Utility Commission
Regular MeetingLittle Chute, WI · September 18, 2018
Agenda
AGENDA
VILLAGE OF LITTLE CHUTE UTILITY COMMISSION MEETING
PLACE: Village Hall Board Room
DATE: Tuesday, September 18, 2018
TIME: 6:00 p.m.
A. Call to Order
B. Roll Call
C. Public Appearance for Items Not on the Agenda
────────────────────────────────────────────────────────────
1. Approval of Minutes
Utility Commission Minutes of August 21, 2018
2. Discussion—2019-2023 CIP
3. Action—Election of Officers
4. Discussion/Action—2019 Salt RFP Bid Results
5. Progress Reports
a. MCO Operations Update
b. Director of Public Works
c. Finance Director
6. Approval of Vouchers
7. Unfinished Business
8. Items for Future Agenda
9. Adjournment
Requests from persons with disabilities who need assistance to participate in this meeting should be made with as much advance notice as
possible to the Clerk's Office at 108 West Main Street, (920) 423-3852 Prepared: September 12, 2018
MINUTES OF THE UTILITY COMMISSION MEETING AUGUST 28, 2018
Call to Order
The Utility Commission meeting was called to order at 6:00 P.M. by Kevin Coffey, Chair
Roll Call
PRESENT: Kevin Coffey, Chair
Michael Vanden Berg
Mark Gloudemans
Jessica Schultz
EXCUSED: Tim Bevers
Tim Wegand
ALSO PRESENT: Village Administrator James Fenlon, Director of Public Works Kent Taylor,
Finance Director Valerie Clarizio,
Public Appearance for Items Not on the Agenda
None
Approval of Minutes from the Utility Commission Meeting of July 17, 2018
Moved by M. Gloudemans, seconded by J. Schultz to Approve Minutes from the Utility
Commission of July 17, 2018
All Ayes – Motion Carried
Review/Approve—Partial Relay Homewood Court
Director Taylor advised the Board of the need for a Partial Relay due to 6 water main breaks.
Moved by K. Coffey, seconded by M. Gloudemans to Approve the Partial Relay for Homewood
Court, price not to exceed $15,000.
All Ayes – Motion Carried
Review/Approve—Well #4 Well/Pump Repair Proposal
Director Taylor advised the Board that Well #4 failed on July 10th, 2018 which caused damage and
needs to be repaired.
Moved by K. Coffey, seconded by M. Gloudemans to Approve the Well #4 Repair not to exceed
$107,000.00
All Ayes – Motion Carried
Review/Approve—UCMR 4 Testing Proposals
Director Taylor went over the EPA requirements for all Utilities with a population over 10,000. This
was the 4th round of testing. The Water Department is recommending approval of the Pace Analytical
proposal for $4, 436.00.
Moved by J. Schultz, seconded by M. Gloudemans to Approve the Pace Analytical proposal in
the amount of $4,436.00
All Ayes – Motion Carried
Progress Reports
MCO Operations Update
Jerry Verstegen, MCO went over documents regarding any breakdowns and hydrant replacements, also
water main breaks found and fixed on Taylor Street. Also advised residential testing is on-going.
Director of Public Works
Director Taylor went over current projects and advised a few streets were flooded and Public Works is
working on those. Lyle Street was questioned regarding the storm water lateral. After Public Works
dug this up and found that Gas was there and WE Energies is dealing with the home owner for repairs.
Finance Director
Director Clarizio advised that she is working with the auditors and getting up to speed on Finance.
Approval of Vouchers
Moved by M. Gloudemans, seconded by J. Schultz to Approve and Authorize payment of the
vouchers and draw from the respective funds
All Ayes – Motion Carried
Unfinished Business
Administrator Fenlon advised that the Heart of the Valley Metro Sewage Department (HOVMSD) is
hosting a meeting on 8/29/2018
Items for Future Agenda
September or October a draft CIP update should be available
October Meeting should have budget updates for early November
Adjournment
Moved by M. Gloudemans, seconded by K. Coffey to Adjourn the Meeting at 6:23 p.m.
