Community Preservation Committee
Regular MeetingLowell, MA · October 6, 2022
Minutes
City of Lowell – Community
Preservation Committee
Community Preservation Committee Meeting Minutes
Thursday, October 6, 2022, 6:30p.m.
Conducted in-person and via zoom
Note: These minutes are not completed verbatim. For a recording of the meeting, visit www.ltc.org
Members Present
Adam Baacke, Chair
Sinead Gallivan, Member
Francesca Cigliano, Member
Yovani Baez-Rose, Member
Sidney Liang, Member
Troy Depeiza, Member
Brad Buitenhuys, Member
Philip Shea, Member
Members Absent
Ryan Rourke, Member
Others Present
Dylan Ricker, Associate Planner
A quorum of the Committee was present. A. Baacke called the meeting to order, the time was 6:30 pm.
I. Minutes for Approval
September 22, 2022 Meeting Minutes
P. Shea said the minutes indicated he was absent, and he stated that he was not let into the zoom by the host. P.
Shea said he watched the entire meeting and listened.
II. Continued Business
III. New Business
A. Baacke stated this meeting will be used to hear presentations and the for the CPC to ask questions. A. Baacke said
the CPC will vote on funding at a later meeting.
CPA Application: Donahoe Park
The City of Lowell has applied to the Community Preservation Committee seeking $802,500 of CPA funding for an
Outdoor Recreation project. The applicant seeks to make capital improvements to the City’s Donahoe Park at 2
Stratham Street.
On Behalf:
J. Wilson said the proposal is a collaboration with the Parks Department with the goal of giving the park a facelift to
bring the park up to a higher standard. J. Wilson said the playground will be updated with a new surface, and new
equipment. J. Wilson said the plan includes irrigation for the existing baseball field among other improvements. J.
Wilson said a rain garden will be added as well to address stormwater related erosion, along with additional
improvements. J. Wilson said she will be applying for Land, Water, and Conservation funds to close funding gaps.
Discussion:
A. Baacke noted the limitations of total CPA funds available. A. Baacke asked if the playground is the priority, J.
Wilson confirmed. A. Baacke asked if accessibility work is required or if the playground could stand on its own as a
project. J. Wilson said the playground could stand on its own as a project. J. Wilson said the project will be done in
phases based on priorities.
CPA Application: O’Donnell Park
The City of Lowell has applied to the Community Preservation Committee seeking $1,668,750 of CPA funds for an
Outdoor Recreation project. The applicant intends to make capital improvements to the City’s O’Donnell Park at
1170 Gorham Street.
On Behalf:
Jessica Wilson, Applicant
J. Wilson said the park has been assessed to determine the needs. J. Wilson said the basketball courts are so
damaged they are unplayable, and funds will be used for resurfacing and a priority will also be to upgrade the
playground. J. Wilson said the playground is becoming a safety hazard, and noted the need for a new playground
surface. J. Wilson said the principal of the nearby school asked for an outdoor classroom which was included in the
plans as well. J. Wilson said the overall improvements to the playground and park is the highest priority. J. Wilson
added that Land, Water, and Conservation grants will be applied for to close any funding gaps.
Discussion:
T. Depeiza asked about contamination issues at the site. J. Wilson said she does not know the full extent, but she is
working with the City’s Senior Environmental Office to address these concerns and nature of contamination of the
site.
A. Baacke asked which of the proposed park projects is the highest priority. J. Wilson said the O’Donnell Park is the
highest priority.
Y. Baez-Rose asked if the School Department will contribute any funding. J. Wilson said the School Department will
help with fundraising efforts.
CPA Application: St. George’s Church
St. George’s Parish Council has applied to the Community Preservation Committee seeking $500,000 of CPA funds
for a Historic Preservation project. The applicant seeks to restore the dome of the historic St. George’s Church at 44
Princeton Boulevard.
