upon the Council-adopted
2022-2027 Transportation Improvement Plan, and updated cost information. Portions of some
projects funded in 2021 that were deferred due to supply-chain and staffing issues are carried
over to 2022.
Maintenance Projects for Parks & Public Facilities reflect funding for specific projects identified
in the asset management software, with prioritized maintenance projects reflected in the 2022
budget to protect the City’s existing investments. The maintenance projects identified in the CFP
include design and engineering costs, equipment, taxes, and contingency where applicable.
Utilities and Transportation Capital Projects by Others were updated, based upon input from
Liberty Lake Water & Sewer District, Spokane Transit, and Greenstone.
City of Liberty Lake 2022 – 2027 Capital Facilities Plan 2
As Adopted December 21, 2021
GLOSSARY OF FUNDING ACRONYMS
ABBREVIATION FUNDING SOURCE
APA Aquifer Protection Fund
ARP American Rescue Plan
CW Connecting Washington
GF General Fund
GOLF Golf Enterprise Fund
HRM Harvard Road Mitigation Fund
LIB CAP Library Capital Fund
LIFT Local Improvement Financing Tool
OTR Funding By Others
REET Real Estate Excise Tax
STREETS Street Fund
STRMW Stormwater Fund
TIB Transportation Improvement Board Grant
TIF Tax Increment Financing
UT Utility Tax - Streets Capital
City of Liberty Lake 2022 – 2027 Capital Facilities Plan 3
As Adopted December 21, 2021
Transportation & Pedestrian Projects
City of Liberty Lake 2022 – 2027 Capital Facilities Plan 5
As Adopted December 21, 2021
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 7
AS Amended November 30, 2021
TRANSPORTATION & PEDESTRIAN PROJECT DESCRIPTIONS
Transportation Projects
TP-1 - Harvard Rd Bridge Widening/ Kramer Parkway Overpass: Combines Harvard & Henry Roads, as state funding is intertwined, and depends
on credits for ROW, etc. For the Harvard Road bridge widening and ramp improvements, construction has been completed, thought the project
has not yet been closed out. Kramer Parkway Overpass and Roadway extension construction is underway, with construction anticipated to
continue through 2022.
TP-2 - Country Vista & Legacy Ridge Intersection Improvements: A contract has been awarded for signal installation, with construction anticipated
to begin in the spring.
TP-3 - Country Vista Rebuild/Operational Improvements: Improvement costs to include design, construction, inspection, and contingency for
pavement replacement and operational corridor improvements to include landscape islands, pedestrian crossings, as may be identified in Network
Analysis and Corridor Study, from Liberty Lake Road west to the City limits. Design will be undertaken in 2022 to allow for grant applications to be
pursued, with construction planned for 2024 and 2025.
TP-4 - Country Vista & Appleway Intersection Improvements: Intersection improvements to include design, construction, inspection and
contingency, for the addition of a right turn lane.
TP-5 - Appleway Improvements - Fairway to E City Limits: Improvement costs to include design, construction, inspection and contingency, for
road widening, sidewalks, swales, and street trees along frontages not subject to developer improvements, and the addition of medians consistent
with Appleway Avenue’s aesthetic corridor designation. Design is programmed for 2025 to allow for grant applications to be pursued, with
construction programmed for 2027.
TP-6 - Mission Ave Frontage Improvements - Southside, City Limits east to Glenbrook: Acquisition of right-of-way, and design, construction,
inspection and contingency for road widening, curbs, swales, street trees and sidewalks along the south side of Mission Avenue, from City limits
east to Glenbrook. Funding for design programmed for 2025 with construction anticipated in 2026.
TP-7 - Smart Signal Control: To provide signal coordination on Appleway and Liberty Lake /Harvard Road. Cost includes signal communication
consultant, controller communication, installation and cloud storage. Funding for this project has been deferred to 2023 to allow for the
incorporation of Kramer Parkway/ Country Vista traffic signal into the network.
City of Liberty Lake 2022 – 2027 Capital Facilities Plan 8
As Adopted December 21, 2021
TP-8 - Stormwater Master Plan: With funding from Washington State Department of Ecology’s CMAQ grant, along with a small match from the
Stormwater Reserves and Aquifer Protection funds, the master plan will help the City develop a policy and capital improvement plan to maintain
and upgrade the City’s stormwater management facilities.
TP-9 - Project Development: This $100,000 is a contingency fund to allow for the design of unplanned roadway repairs.
TP-10 - Solar-powered Flashing Speed Signs: This 2022 project includes the cost of equipment and installation of solar-powered flashing speed
limit signs on Appleway, between Molter Road and the eastern City limits to promote driver awareness and calm traffic
TP-11 - Annual Street Maintenance Allocation: Annual funding for pot-hole repair, crack sealing, restriping, and roadway repairs and
maintenance.