All Ayes – Motion Carried
VILLAGE OF LITTLE CHUTE
By: Kevin Coffey, Chair
Attest: Laurie Decker, Village Clerk
VILLAGE OF LITTLE CHUTE
CAPITAL IMPROVEMENT BUDGET PROJECT COSTS SPECIAL ASSESSMENT RECOVERIES FUNDING SOURCES
2019 Projects Village Sewer Water Stormwater
Special Special Special Special TID/ Utilities
Sheet 2019 Facilities Utilities Assessment Assessment Assessment Assessment Bond Tax Grants/ Other Funding Retained Fund 2019 CIP
Number Project Name Projects Village Fleet Technology Sewer Water Storm Recovery Recovery Recovery Recovery Proceeds Levy Donations Soruces Earnings Balance Borrowing
PUBLIC WORKS
PW5 Evergreen Drive (French - CTH "N") $ 3,200,000 $ 2,030,000 $ 70,000 $ 1,100,000 $ 3,200,000
Park Avenue (Mill-Resurfacing) $ 300,000 $ 300,000 $ 210,000 $ 300,000
Land Acquisition - Downtown Master Plan $ 210,000 $ 210,000 $ (60,000) - $ (150,000) $ -
Temporary Lights CTY H & OO $ 30,000 $ 30,000 $ 30,000
Quiet Zone $ 185,000 $ 185,000 $ 185,000
PARKS $ -
PR3 Fox River Boardwalk $ 330,000 $ 330,000 $ 330,000
Creekview Park Playground Phase 2 $ 25,000 $ 25,000 $ (25,000) $ -
Creekview Park Trail to N and Interior Park Trails $ 100,000 $ 100,000 $ (100,000) $ -
Legion 3 Outfield Fence $ 8,000 $ 8,000 $ (8,000) $ -
BUILDING & GROUNDS $ -
Public Safety Building Flooring $ 30,000 $ 30,000 $ (18,600) $ (11,400) $ -
SEWER $ -
STORMWATER $ -
SW1 Stream Corridor Storm Sewer - Evergreen Drive $ 858,760 $ 858,760 $ (858,760.0) $ -
FT1 2009 TYMCO #800 Sweeper #13 $ 238,000 $ 238,000 $ (238,000) $ -
WATER $ -
Bohm Drive (Elm - "OO") $ 370,000 $ 370,000 $ 370,000
Resin Replacement for Well #4 (Compl. 2018 Proj) $ 50,000 $ 50,000 $ (50,000.0) $ -
2009 Truck Replacement #59 Ford F350 $ 32,500 $ 32,500 $ (32,500) $ -
FLEET $ -
FT1 International Dump Truck (#88 - 2000) $ 155,000 $ 155,000 $ (20,000) $ (135,000) $ - $ -
FT1 Crack Sealer ( New) $ 42,000 $ 42,000 $ (12,000) $ (30,000) $ -
FT1 John Deere Progator #9 $ 30,000 $ 30,000 $ (30,000) $ -
Used Car/Van (Additional) $ 10,000 $ 10,000 $ (10,000) $ -
TOTAL 2019 CIP BUDGET REQUEST $ 6,204,260 $ 3,248,000 $ 237,000 $ - $ - $ 522,500 $ 2,196,760 $ 210,000 $ - $ - $ - $ (938,760) $ (73,600) $ - $ (11,400) $ (455,500) $ (310,000) $ 4,415,000
TOTAL BORROWING $ 4,415,000 $ 2,875,000 $ - $ - $ - $ 440,000 $ 1,100,000
LESS: SPECIAL ASSESSMENT RECOVERY $ 210,000 $ 210,000 $ - $ - $ - $ - $ - Public Works $ 2,755,000
$ 4,205,000 $ 2,665,000 $ - $ - $ - $ 440,000 $ 1,100,000 Parks & Recreation $ 463,000
Public Safety $ -
$ 3,248,000 $ 237,000 $ - $ - $ 522,500 $ 2,196,760 $ 6,204,260 Buildings & Grounds $ 30,000
LESS: TID PORTION/BOND PROCEEDS $ (60,000) $ (20,000) $ - $ - $ - $ (858,760) $ (938,760) General Government $ -
LESS: RETAINED EARNINGS $ - $ (135,000) $ - $ - $ (82,500) $ (238,000) $ (455,500) Library $ -