On Behalf:
Stella McAuliffe, Applicant
Constantine Cambas, Applicant
C. Cambas said the church is over 100 years old, and the dome has several leaks due to storms between 2017-2019.
C. Cambas said there is insurance money for the exterior of the dome, and C. Cambas said the dome is the major
source of leaks, and noted the dome was an architectural marvel when it was completed. C. Cambas said they have
roughly $800,000 for the repair, but the total repair estimate was over $1,000,000. C. Cambas said the work would
be to repair the dome and underlying structures. C. Cambas said the timeline will depend on the contractor, and
they anticipate the work timeframe being roughly 3 months. C. Cambas said they expect the total repair to be
around $1,300,000 based on a previous estimate.
C. Cambas noted that in addition to church services, the UMass Lowell History Dept. visits the church with students
to review the historic architecture and religious artwork.
Discussion:
B. Buitenhuys asked the applicant if they factored in increased costs. C. Cambas said they expect the exterior to be
roughly $800,000 with an additional $400,000-$500,000 expected. B. Buitenhuys asked how the applicant is
anticipating cost increases. C. Cambas said they would plan to plug any funding gap with CPC funds and additional
church fundraising. B. Buitenhuys asked about contingency funds. C. Cambas said without a final estimate they are
not certain. B. Buitenhuys expressed concern about funding something without a final estimate. C. Cambas noted
the information is incomplete, but this is what is available at this time.
S. McAuliffe said they have contacted an engineering firm and are waiting to hear back for estimates.
F. Cigliano notes that since this is a Historic Preservation project it would require a Preservation Restriction be
placed on the property. B. Buitenhuys explained requirements of the Preservation Restriction. A. Baacke said the
restriction would likely be in perpetuity to ensure the preservation of the historic structure. S. McAuliffe agreed.
A. Baacke noted that some of the requests are not eligible for CPA funding. S. McAuliffe said they are aware.
S. Liang asked if there is a safety concern right now. S. McAuliffe said there are no safety concerns to their
knowledge.
P. Shea asked the applicant to indicate whether they could receive phased funding. P. Shea asked about expected
start date. C. Cambas said they had a preliminary assessment for the exterior of the dome, but they are now waiting
on a full estimate including the interior work. C. Cambas said the full estimate received in 2019 was for $1,300,000.
C. Cambas said the work is likely a 3 month project, but possibly longer. C. Cambas said they are waiting for a
specialist to review the work as well.
P. Shea said it would be beneficial for this info to be provided as well.
CPA Application: Hadley House
The Lowell Housing Authority has applied to the Community Preservation Committee seeking $150,000 of CPA
funds for a Community Housing project. The applicant seeks to restore the Hadley House and create up to five (5)
affordable units of veterans housing at 719 Broadway Street.
P. Shea recused himself from the discussion as a member of the Lowell Housing Authority Board.
On Behalf:
Gary Wallace, Applicant
Adam Garvey, Applicant
Laura Watts, Applicant
Kevin Murphy, Applicant’s Representative
G. Wallace said the property is 200 years old. G. Wallace said the property was acquired in 2019, and recent
legislation was passed for a land acquisition. G. Wallace said the plan is to restore the historic building and create
veterans housing. G. Wallace explained the proposed site improvements. G. Wallace explained the prior designs and
plans which were completed by the Housing Authority years ago. G. Wallace explained the total proposed units and
their sizes and amenities. G. Wallace said the project meets CPA, City goals, and CTI’s Community Needs
Assessment. G. Wallace explained the funding sources for the projects and noted that CPA funding is only a portion
among other sources of funding. G. Wallace noted the Lowell Housing Authority’s passed experience constructing
affordable housing.
Discussion:
F. Cigliano said the project is a great candidate for CPA funding as it addresses Community Housing and Historic
Preservation. F. Cigliano noted the ask money-wise is modest and includes many other funding sources. F. Cigliano
asked where TBD funding is expected to come from. G. Wallace said this has been determined yet, this could be
from MassDevelopment or from their non-profit partner. F. Cigliano noted the project has not yet obtained their
discretionary permits yet from City Boards, and said having these permits are preferable as it shows the project is
more shovel ready.