TP-12 - Mission Avenue Overlay– Country Vista to Molter Rd: This maintenance project is programmed for 2023, given relative roadway
condition, and will be a candidate for TIB preservation grant to cover 70% of the cost.
TP-13 - Sprague Avenue Overlay: Potential grind and overlay project proposed for 2026 for possible TIB grant funding at 70%.
TP-14 - Kramer Parkway Partial Reconstruction: Based upon geotechnical evaluation of the roadway, the planned overlay project has been
updated to a partial reconstruction project, with cost updated based upon actual design. Originally planned for construction in 2024, construction
is now proposed for 2022 based on current roadway conditions. An application has been submitted to TIB for grant funding, with the results of
that application anticipated shortly.
TP-15 - Pavement Condition Study/ Preservation Master Plan: This 2024 project proposes to complete a City-wide pavement condition study,
and to develop a data-driven street preservation master plan to identify and prioritize needed roadway preservation projects as the City’s
infrastructure ages.
TP-16 – Appleway Overlay: Overlay project from Fairway Lane to E City Limits, is a new project, based upon current roadway conditions. Staff
will apply for potential TIB funding in 2022, for construction in 2023.
City of Liberty Lake 2022 – 2027 Capital Facilities Plan 9
As Adopted December 21, 2021
Pedestrian Projects
TP-17 – Sidewalk & Pathway Maintenance: Annual maintenance allocation to address major sidewalk and trail maintenance projects, such as
repaving of trails, or repair/replacement of ADA accessible pedestrian ramps, along with minor maintenance and repair activities, to include crack-
sealing, sidewalk grinding or lifting, etc.
TP-18 - Annual Pedestrian Crossing Allocation: Funding for pedestrian crossing improvements and flashing beacons. Funding proposed to address
crossings at Bitterroot & Mission, Boone & Malvern, Boone & Stevenson, Country Vista and Sharp, Harvest Parkway & Nora, and Country Vista
Blvd. & Blueridge, to be spread over 2022 and 2023.
TP-19 - Sidewalk Improvements on Madson, from Mission to Appleway: Proposed construction of missing sidewalks on either side of Madson,
south of Appleway in 2025.
TP -20 - Sidewalk Improvements-Mission Ave, Northside, between Aladdin & Caufield: Remaining funds from the sidewalk Improvements to
close sidewalk gaps on the north side of Mission from City limits to SW corner of River Crossing East, and Mission Ave Temporary Trail grindings in
2019. This project will address the final, 330-foot sidewalk gap on north side of Mission Ave, west of Caulfield & east of Aladdin. Design is
underway and will be bid by year’s end, with construction planned for spring of 2022.
TP-21 - Sidewalk Master Plan: Funding for potential project in moved to 2024 to allow inventory to be completed and incorporated in pavement
condition software as a foundation in the master plan to identify and prioritize pedestrian projects.
City of Liberty Lake 2022 – 2027 Capital Facilities Plan 10
As Adopted December 21, 2021
Parks & Public Facilities Projects
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 11
As Adopted December 21, 2021
PARKS & PUBLIC FACILITIES PROJECT DESCRIPTIONS
Parks & Public Facilities Capital Projects
PF-1 - Trailhead Facility Upgrades: Funding for the demolition and reconstruction of the Trailhead Club house to include the pro shop, offices, a
full-service bar and restaurant (lease space), flex space for public meetings/events, and cart storage. This project is approved as a design build
with contraction anticipated to be completed in 2023.
PF-2 - Public Works Yard Development: Clearing, grading, site planning, permanent fencing, permanent lighting, electricity, temporary structures,
utility installation and frontage improvements have been completed to date. Design for the building and final site improvements is underway.
The project is anticipated to be bid in early 2022, with construction to be completed by early 2023.
PF-3 - Shade Structure for Rock Hill Park: Project originally funded at $20,000 for installation has been deferred to 2023.
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 13
As Adopted December 21, 2021
PF-4 - Library Facility Upgrades: Funding to allow the City to hire an architect for the purpose of evaluating the current building’s capacity to
accommodate the areas deemed inadequate or poor in the Library Needs Assessment, with funding for improvements as identified by the architect
spread over the next several years.
PF-5 - Public Art: Funding proposal as recommended in the Strategic Plan by the Parks & Art Commission.
PF-6- Pavillion Park Improvements: Site and facility improvements to include shingle roof replacement; replacement of wind screens; lighting
and electrical updates. Staff will prioritize project list based on priority, need and resources.
PF-7 – Rocky Hill Park Improvements: Restroom building lighting improvements.
PF-8 – Trailhead Improvements: 2021 funding addressed essential maintenance at the facility. With construction of a new facility (see PF-1), no
maintenance funds have been programmed for 2022 through 2027.
PF-9 - Town Square Improvements: Funding in 2021 was for essential maintenance; maintenance as needed in out years (2024 – 2027) to be
determined.