LESS: TAX LEVY $ (51,600) $ (22,000) $ - $ - $ - $ - $ (73,600) Fleet $ 237,000
LESS: GRANTS/DONATIONS $ - $ - $ - $ - $ - $ - $ - Sewer $ -
LESS: OTHER FUNDING SOURCES $ (11,400) $ - $ - $ - $ - $ - $ (11,400) Water $ 522,500
LESS: FUND BALANCE $ (250,000) $ (60,000) $ - $ - $ - $ - $ (310,000) Stormwater $ 2,196,760
$ 2,875,000 $ - $ - $ - $ 440,000 $ 1,100,000 $ 4,415,000 $ 6,204,260
9/12/2018
VILLAGE OF LITTLE CHUTE
CAPITAL IMPROVEMENT BUDGET PROJECT COSTS SPECIAL ASSESSMENT RECOVERIES FUNDING SOURCES
2020 Projects Village Sewer Water Stormwater
Special Special Special Special TID/ Utilities
Sheet 2020 Facilities Utilities Assessment Assessment Assessment Assessment Bond Tax Grants/ Other Funding Retained Fund 2019 CIP
Number Project Name Projects Village Fleet Technology Sewer Water Storm Recovery Recovery Recovery Recovery Proceeds Levy Donations Soruces Earnings Balance Borrowing
PUBLIC WORKS
PW1 Annual Paving Program $ 1,943,231 $ 1,186,175 $ - $ 384,259 $ 372,797 $ 544,612 $ - $ - $ - $ 1,943,231
Homewood Court $ 629,965 $ 169,520 $ 187,115 $ 261,973 $ - $ - $ -
Carol Lynn Drive $ 556,210 $ 214,739 $ 185,682 $ 282,639 $ - $ - $ -
Downtown Parking Lot (Property Purchase) $ 150,000 $ 150,000 $ (75,000) $ 75,000
PW4 Hartzheim Drive (Well #4 to Buchanan Road) $ 1,130,449 $ 629,100 $ 179,043 $ 122,947 $ 199,359 $ 564,426 $ 130,896 $ 107,151 $ 278,925 $ (301,990) $ 828,459
Lights at Cty N & Evergreen $ 173,000 $ 173,000 $ 173,000
PARKS $ -
VanLieshout Park - Playground and Pour in Place
Surface $ 75,000 $ 75,000 $ 75,000
Heesakker Park - Concrete Playground Boarder $ 10,000 $ 10,000 $ (10,000) $ -
PUBLIC SAFETY $ -
BUILDING & GROUNDS $ -
SEWER $ -
FT1 Camel Sewer Jetter (#8 - 2008) $ 400,000 $ 400,000 $ (200,000) $ (200,000) $ -
STORMWATER $ -
Pheasant Run Storm Sewer $ 300,000 $ 300,000 $ 300,000
WATER $ -
Resin Replacement #2 $ 88,600 $ 88,600 $ (88,600) $ -
Well #3 (Pull and Inspection) $ 75,000 $ 75,000 $ (75,000) $ -
$ -
FLEET $ -
FT1 Toro Infield Pro (#37 - 2009) $ 20,000 $ 20,000 $ (20,000) $ -
FT1 2009 Harper Slope Mower - #76 $ 52,000 $ 52,000 $ (52,000) $ -
FT1 2007 Chrysler T&C Van #16 $ 20,000 $ 20,000 $ (20,000) $ -
$ -
TOTAL 2020 CIP BUDGET REQUEST $ 4,437,280 $ 2,223,275 $ 92,000 $ - $ 579,043 $ 670,806 $ 872,156 $ 1,109,038 $ 130,896 $ 107,151 $ 278,925 $ - $ (177,000) $ - $ (200,000) $ (665,590) $ - $ 3,394,690
TOTAL BORROWING $ 3,394,690 $ 2,138,275 $ - $ - $ - $ 384,259 $ 872,156
LESS: SPECIAL ASSESSMENT RECOVERY $ 1,518,859 $ 1,109,038 $ - $ - $ 130,896 $ - $ 278,925 Public Works $ 2,138,275
$ 1,875,831 $ 1,029,237 $ - $ - $ (130,896) $ 384,259 $ 593,231 Parks & Recreation $ 85,000
Public Safety $ -
$ 2,223,275 $ 92,000 $ - $ 579,043 $ 670,806 $ 872,156 $ 4,437,280 Buildings & Grounds $ -