A. Baacke asked the applicant about their permitting schedule. K. Murphy said the land is still owned by the
Commonwealth, and it has been a slow process for the Housing Authority to obtain the land. K. Murphy said they
are now finally in the process of acquiring the land, and said that they cannot apply for the permits until they
acquire the property. K. Murphy said he is confident that once the property is obtained the permits will be applied
for. K. Murphy said the applicant has already had meetings with City staff.
B. Buitenhuys agreed with F. Cigliano, and said that there should be permits in hand before any funding is granted
from the CPA.
Y. Baez-Rose asked about the affordability restrictions. G. Wallace said the units will be designated for veterans’
supportive housing for veterans earning between 0%-30% AMI.
T. Depeiza asked whether the applicant had a detailed cost estimate due to the current volatility in the construction
market right now. G. Wallace said the estimate is very detailed and was done in house by Housing Authority staff
current to 2022 construction prices.
A. Baacke asked about the site plan and whether it is current and how the existing walking path would be addressed.
G. Wallace said they will work with the Planning Department on the issues and added that they would work with any
easements. A. Baacke said the concern is that it is in conflict with the proposed parking. G. Wallace said the concerns
have not been fully addressed yet.
IV. Other Business
Election of a new Vice-Chair
The Community Preservation Committee will vote to elect a new Vice-Chair.
B. Buitenhuys motioned, and S. Gallivan seconded the motion to nominate Francesca Cigliano as Vice-Chair. The
motion passed unanimously, (8-0).
V. Notices
VI. Further Comments from Community Preservation Committee Members
B. Buitenhuys requested all CPA materials be provided to the City Council prior to CPA deliberations. Staff agreed.
S. Gallivan said that staff provided a breakdown and summary of available funding prior to last year’s deliberation
which was helpful. Staff said this would be provided.
VII. Adjournment
B. Buitenhuys motioned, and F. Cigliano seconded the motion to adjourn. The motion passed unanimously (8-0). The
time was 7:15pm.
Agenda
City of Lowell - Community
Preservation Committee
Community Preservation Committee Agenda
Thursday, October 6, 2022 at 6:30 p.m.
This meeting will occur in-person with the option to join remotely. You can choose to
attend in-person in the City Council Chambers, City Hall, 375 Merrimack Street, Lowell, MA
01852; or you can choose to attend remotely by using one of the following four options to
access the meeting:
1. Join via your computer, tablet, or smartphone: https://lowellma.zoom.us/j/83405487408
2. Call 646-558-8656 and enter the MEETING ID: 834 0548 7408
3. Watch LTC Channel 99
4. Watch online at: www.ltc.org/watch/channel-99
I. Call to Order
II. Minutes for Approval
September 22, 2022 Meeting Minutes
III. Continued Business
IV. New Business
CPA Application: Donahoe Park
The City of Lowell has applied to the Community Preservation Committee seeking $802,500 of CPA funding for an
Outdoor Recreation project. The applicant seeks to make capital improvements to the City’s Donahoe Park at 2 Stratham
Street.
CPA Application: O’Donnell Park
The City of Lowell has applied to the Community Preservation Committee seeking $1,668,750 of CPA funds for an
Outdoor Recreation project. The applicant intends to make capital improvements to the City’s O’Donnell Park at 1170
Gorham Street.
CPA Application: St. George’s Church
St. George’s Parish Council has applied to the Community Preservation Committee seeking $500,000 of CPA funds for a
Historic Preservation project. The applicant seeks to restore the dome of the historic St. George’s Church at 44 Princeton
Boulevard.
CPA Application: Hadley House
The Lowell Housing Authority has applied to the Community Preservation Committee seeking $150,000 of CPA funds for
a Community Housing project. The applicant seeks to restore the Hadley House and create up to five (5) affordable units
of veterans housing at 719 Broadway Street.
V. Other Business
Election of a new Vice-Chair
The Community Preservation Committee will vote to elect a new Vice-Chair.
VI. Notices
VII. Further Comments from Community Preservation Committee Members
VIII. Adjournment
Get email alerts for Lowell
A daily email when new agendas and minutes are posted.