PF-10 - City Hall Building Improvements: City Hall campus includes the main building, little house, maintenance shop and site. Maintenance for
2022 includes the following: facility structure repairs including paint, tile flooring and carpeting, lighting updates and doors; fire alarm system and
water heater updates.
PF -11 – City Hall Parking Lot Configuration: Funding in 2023 to reconfigure the parking to maximize parking, repave and stripe, replace lighting,
repair sidewalks to meet newer ADA requirements, and address stormwater. May be consolidated with Trailhead parking lot improvements (see
PF-1).
PF – 12 - Library / PD Site: Maintenance improvements to site and building include restroom exhaust fans, exterior window replacement and
emergency lighting updates.
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 14
As Adopted December 21, 2021
Equipment & Technology
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 13
As Adopted December 21, 2021
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 15
As Adopted December 21, 2021
Projects by Others
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 17
As Adopted December 21, 2021
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 19
As Adopted December 21, 2021
UTILITY & TRANSPORTATION PROJECTS BY OTHERS
Utilities-Capital Projects by Others: The following utility projects are developer driven and will be constructed by others. They are included in
the City’s CFP, however, because they are eligible for reimbursement through TIF/LIFT.
• River District - Indiana Ave. Sewer (Trutina Development - Harvard Rd. to east of Harvard Rd.)
• River District - Indiana Ave. Water (Trutina Development - Harvard Rd. to east of Harvard Rd.)
• River District - Indiana Ave. Sewer (Bitterroot to Harvard Rd)
• River District - Indiana Ave. Water (W. Of Harvard Rd. to W. Boundary of Courtyard Plat 2013.Pl0002)
• River District - Sewer Lift Station, Force Main, & Other Associated Improvements
• River District - Telido Station Offsite Sewer
• River District - Telido Station Offsite Water Main
• River District - Wellington St. Sewer
• River District - Wellington St. Water
• Underground Utility Program (Liberty Lake Rd., Molter Rd., Mission Ave.)
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 20
As Adopted December 21, 2021
Transportation Capital Projects by Others: The following transportation capital projects are developer
driven, and will be constructed by others. They are included in the City’s CFP, however, because they are
eligible for reimbursement through TIF/LIFT.
• Harvard Rd & Indiana Ave Intersection Improvements
• Harvard Road & Wellington Roundabout
• Mission Improvements - Harvest Parkway east to Corrigan Road
• Indiana Ave. (Trutina Development - Harvard Rd. to east of Harvard Rd.)
• Indiana Ave. Water (Bitterroot to Harvard Rd.)
• Transit Parking (STA Project – Location TBD)
• Cataldo Extension & Connection – Phase I (Western States CAT)
• Cataldo Extension & Connection – Phase II (Centennial Properties)
• Indiana Ave Construction – Trutina, East of Harvard Rd
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 21
As Adopted December 21, 2021
Unfunded Projects
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 23
As Adopted December 21, 2021
City of Liberty Lake Proposed 2022 – 2027 Capital Facilities Plan 25
As Adopted December 21, 2021
PLANNING, ENGINEERING
& BUILDING SERVICES
2022 Potential Docket
City-Initiated Comprehensive Plan & Code Amendments
Proposed Amendment Description Reason
Comprehensive Plan Maps Map 1.1, Liberty Lake Boundary Add newly annexed CVSD school
Map 3.2, Cultural Landmarks property to Comp Plan Maps
Map 5.1, Comp Plan Land Use Map
Map 5.3, City Annexed Areas
Map 8.1, City Street System
Zoning Map Amend Zoning Map (City Code §10- Update based on CVSD Annexation
2A-5) Ordinance 278, Resolution 22-297 re
Centennial Split Zoned Property, and
outcome of MTC Zone Change
Garages & Carport Requirement Amend City Development Code §10- Eliminate requirement for garage or
for Manufactured Homes 2B-3(C)(12)(d) & §10-2C-3(C)(12)(d) carport (creates an obstacle to
affordability)
Building Height Definition Amend definition of building height in Replace the convoluted and
City Development Code §10-1C confusing definition with a simplified
definition
Parking Code Update Update City Development Code §10- Current bicycle & parking standards
3D, based on ITE Parking Demand are significantly overstated for some
Standards uses, understated for others
Sign Code Amendment Amend City Development Code §10- Current sign code is out of date and
3E to address content neutrality does not reflect current standards for
requirements content neutrality
Codify Specific Area Plan Amend City Development Code §10-2 To increase transparency and make
Regulations to add new zones regulations for RD- the development code more
R, RD-M, and RD-C as per River accessible and understandable for
District SAP, and new Liberty Village the citizens, as well as the
Zone, as per Liberty Village SAP; and development community.
amend City Development Code §10-3
to add standards for the River District
Overlay and the Liberty Village
Overlay, as per the respective SAPs
22710 E. COUNTRY VISTA DR., LIBERTY LAKE WA 99019
TELEPHONE (509) 755-6700 FAX: (509) 755-6713
WWW.LIBERTYLAKEWA.GOV