LESS: PRIOR YR BOND PROCEEDS $ - $ - $ - $ - $ - $ - $ - General Government $ -
LESS: RETAINED EARNINGS $ (301,990) $ - $ - $ (200,000) $ (163,600) $ - $ (665,590) Library $ -
LESS: TAX LEVY $ (85,000) $ (92,000) $ - $ - $ - $ - $ (177,000) Fleet $ 92,000
LESS: GRANTS/DONATIONS $ - $ - $ - $ - $ - $ - $ - Sewer $ 579,043
LESS: OTHER FUNDING SOURCES $ - $ - $ - $ (200,000) $ - $ - $ (200,000) Water $ 670,806
LESS: FUND BALANCE $ - $ - $ - $ - $ - $ - $ - Stormwater $ 872,156
$ 1,836,285 $ - $ - $ 179,043 $ 507,206 $ 872,156 $ 3,394,690 $ 4,437,280
9/12/2018
VILLAGE OF LITTLE CHUTE
CAPITAL IMPROVEMENT BUDGET PROJECT COSTS SPECIAL ASSESSMENT RECOVERIES FUNDING SOURCES
2021 Projects Village Sewer Water Stormwater
Special Special Special Special TID/ Utilities
Sheet 2021 Facilities Utilities Assessment Assessment Assessment Assessment Bond Tax Grants/ Other Funding Retained Fund 2019 CIP
Number Project Name Projects Village Fleet Technology Sewer Water Storm Recovery Recovery Recovery Recovery Proceeds Levy Donations Soruces Earnings Balance Borrowing
PUBLIC WORKS
PW1 Annual Paving Program $ 1,644,710 $ 825,680 $ 360,765 $ 217,325 $ 240,940 $ 355,674 $ 83,200 $ - $ - $ (360,765) $ 1,283,945
Miami Circle (Vandenbroek - Florida) $ 700,940 $ 360,765 $ 217,325 $ 217,140 $ 313,830 $ 83,200 $ - $ -
Bittersweet Court $ 124,740 $ - $ - $ 23,800 $ 41,844 $ - $ - $ -
$ - $ - $ - $ - $ - $ - $ - $ -
Randolph Drive (Utilities) - East $ 1,353,140 $ 676,570 $ 209,171 $ 206,628 $ 260,771 $ 146,146 $ (209,171) $ 1,143,969
Randolph Drive (Utilities) - West $ 1,441,348 $ 720,674 $ 169,146 $ 230,941 $ 320,587 $ 146,146 $ 1,441,348
PARKS
Doyle Park - Pour and Play Surface $ 70,000 $ 70,000 $ 70,000
Island Park - Shelter $ 25,000 $ 25,000 $ (25,000) $ -
PUBLIC SAFETY
BUILDINGS & GROUNDS
LIBRARY
STORMWATER
WATER
Wel #1 Brine Tank Repair $ 38,000 $ 38,000 $ (38,000.0) $ -
Well # 4 Reservoir Repair $ 15,000 $ 15,000 $ (15,000.0) $ -
FLEET
FT1 International Dump Truck (#7 - 2006) $ 173,000 $ 173,000 $ 173,000
FT1 Ford F150 Pickup (#82 - 2011) $ 30,000 $ 30,000 $ (30,000) $ -
FT1 Ford F150 Pickup (#90 - 2011) $ 30,000 $ 30,000 $ (30,000) $ -
TOTAL 2021 CIP BUDGET REQUEST $ 4,820,198 $ 2,317,924 $ 233,000 $ - $ 739,082 $ 707,894 $ 822,298 $ 355,674 $ 83,200 $ - $ 292,292 $ - $ (85,000) $ - $ - $ (622,936) $ - $ 4,112,262
TOTAL BORROWING $ 4,112,262 $ 2,292,924 $ 173,000 $ - $ 169,146 $ 654,894 $ 822,298
LESS: SPECIAL ASSESSMENT RECOVERY $ 731,166 $ 355,674 $ - $ - $ 83,200 $ - $ 292,292 Public Works $ 2,222,924
$ 3,381,096 $ 1,937,250 $ 173,000 $ - $ 85,946 $ 654,894 $ 530,006 Parks & Recreation $ 95,000
Public Safety $ -
$ 2,317,924 $ 233,000 $ - $ 739,082 $ 707,894 $ 822,298 $ 4,820,198 Buildings & Grounds $ -
LESS: TID PORTION $ - $ - $ - $ - $ - $ - $ - General Government $ -
LESS: RETAINED EARNINGS $ - $ - $ - $ (569,936) $ (53,000) $ (622,936) Library $ -
LESS: TAX LEVY $ (25,000) $ (60,000) $ - $ - $ - $ - $ (85,000) Fleet $ 233,000
LESS: GRANTS/DONATIONS $ - $ - $ - $ - $ - $ - $ - Sewer $ 739,082
LESS: OTHER FUNDING SOURCES Water $ 707,894
LESS: FUND BALANCE $ - $ - $ - $ - $ - $ - $ - Stormwater $ 822,298
$ 2,292,924 $ 173,000 $ - $ 169,146 $ 654,894 $ 822,298 $ 4,112,262 $ 4,820,198
9/12/2018
VILLAGE OF LITTLE CHUTE
CAPITAL IMPROVEMENT BUDGET PROJECT COSTS SPECIAL ASSESSMENT RECOVERIES FUNDING SOURCES
2022 Projects Village Sewer Water Stormwater
Special Special Special Special TID/ Utilities
Sheet 2022 Facilities Utilities Assessment Assessment Assessment Assessment Bond Tax Grants/ Other Funding Retained Fund 2019 CIP
Number Project Name Projects Village Fleet Technology Sewer Water Storm Recovery Recovery Recovery Recovery Proceeds Levy Donations Soruces Earnings Balance Borrowing
PUBLIC WORKS
PW1 Annual Paving Program $ 2,048,977 $ 1,366,954 $ 130,600 $ 389,638 $ 161,785 $ 551,580 $ 28,600 $ - $ - $ (130,600) $ 1,918,377
Adams Way (McKinley - Pierce) $ 529,979 $ - $ 150,488 $ - $ 194,004 $ - $ - $ -
Tampa Way (East End - Vandenbroek) $ 271,910 $ 130,600 $ 72,645 $ 76,730 $ 114,120 $ 28,600 $ - $ -
Roosevelt (Florida - Elm) $ 565,065 $ - $ 166,505 $ 85,055 $ 243,456 $ - $ - $ -
Randolph Drive - East $ 306,400 $ 306,400 $ 306,400
Randolph Drive - West $ 392,897 $ 392,897 $ 392,897
Pine Street Parking $ 250,000 $ 250,000 $ 250,000
Main Street Sidewalk/Intersections $ 100,000 $ 100,000 $ 100,000
PARKS
VanLieshout / Legion Park - Splash Pad $ 400,000 $ 400,000 $ 400,000
Heesakker Park - Parking Lot & ADA Path $ 60,000 $ 60,000 $ (60,000) $ -
Mill Street Bridge - Asphalt Trail $ 40,000 $ 40,000 $ (40,000) $ -
PUBLIC SAFETY
BUILDINGS & GROUNDS
LIBRARY
STORMWATER
FT1 Elgin Pelican P Single Sweeper (#14 - 2005) $ 220,000 $ 220,000 $ (220,000) $ -
WATER
W1 2013 Truck Replacement #47 $ 26,500 $ 26,500.0 $ (26,500) $ -
Clean Exterior Towers #1 & #2 $ 10,000 $ 10,000.0 $ (10,000) $ -
FLEET
FT1 Pick-up 3/4 ton (New) $ 30,000 $ 30,000 $ (30,000) $ -
FT1 John Deere Progator (#36 - 2012) $ 37,000 $ 37,000 $ (37,000) $ -
2013 PU Truck #86 $ 30,000 $ 30,000 $ (30,000) $ -
2013 PU Truck #15 $ 38,000 $ 38,000 $ (38,000) $ -
$ -
TOTAL 2022 CIP BUDGET REQUEST $ 3,989,774 $ 2,916,251 $ 135,000 $ - $ 130,600 $ 426,138 $ 381,785 $ 551,580 $ 28,600 $ - $ - $ - $ (235,000) $ - $ - $ (387,100) $ - $ 3,367,674
TOTAL BORROWING $ 3,367,674 $ 2,816,251 $ - $ - $ - $ 389,638 $ 161,785
LESS: SPECIAL ASSESSMENT RECOVERY $ 580,180 $ 551,580 $ - $ - $ 28,600 $ - $ - Public Works $ 2,416,251
$ 2,787,494 $ 2,264,671 $ - $ - $ (28,600) $ 389,638 $ 161,785 Parks & Recreation $ 500,000
Public Safety $ -
$ 2,916,251 $ 135,000 $ - $ 130,600 $ 426,138 $ 381,785 $ 3,989,774 Buildings & Grounds $ -
LESS: TID/BOND PROCEEDS $ - $ - $ - $ - $ - $ - $ - General Government $ -
LESS: RETAINED EARNINGS $ - $ - $ - $ (130,600) $ (36,500) $ (220,000) $ (387,100) Library $ -
LESS: TAX LEVY $ (100,000) $ (135,000) $ - $ - $ - $ - $ (235,000) Fleet $ 135,000
LESS: INTERGOVERNMENTAL GRANTS/DONATIONS $ - $ - $ - $ - $ - $ - $ - Sewer $ 130,600
LESS: OTHER FUNDING SOURCES $ - $ - $ - $ - $ - $ - $ - Water $ 426,138
LESS: PRIOR YEAR BOND PROCEEDS $ - $ - $ - $ - $ - $ - $ - Stormwater $ 381,785
$ 2,816,251 $ - $ - $ - $ 389,638 $ 161,785 $ 3,367,674 $ 3,989,774
9/12/2018
VILLAGE OF LITTLE CHUTE
CAPITAL IMPROVEMENT BUDGET PROJECT COSTS SPECIAL ASSESSMENT RECOVERIES FUNDING SOURCES
2023 Projects Village Sewer Water Stormwater
Special Special Special Special TID/ Utilities
Sheet 2023 Facilities Utilities Assessment Assessment Assessment Assessment Bond Tax Grants/ Other Funding Retained Fund 2019 CIP
Number Project Name Projects Village Fleet Technology Sewer Water Storm Recovery Recovery Recovery Recovery Proceeds Levy Donations Soruces Earnings Balance Borrowing
PUBLIC WORKS
PW1 Annual Paving Program $ 3,126,852 $ 1,662,215 $ 498,861 $ 486,458 $ 479,318 $ 270,084 $ - $ - $ - $ 3,126,852
Biscayne Drive (Miami Circle - Florida) $ 513,625 $ 343,222 $ 141,589 $ 169,756 $ - $ - $ - $ -
Hoover Avenue (Roosevelt - Buchanan) $ 165,650 $ 50,986 $ 50,740 $ 40,037 $ - $ - $ - $ -
Grant Street (Green Field - Florida) $ 378,495 $ 104,653 $ 116,444 $ 79,690 $ - $ - $ - $ -
Orchard Lane (W Florida Ave - Bittersweet Ct -
W Florida Ave) $ 604,445 $ - $ 177,685 $ 189,835 $ 270,084 $ - $ - $ -
PARKS
Creekview - Shelter and Restroom $ 200,000 $ 200,000 $ 200,000
Heesakker Park - Playground Pour and Play &
Updates $ 90,000 $ 90,000 $ 90,000
PUBLIC SAFETY
BUILDINGS & GROUNDS
LIBRARY
STORMWATER
WATER
W1 Well #1 Floor Repair and Paint $ 15,000 $ 15,000 $ (15,000) $ -
Security Cameras $ 20,000 $ 20,000 $ (20,000) $ -
FLEET
Dodge Caravan (#56 2009) $ 20,000 $ 20,000 $ (20,000) $ -
2013 PU Truck #28 $ 21,600 $ 21,600 $ (21,600) $ -
2019 PU Truck #31 $ 21,600 $ 21,600 $ (21,600) $ -
TOTAL 2023 CIP BUDGET REQUEST $ 3,515,052 $ 1,952,215 $ 63,200 $ - $ 498,861 $ 521,458 $ 479,318 $ 270,084 $ - $ - $ - $ - $ (63,200) $ - $ - $ (35,000) $ - $ 3,416,852
TOTAL BORROWING $ 3,416,852 $ 1,952,215 $ - $ - $ 498,861 $ 486,458 $ 479,318
LESS: SPECIAL ASSESSMENT RECOVERY $ 270,084 $ 270,084 $ - $ - $ - $ - $ - Public Works $ 1,662,215
$ 3,146,768 $ 1,682,131 $ - $ - $ 498,861 $ 486,458 $ 479,318 Parks & Recreation $ 290,000
Public Safety $ -
$ 1,952,215 $ 63,200 $ - $ 498,861 $ 521,458 $ 479,318 $ 3,515,052 Buildings & Grounds $ -
LESS: TID/BOND PROCEEDS $ - $ - $ - $ - $ - $ - $ - General Government $ -
LESS: RETAINED EARNINGS $ - $ - $ - $ - $ (35,000) $ - $ (35,000) Library $ -
LESS: TAX LEVY $ - $ (63,200) $ - $ - $ - $ - $ (63,200) Fleet $ 63,200
LESS: INTERGOVERNMENTAL GRANTS/DONATIONS $ - $ - $ - $ - $ - $ - $ - Sewer $ 498,861
LESS: OTHER FUNDING SOURCES $ - $ - $ - $ - $ - $ - $ - Water $ 521,458
LESS: PRIOR YEAR BOND PROCEEDS $ - $ - $ - $ - $ - $ - $ - Stormwater $ 479,318
$ 1,952,215 $ - $ - $ 498,861 $ 486,458 $ 479,318 $ 3,416,852 $ 3,515,052
9/12/2018
Engineering Department &
Department of Public Works
Monthly Utility Commission
Report for August 2018
Sanitary Sewer
Street Notes:
Called out Saturday August 4th for possible sanitary sewer back up at 1004 Evergreen Dr.
Mainline was running fine with no restriction. Suggested to home owner to have lateral
cleaned.
Demo on new camel combo jetter/vacuum.
Also viewed a ECO combo unit by Sewer Equipment of America.
At the request of home owner we helped him find sewer odor at his father’s home at 1901
Vandenberg Ln.
Rebuilt chimney on sanitary manhole on west Lincoln due to deterioration and surface
cracking.
Continued with 2018 preventative maintenance jetting.
Storm Sewer
Engineering Installed information:
Village contractor installed 517 LF of 42 inch of storm main, 103 LF of 36 inch storm main, three
eight foot storm manholes, three 6 foot storm manholes, one 5 foot storm manhole, 36 LF of 8 inch
storm lateral, and 57 LF of 4 inch storm lateral.
Street Notes:
Got called out by a resident on Carol Lynn about a storm structure lid that pops off during
heavy rains. Checked surrounding manholes finding two factors that may contribute. One
being larger 24” pipe decreased to an 18” and the downstream manhole has rooting issue.
8/28/18 large amount of rain over 2” had some flooding in areas. Areas of concern were
called in but not limited to Florida Ave at Taylor St., Appletree at Orchard Ln., Miami Circle,
607 Sanitorium Rd, and 1725 Lyle.
8/28/18 called out to 213 Hayes St. for storm water concern. Outcome being contractor
failed to remove temporary plug during rebuild construction. (per Tim Paulson engineering)
Rebuilt chimney on storm manhole west Lincoln due to deterioration and surface cracking.
Storm Ponds
Street Notes:
Checked pumps and trash racks weekly and pulled some noxious weeds from several pond
(Queen Ann’s Lace).
Sent sweeper through town twice to clean flow lines.
Water
Street Notes:
Water break Moasis drive at Taylor St. on 8/28/18 during heavy rains prematurely adding to
flooding of streets. Road had to be closed off.
Engineering Notes:
2018 Utility Construction Projects
The 42-inch diameter downtown storm sewer pipe continues through August and remains on
schedule. Restoration for pavements is expected to be completed in September.
2019 Utility Projects
Design efforts for Evergreen Drive storm sewer & Bohm Drive water relay have begun.